AZ_Proposed_Payment_Milestones_Final.xlsx

XLSX spreadsheet 14 KB Posted

Attached to
Master Agreement AZ|CTR069956
Contract number
CTR069956
Issued by
Arizona

About this file

The document is a detailed payment schedule (CTR069956) for a state or local government contract, specifically an Excel spreadsheet outlining payment milestones for a technology implementation project. While the specific state or agency is not explicitly named, the document provides a comprehensive breakdown of deliverables, associated payments, and project timelines spanning from May 2024 to August 2029.

The contract appears to be for a complex system implementation, with a total contract value of $5,454,145.00, comprised of $3,426,445.00 for implementation and $2,027,700.00 for maintenance, hosting, and licensing. The payment structure includes incremental deliverable payments with 10% holdbacks, broken into multiple phases such as project kickoff, system design, user stories, sprint showcases, data conversion, testing, training, and go-live. The contract includes a 3-month warranty period and six years of maintenance and support (with years 2-5 at $399,600 annually and prorated first and last years at different rates). Key milestones are scheduled between May 2024 and August 2029, with payment triggers tied to specific project deliverables and performance benchmarks.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

CTR069956 - PAYMENT SCHEDULE
Added items as agreed by Agency and Supplier to be part of payment schedule
Task NameFinishPaymentHoldbackNet Invoice
Contract Signing5/13/24$260,000.00$26,000.00$234,000.00
Deliverable 1 - Project Kickoff Meeting5/13/24$31,664.45$3,166.45$28,498.01
Deliverable 2 - Project Management Plan and Subsections6/6/24$94,993.35$9,499.34$85,494.02
Deliverable 3a - System Design/Gap Sessions and Gap Notes (Sprints 1 - 3)5/31/24$126,657.80$12,665.78$113,992.02
Deliverable 3b - System Design/Gap Sessions and Gap Notes (Sprint 4 & 5)7/26/24$126,657.80$12,665.78$113,992.02
Deliverable 3c - System Design/Gap Sessions and Gap Notes (Sprint 6 & 7)8/16/24$126,657.80$12,665.78$113,992.02
Deliverable 3d - System Design/Gap Sessions and Gap Notes (Sprints 8 & 9)10/18/24$126,657.80$12,665.78$113,992.02
Deliverable 3e - System Design/Gap Sessions and Gap Notes (Sprint 10 & 11)11/29/24$126,657.80$12,665.78$113,992.02
Deliverable 3f - System Design/Gap Sessions and Gap Notes (Sprint 12)12/20/24$63,328.90$6,332.89$56,996.01
Deliverable 4a - Updated User Stories (Sprints 1 - 3)6/28/24$126,657.80$12,665.78$113,992.02
Deliverable 4b - Updated User Stories (Sprints 4 & 5)8/2/24$94,993.35$9,499.34$85,494.02
Deliverable 4c - Updated User Stories (Sprints 6 & 7)9/13/24$94,993.35$9,499.34$85,494.02
Deliverable 4d - Updated User Stories (Sprints 8 & 9)10/25/24$94,993.35$9,499.34$85,494.02
Deliverable 4e - Updated User Stories (Sprint 10 & 11)12/6/24$94,993.35$9,499.34$85,494.02
Deliverable 4f - Updated User Stories (Sprint 12)12/27/24$94,993.35$9,499.34$85,494.02
Deliverable 5a - SPRINT SHOWCASE 1 (DEMO Sprint 1 & 2)8/16/24$158,322.25$15,832.23$142,490.03
Deliverable 5b - SPRINT SHOWCASE 2 (DEMO Sprint 3 & 4)9/27/24$158,322.25$15,832.23$142,490.03
Deliverable 5c - SPRINT SHOWCASE 3 (DEMO Sprint 5 & 6)11/8/24$158,322.25$15,832.23$142,490.03
Deliverable 5d - SPRINT SHOWCASE 4 (DEMO Sprint 7 & 8)12/20/24$158,322.25$15,832.23$142,490.03
Deliverable 5e - SPRINT SHOWCASE 5 (DEMO Sprint 9 & 10 )1/31/25$158,322.25$15,832.23$142,490.03
Deliverable 5f - SPRINT SHOWCASE 6 (DEMO Sprint 11 & 12)3/14/25$158,322.25$15,832.23$142,490.03
Deliverable 6a - Data Conversion for UAT3/14/25$189,986.70$18,998.67$170,988.03
Deliverable 6b - Data Conversion for Implementation5/16/25$94,993.35$9,499.34$85,494.02
Deliverable 7 - Final Test Plan and Test Cases3/14/25$31,664.45$3,166.45$28,498.01
Deliverable 8 - UAT Support4/24/25$158,322.25$15,832.23$142,490.03
Deliverable 9a - Initial Training Plan and Materials3/14/25$63,328.90$6,332.89$56,996.01
Deliverable 9b - Final Training Plan and Materials4/17/25$31,664.45$3,166.45$28,498.01
Deliverable 9c - User Training5/8/25$94,993.35$9,499.34$85,494.02
Deliverable 10 - Installation Go-Live/Operation of System Software5/16/25$126,657.80$12,665.78$113,992.02
Deliverable 11a - Start of UAT - 50% Holdback Released3/17/25$171,322.25
Deliverable 11b - End of 90-day Warranty - 50% Holdback Released8/15/25$171,322.25
Implementation:$ 3,426,445.00$ 342,644.50$ 3,426,445.00
Maintenance, Hosting, and License Fee - Year 1 (Prorated to include 3-Month Warranty with no-cost Maintenance and Support )8/15/25$329,400.00
Maintenance, Hosting, and License Fee - Year 28/15/26$399,600.00
Maintenance, Hosting, and License Fee - Year 38/15/27$399,600.00
Maintenance, Hosting, and License Fee - Year 48/15/28$399,600.00
Maintenance, Hosting, and License Fee - Year 58/15/29$399,600.00
Maintenance, Hosting, and License Fee - Year 6 (Prorated to 3 months to complete total 5 Years of Maintenance and Support after Warranty)8/15/30$99,900.00
Total Maintenance, Hosting, and Licensing:$2,027,700.00
Total Contract Value:$5,454,145.00

File details come from the government source that posted it. Updated .