ATTM 011 CDML.docx

DOCX document 185 KB Posted

Attached to
BABYNET IDEA PART C
Solicitation number
5400018456
Issued by
Richland County, South Carolina

About this file

BABYNET IDEA PART C - Consolidated Deliverables Management List

This document is a Consolidated Deliverables Management List (CDML) established by the South Carolina Department of Health and Human Services (SCDHHS) Project Management Office to define and manage deliverables for contractors and vendors engaged on SCDHHS projects. The CDML serves as the standard template for identifying and tracking quantifiable goods and services—both tangible and intangible—that contractors must provide throughout the project lifecycle. All deliverables listed are owned by the State of South Carolina and are classified into five primary categories: Governance and Project Management, Security, Transition to Operations (Post-Implementation), and Systems/Software Development. Contractors must submit deliverables electronically by close of business (5:00 p.m. Eastern Time) unless otherwise specified. Deliverables include foundational project management documents such as Project Status Reports (due weekly by Thursday), Project Schedules (due within 30 calendar days of project kickoff with weekly updates), and Decisions, Assumptions, Constraints Lists and Action Items (due within 10 calendar days of contract start with weekly updates thereafter).

The CDML encompasses 44 standard deliverables organized across multiple project phases, including comprehensive Project Management Plans adhering to SCDHHS PMO requirements in areas such as Risk Management, Issue Management, Change Management, Communications, Scope, Staff, Cost, Schedule, Requirements, and Quality Management. All plans require contractor adherence within 10 calendar days of project kickoff. Technical deliverables include Requirements Documents, Requirements Traceability Matrices, Functional and Technical Design Specifications, logical and physical data models, and data dictionaries. Security-related deliverables comprise System Security Plans (due 60-120 calendar days post-kickoff), Information Security Risk Assessments (due 150 calendar days post-kickoff), Privacy Impact Assessments, and Disaster Recovery and Business Continuity Plans requiring 24-hour Recovery Time Objectives and 8-hour Recovery Point Objectives. Testing deliverables include Master Test Plans, User Acceptance Test Plans, Test Status Reports (submitted weekly during applicable phases), Test Estimation Templates, Inspection Logs, Performance Test Plans, Test Scenarios, Test Cases, and Test Closure Reports. Additional deliverables address implementation, training, help desk operations, user manuals, system utilization reports (due 30 business days pre-Go-Live with monthly submissions thereafter), interface control documents, and data conversion plans. Updates to most recurring deliverables occur annually unless specified otherwise, with initial submissions requiring preliminary, baseline, and final status designations as applicable.

View the file

Other files

File Type Posted
PL 008 TRA RAW DATA LAKE.docx DOCX document
ATTM 007 CERTIFICATION FOR CONTRACTS GRANTS LOANS AND COOPERATIV.docx DOCX document
ATTM 013 EXPERIENCE TABLE.docx DOCX document
ATTM 010 QUESTIONS TEMPLATE.docx DOCX document
ATTM 006 ORGANIZATIONAL CONFLICT OF INTEREST DISCLOSURE.docx DOCX document
PL 006 TRA MANAGED FILE TRANSFER.docx DOCX document
Award Extension.pdf PDF
PL 002 TRA INTEGRATION HUB.docx DOCX document
ATTM 008 BABYNET PRICING TABLES EXAMPLE.xls XLS spreadsheet
ATTM 009 BABYNET PRICING TABLES BLANK.xls XLS spreadsheet
PL 003 TRA ENTERPRISE SERVICE BUS.docx DOCX document
ATTM 001 IMPORTANT NOTICE - NONRESIDENTS ONLY.docx DOCX document
ATTM 014 LIST OF INCLUDED SYSTEM REPORTS.docx DOCX document
ATTM 004 DISCLOSURE OF OWNERSHIP.docx DOCX document
PL 004 TRA WEB SERVICES.docx DOCX document
ATTM 002 OFFERORS CHECKLIST.docx DOCX document
ATTM 003 CERTIFICATION REGARDING DEBARMENT SUSPENSION INELIGIBIL.docx DOCX document
PL 007 TRA ENTERPRISE DATA SERVICES.docx DOCX document
PL 011 OandM MANUAL TEMPLATE.pdf PDF
ATTM 012 SERVICE LEVEL AGREEMENTS (SLA).docx DOCX document
Solicitation.pdf PDF
PL 005 TRA EXTRACT TRANSFORM LOAD.docx DOCX document
Award Notice.pdf PDF
Amendment #1.pdf PDF
ATTM 015 SPSAQ (REVISED).docx DOCX document
PL 009 TRA OPERATIONAL DATA STORE.docx DOCX document
PL 001 ELECTRONIC DATA INTERCHANGE (EDI).pdf PDF
Amendment #2.pdf PDF
PL 010 IDEA PART C DATA COLLECTION REGULATIONS.docx DOCX document
ATTM 005 HIPAA BAA.docx DOCX document
ATTM 016 Qestions and Answers.xlsx XLSX spreadsheet
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCDHHS Project Management Office

CONSOLIDATED DELIVERABLES MANAGEMENT LIST

1.0 INTRODUCTION

The South Carolina Department of Health and Human Services (SCDHHS) defines a deliverable as a quantifiable good or service that will be provided or adhered to throughout the Project Lifecycle. Deliverables can be tangible or intangible, and are most often specified functions or characteristics of the project. The following tangible deliverables are included as part of the Consolidated Deliverables Management List (CDML) applicable to (SCDHHS) contractors managed in accordance with the Contractor (Vendor) Management Plan. The deliverables listed herein are the expected minimum list for SCDHHS third-party contracts. Depending on the scope of work (SOW), SCDHHS may include additional deliverables to this list or exclude by exception only. Therefore, this is not an all-inclusive list.

Unless otherwise indicated in the specific deliverable list below, deliverables will be submitted electronically by close of business (COB) at SCDHHS (5:00 p.m. Eastern Time). The ‘data rights of ownership’ for each deliverable is the State of South Carolina. Unless otherwise specified within the individual deliverable, any updates to a deliverable after the initial submission and SCDHHS’ approval will be communicated minimally on an annual basis.

Project-based deliverables are documented, monitored, measured and reported via the SCDHHS defined method (e.g., Schedule Management Plan, Communications Management Plan, etc.) throughout the contracted life of the projects lifecycle.

2.0 CONSOLIDATED DELIVERABLES MANAGEMENT LIST

2.1 BASIC TEMPLATE FIELDS

Item Number
This field contains the prefix of ‘D-‘ and then the 3-digit number (e.g., D-001) correlating to the deliverable name
Deliverable Name
This field contains the SCDHHS approved deliverable name
SCDHHS Owner(s)
SCDHHS Approver(s)
Vendor Owner(s)
Vendor Approver(s)
Type of Data
|_|Governance or Project Management|_|Other: ___________________________________
|_|Security|_|Transition to Operations (Post-Implementation)
|_|Systems/Software Development

This field is a checkbox categorizing the deliverable’s ‘Type of Data’

Submission Due Indicator
|_|Initial

|_| Recurring |_| Not Applicable (N/A)

Type of Deliverable Due: |_| Submission |_| Adherence

Status
Initial
|_|Preliminary|_|Baseline
|_|Final
|_|Not Applicable (N/A)

This field is contains the applicable status checkbox(es) for an initial deliverable.

Recurring
|_|Annual Update|_|Other: ________________
|_|Not Applicable (N/A)

When a recurring submission, the Status can be either ‘Annual Update’, ‘N/A’, or ‘Other: as specified’

Deliverable Specification
This field is the Submission Due description in conjunction with the Submission Due Indicator checkbox(es) indicating the SCDHHS approved submission due date for the deliverable (e.g., Project Kickoff plus (+) five (5) business days; Within ten (10) calendar days from approved project kick-off date, weekly, etc.).
Note
This field provides the detailed explanation when SCDHHS indicates the deliverable status is ‘N/A’ or for special instructions
Description
This field provides the detailed description of the SCDHHS required deliverable

2.2 SCDHHS Standard Deliverables List

Item Number
D-001
Deliverable Name
Project Status Report
SCDHHS Owner(s)
SCDHHS Approver(s)
Vendor Owner(s)
Vendor Approver(s)
Type of Data
|X|Governance or Project Management|_|Other: ___________________________________
|_|Security|_|Transition to Operations (Post-Implementation)
|_|Systems/Software Development
Submission Due Indicator
|X|Initial
|X|Recurring
|_|Not Applicable (N/A)
Type of Deliverable Due: |X| Submission |_| Adherence
Status
Initial
|X|Preliminary|_|Baseline
|_|Final
|_|Not Applicable (N/A)
Recurring
|_|Annual Update|X|Other: Weekly
|_|Not Applicable (N/A)
Deliverable Specification
The Contractor (Vendor)’s initial Project Status Report submission is due ten (10) calendar days from the contract start date.

The recurring project status reports are weekly due by Close of Business (COB) each Thursday.

Note
Recurring project status reports are required using the SCDHHS PMO Microsoft® Project Web App (PWA) online status report template.
Description
Project related status reports will be produced during the life of the project.

The project status report is to outline progress toward the information related to the overall status of project delivery. The status reports will be produced weekly to provide stakeholders project information on the status and progress of the project’s delivery. The information provided will contain enough detail to allow stakeholders to make informed decisions and maintain oversight of the project.

At a minimum the reports will contain:

· Overall project status

· Deliverables, milestones, key activities accomplished

· Status of issues and/or risks

· Upcoming key tasks

· Upcoming deliverables and milestones

· Cost Performance Index (CPI)

· Schedule Performance Index (SPI)

· Key decisions made or needed Please refer to the SCDHHS PMO Communications Management Plan and Schedule Management Plan for additional information.

Item Number
D-002
Deliverable Name
Project Schedule
SCDHHS Owner(s)
SCDHHS Approver(s)
Vendor Owner(s)
Vendor Approver(s)
Type of Data
|X|Governance or Project Management|_|Other: ___________________________________
|_|Security|_|Transition to Operations (Post-Implementation)
|_|Systems/Software Development
Submission Due Indicator
|X|Initial
|X|Recurring
|_|Not Applicable (N/A)
Type of Deliverable Due: |X| Submission |_| Adherence
Status
Initial
|X|Preliminary|_|Baseline
|_|Final
|_|Not Applicable (N/A)
Recurring
|_|Annual Update|X|Other: Weekly
|_|Not Applicable (N/A)
Deliverable Specification
The Contractor (Vendor)’s initial project schedule submission is due thirty (30) calendar days from the project kickoff date. The project schedule will not be baselined by the Contractor (Vendor) until SCDHHS approves the project schedule.

Recurring project schedule updates are weekly due by COB each Thursday.

Note
Recurring project schedule updates are required using the SCDHHS PMO Project Web App (PWA)
Description
Project schedules will be developed and maintained during the life of the project. The project schedule is to a formal, approved document used to guide both project execution and project control and serves as a roadmap for managing project activities.

The contractor (vendor) is expected to utilize the SCDHHS PMO project schedule basic template requirements. Use of an Integrated Master Schedule (IMS) may be required to organize and link multiple project schedules.

The primary functions of the project schedule are to document planning assumptions and decisions, facilitate communication among stakeholders, and document approved scope, cost, and schedule baselines

Please refer to the SCDHHS PMO Schedule Management Plan for additional information.

Item Number
D-003
Deliverable Name
Decisions, Assumptions, Constraints Lists, and Action Items
Type of Data
|X|Governance or Project Management|_|Other: ___________________________________
|_|Security|_|Transition to Operations (Post-Implementation)
|_|Systems/Software Development
Submission Due Indicator
|X|Initial
|X|Recurring
|_|Not Applicable (N/A)
Type of Deliverable Due: |X| Submission |_| Adherence
Status
Initial
|X|Preliminary|_|Baseline
|_|Final
|_|Not Applicable (N/A)
Recurring
|_|Annual Update|X|Other: Weekly
|_|Not Applicable (N/A)
Deliverable Specification
The Contractor (Vendor)’s submission of the initial lists for decisions, assumptions, constraints, and actions items are due ten (10) calendar days from the contract start date. They are updated and maintained through project delivery.

The recurring list updates are due weekly by COB each Thursday.

Note
Recurring decision, assumption, and/or constraint updates are required using the SCDHHS PMO Microsoft Project Web App (PWA)
Description
Decisions, assumptions, and constraints identified during the life of the project need to be documented and maintained.
Item Number
D-004
Deliverable Name
SCDHHS PMO Project Management Plan (PMP) –

Risk Management Plan

Type of Data
|X|Governance or Project Management|_|Other: ___________________________________
|_|Security|_|Transition to Operations (Post-Implementation)
|_|Systems/Software Development
Submission Due Indicator
|X|Initial
|_|Recurring
|_|Not Applicable (N/A)
Type of Deliverable Due: |_| Submission |X| Adherence
Status
Initial
|_|Preliminary|_|Baseline
|X|Final
|_|Not Applicable (N/A)
Recurring
|_|Annual Update|_|Other: ________________
|_|Not Applicable (N/A)
Deliverable Specification
PROJECT KICKOFF + ten (10) calendar days, the Contractor (Vendor) will adhere to the SCDHHS PMO Risk Management Plan requirements as well as the related risk processes and procedures.
Note
The SCDHHS PMO is the owner of the Risk Management Plan at an Enterprise level. The contractor (vendor) will be notified and provided an updated copy if changes are made to this PMP.
Description
A risk is an event or condition that, if it occurs, could have a negative effect or create a positive opportunity on the program’s or a project’s objectives. A negative risk is an undesirable or unexpected event that if occurred it would cause an unfavorable impact on the program’s or project’s scope, cost, schedule, technical, and/or quality aspect. A positive opportunity is an event or condition that if occurred could potentially produce a favorable outcome for the program or project.

The Risk Management Plan defines how risks associated with SCDHHS programs or projects are identified, analyzed, and managed. It outlines how risk management activities are recorded, performed, and monitored throughout the lifecycle of the various projects in the portfolio and provides templates and practices for prioritizing risks by SCDHHS leadership.

The Risk Management Plan also provides standard terminology, clear roles and responsibilities; a detailed description of the risk management process; and the standard templates and tools used in the risk management process. It is designed to guide the PMO, program teams, project teams and other SCDHHS stakeholders for consistent risk management activities.

The primary objective of the risk management process is to ensure that risks are evaluated quantitatively and qualitatively; mechanisms to mitigate or eliminate risks are selected; and the success of the risk mitigation techniques are continuously monitored, measured, and reported.

The Risk Management Plan is a core document for PMO governance activities.

Item Number
D-005
Deliverable Name
SCDHHS PMO Project Management Plan (PMP) –

Issue Management Plan

Type of Data
|X|Governance or Project Management|_|Other: ___________________________________
|_|Security|_|Transition to Operations (Post-Implementation)
|_|Systems/Software Development
Submission Due Indicator
|X|Initial
|_|Recurring
|_|Not Applicable (N/A)
Type of Deliverable Due: |_| Submission |X| Adherence
Status
Initial
|_|Preliminary|_|Baseline
|X|Final
|_|Not Applicable (N/A)
Recurring
|_|Annual Update|_|Other: ________________
|_|Not Applicable (N/A)
Deliverable Specification
PROJECT KICKOFF + ten (10) calendar days, the Contractor (Vendor) will adhere to the SCDHHS PMO Issue Management Plan requirements as well as the related issue management processes and procedures.
Note
The SCDHHS PMO is the owner of the Issue Management Plan at an Enterprise level. The contractor (vendor) will be notified and provided an updated copy if changes are made to this PMP.
Description
An issue is an item or event that has already occurred, therefore it must be acknowledged, managed and resolved immediately. Once identified and implemented, resolutions to any issue have the potential to impact the programs or project’s scope, cost, schedule, technical, and/or quality aspect and therefore may invoke the change management process.

The Issue Management Plan defines how issues associated with SCDHHS programs or projects are identified, analyzed, and managed. It outlines how issue management activities are performed, recorded, and monitored throughout the lifecycle of the various projects and provides templates and practices for documenting and prioritizing issues by SCDHHS leadership.

The overall goal of issue management is to protect the project from the negative impact of issues or unsatisfactory completion.

The objectives of issue management are as follows:

Ensure issues are documented in a standard and consistent manner Monitor a project to identify new or changing issues Analyze the issue to minimize the cost and other impacts Escalate issues where appropriate to acquire timely resolution Focus management’s attention on higher priority issues Make issue-related decisions at the proper level of authority (i.e. resolution activities, issue transference, closure, etc.)

Communicate clearly about issues with the team and project stakeholders Monitor, measure and report issues in a consistent manner to ensure appropriate management occurs through resolution Maintain a clear and accurate record of issues and related actions over the life of the project The Issue Management Plan is a core document for PMO governance activities.

Item Number

D-006
Deliverable Name
SCDHHS PMO Project Management Plan (PMP) –

Change Management Plan

Type of Data
|X|Governance or Project Management|_|Other: ___________________________________
|_|Security|_|Transition to Operations (Post-Implementation)
|_|Systems/Software Development
Submission Due Indicator
|X|Initial
|_|Recurring
|_|Not Applicable (N/A)
Type of Deliverable Due: |_| Submission |X| Adherence
Status
Initial
|_|Preliminary|_|Baseline
|X|Final
|_|Not Applicable (N/A)
Recurring
|_|Annual Update|_|Other: ________________
|_|Not Applicable (N/A)
Deliverable Specification
PROJECT KICKOFF + ten (10) calendar days, the Contractor (Vendor) will adhere to the SCDHHS PMO Change Management Plan requirements as well as the related change management processes and procedures.
Note
The SCDHHS PMO is the owner of the Change Management Plan at an Enterprise level. The contractor (vendor) will be notified and provided an updated copy if changes are made to this PMP.
Description
A change is a modification that affects: a project’s baselined scope, schedule, or cost/budget; non-maintenance Information Technology (IT) maintenance related to technical or network infrastructure/systems, databases, etc.; and/or SCDHHS Deputy Area policy-based initiatives which require the discipline of formal change management.

Change Management is the formal process for identifying and requesting, analyzing, reviewing, escalating, communicating, implementing, monitoring, measuring and reporting of SCDHHS changes in a defined, consistent and repeatable manner.

The change management process provides the mechanism for allowing SCDHHS leadership and other stakeholders to effectively prioritize changes, evaluate progress, manage costs and communicate status of identified changes.

The Change Management Plan outlines how change management activities will be performed, recorded and monitored including documenting and prioritizing approved changes.

The scope of change management includes the following:

Changes provide value to the program or project and are applicable to: Project Schedule, Budget/Cost, and/or Scope;

Non-project changes which includes IT Technical changes considered non-maintenance; and/or SCDHHS Deputy Areas’ policy-based initiatives Changes will follow a defined, repeatable process to ensure routine changes are completed with minimal restrictions while complex, high impact changes receive the necessary oversight.

The Change Management Plan is a core document for PMO governance activities.

Item Number
D-007
Deliverable Name
SCDHHS PMO Project Management Plan (PMP) –

Communications Management Plan

SCDHHS Owner(s)
SCDHHS Approver(s)
Vendor Owner(s)
Vendor Approver(s)
Type of Data
|X|Governance or Project Management|_|Other: ___________________________________
|_|Security|_|Transition to Operations (Post-Implementation)
|_|Systems/Software Development
Submission Due Indicator
|X|Initial
|_|Recurring
|_|Not Applicable (N/A)
Type of Deliverable Due: |_| Submission |X| Adherence
Status
Initial
|_|Preliminary|_|Baseline
|X|Final
|_|Not Applicable (N/A)
Recurring
|_|Annual Update|_|Other: ________________
|_|Not Applicable (N/A)
Deliverable Specification
PROJECT KICKOFF + ten (10) calendar days, the Contractor (Vendor) will adhere to the SCDHHS PMO Communications Management Plan requirements as well as the related communication management processes and procedures.
Note
The SCDHHS PMO is the owner of the Communications Management Plan at an Enterprise level. The contractor (vendor) will be notified and provided an updated copy if changes are made to this PMP.

The purpose of the Communications Management Plan is to outline the communication management approach, methodology, and tools used to provide a unified communication framework for sharing accurate information with stakeholders (both internal and external) to ensure the positive impact SCDHHS program and projects in the portfolio. The approved communication management process ensures a defined, documented, repeatable and measurable process exists for successful quality management.

The Communications Management Plan defines how communications associated with SCDHHS programs or projects will be identified, created, approved, managed and distributed. It outlines how communications-related activities will be performed, recorded, and monitored throughout the lifecycle of the various projects and provides templates and practices for documenting and prioritizing communication artifacts by SCDHHS leadership.

The approach to communications management throughout any SCDHHS program and project in the portfolio is intended to be defined for each of two levels;

· Level 1 – Basic Internal SCDHHS-related Communications, and

· Level 2 – Advanced Internal SCDHHS-related Communications and External-facing Communications.

SCDHHS intends to work collaboratively with internal and external stakeholders during the life of the project in order to ensure a seamless approach to communications. Open, ongoing communication between stakeholders is critical to the success of all PMO projects

The Communications Management Plan is a core document for PMO governance activities.

Item Number
D-008
Deliverable Name
SCDHHS PMO Project Management Plan (PMP) –

Scope Management Plan

Type of Data
|X|Governance or Project Management|_|Other: ___________________________________
|_|Security|_|Transition to Operations (Post-Implementation)
|_|Systems/Software Development
Submission Due Indicator
|X|Initial
|_|Recurring
|_|Not Applicable (N/A)
Type of Deliverable Due: |_| Submission |X| Adherence
Status
Initial
|_|Preliminary|_|Baseline
|X|Final
|_|Not Applicable (N/A)
Recurring
|_|Annual Update|_|Other: ________________
|_|Not Applicable (N/A)
Deliverable Specification
PROJECT KICKOFF + ten (10) calendar days, the Contractor (Vendor) will adhere to the SCDHHS PMO Scope Management Plan requirements as well as the related scope management processes and procedures.
Note
The SCDHHS PMO is the owner of the Scope Management Plan at an Enterprise level. The contractor (vendor) will be notified and provided an updated copy if changes are made to this PMP.
Description
Scope Management includes defining a program or project’s scope statement and managing all the approved work, while excluding unnecessary work, through a formal process(es) which includes monitoring, controlling and reporting in a defined, consistent and repeatable manner for successful quality management.

Scope Management typically follows a five-step process to include:

1) Collect Requirements,

2) Define Scope,

3) Create the work breakdown structure (WBS),

4) Verify Scope, and

5) Monitor and Control Scope.

The purpose of the Scope Management Plan is to outline the scope management approach, methodology, and tools used to define, develop, verify, monitor, control and report scope-related work and components that could impact SCDHHS program and/or projects in the portfolio.

Other program or project components which may directly affect scope management include at a minimum:

· Identifying new or missed requirements

· Changes to the baseline project schedule

· Variation in budget or costs The Scope Management Plan is a core document for PMO governance activities.

Item Number
D-009
Deliverable Name
SCDHHS PMO Project Management Plan (PMP) –

Staff Management Plan

Type of Data
|X|Governance or Project Management|_|Other: ___________________________________
|_|Security|_|Transition to Operations (Post-Implementation)
|_|Systems/Software Development
Submission Due Indicator
|X|Initial
|_|Recurring
|_|Not Applicable (N/A)
Type of Deliverable Due: |_| Submission |X| Adherence
Status
Initial
|_|Preliminary|_|Baseline
|X|Final
|_|Not Applicable (N/A)
Recurring
|_|Annual Update|_|Other: ________________
|_|Not Applicable (N/A)
Deliverable Specification
PROJECT KICKOFF + ten (10) calendar days, the Contractor (Vendor) will adhere to the SCDHHS PMO Staff Management Plan requirements as well as the related staff management processes and procedures.
Note
The SCDHHS PMO is the owner of the Staff Management Plan at an Enterprise level. The contractor (vendor) will be notified and provided an updated copy if changes are made to this PMP.
Description
The purpose of the Staff Management Plan is to outline the staff management approach, methodology and tools used to define, manage, verify, monitor, control and report staff-related components of the SCDHHS program and/or project(s) in the portfolio. The approved staff management process ensures a defined, documented, repeatable and measurable process exists for successful quality management.

The Project’s Leadership or Designee plans for necessary staff for the duration of the project during the Inception, Concept and Planning Phase of the project. Staff planning and estimating occurs to identify the necessary state and contractor roles needed. In addition, staff planning and estimating identifies each specific role and the role’s timeframe assigned to the project. The staff planning and estimating model directly affects the project’s overall budget.

The plan also describes the planning, acquisition and management of both state staff and consulting or contractor staff and describes the responsibilities assigned to key staff roles.

The Staff Management Plan is a core document for PMO governance activities.

Item Number
D-010
Deliverable Name
SCDHHS PMO Project Management Plan (PMP) –

Cost Management Plan

Type of Data
|X|Governance or Project Management|_|Other: ___________________________________
|_|Security|_|Transition to Operations (Post-Implementation)
|_|Systems/Software Development
Submission Due Indicator
|X|Initial
|_|Recurring
|_|Not Applicable (N/A)
Type of Deliverable Due: |_| Submission |X| Adherence
xStatus
Initial
|_|Preliminary|_|Baseline
|X|Final
|_|Not Applicable (N/A)
Recurring
|_|Annual Update|_|Other: ________________
|_|Not Applicable (N/A)
Deliverable Specification
PROJECT KICKOFF + ten (10) calendar days, the Contractor (Vendor) will adhere to the SCDHHS PMO Cost Management Plan requirements as well as the related cost management processes and procedures.
Note
The SCDHHS PMO is the owner of the Cost Management Plan at an Enterprise Level. The contractor (vendor) will be notified and provided an updated copy if changes are made to this PMP.
Description
The purpose of the Cost Management Plan is to outline the cost management approach, methodology and tools used to identify and estimate costs, analyze expenditures and variances, track and reconcile estimates to invoices, monitor, control and report actual cost/budget expenditures. The approved cost management process ensures a defined, documented, repeatable and measurable process exists for successful quality management.

Cost management includes estimating, tracking, and controlling expenditures related to all SCDHHS major projects, system-based changes, IT equipment (i.e., infrastructure, hardware, software) and staff (i.e., contract and non-contract) costs.

The Cost Management Plan is a core document for PMO governance activities.

Item Number
D-011
Deliverable Name
SCDHHS PMO Project Management Plan (PMP) –

Schedule Management Plan

Type of Data
|X|Governance or Project Management|_|Other: ___________________________________
|_|Security|_|Transition to Operations (Post-Implementation)
|_|Systems/Software Development
Submission Due Indicator
|X|Initial
|_|Recurring
|_|Not Applicable (N/A)
Type of Deliverable Due: |_| Submission |X| Adherence
Status
Initial
|_|Preliminary|_|Baseline
|X|Final
|_|Not Applicable (N/A)
Recurring
|_|Annual Update|_|Other: ________________
|_|Not Applicable (N/A)
Deliverable Specification
PROJECT KICKOFF + ten (10) calendar days, the Contractor (Vendor) will adhere to the SCDHHS PMO Schedule Management Plan requirements as well as the related schedule management processes and procedures.
Note
The SCDHHS PMO is the owner of the Schedule Management Plan at an Enterprise level. The contractor (vendor) will be notified and provided an updated copy if changes are made to this PMP.
Description
The project schedule is a formal, approved document used to guide both project execution and project control and serves as a roadmap for managing project activities throughout the life of the project. The primary functions of the project schedule are to document planning assumptions and decisions, facilitate communication among stakeholders, and document approved scope, cost, and schedule baselines. Project schedules are an important part of any project as they provide the project team, sponsor, and stakeholders a snapshot of the project’s status at any given time. The approved schedule management process ensures a defined, documented, repeatable and measurable process exists for successful quality management.

The Schedule Management Plan is a core document for PMO governance activities.

Item Number
D-012
Deliverable Name
SCDHHS PMO Project Management Plan (PMP) –

Requirements Management Plan

Type of Data
|X|Governance or Project Management|_|Other: ___________________________________
|_|Security|_|Transition to Operations (Post-Implementation)
|_|Systems/Software Development
Submission Due Indicator
|X|Initial
|_|Recurring
|_|Not Applicable (N/A)
Type of Deliverable Due: |_| Submission |X| Adherence
Status
Initial
|_|Preliminary|_|Baseline
|X|Final
|_|Not Applicable (N/A)
Recurring
|_|Annual Update|_|Other: ________________
|_|Not Applicable (N/A)
Deliverable Specification
PROJECT KICKOFF + ten (10) calendar days, the Contractor (Vendor) will adhere to the SCDHHS PMO Requirements Management Plan requirements as well as the related requirements management processes and procedures.
Note
The SCDHHS PMO is the owner of the Requirements Management Plan at an Enterprise level. The contractor (vendor) will be notified and provided an updated copy if changes are made to this PMP.
Description
The purpose of the Requirements Management Plan is to outline the requirements management approach, methodology, and tools used to define, manage, verify, monitor, control and report requirements-related components of the SCDHHS program and/or project(s) in the portfolio. The approved requirements management process ensures a defined, documented, repeatable and measurable process exists for successful quality management.

Requirements Management is the process of gathering, documenting, analyzing, tracing, prioritizing, and validating requirements. This also includes the requirements are implemented in accordance to standards and based on in scope of the program or project. Finally, controlling requirements in a defined, consistent and repeatable manner is inclusive of the requirements management process.

A requirement is a function or capability to which a project outcome should conform and meet the expectations of the customer and internal and external stakeholders. Requirements will be defined and managed throughout the life of the project via requirements traceability.

The Requirements Management Plan is a core document for PMO governance activities.

Item Number
D-013
Deliverable Name
SCDHHS PMO Project Management Plan (PMP) –

Quality Management Plan

Type of Data
|X|Governance or Project Management|_|Other: ___________________________________
|_|Security|_|Transition to Operations (Post-Implementation)
|_|Systems/Software Development
Submission Due Indicator
|X|Initial
|_|Recurring
|_|Not Applicable (N/A)
|_|Not Applicable (N/A)
Type of Deliverable Due: |_| Submission |X| Adherence
Status
Initial
|_|Preliminary|_|Baseline
|X|Final
|_|Not Applicable (N/A)
Recurring
|_|Annual Update|_|Other: ________________
|_|Not Applicable (N/A)
Deliverable Specification
PROJECT KICKOFF + ten (10) calendar days, the Contractor (Vendor) will adhere to the SCDHHS PMO Quality Management Plan requirements as well as the related quality management processes and procedures.
Note
The SCDHHS PMO is the owner of the Quality Management Plan at an Enterprise level. The contractor (vendor) will be notified and provided an updated copy if changes are made to this PMP.
Description
The Quality Management Plan details the approach, method, processes and any tools that the QMO will use to independently examine, review and assess SCDHHS project delivery processes.

This plan describes the approach to measuring the quality of work being performed, assessing compliance and incorporating continuous improvement across the project delivery area. The SCDHHS Quality Management Plan is built for:

Quality Planning Quality Assurance (QA) Quality Control (QC) Quality/Continuous Improvement

A well-established and disciplined quality management framework drastically reduces the risk of failure or unacceptable delays for completion, reduces the number and types of defects, understands the root cause of defects, demonstrates end-to-end requirements traceability, allows for more thorough and results-driven testing and provides thorough documented evidence throughout the life of the project.

All SCDHHS projects are subject to quality reviews. Quality reviews include evaluating services, processes and/or activities provided and comparing evaluation results with the accepted standards. Deviations from stated requirements or acceptable results are considered deficiencies and identified for improvement.

The Quality Management Plan is a core document for PMO governance activities.

Item Number
D-014
Deliverable Name
SCDHHS PMO Project Management Plan (PMP) –

Contractor Management Plan

Type of Data
|X|Governance or Project Management|_|Other: ___________________________________
|_|Security|_|Transition to Operations (Post-Implementation)
|_|Systems/Software Development
Submission Due Indicator
|X|Initial
|_|Recurring
|_|Not Applicable (N/A)
Type of Deliverable Due: |_| Submission |X| Adherence
Status
Initial
|_|Preliminary|_|Baseline
|X|Final
|_|Not Applicable (N/A)
Recurring
|_|Annual Update|_|Other: ________________
|_|Not Applicable (N/A)
Deliverable Specification
PROJECT KICKOFF + ten (10) calendar days, the Contractor (Vendor) will adhere to the SCDHHS PMO Contractor Management Plan requirements as well as the related contractor management processes and procedures.
Note
The SCDHHS PMO is the owner of the Contractor Management Plan at an Enterprise level. The contractor (vendor) will be notified and provided an updated copy if changes are made to this PMP.
Description
SCDHHS has many contractors (i.e., contractor(s) engaged to provide approved services in accordance with their specific contract terms. A contractor’s scope of work (SOW) may be integrated with other contractors’ SOW with the goal for SCDHHS to have a fully integrated and successfully operational State Medicaid Agency (SMA).

Having consistent and well-defined deliverables and a process to manage these deliverables are critical for effective contractor management as well as successful project delivery. To this end, SCDHHS must identify and manage the contractor’s contracted deliverables throughout the life of the project.

The Contractor (Vendor) Management Plan identifies the process, procedures and tools used to identify and manage deliverables during the life of the project and includes this Consolidated Deliverables Management List and contains the SCDHHS Deliverables Management process.

An approved deliverables management process ensures a defined, documented, repeatable and measurable process exists for successful quality management.

The Contractor (Vendor) Management Plan is a core document for PMO governance activities.

Item Number
D-015
Deliverable Name
Requirements Document (RD)
SCDHHS Owner(s)
SCDHHS Approver(s)
Vendor Owner(s)
Vendor Approver(s)
Type of Data
|X|Governance or Project Management|_|Other: ___________________________________
|_|Security|_|Transition to Operations (Post-Implementation)
|_|Systems/Software Development
Submission Due Indicator
|X|Initial
|_|Recurring
|_|Not Applicable (N/A)
Type of Deliverable Due: |X| Submission |_| Adherence
Status
Initial
|X|Preliminary|_|Baseline
|X|Final
|_|Not Applicable (N/A)
Recurring
|_|Annual Update|_|Other: ________________
|X|Not Applicable (N/A)
Deliverable Specification
Ten (10) business days after beginning the Requirements and Analysis, the Contractor (Vendor) will provide preliminary Requirements Document to SCDHHS for review. The final version is due ten (10) business days before the Design Phase begins. SCDHHS needs to review and approve prior to the Contractor (Vendor) commencing the Design Phase.

Note

Description
The purpose of the Requirements Document (RD) is to provide full identifying information related to the automated system, application or project’s business case for which the RD applies. Pursuant to the scope located on the Intake Request Form and/or Project Charter, the requirements identified will provide internal stakeholders a narrative of the intended requirements’ information, both business and technical and any links to external documentation. A sanitized version of the RD may be provided to external stakeholders with the approval of the project’s leadership.

The RD also provides a summary of the tools which will used to enter, store and manage business requirements, business rules, user requirements and functional and non-functional requirements for the project through to traceability.

Item Number
D-016
Deliverable Name
Requirements Traceability Matrix (RTM)
SCDHHS Owner(s)
SCDHHS Approver(s)
Vendor Owner(s)
Vendor Approver(s)
Type of Data
|X|Governance or Project Management|_|Other: ___________________________________
|_|Security|_|Transition to Operations (Post-Implementation)
|_|Systems/Software Development
Submission Due Indicator
|X|Initial
|_|Recurring
|_|Not Applicable (N/A)
Type of Deliverable Due: |X| Submission |_| Adherence
Status
Initial
|X|Preliminary|_|Baseline
|X|Final
|_|Not Applicable (N/A)
Recurring
|_|Annual Update|_|Other: ________________
|X|Not Applicable (N/A)
Deliverable Specification
Thirty (30) business days after beginning the Requirements and Analysis, the Contractor (Vendor) will provide preliminary Requirements Document to SCDHHS for review. The final version is due ten (10) business days before the Design Phase begins. SCDHHS needs to review and approve prior to the Contractor (Vendor) commencing the Design Phase.

Note

Description
The Requirements Traceability Matrix (RTM) is a document that links requirements throughout the project lifecycle. The purpose of the RTM is to ensure that all requirements defined for a system are tested in the test protocols. The traceability matrix is a tool both for the project team, to ensure that requirements are not lost during the project’s implementation, and allows for auditors to review the validation documentation.

The RTM is developed in concurrence with the initial list of requirements (either the User Requirements Specification or Functional Requirements Specification). As the Design Specifications and Test Activities are developed, the traceability matrix is updated to include the updated documents. Requirements must be traced to the specific test step during the testing process. The RTM includes the following elements:

· Requirement ID

· Requirement Type

· Requirement Description

· Success Criteria

· Use Case or Story ID

· Use Case Description

· MITA 7 Conditions and Standards

· Status

· Priority

· Functional Design Specification

· Architectural Design Specification

· Systems Components

· Software Module (s)

· Interface Requirement?

· Unit Test Case ID

· Unit Test Case Description

· Integration Test Case ID

· Integration Test Case Description

· UAT Test Case ID

· UAT Test Case Description

· Comments

Item Number
D-017
Deliverable Name
System Security Plan (SSP)
SCDHHS Owner(s)
SCDHHS Approver(s)
Vendor Owner(s)
Vendor Approver(s)
Type of Data
|_|Governance or Project Management|_|Other: ___________________________________
|X|Security|_|Transition to Operations (Post-Implementation)
|_|Systems/Software Development
Submission Due Indicator
|X|Initial
|X|Recurring
|_|Not Applicable (N/A)

Type of Deliverable Due: |X| Submission |_| Adherence

Status
Initial
|X|Preliminary|_|Baseline
|X|Final
|_|Not Applicable (N/A)
Recurring
|X|Annual Update|_|Other: ________________
|_|Not Applicable (N/A)
Deliverable Specification
PROJECT KICKOFF + sixty (60) calendar days, the Contractor (Vendor) will provide preliminary SSP Part A or update to an existing SSP Part A to SCDHHS for review. PROJECT KICKOFF + 120 calendar days, the Contractor (Vendor) will provide Preliminary SSP Parts B, C and D or update to existing SSP Parts B, C and D to SCDHHS to review. The final version is due ten (10) business days after successful user acceptance testing (UAT). SCDHHS needs to review and approve prior to the Contractor (Vendor) commencing the Implementation Phase. Updates will occur minimally on an annual basis.

Note

Description
The SSP documents the description of managerial, technical, and operational security controls.

Contractor (Vendor) must use either an SSP template, completed using SCDHHS approved formatting and governance, or use the SCDHHS Governance, Risk and Compliance (GRC) solution to document system security and operating controls to ensure that the design and implementation of the services delivered contain such controls, processes and procedures that meet or exceed federal standards and guidance. Information about the use of a template or GRC solution will be provided at the kick-off meeting.

Item Number
D-018
Deliverable Name
Information Security Risk Assessment (ISRA)
SCDHHS Owner(s)
SCDHHS Approver(s)
Vendor Owner(s)
Vendor Approver(s)
Type of Data
|_|Governance or Project Management|_|Other: ___________________________________
|X|Security|_|Transition to Operations (Post-Implementation)
|_|Systems/Software Development
Submission Due Indicator
|X|Initial
|_|Recurring
|_|Not Applicable (N/A)

Type of Deliverable Due: |X| Submission |_| Adherence

Status
Initial
|X|Preliminary|_|Baseline
|X|Final
|_|Not Applicable (N/A)
Recurring
|X|Annual Update|_|Other: ________________
|_|Not Applicable (N/A)
Deliverable Specification
PROJECT KICKOFF + 150 calendar days, the Contractor (Vendor) will provide preliminary ISRA to SCDHHS for review. The final version is due ten (10) business days after successful UAT. SCDHHS needs to review and approve prior to the Contractor (Vendor) commencing the Implementation Phase.

Note

Description
The ISRA contains a list of threats and vulnerabilities, an evaluation of current security controls, their resulting risk levels, and any recommended safeguards to reduce risk exposure.

Contractor (Vendor) must use an ISRA template, completed using SCDHHS approved formatting and governance, or use the SCDHHS Governance, Risk and Compliance (GRC) solution to show the system risks in the context of MARS-E V2.0 control RA-3. Information about the use of a template or GRC solution will be provided during the kick-off meeting.

Item Number
D-019
Deliverable Name
Privacy Impact Assessment (PIA)
SCDHHS Owner(s)
SCDHHS Approver(s)
Vendor Owner(s)
Vendor Approver(s)
Type of Data
|_|Governance or Project Management|_|Other: ___________________________________
|X|Security|_|Transition to Operations (Post-Implementation)
|_|Systems/Software Development
Submission Due Indicator
|X|Initial
|_|Recurring
|_|Not Applicable (N/A)

Type of Deliverable Due: |X| Submission |_| Adherence

Status
Initial
|X|Preliminary|_|Baseline
|X|Final
|_|Not Applicable (N/A)
Recurring
|X|Annual Update|_|Other: ________________
|_|Not Applicable (N/A)
Deliverable Specification
PROJECT KICKOFF + sixty (60) calendar days, the Contractor (Vendor) will provide preliminary PIA to SCDHHS for review. The final version is due ten (10) business days after successful UAT. SCDHHS needs to review and approve prior to the Contractor (Vendor) commencing the Implementation Phase.

Note

Description
The PIA ensures there’s no collection, storage, access, use or dissemination of identifiable respondent information unless it is needed and permitted. Contractor (Vendor) must use a PIA template, completed using SCDHHS approved formatting and governance or use the SCDHHS Governance, Risk and Compliance (GRC) solution to submit the PIA. Information about the template or GRC solution will be provided during the kick-off meeting.
Item Number
D-020
Deliverable Name
Disaster Recovery and Business Continuity (DR/BC) Plan
SCDHHS Owner(s)
SCDHHS Approver(s)
Vendor Owner(s)
Vendor Approver(s)
Type of Data
|_|Governance or Project Management|_|Other: ___________________________________
|X|Security|X|Transition to Operations (Post-Implementation)
|_|Systems/Software Development
Submission Due Indicator
|X|Initial
|X|Recurring
|_|Not Applicable (N/A)

Type of Deliverable Due: |X| Submission |_| Adherence

Status
Initial
|X|Preliminary|_|Baseline
|X|Final
|_|Not Applicable (N/A)
Recurring
|X|Annual Update|_|Other: ________________
|_|Not Applicable (N/A)
Deliverable Specification
Sixty (60) calendar days from the contract start date, the Contractor (Vendor) will provide preliminary DR/BC to SCDHHS for review and approval. An interim update of the DR/BC Plan is due ten (10) business days before UAT for SCDHHS review and approval. The final version of the DR/BC Plan is due five (5) business days after successful go-live. Annual updates to be submitted thirty (30) calendar days before and then ten (10) calendar days after the annual DR/BC Test.

Note

Description
Contractor (Vendor) must provide a detailed Disaster Recovery and Business Continuity (DR/BC) Plan designed to minimize any potential disruption to operations. This plan must be approved by SCDHHS prior to implementation and is to be modified with approval as circumstances warrant.

This plan must:

· Be tested periodically, at schedules agreed upon by the Contractor (Vendor) and SCDHHS, with a written report to SCDHHS. It will be the Contractor’s (Vendor) sole responsibility to maintain adequate back-up to ensure continuous operations.

· Include procedures for accessing necessary electronic Protected Health Information (ePHI) in the event of an emergency; continue protection of ePHI during emergency operations.

· Contain all necessary documentation e.g., process flows, technical diagrams, functional design document, functional design document s, etc.

The Contractor (Vendor) must:

· Support a Recovery Time Objective (RTO) of 24 hours from the time of a disaster declaration and Recovery Point Objective (RPO) of eight (8) hours.

· Propose a schedule for testing the Disaster Recovery Plan before and after implementation, and included in the project schedule.

· Have geographically diverse operations to minimize impact in the event of a disaster.

· Provide a plan to return operational status to normal in the event of a disaster.

· Describe recovery processes, including requirements for communication plans and redundant or stand-by hardware, software, and staffing.

· Describe provisions to support interim manual operations during recovery.

SCDHHS welcomes the Contractor (Vendor) to propose Disaster Recovery/Business Continuity as a Service where the Contractor (Vendor)’s solution can be integrated with other SCDHHS DR/BC requirements, systems, and teams.

Item Number
D-021
Deliverable Name
Solution Plan
SCDHHS Owner(s)
SCDHHS Approver(s)
Vendor Owner(s)
Vendor Approver(s)
Type of Data
|_|Governance or Project Management|_|Other: ___________________________________
|_|Security|_|Transition to Operations (Post-Implementation)
|X|Systems/Software Development
Submission Due Indicator
|X|Initial
|_|Recurring
|_|Not Applicable (N/A)

Type of Deliverable Due: |X| Submission |_| Adherence

Status
Initial
|X|Preliminary|_|Baseline
|X|Final
|_|Not Applicable (N/A)
Recurring
|_|Annual Update|_|Other: ________________
|_|Not Applicable (N/A)
Deliverable Specification
PROJECT KICKOFF + thirty (30) calendar days, the Contractor (Vendor) will provide preliminary Solution Plan document to SCDHHS for review. The final version is due ten (10) business days before the Development Phase begins. SCDHHS needs to review and approve prior to the Contractor (Vendor) commencing the Development Phase.

Note

Description
The solution plan is a high-level description of the current state, future state and implementation considerations. It describes the required outcomes, user interfaces, data interfaces, batch processes, reports, business process changes and policy impacts.

It is a description at the very highest level to start setting the expectation on both business and technology changes that would be implemented by the project.

This document will be used to drive business requirements that would meet the goals expressed. If available, this activity will use the business architecture, information architecture and information flows as input and describe the impact that the project would have on these architectures.

Item Number
D-022
Deliverable Name
Functional Design Specification Document (FDS)
SCDHHS Owner(s)
SCDHHS Approver(s)
Vendor Owner(s)
Vendor Approver(s)
Type of Data
|_|Governance or Project Management|_|Other: ___________________________________
|_|Security|_|Transition to Operations (Post-Implementation)
|X|Systems/Software Development
Submission Due Indicator
|X|Initial
|_|Recurring
|_|Not Applicable (N/A)

Type of Deliverable Due: |X| Submission |_| Adherence

Status
Initial
|X|Preliminary|_|Baseline
|X|Final
|_|Not Applicable (N/A)
Recurring
|_|Annual Update|_|Other: ________________
|_|Not Applicable (N/A)
Deliverable Specification
Ten (10) business days after beginning the Design Phase, the Contractor (Vendor) will provide preliminary Functional Design Specification Document to SCDHHS for review. The final version is due ten (10) business days before the Development Phase begins. SCDHHS needs to review and approve prior to the Contractor (Vendor) commencing the Development Phase.

Note

Description
The functional design specification is an elaboration of the requirements, describing HOW the requirements would be implemented. Focusing on the functional (or logical) viewpoint, the functional design specification describes the user interfaces, reusable components, data movements, data interfaces and data model without going into the physical implementation details.

Components of the FDS include: Sequence Diagram, Component Diagram (including UI wireframes), Information Flow Diagram, Conceptual Data Model, Interface Diagram

The FDS is used to update the Business Architecture, Application Architecture and Information Architecture.

Item Number
D-023
Deliverable Name
Technical Design Specification Document (TDS)
SCDHHS Owner(s)
SCDHHS Approver(s)
Vendor Owner(s)
Vendor Approver(s)
Type of Data
|_|Governance or Project Management|_|Other: ___________________________________
|_|Security|_|Transition to Operations (Post-Implementation)
|X|Systems/Software Development
Submission Due Indicator
|X|Initial
|_|Recurring
|_|Not Applicable (N/A)

Type of Deliverable Due: |X| Submission |_| Adherence

Status
Initial
|X|Preliminary|_|Baseline
|X|Final
|_|Not Applicable (N/A)
Recurring
|_|Annual Update|_|Other: ________________
|_|Not Applicable (N/A)
Deliverable Specification
Ten (10) business days after beginning the Design Phase, the Contractor (Vendor) will provide preliminary Technical Design Specification Document to SCDHHS for review. The final version is due ten (10) business days before the Development Phase begins. SCDHHS needs to review and approve prior to the Contractor (Vendor) commencing the Development Phase.

Note

Description
The Technical Design Specification describes the physical components that will accomplish the design of the FDS to satisfy project requirements.

The TDS defines platform requirements, user interfaces, components, batch jobs, interfaces and data models as it is physically implemented.

Components of the TDS include: Interface Control Documents, Deployment Model, Platform architecture, Physical Data Model, Component Diagram (including user interfaces), etc.

Item Number
D-024
Deliverable Name
Logical Data Model
SCDHHS Owner(s)
SCDHHS Approver(s)
Vendor Owner(s)
Vendor Approver(s)
Type of Data
|_|Governance or Project Management|_|Other: ___________________________________
|_|Security|_|Transition to Operations (Post-Implementation)
|X|Systems/Software Development
Submission Due Indicator
|X|Initial
|_|Recurring