This document is a schedule of values for replacing aeration equipment at Lake Mead Wastewater Lagoons under solicitation number 140P8123Q0039 issued by the Department of the Interior National Park Service Pacific West Region. The schedule lists line items for aerators of various horsepower ratings and voltage specifications along with unit prices and total prices. The base bid includes nine aerators totaling three 5HP 3-phase units, five 2HP 1-phase units, and three 2HP 3-phase units. There are also three option line items for additional aerators that may or may not be exercised. The total price will be evaluated for both the base bid and all options. Prices must include labor, overhead, and profit.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attch_1_-_Specifications.pdf | ||
| Sol_140P8123Q0039.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Item Number
Contract Line Item Title Quantity Unit of
Measure Unit Price Total Price
10 Aerator : 5 Horse power, 3 phase, 230/460 volts 4 Each
20 Aerator : 2 Horse power, 1 phase, 115/208-230 volts 5 Each
30 Aerator : 2 Horse power, 3 phase, 230/460 volts 3 Each
Total for Base Bid
Option A Aerator : 5 Horse power, 3 phase, 230/460 volts 1 Each
Option B Aerator : 2 Horse power, 1 phase, 115/208-230 volts 1 Each
Option C Aerator : 2 Horse power, 3 phase, 230/460 volts 1 Each
Total for all Options
Schedule of Values Replace Aeration Equipment
PMIS 255480
Total Price for Total of all option (Total bid plus Options)
Total Price for Base Bid
Note: This is a firm fixed price requirement. All costs associated to perform the work in accordance with the Statement of Work shall be included.
Note: For price evaluation purposes, the Total Bid Plus Options will be evualated to determine price reasonableness.
Note: Options will be reviewed for price reasonableness and may or may not be exercised at time of award. Individual selection of the different options may be done.
Note: Prices should include labor, overhead and profit.