STATEMENT OF WORK
For
Juno Tower Replacement
1.0 Scope of Work
The purpose of this statement of work includes obtaining design-build services under a single procurement for the replacement of the Tactical Communications (TACCOM) 250’ guyed tower in Uvalde, TX (Juno) (Latitude 30.1426, Longitude -101.3146). The proposed replacement would be a 260’ guyed tower (10’ taller than the existing tower). It is anticipated that the new tower will be located 15-20 feet northwest of the existing tower and will be constructed prior to the existing tower coming down. The technology currently in service on the existing tower will be transferred to the new tower and tested in accordance with applicable standards. Installations will meet the requirements defined below and maintain satisfactory operability of communications equipment. Currently on the site, there is an abandoned 4 x 4 shelter and propane tank that will need to be removed and disposed of as a result of this effort. During the site condition assessment, the contractor will be required to perform a site survey, geotechnical investigation, and data collection to facilitate production of a construction package for the site. Contractor will not have on demand access to the tower site and should plan for a single site visit to complete all necessary data reconnaissance for the project. Site survey will be used for the purpose of developing a scope for the construction package that will be used to complete the replacement of the tower system and infrastructure of the existing owned or leased Customs and Border Protection (CBP) properties for the Juno tower site. The construction package must show the proposed site layout and any recommendations based upon information gathered to replace the tower. The construction package must be signed, sealed and dated by a registered professional engineer in the state of Texas.
The contractor will provide labor, travel, permits/application fees, mobilization costs and tools for technicians to travel to Uvalde, TX to replace the Juno tower as described in this SOW. A site condition assessment may be required to gather information to complete an assessment for the tower and adjacent facilities located in Uvalde, TX. During the site condition assessment, a site survey, geotechnical investigation and data collection may be required to facilitate the tower and infrastructure replacement as outlined in this SOW. The site survey will be used for the purpose of developing any additions or deletions to this scope associated with the replacement of the tower and infrastructure of the existing owned or leased Customs and Border Protection (CBP) properties for the Juno site.
1.1 Objectives
This SOW shall achieve the following specific objectives:
Tower shall be designed to meet structural design in accordance with IBC 2010; ASCE-2007; NEC, NFPA, ANSI/ASTM and TIA-222-H. Structure shall be designed to accommodate the proposed loading and be structurally modeled for 50% capacity in controlling element using a commercially acceptable modeling program (e.g., TnX, or RISA). Loading calculations shall include all climb systems, proposed communications equipment, and lightning rod protection.
Procure and build replacement tower with guy anchors and mast foundation o Preferable tower type will be a 260’ guyed tower with solid round members (Rohn GSR or equivalent).
o OB med-dual light installed in accordance with FAA 7460 determination (see attached) o Install a ladder safety climb device o Provide manufacturer drawings for completed tower assembly as applicable
For the protection of electronic systems, the tower site and its components shall comply with FAA-STD-019f (primary), NFPA780, UL96, UL96A, and LPI-175 (supplementary) for grounding, bonding, surge protection, and lightning protection requirements. All associated infrastructure shall be tied into the grounding ring system, Earth Electrode System (EES).
Replace all feedlines and mounting hardware for all existing appurtenances Install ice bridge to two existing shelters (CBP’s 12 x 8 shelter and Texas Parks & Wildlife 8 x 10 shelter) Remove and dispose of third abandoned 4 x 4 shelter and propane tank Submit and obtain local building permits as required The contractor shall remove the existing tower and ancillary infrastructure and restore these locations to the natural state as determined by surrounding area. The mast foundation and guy anchors shall be removed to the depth of 24 inches below grade and backfill/restore the areas to the most practical extent.
Dismantle and dispose of existing tower. Confirmation of disposal will require the submission of disposal tickets.
Transfer and relocate technology from existing tower to the new tower and test for operability. A temporary tower may be required based upon space availability and site layout.
Geotech will determine the tower base and anchor foundation per manufacturer guidelines.
Provide as built drawings and structural analysis report
1.2 References
All applicable documents referenced in this SOW are listed below.
1) Government furnished documents.
2) Applicable Federal, State, and Local Requirements.
3) Applicable Standard Industry Quality and Safety Requirements
2.0 Requirements
Contractor will:
Must submit and clear a law enforcement clearance through the local CBP sector office for all personnel including sub-contractor personnel
Provide all necessary labor (or sub-contract labor) of appropriate skill to accomplish all tasks with this SOW Submit Project Completion Report as Described in Section 3.0 Travel as necessary to accomplish all tasks in the SOW.
Provide specialized services to accomplish all tasks specified in the SOW.
Provide procurement services as required for materials and equipment.
Complete all tasks as required in Section 3.0 Provide deliverables as required in Section 3.1 Schedule and coordinate as required by Section 4.0 Provide progress/compliance as required in section 4.0 Provide construction site access to government construction monitors for the purpose of monitoring progress and quality. The contractor will retain the right to limit access to the immediate construction area during high safety risk activities. The contractor will provide an observation area for monitors during high safety risk activities.
3.0 Tasks
The tasks to be performed under this SOW are described below in several categories. Where conflicts arise between documents this document shall supersede.
1) Phase I: Security Clearance
a) All contractor personnel shall submit personal information to the Government for the purposes of submitting to security clearance check. Security clearance check will be performed by DHS-CBP. All personal and private information (PPI) will be submitted on Security Clearance Form in Appendix B and submitted directly to DHS-CBP. Point of contact for receipt of PPI will be provided upon submission of project schedule after award. Security clearance must be completed 3 weeks prior to construction start date or any requested site visit.
2) Phase II: Project Planning
a) Contractor will provide complete project schedule that denotes start dates, end dates and duration of all major project activities. Project schedule may include as many lines and work activities as necessary for the contractor to control and manage the project.
b) Schedule shall be reasonable and denote working hours for all on-site activities.
c) Contractor shall provide a site survey report with proposed site layout and site survey finding to determine a government approved tower site configuration and conceptual design. After site survey report contractor shall provide 95% design plans and specifications to ensure tower site construction will meet SOW and Design Requirements..
3) Phase III: Construction/Installation
a) Contractor will install assets and make other site improvements as required in the construction work package.
b) Contractor will be present and attend final inspection and acceptance performed by government.
4) Phase IV: Project Close Out
a) Contractor will submit project close out report and photographs of all completed work. Contractor will author a summary document of the effort provided during the completion of the work. The document will provide a list of the work completed, list of materials used for each installation, pre installation pictures of major components, post installation pictures of major components, field observations made (if additional work was identified) and redlines of government furnished information to produce construction as-built documentation
3.1 End Results/Deliverables
The deliverables to be completed and submitted under this SOW is the tower replacement as outlined in this SOW and a project close out package that reflects the milestones of this agreement that are agreed upon by all parties at the site survey visit. Basic requirements may include, but not limited to, the tasks listed in Section 3.2, and other applicable documents for the completed site made up of red line drawings, tests and material data sheets/information, etc. for the project.
3.2 List of Deliverables by Task
The deliverables to be completed and submitted for each task under this SOW are described below. Acceptance of the work will be based on conformance with construction drawings and other government furnished information.
1) Security
a) Complete and Submit Security Clearance Form referenced in Appendix B.
b) Complete and Submit Project Schedule reference Schedule Section for major components to be captured.
2) Project Planning and Construction
a) Conduct site assessment survey to gather information to assemble the construction package for this project as noted in section 1.0 of this SOW.
b) Complete design package that includes all applicable drawings, i.e. survey, layout, elevation, foundations, electrical, structural, grounding, ice bridge, etc.
c) Complete schedule
d) Mobilize for construction.
e) Replace existing tower with a 260’ guyed tower.
f) Move the existing technology on tower to the new structure and test accordingly as noted in this SOW.
g) Restore surrounding area to previous natural state.
h) Clear all debris from the work area.
i) Conduct a Final Inspection and Acceptance with FAA and/or CBP.
j) Complete punch list items identified in the Final Inspection.
k) Conduct punch list verification walk through with FAA and/or CBP if requested.
l) Demobilize from construction efforts
3) Project Completion
a) Complete and Submit Project Completion report as described in Section 3.
4.0 Schedules/Milestones
Project scheduling and milestones for the site will be submitted within 7 days of award and include no less than the following milestones:
Security clearance Pre-work meeting Mobilization Site work Final Inspection & Acceptance Punch list item completion Demobilization Close-out report submission
5.0 Other Considerations
All personnel shall be required to submit and clear a law enforcement clearance through the centralized CBP office by completing and submitting the form in Appendix B.
Coordination with CBP technical personnel will be required and will be done through communication through the FAA project leadership.
A note should be included in the final report regarding the decommissioning of any old assets.
“As-built” drawings based upon the redlines will be part of the closeout so a note shall be included in the final report annotating this requirement, to be completed 30 days after receipt of the redline drawings.
6.0 Progress/Compliance
The following will be coordinated with FAA-AJW-L500 in order to monitor progress and ensure compliance (identify action):
Security clearance paperwork Preconstruction Meeting Design/Progress Meetings Final Inspection and Acceptance Submission of documents in Sections 3.1 & 4.0 Government construction monitors may be on site to verify progress and compliance.
7.0 Period of performance
After contract is awarded, the awarded contractor should be prepared to submit the site access form found in Appendix B within 5 calendar days and to attend site visit within 30 days after award. A kickoff meeting will be scheduled within 7 calendar days prior to the site visit. Site visit hours may be constricted due to allowable working hours for Government Escort. Working hours are typically Monday through Friday 8 am to 5 pm unless otherwise approved. All weekend work must be approved with agency of Government Escort. The design package should be completed within 90 days after the site visit is conducted. The anticipated completion of all construction efforts would be 120 days thereafter, 210 days total project duration.
8.0 Place of performance
The place of performance is Uvalde, TX (Juno) (Latitude 30.1426, Longitude -101.3146)
An auditable system containing all elements of the ASQ/ANSI/ISO 9001:2015 standard exists. Product will be inspected and accepted/rejected at destination by the FAA for Technical Specifications and Packaging Specifications, as stated in the contract. Certificates of Compliance shall be supplied where applicable.”
Appendix A – Construction Requirements
CONTRACTOR SITE VISIT
When required by the Contractor to adequately prepare a Work Plan or as identified in the Scope of Work Requirements, the project location identified in the scope of work will be visited to perform a site survey. The site survey shall provide the basis of the Contractor’s Work Plan and no formal site survey report submission shall be necessary when the site survey is conducted to produce a Work Plan.
CONTRACTOR WORK PLAN
The Contractor shall be required to produce a Work Plan and the Work Plan will follow the guidance provided below.
When the requirement for a site visit is waived by the Contractor in order to develop a Work Plan, the Work Plan will include no less than a summary of work to be completed (with limitations, exclusion and assumptions) and schedule to complete the work. Work Plan will also include the following items (unless waived or documentation provided with base contract). List of Quality Control Activities, Definable Features of Work, Materials, Verification and Testing Activities, Submittal Register, Non-compliance/Deficiency Process, Change Management Process, Construction Reporting and Inspection, Construction Tolerances, Workmanship and Warranty Requirements. Each of these items will be defined as described below:
FEATURES OF WORK: Include a list of defined features of work (DFOW) with descriptions of work requiring any preparatory inspections and descriptions of the verification, inspection, testing, acceptance, and quality control requirements for each element of work to be reviewed (such as photographs, measurements, and tests).
MATERIALS: All equipment and materials to be incorporated into the design and construction drawings are to be identified and appropriate documentation to be provided to government to assure the proper materials are being utilized and will not affect the service, capacity or operation of the constructed tactical infrastructure. The equipment and materials incorporated into require a certification. Certifications will be provide as one of the following types of certifications:
Type A: Manufacturer prepared certification consisting of a certified report detailing tests conducted by a laboratory certified on samples obtained from the lot of material in shipment.
Type B: Manufacturer prepared certification showing the limits of test values as determined by a laboratory certified, qualified commercial laboratory or another approved laboratory.
Type C: Manufacturer certification certifying that the material in the shipment conforms to the same formula or is essentially the same as the material previously approved for construction.
Type D: Manufacturers prepared certification stating that the material meets the contract requirements, listed by specification reference number, section reference or other appropriate identification approved by the Resident Engineer/Government Inspector.
Type E: Fabricator prepared certification covering a composite item incorporating two or more materials previously approved on an individual basis, but that lose their identities when incorporated into the composite item.
Type F: Resident Engineer’s acceptance based on confirmation that supplier delivery invoices materially matches contract required materials, all contract requirements have been met and visual inspection at the point of incorporation shows satisfactory workmanship and condition of the material.
Type F Certifications will not be accepted for equipment or materials specified in the design and construction drawings where the source or supplier of the equipment is known in advance of construction. When equipment or materials are specified by brand and model name the equipment or material or equal must provide a Type A – Type E Certification as a part of the final design submission package. All other materials where the source, supplier or model and brand name are unknown until the date of delivery by the contractor a Type A – Type F Certification may be accepted. All equipment and/or material certifications collected after the beginning of construction will be supplied with the as-built submission package.
Certifications will be required for all equipment and materials incorporated into the design and construction of the project.
Material certifications will not be required for any of the following reasons;
Equipment and/or Material provided as Government Furnished Equipment or Materials Equipment and/or Material salvaged or produced from local sources adjacent to project permanent and/or temporary easements. This does not alleviate necessary documentation to validate material meets sampling and testing requirements.
Equipment and/or Material is on approved State Department of Transportation (SDOT) Material List. Materials meeting this condition must still be documented as approved SDOT Material and furnished to the Resident Engineer during construction.
HEALTH AND SAFETY PLAN: The HSP will identify the local emergency services and provide a local emergency preparedness plan. The HSP shall conform to the requirement of the United Facilities Guide Specifications, division 01, Section 01 35 26 (Government Safety Requirements), Parts 1.7 and 1.8. Government will not be held responsible for wellbeing of Contractor Personnel. The Contractor shall conform to all applicable safety standards published in the Federal Register, OSHA or applicable life safety code. The Contractor shall ensure employees observe all safety, security, traffic control, and fire prevention requirements in effect at the site. Government safety personnel may observe Contractor operations/processes at any time on Government premises. Imminent danger situations shall be corrected on the spot; other safety issues shall be processed through the Contracting Officer’s Representative (COR). The HSP shall be specific to the project site and identify emergency contact information, communication and reporting procedures.
QUALITY CONTROL ACTIVITIES: Include a description of the quality control activities that will be performed (e.g., the steps that will be taken to successfully review the specific elements of the construction, including visual inspection (periodic or continuous), measurement, frequency and other checks designed to verify compliance with stated requirements) to include Contractor acceptance of the construction elements such as construction tolerances and other criteria used to approve craftsmanship and work.
QUALITY CONTROL PLAN: Include how the Contractor plans to develop and maintain quality, timely and efficient operations. QCP should include a description of the inspection and monitoring of services provided with the process for identifying, reporting and preventing/correcting nonconformities. When material, equipment, or components are unacceptable to the Government, the Contractor shall, at no cost to the Government, remove, replace, and rework material, equipment, and components so that compliance with the Government's requirements are satisfied.
VERIFICATION & TESTING ACTIVITIES: Identify the verification and testing laboratory facilities, qualifications and procedural requirements that complement the quality control activities and definable features of work. Include in project schedule milestones for verification and testing. All verification and testing should be with the project close out package and include conducted, by whom, the standard to which it is verified / tested, and the documentation to provide evidence of verification / test results.
SUBCONTRACTOR MANAGEMENT PLAN: Identify the list of subcontractor(s)’s employees employed in the execution of the contract, services performed, certifications, licenses, qualifications, and experience. The Contractor shall describe in detail how the subcontractors will be managed to ensure quality, timely performance of contract requirements.
SUBMITTAL REGISTER: Include a submittal register for all anticipated materials certifications, verification/testing/acceptance logs, shop/fabrication drawings, cut sheets, manufacturer installation instructions, and other reports, as necessary, to include when submittals are due to the Government.
NON-COMPLIANCE / DEFICIENCY PROCESS: Describe the non-conformance management and resolution process and how non-conformities are resolved when identified.
CHANGE MANAGEMENT PROCESS: Describe the process for addressing and proposing changes to awarded documentation.
WARRANTIES: Describe the warranty of all craftsmanship and materials incorporated into Customer Assets and/or Facilities.
WEEKLY PROGESS MEETINGS
The Contract Manager shall be required to meet weekly during the implementation of Contractor Work Plans unless waived. Meetings may be held onsite or via a teleconference with government representatives.
HOURS OF OPERATION
Government core duty hours are Monday through Friday, 0600 to 1800. Typical work hours are 0700 to 1700 with no work being done before 30 minutes after sunrise and after 30 minutes before sunset. Some emergency situations may require the Contractor to work outside core duty hours. These situations include, but are not limited to, disruption of services, e.g., unscheduled/scheduled outages of facility services, or contingency accidents/incidents, or other emergencies. Late or nighttime work hours may be permitted to avoid the high summer temperatures.
FAA personnel observe the following days as holidays:
New Year's Day, Martin Luther King's Birthday Presidents' Day, Memorial Day, Independence Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day, Christmas Day.
Any other day designated by Federal statute, by Executive Order or by the President's proclamation or as identified on scope of work.
When any such day falls on a Saturday, the preceding Friday is observed. When any such day falls on a Sunday, the following Monday is observed. Observance of such days by Government personnel shall not be cause for an extension to the delivery schedule or period of performance or adjustment to the price, except as set forth in the contract. Except for designated around-the-clock or emergency operations, Contractor personnel will not be able to perform on site under this contract with FAA on holidays set forth above unless identified on the scope of work or Work Plan. Extreme weather conditions, other emergency situations, and other acts of nature (e.g. floods, earthquake) may warrant an office closure or a delay in normal operating hours.
WORK COORDINATION
The Contractor shall coordinate with the government manager’s or building manager’s office to ensure the work to be performed does not disrupt customer operations. A twenty-one (21) calendar day notice to the government and facility personnel is required for all work that require site access, service interruption, disconnects or cut-off of any utility to or within the facility, or requires the facility to be vacated. This is not intended to include outrages associated with the communication cutover plan. Notices will be identified with the submission of Site Access Forms. Site Access Forms are required to properly conduct a background check. All Contractor Personnel who fail background investigation will be denied access and the cost and impacts associated will be borne by the Contractor. All contractor personnel will be required to provide name, title, company, home address, last four of social security number, date of birth, driver’s license number and state driver’s license is issued. All information will be used to perform at a minimum a criminal records search at local, state and federal levels.
ELETRONIC DATA REQUIREMENTS
The Contractor shall provide all submittals and requested data in electronic format, except when requested in hardcopy by the government. The data and information obtained through the execution of the contract is hereby owned solely by U.S.
Government. FAA shall have unlimited and unrestricted use of such data. The associated rights and privileges are assignable only by FAA. The Contractor shall maintain all records and submittals generated electronically for 2 years and hard copy for the remaining duration of the contract..
The Contractor shall provide document source files in Microsoft Office Professional formats; provide each document in Portable Document Format (PDF) which is book-marked and fully text retrievable; and provide a cover sheet containing key cataloging formation and a table of contents.
Appendix B – Security Clearance Form
All contractor and sub-contractor personnel must undergo a CBP background check through the completion of this form in its entirety and submission of a color copy of a photo ID, i.e. driver’s license, state ID card, passport, etc. All personnel entering in or working on Federal Property will be screened and checked for criminal history and proper immigration status. Personnel who do not meet the minimum standards will not be allowed on the job site. The following items determine whether or not a person has met the minimum standards as it relates to the criminal history requirement:
. Any felony conviction (at any time) . Immigration violation (unless exonerated by a judge) . Active warrant (anywhere)
Be advised that if an individual does not clear vetting, CBP cannot disclose (for privacy reasons) why they failed.
Mail Processing Center Federal Aviation Administration Southwest Regional Office Obstruction Evaluation Group 10101 Hillwood Parkway Fort Worth, TX 76177
Aeronautical Study No.
2021-ASW-4142-OE
Prior Study No.
2015-ASW-8027-OE
Issued Date: 04/05/2021
Scott Heiser US Customs and Border Protection 1331 Pennsylvania Avenue Suite 755N Washington DC, NW, DC 20229
** DETERMINATION OF NO HAZARD TO AIR NAVIGATION **
The Federal Aviation Administration has conducted an aeronautical study under the provisions of 49 U.S.C., Section 44718 and if applicable Title 14 of the Code of Federal Regulations, part 77, concerning:
Structure: Antenna Tower Antenna Tower Juno Location: Ozona, TX Latitude: 30-08-33.41N NAD 83 Longitude: 101-18-52.58W Heights: 2181 feet site elevation (SE)
275 feet above ground level (AGL) 2456 feet above mean sea level (AMSL)
This aeronautical study revealed that the structure does not exceed obstruction standards and would not be a hazard to air navigation provided the following condition(s), if any, is(are) met:
As a condition to this Determination, the structure is to be marked/lighted in accordance with FAA Advisory circular 70/7460-1 M, Obstruction Marking and Lighting, a med-dual system-Chapters 4,8(M-Dual),&15.
Any failure or malfunction that lasts more than thirty (30) minutes and affects a top light or flashing obstruction light, regardless of its position, should be reported immediately to (877) 487-6867 so a Notice to Airmen (NOTAM) can be issued. As soon as the normal operation is restored, notify the same number.
It is required that FAA Form 7460-2, Notice of Actual Construction or Alteration, be e-filed any time the project is abandoned or:
_____ At least 10 days prior to start of construction (7460-2, Part 1) __X__ Within 5 days after the construction reaches its greatest height (7460-2, Part 2)
See attachment for additional condition(s) or information.
This determination expires on 10/05/2022 unless:
(a) the construction is started (not necessarily completed) and FAA Form 7460-2, Notice of Actual Construction or Alteration, is received by this office.
(b) extended, revised, or terminated by the issuing office.
(c) the construction is subject to the licensing authority of the Federal Communications Commission (FCC) and an application for a construction permit has been filed, as required by the FCC, within 6 months of the date of this determination. In such case, the determination expires on the date prescribed by the FCC for completion of construction, or the date the FCC denies the application.
NOTE: REQUEST FOR EXTENSION OF THE EFFECTIVE PERIOD OF THIS DETERMINATION MUST
BE E-FILED AT LEAST 15 DAYS PRIOR TO THE EXPIRATION DATE. AFTER RE-EVALUATION
OF CURRENT OPERATIONS IN THE AREA OF THE STRUCTURE TO DETERMINE THAT NO
SIGNIFICANT AERONAUTICAL CHANGES HAVE OCCURRED, YOUR DETERMINATION MAY BE
ELIGIBLE FOR ONE EXTENSION OF THE EFFECTIVE PERIOD.
This determination is based, in part, on the foregoing description which includes specific coordinates, heights, frequency(ies) and power. Any changes in coordinates, heights, and frequencies or use of greater power, except those frequencies specified in the Colo Void Clause Coalition; Antenna System Co-Location; Voluntary Best Practices, effective 21 Nov 2007, will void this determination. Any future construction or alteration, including increase to heights, power, or the addition of other transmitters, requires separate notice to the FAA.This determination includes all previously filed frequencies and power for this structure.
If construction or alteration is dismantled or destroyed, you must submit notice to the FAA within 5 days after the construction or alteration is dismantled or destroyed.
This determination does include temporary construction equipment such as cranes, derricks, etc., which may be used during actual construction of the structure. However, this equipment shall not exceed the overall heights as indicated above. Equipment which has a height greater than the studied structure requires separate notice to the
FAA.
This determination concerns the effect of this structure on the safe and efficient use of navigable airspace by aircraft and does not relieve the sponsor of compliance responsibilities relating to any law, ordinance, or regulation of any Federal, State, or local government body.
A copy of this determination will be forwarded to the Federal Communications Commission (FCC) because the structure is subject to their licensing authority.
If we can be of further assistance, please contact our office at (817) 222-5922, or debbie.cardenas@faa.gov. On any future correspondence concerning this matter, please refer to Aeronautical Study Number 2021-ASW-4142-
OE.
Signature Control No: 474429439-476553004 ( DNE ) Debbie Cardenas Technician
Attachment(s) Additional Information Frequency Data Map(s) cc: FCC
Additional information for ASN 2021-ASW-4142-OE
Please submitted FAA Form 7460-2 dismantlement on ASN 2015-ASW-8027-OE when new structure is constructed.
Frequency Data for ASN 2021-ASW-4142-OE
LOW
FREQUENCY
HIGH
FREQUENCY
FREQUENCY
UNIT ERP
ERP
UNIT
136 225 MHz 500 W 138 174 MHz 200 W 138 174 MHz 250 W 150 174 MHz 500 W 164 174 MHz 500 W
Verified Map for ASN 2021-ASW-4142-OE