Attachment J-7 Climate Risk Matrix - Public Accountability and Justice Strengthening.pdf

PDF 66 KB Posted

Attached to
Public Accountability and Justice Strengthening Activity Federal contract opportunity
Solicitation number
72027821R00007
Issued by
US Agency for International Development Jordan

About this file

This Request for Proposals from the United States Agency for International Development seeks proposals from qualified organizations to implement the Public Accountability and Justice Strengthening activity in Jordan over a four-year period. USAID intends to make one award as a result of this solicitation for an estimated funding range of $35-39 million. Interested organizations must carefully read Sections L and M of the RFP, which provide instructions for proposal preparation and submission, and evaluation criteria. Any questions must be submitted in writing to USAID by the stated deadline.

View the file

Other files for this federal contract opportunity

Other files attached to Public Accountability and Justice Strengthening Activity, newest first.
File Type Posted
Removed - Attachment J-4 Past Performance Report.pdf PDF
Amendment 01 - RFP No.72027821R00007_PAJ.pdf PDF
Attachment J-3 Budget Template.xlsx XLSX spreadsheet
Questions and Answers RFP No. 72027821R00007 PAJ.pdf PDF
RFP No. 72027821R00007_PAJ_ with Amendment 01.pdf PDF
Attachment J-4 Past Performance Report.pdf PDF
Attachment J-8 - ROLPAS Activity Results.pdf PDF
RFP No. 72027821R00007.pdf PDF
PAJ RFP - Attachment J-3 - Summary Budget Template.xlsx XLSX spreadsheet

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment J-7 Climate Risk Screening for Public Accountability and Justice Strengthening activity - 12/3/2020

Tasks/ Defined or Illustrative Interventions

Climate Risks List key risks related to the defined/illustrative interventions identified in the screening and additional assessment.

Risk Rating Low/Moderate/ High

How Risks are Addressed Describe how risks have been addressed in activity design and/or additional steps that will be taken in implementation. If you choose to accept the risk, briefly explain why.

Opportunities to Strengthen Climate Resilience Describe any opportunities to achieve multiple development objectives by integrating climate resilience or mitigation measures

Activities related to capacity building, technical assistance, trainings, workshops, and awareness sessions including printing of material and publications

Extreme weather conditions, Increase in temperatures, Flash Floods may negatively impact the ability to access rural and remote areas. As well as it will impact the attendance to sessions and the ability to deliver those sessions especially in rural and remote areas.

Low Advise the implementing partner on possible climate risks and the possible impact of extreme weather conditions.

The IP is advised to consider seasonal forecasts and rainy seasons when planning for training or similar activities and use contingency planning and consider virtual training as options.

N/A

Procurement of IT equipment, IT software and solutions, furniture, and automobile

Extreme weather conditions, Increase in temperatures, flash floods, heat waves may impose risk on the delivery of procured items and on the functioning of some sensitive IT equipment

Moderate The IP is required to screen for activity and site specific climate risks using the CRM tool and integrate necessary actions to mitigate risks; e.g. building insulation, rainwater drainage system, etc.

The IP should report actions as part of the Environmental Mitigation and Monitoring Plan (EMMP).

For awareness, discuss climate risks with stakeholders when possible.

Apply green building standards if possible. Consider installing energy saving equipment and devices, PV systems, etc.

Renovation and Small

Scale Construction Activities

Extreme weather conditions, Increase in temperatures, Flash Floods, heat waves may impose risk to the new or upgraded building