Attachment II - Replace Boiler SOW 20200806.pdf
PDF 66 KB Posted
- Attached to
- Boiler Replacement Federal contract opportunity
- Solicitation number
- 12805B20Q0161
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Pictures of Nod 1 Panel Schematics.pdf | ||
| 2020.09.04 - Questions and Answers.pdf | ||
| 2020.09.03 - Questions and Answers.pdf | ||
| Site Visit Sign in Sheet.pdf | ||
| Attachment VII - Existing Boiler Room Plan 20200722.pdf | ||
| Attachment VIII - Mech Plan 1993.pdf | ||
| Attachment III - ARS-371.pdf | ||
| RFQ - 12805B20Q0161.pdf | ||
| Attachment VI - FAR Deviation Accelerated Payments to Small Business.pdf | ||
| Attachment IV - ARS-372.pdf | ||
| Attachment I - DBA Wage Rates.pdf | ||
| Attachment V - Bond Forms.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REPLACE FIRE-TUBE BOILER
USDA, ARS, NPA
Central Plains Resources Management Research Unit
Near Akron, Colorado
1. The work consists of furnishing all labor, materials, equipment, and performing all work to replace the existing 1995 Rite A 180 Boiler, Serial Number 23994 in Building 1.
2. This is a hot water boiler with a closed loop system. The sea level output is 1440 MBH, with a High-Low-Off Firing Control.
3. See attached file “Mech Plan 1993.tif” and “Existing Boiler Room Plan 20200722.jpg” for additional information about the Boiler, Pump, and location of existing boiler.
4. Existing Boiler is 69” long by 42” wide by 57” tall.
5. Pumps were replaced 2010 with rating of 169 GPM flow pumps
6. 2012 Boiler controls were upgraded to Siemens controls.
7. The replacement boiler will be a Higher efficient boiler than the existing one, equal to or similar to the Harsco Industrial, Patterson-Kelley, Velox Boiler Model N1700VX, point of contact is Marshall Paulson, at 720-990-9683.
8. The project will be completed before freezing temperatures, if not the project will be completed in May 2021.