2020.09.03 - Questions and Answers.pdf

PDF 116 KB Posted

Attached to
Boiler Replacement Federal contract opportunity
Solicitation number
12805B20Q0161
Issued by
Department of Agriculture Agricultural Research Service Field Research Implementation and Information Delivery Plains Area

View the file

Other files for this federal contract opportunity

Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

09/03/20

Solicitation (RFQ) – 12805B20Q0161- Boiler Replacement

USDA ARS Akron, CO

Questions & Answers

Answers are in Red:

1. Would you like us to provide past performance (CPARS) in our proposal, or are you going to look at all CPARS reviews online? See section M. Evaluation Factors for Award, page 26 of the

Solicitation. I will be looking online.

2. Can the bid due date be extended due to the fact that the site visit was on 9/1 and once RFI’s are returned, we will likely only have 1-2 days to compile an accurate proposal? Yes it will be extended.

3. The SOW #3 states “See attached file “Mech Plan 1993.tif” and “Existing Boiler Room Plan

20200722.jpg” for additional information about the Boiler, Pump, and location of existing boiler. These files were not included on the SAM website. Please provide. These attachments added to Beta.Sam

4. Please provide the site visit list. Added to beta.sam

5. Please confirm if the boiler is condensing or non-condensing. Non-condensing

6. Please confirm if the existing pump is to be replaced. The three Temperature Zone circulating

Pumps will not be replaced. If the Boiler calls for an internal circulating pump That will need to be provided.

7. Please confirm if this is a glycol system. If so, what percentage is required? No