Attachment I - DRAFT Statement of Work - Reflective Cracking Indoors Phase VII Construction-Replacement.pdf
PDF 183 KB Posted
- Attached to
- Reflective Cracking Indoors Phase VII Construction/Replacement MARKET SURVEY Federal contract opportunity
- Solicitation number
- 692M15-22-R-00013
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment V Appendix II Reflective Cracking Indoors Phase VII Construction Plan 100 Percent Design Drawings.pdf | ||
| Attachment IV Appendix I Specifications NAPT Reflective Cracking Indoors Phase VII.pdf | ||
| Attachment III - Important Information to Potential Vendors - Reflective Cracking Indoors Phase VII Construction-Replacement.pdf | ||
| Attachment II - Pre-qualifications Requirements_Reflective Cracking Indoors Phase VII Construction-Replacement.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT I - DRAFT STATEMENT OF WORK - REFLECTIVE CRACKING
INDOORS PHASE VII CONSTRUCTION-REPLACEMENT
C.1 SUMMARY OF WORK
The purpose of this Statement of Work is demolition of existing Hot Mix Asphalt (HMA) overlay test item, construction of new HMA overlay test item with associated instrumentation, and incidental related efforts at the Reflective Cracking Indoor (RCID) rig at the National Airport Pavement Test Facility (NAPTF) (Building 296) in the William J. Hughes Technical Center, Atlantic City International Airport, New Jersey, 08234 by means of a firm fixed-price contract. This work includes, but is not limited to the following principle line items:
1. Demolition and removal of existing HMA Overlay pavement. This work includes necessary precautions to avoid damage to existing materials and instrumentation to remain in place, be reused, or be retained by the FAA. Do not overload pavements to remain. Provide supports and reinforcement for existing items weakened by demolition, deconstruction, or removal work. Reinforcement and supports require approval by the FAA prior to performing such work.
2. Placement of approximately 300 square feet of new HMA overlay test item and associated appurtenances in accordance with the FAA Advisory Circular 150/5370-10H Standard Specifications for Construction of Airports including:
A. Clean the milled concrete surface for the placement of asphalt pavement B. Neat asphalt binder applied on top of concrete as a tack coat C. Neat asphalt binder applied between asphalt pavement compacted lifts D. Place the north side test strip in one 3” asphalt pavement compacted lift E. Place the south side test strip in two 3” asphalt pavement compacted lifts
3. Miscellaneous site work including the following:
A. Placement of a pavement overrun area as shown in the drawings B. Build the wood frame for the construction of two separate asphalt strips C. Placement of various instrumentation sensors in different locations shown on the drawings D. Use of specific construction techniques identified in the project documents for research purposes
C.2 GENERAL REQUIREMENTS
1. The Contractor must furnish all labor, supervision, tools, materials, equipment, incidental engineering, transportation, and management necessary for the site work specified herein and the attached drawings.
2. The extent of asphalt concrete pavement construction is indicated on the drawings and this Statement of Work.
3. New pavement construction will include placing tack coats and asphalt pavement on concrete.
4. Asphalt pavement must meet the standard specifications for construction of airports provided.
5. The intent of the contract is to provide for construction and completion, in every detail, of the work described. It is further intended that the Contractor must furnish all labor, materials, equipment, tools, transportation, and supplies required to complete the work in accordance with the plans, specifications, and terms of the contract.
C.3 REGULATORY REQUIREMENTS
1. All work must be accomplished in accordance with all local, state, and federal codes including but not limited to applicable Occupational Safety and Health Association (OSHA), Environmental Protection Association (EPA), National Electrical Code (NEC), and Life-Safety codes. OSHA reserves the right to inspect the Contractor's work area without advance notice.
2. When the Contractor observes that contract documents are at variance with OSHA, the National Electrical Code, or Federal, State, or local rules and regulations, the contractor must notify the Contracting Officer Representative (COR) immediately.
3. The contractor must conform to the safety requirements in accordance with the NAPTF Health and Safety Plan, Federal, state, and local laws, and rules and regulations concerning construction safety and health standards, including Corps of Engineers manual EM 385-1-1. The contractor must comply with the Environmental Protection Agency requirements. The Contractor will not require or allow any worker to work in surroundings or under conditions that are unsanitary, hazardous, or dangerous to health or safety.
C.4 Asphalt Pavement Requirements and Procedures
1. Applicable Standards
A. FAA Advisory Circular 150/5370-10H Standard Specifications for Construction of Airports material referenced herein.
B. Specifications for NAPTF – Reflective Cracking Indoors Phase VII is available for download in Appendix 1.
2. Material Requirements
A. Provide locally available materials that comply with the Specifications for NAPTF – Reflective Cracking Indoors Phase VII for asphalt concrete pavements and all materials specified herein.
3. Asphalt Pavement Construction
A. Provide construction methods that comply with the Specifications for NAPTF – Reflective Cracking Indoors Phase VII.
C.5 QUALITY ASSURANCE
1. The Contractor must verify all existing conditions and verify measurements for obtaining quantities of materials delivered. No subsequent extras will be allowed due to any claim of lack of knowledge for conditions, which can be determined by examining the site.
C.6 SCHEDULE OF WORK
1. The Contractor must schedule and arrange work so as to cause the least interference with the normal occurrence of Government business and mission. In those cases where some interference may be essentially unavoidable, the Contractor must make every effort to minimize the impact of the interference, inconvenience, equipment downtime, interrupted service, customer discomfort, etc.
2. Work will not begin until authorization is received from the FAA. The schedule of the availability of work areas will be confirmed by the FAA. Completion of the work must be done during standard work hours at the facility of 7:00AM to 5:00PM. Requests for extended work hours must be submitted in writing five work days in advance, and may be granted at the discretion of the FAA.
C.7 PERIOD OF PERFORMANCE
The period of performance will be 180 calendar days from the Notice to Proceed (NTP).
C.8 CONTRACT SPECIFICATIONS
The contract specifications for this project are attached as “Appendix 1 Reflective Cracking Indoors Phase 7 Construction Specificaitons_220415”.
C.9 CONTRACT DRAWINGS
The contract drawings are considered the property of the Government and must not be used for any purpose other than that contemplated by the specifications. The contract drawings indicate general arrangements, approximate sizes and relative locations of principal materials to be provided or tasks to be completed. Contract drawings are diagrammatic and are a graphic representation of contract requirements to best available standards at the scale used. The Contractor must provide offsets to clear interferences and supports which are not specifically shown, but which are obviously needed to make the system complete, operable, and safe. The Contractor must verify all elevations, dimensions and clearances at the site. The following contract drawings accompany the specifications showing details of asphalt pavement is available for download in Appendix II and are a part thereof:
Appendix II Reflective Cracking Indoors Phase VII Construction Plan 100% Design Drawings
C.10 SECURITY REQUIREMENTS
The William J. Hughes FAA Technical Center is under security at all times. All critical areas (e.g. air traffic control towers) are controlled by means of a personal identification system. All personnel entering the facility will require a badge or visitor badge, which must be visible and worn at all times while on the premises. Further instructions regarding security requirements will be furnished at the time the badges are issued.
C.11 DISPOSAL/CLEANING REQUIREMENTS
1. The contractor must follow the following disposal, storage, and cleaning requirements:
A. Do not store rubbish or debris on unstabilized materials. Maintain staging and stockpile areas in a neat and organized manner, properly drained, and in a manner to prevent contamination of stockpiles and materials.
B. Prevent the spread of dust and debris beyond the project limits. Use of water is permitted outside of Building 296, however, do not use water if it results in hazardous or objectionable conditions such as, but not limited to, an increase in subgrade moisture content, ice, flooding, or pollution. Water trucks are not permitted inside the test facility except to refill equipment.
Prevent the accumulation of loose dust, dirt, mud, or debris on haul routes, roadways, staging areas, and parking lots. Provide protective measures to control accumulation and migration of dust and dirt into work areas and office spaces.
C. Upon completion of the work and before acceptance and final payment will be made, the Contractor must remove from the site all machinery, equipment, surplus and discarded materials, rubbish, temporary structures, and stumps or portions of trees. The Contractor must cut all brush and woods within the limits indicated and must leave the site in a neat and presentable condition.
Material cleared from the site and deposited on adjacent property will not be considered as having been disposed of satisfactorily, unless the Contractor has obtained the written permission of the property Owner.
C.12 PROTECTION OF EQUIPMENT AND STRUCTURES
1. The Contractor must protect all buildings, structures, and equipment during demolition as directed by the COR.
2. The contractor must take all necessary precautions to avoid damage to existing materials and instrumentation to remain in place, be reused, or be retained by the FAA. Do not overload pavements to remain. Provide supports and reinforcement for existing items weakened by demolition, deconstruction, or removal work. Reinforcement and supports require approval by the FAA prior to performing such work. List necessary shop drawings on submittal register and provide in accordance with Section 61MR.
Pavements to be removed that are adjacent to structures must be double saw cut adjacent to the structures in a manner to avoid damage to the structure. Prevent contamination of materials to remain with foreign or demolished pavement materials, debris, and refuse. Repair or replace damaged items as directed by and at no additional cost to the FAA.
C.13 IDENTIFICATION OF UTILITIES
1. FAA utilities: All work associated with the location and identification of buried communications, electrical, mechanical, or plumbing systems owned by the FAA, shall be performed by FAA personnel.
2. Utility Disruption: In the event that properly identified utility or communication services either overhead or buried, are damaged as a result of the Contractor’s activity, such services must be immediately repaired and the COR and the Contracting Officer (CO) immediately notified.
3. Utilities to remain, including instrumentation, must remain in service for the duration of project activities. Protect against damage during demolition and deconstruction operations. Notify the FAA immediately if utility infrastructure is damaged, or if an unmarked utility is located.
C.14 GOVERNING DOCUMENTS
1. For Conflicts between the drawing(s) and the standard FAA Advisory Circular 150/5370-10H Standard Specifications for Construction of Airports requirements, the drawing(s) will govern.
2. For conflict between the FAA Advisory Circular 150/5370-10H Standard Specifications for Construction of Airports requirements and the provided specification requirements, the more stringent requirement will apply.
C.15 PROJECT MEETINGS
1. The Contractor and COR will conduct project meetings throughout the construction period as deemed necessary by the FAA and requested by the Contractor.
C.16 SPECIAL RESEARCH REQUIREMENTS
1. Construction work at the NAPTF is conducted to support research activities and is subject to unique requirements. Test items may be indicated in the project plans to be constructed indoors, with associated issues of lighting, equipment and material entry into the building, operation inside the building, and adequate ventilation. Test items are subject to intense testing and documentation. Demolition and construction of layers are to be constructed in the sequence that is indicated in project documents.
Complete each layer before commencing with subsequent layers unless otherwise indicated in the project documents. Furnish materials to NAPTF personnel for sampling and testing as indicated in project documents. Cease demolition and construction activities for the duration of testing at times indicated in the project documents. Expect a work stoppage of 1 to 3 days, or as indicated in project documents, after completion of each layer to allow adequate time for the FAA to obtain samples, run tests, and install instrumentation. Coordinate activities with the NAPTF to avoid disturbance of research occurring outside the limits of this project (e.g. CC8 post-traffic testing, CC9 trafficking, etc.). Any requirement of these specifications may be waived to further the research goals of the project by written notification from the FAA to the Contractor.
C.17 Schedule of Submittals
1. Submit all submittals in accordance with Section 61MR Submittal Procedures that comply with the Appendix 1 Specifications for NAPTF – Reflective Cracking Indoors Phase VII.
A. Preconstruction Submittals - The Contractor must submit the following documents to the COR. The COR must approve all submittals before work can begin.
i. Construction operations plan. Contractor must document the intended general sequence of work activities, general types of anticipated equipment, anticipated utility and service interruptions, and anticipated impact to research or other activities near the work site.
ii. Project schedule. Contractor must prepare and maintain a schedule in MS Project format. Use the Critical Path Method to schedule and control project activities. Include submittals, review periods, all construction activities, inspection, testing, and closeout activities. Saturdays, Sundays, and Federal holidays are non-work days. Indicate if extended work hours will be requested.
iii. Safety plan. Contractor must identify potentially hazardous construction activities and planned mitigation procedures. The plan should include excavation, heavy equipment operation, and minimum Personal Protective Equipment requirements for site access in addition to each major construction activity.
| C.1 SUMMARY OF WORK |
| C.2 GENERAL REQUIREMENTS |
| C.3 REGULATORY REQUIREMENTS |
| C.4 Asphalt Pavement Requirements and Procedures |
| 1. Applicable Standards |
| A. FAA Advisory Circular 150/5370-10H Standard Specifications for Construction of Airports material referenced herein. |
| B. Specifications for NAPTF – Reflective Cracking Indoors Phase VII is available for download in Appendix 1. |
| 2. Material Requirements |
| A. Provide locally available materials that comply with the Specifications for NAPTF – Reflective Cracking Indoors Phase VII for asphalt concrete pavements and all materials specified herein. |
| 3. Asphalt Pavement Construction |
| A. Provide construction methods that comply with the Specifications for NAPTF – Reflective Cracking Indoors Phase VII. |
| C.5 QUALITY ASSURANCE |
| C.17 Schedule of Submittals |
| A. Preconstruction Submittals - The Contractor must submit the following documents to the COR. The COR must approve all submittals before work can begin. |