Attachment E.pdf

PDF 460 KB Posted

Attached to
PAVEMENT DATA COLLECTION State and local contract opportunity
Solicitation number
5400025010
Issued by
Richland County, South Carolina

About this file

This attachment outlines the payment schedule for pavement data collection services for the South Carolina Department of Transportation (SCDOT). The contract utilizes a milestone-based payment structure organized by geographic deliverables and district divisions. For the 2023 short-year schedule, compensation is calculated on a per-mile basis across seven deliverables representing Districts 1 through 7. Each deliverable contains three milestones with staggered payments: 30% upon verification of collected data and images, 40% upon delivery of rated data and images, and 30% following SCDOT review and approval. Beginning in 2024 and continuing for each subsequent year under the full-year schedule, the payment structure expands to eight deliverables, adding an Interstates category as Deliverable 1, with Districts 1 through 7 comprising Deliverables 2 through 8. The milestone payment percentages remain consistent at 30%, 40%, and 30% respectively across all deliverables.

All deliverables may be submitted in any order at the contractor's discretion, provided the complete schedule is presented and approved by SCDOT prior to the commencement of annual data collection activities. The payment methodology is designed to incentivize timely collection and delivery of pavement condition data while ensuring quality control through the final SCDOT approval phase. This structure provides predictable cash flow throughout the contract performance period while protecting the government's interest through conditional payments tied to verification, rating, and approval milestones.

View the file

Other files for this state and local contract opportunity

Other files attached to PAVEMENT DATA COLLECTION, newest first.
File Type Posted
Amendment 1.pdf PDF
Attachment A.pdf PDF
Attachment F.pdf PDF
Amendment 2.pdf PDF
Amendment 3.pdf PDF
Attachment D.pdf PDF
Attachment C.pdf PDF
Solicitation.pdf PDF
Attachment G.xlsx XLSX spreadsheet
Attachment B.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment E

2023 – short year schedule

Payments will be made on a per mile per deliverable basis using the following Deliverables and

Milestones. The Deliverables may be scheduled to be submitted in any order. The schedule is to be presented and approved by SCDDOT prior to the beginning of annual data collection).

Deliverable 1 – District 1

Milestone 1 – 30% shall be paid upon verification of the data and images collected

Milestone 2 – 40% shall be paid upon delivery of rated data and images

Milestone 3 – 30% shall be paid after the data and images have been reviewed and approved by

SCDOT

Deliverable 2 – District 2

Milestone 1 – 30% shall be paid upon verification of the data and images collected

Milestone 2 – 40% shall be paid upon delivery of rated data and images

Milestone 3 – 30% shall be paid after the data and images have been reviewed and approved by

SCDOT

Deliverable 3 – District 3

Milestone 1 – 30% shall be paid upon verification of the data and images collected

Milestone 2 – 40% shall be paid upon delivery of rated data and images

Milestone 3 – 30% shall be paid after the data and images have been reviewed and approved by

SCDOT

Deliverable 4 – District 4

Milestone 1 – 30% shall be paid upon verification of the data and images collected

Milestone 2 – 40% shall be paid upon delivery of rated data and images

Milestone 3 – 30% shall be paid after the data and images have been reviewed and approved by

SCDOT

Deliverable 5 – District 5

Milestone 1 – 30% shall be paid upon verification of the data and images collected

Milestone 2 – 40% shall be paid upon delivery of rated data and images

Milestone 3 – 30% shall be paid after the data and images have been reviewed and approved by

SCDOT

Deliverable 6 – District 6

Milestone 1 – 30% shall be paid upon verification of the data and images collected

Milestone 2 – 40% shall be paid upon delivery of rated data and images

Milestone 3 – 30% shall be paid after the data and images have been reviewed and approved by

SCDOT

Deliverable 7 – District 7

Milestone 1 – 30% shall be paid upon verification of the data and images collected

Milestone 2 – 40% shall be paid upon delivery of rated data and images

Milestone 3 – 30% shall be paid after the data and images have been reviewed and approved by

2024 and every additional year – full year schedule

Payments will be made on a per mile per deliverable basis using the following Deliverables and

Milestones. The Deliverables may be scheduled to be submitted in any order. The schedule is to be presented and approved by SCDDOT prior to the beginning of annual data collection).

Deliverable 1 – Interstates

Milestone 1 – 30% shall be paid upon verification of the data and images collected

Milestone 2 – 40% shall be paid upon delivery of rated data and images

Milestone 3 – 30% shall be paid after the data and images have been reviewed and approved by

SCDOT

Deliverable 2 – District 1

Milestone 1 – 30% shall be paid upon verification of the data and images collected

Milestone 2 – 40% shall be paid upon delivery of rated data and images

Milestone 3 – 30% shall be paid after the data and images have been reviewed and approved by

SCDOT

Deliverable 3 – District 2

Milestone 1 – 30% shall be paid upon verification of the data and images collected

Milestone 2 – 40% shall be paid upon delivery of rated data and images

Milestone 3 – 30% shall be paid after the data and images have been reviewed and approved by

SCDOT

Deliverable 4 – District 3

Milestone 2 – 40% shall be paid upon delivery of rated data and images

SCDOT

Deliverable 5 – District 4

Milestone 1 – 30% shall be paid upon verification of the data and images collected

Milestone 2 – 40% shall be paid upon delivery of rated data and images

Milestone 3 – 30% shall be paid after the data and images have been reviewed and approved by

SCDOT

Deliverable 6 – District 5

Milestone 1 – 30% shall be paid upon verification of the data and images collected

Milestone 2 – 40% shall be paid upon delivery of rated data and images

Milestone 3 – 30% shall be paid after the data and images have been reviewed and approved by

SCDOT

Deliverable 7 – District 6

Milestone 1 – 30% shall be paid upon verification of the data and images collected

Milestone 2 – 40% shall be paid upon delivery of rated data and images

Deliverable 8 – District 7

Milestone 2 – 40% shall be paid upon delivery of rated data and images