Attachment C - Specifications - Pages 1-2.docx
DOCX document 26 KB Posted
- Solicitation number
- 3000026646
- Issued by
- East Baton Rouge Parish, Baton Rouge City, Louisiana
About this file
This specifications document outlines the fire suppression system replacement project for the Department of Military Affairs (DMA) at Hammond Airport in Hammond, Louisiana. The contractor shall furnish all labor, materials, equipment, tools, supervision, and services necessary to replace seven suppression systems. The scope includes installation of five 50-pound Ansul IND-X Industrial Dry Chemical ABC or equivalent suppression systems in weapons vaults and two 100-pound Ansul IND-X Industrial Dry Chemical ABC or equivalent systems, with one installed in a weapons vault and one in the maintenance bay battery storage room. The existing cylinders exhibit rust and corrosion and are no longer available. The project requires the contractor to verify all field dimensions and existing site conditions prior to commencement of work, with hours of operation limited to Tuesday through Friday, 7:00 AM to 5:30 PM, excluding recognized state and federal holidays.
The contractor is responsible for providing all necessary precautions to prevent damage during material delivery, repairs, and equipment movement; securing the building and sensitive items daily; arranging onsite storage locations approved by the Project Manager; and providing a detailed construction work schedule 48 hours prior to work commencement. All work must comply with applicable state and local safety and environmental requirements, OSHA, the National Electrical Code, and parish, city, and state regulations. The contractor must contact LA 1-Call and utility companies prior to any digging and supply all employees with appropriate personal protective equipment. All specification sheets and submittals require pre-approval by the Project Manager before ordering. The contractor provides a one-year workmanship and project warranty commencing from the certificate of completion filing date, with warranty documents delivered to the Project Manager upon final payment. The contractor bears responsibility for disposal and storage of all removed or installed materials throughout the project duration, with weather days included in contract time.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 3000026646-1.pdf | ||
| Attachment A - Special Terms and Conditions Pages 1-15.docx | DOCX document | |
| 3000026646.pdf | ||
| Attachment B - Job Site Verification Form - Page 1.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment C – Specifications RFx 3000026646
**If bidding other than specified, please provide manufacturer’s specs for “or equal” items. **
Scope of Work:
The Contractor shall furnish all labor, materials, equipment, tools, supervision, and services necessary to replace seven suppression systems for the Department of Military Affairs (DMA).
Location:
Hammond Airport RC 1501 B Industrial Park Road Hammond, Louisiana 70401
DMA Contact:
Chuck Finch, (985) 205-7256, charles.g.finch.nfg@army.mil
Specification:
The Contractor shall perform the following:
· Provide and install five 50# Ansul IND-X Industrial Dry Chemical ABC or Equal suppression systems. All five shall be installed in weapons vaults.
Specify Suppression System Bidding: _____________________
· Provide and install two 100# Ansul IND-X Industrial Dry Chemical ABC or Equal. One shall be installed in a weapons vault, and one shall be installed in the maintenance bay battery storage room.
Specify Suppression System Bidding: _____________________
Current cylinders exhibit rust and corrosion, and the cylinders are no longer available.
Terms and Conditions:
· The Contractor is responsible for field verifying all dimensions and existing site conditions of work to be performed. The Contractor shall inspect and verify information provided herein on existing materials and equipment, etc. is correct and inform Project Manager (PM) of any errors or questions prior to commencement of work.
· The Contractor shall take all precautions necessary to prevent damages when delivering materials to site and provide covering to prevent rusting.
· The Contractor shall secure the building, and any sensitive items at the end of each workday in accordance with the designated unit POC.
· The Contractor shall take all necessary precautions to prevent damages during repairs, to include movement and parking of equipment on grass, other improved, or unimproved areas surrounding site.
· All work must comply with all applicable State and Local Safety and Environmental requirements. Occupational Safety and Health Administration (OSHA), National Electrical Code (NEC), Parish, City and State regulations will be required. The Contractor will supply all employees with PPE.
· The Contractor must call LA 1-Call and all utility companies prior to digging.
· Hours of operation Tuesday- Friday, 7:00 AM to 5:30 PM and closed on all recognized state and federal holidays.
· The Contractor is responsible to provide storage containers. If an onsite storage area is required, the contractor must confirm a storage location for any materials, fixtures, equipment, trailers, etc. stored on site during the term length of the contract. The location will be approved by the Project Manager during the pre- construction meeting.
· The Contractor must confirm a storage location for all materials stored on site during the term length of the contract. The location will be approved by the Project Manager prior to delivering.
· The Contractor shall contact, prior to mobilization and demobilization, facility point of contact which will be provided herein.
· The Contractor is responsible for disposal and storage of all materials being removed or installed throughout the project.
· The Contractor shall provide a construction work schedule (Gnant like) 48 hours prior to start of work detailing each task of work.
· All specification sheets and submittals must be pre-approved by the Project Manager prior to ordering.
· The Contractor will warranty their workmanship and the completed project for a one year period. One year period starts the date of the filing of the certificate of completion.
· The contractor will provide all associated warranty documents to the Project Manager upon completion and final payment.
· Weather days are included in the contract time.