About this file
This document is a Specifications Attachment for RFx 3000024600 from the Louisiana Department of Corrections (DOC), specifically covering window glass replacement at Allen Correctional Center in Kinder, LA. The project requires the contractor to remove and replace broken window glass in existing frames across multiple dormitories and cellblocks, with precise specifications for security-grade polycarbonate glass installation. The project involves replacing 12 windows of varying dimensions in Saturn, Mercury, Earth, Jupiter Dormitories, and Mars Cellblock, with windows ranging from 31 1/8" x 37 1/8" to 73" x 47". Work is to be performed during normal business hours (Monday through Friday, 8:30 AM to 4:30 PM), with all contractors subject to background checks and facility security protocols.
The specifications mandate specific technical requirements for the replacement glass, including a three-ply polycarbonate detention glass with a thickness between 0.406" and 0.530", capable of withstanding a .38 special gunshot without penetration. The contractor must provide structural security framing, use polycarbonate-compatible sealants and gaskets, and ensure proper glass installation with minimum 1-inch edge engagement. Additional requirements include removing existing glazing stops, creating new mount holes, and complete waste removal upon project completion. The project emphasizes adherence to industry standards and compliance with federal, state, and local codes, with strict security measures for contractor personnel and equipment while on facility grounds.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| 3000024600-1.pdf | ||
| Addendum No. 1.docx | DOCX document | |
| Revised Attachment C - Specifications - Pages 1-2.docx | DOCX document | |
| Attachment A - Special Terms and Conditions Pages 1-14.docx | DOCX document | |
| Attachment B - Job Site Verification Form - Page 1.docx | DOCX document | |
| 3000024600.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment C – Specifications RFx 3000024600
Scope of Work:
The Contractor shall provide all labor, materials, tools, and equipment necessary to remove and replace broken window glass in the existing frames for the Louisiana Department of Corrections (DOC).
Location:
Allen Correctional Center 3751 Lauderdale Woodyard Road Kinder, LA 70648
Site Visit Contact Taylor Maricle 337-375-6611
Specifications:
1. The Contractor shall install security grade three ply polycarbonate glass- 7/16” GCP detention glass.
2. Thickness of glass: Max – 0.530” and Min – 0.406”
3. Ballistics: Shall withstand one shot of a .38 special, no bullet penetration.
4. Structural security framing shall be installed by the Contractor.
5. Installation by the Contractor shall allow for a minimum of a 1 inch edge engagement in the frame with sufficient rabbet depth to allow for expansion (approx. 1/16”/FT).
6. Polycarbonate compatible sealants and gaskets must be used by the Contractor.
7. Glazing stops shall be removed and pushed back and new mount holes located in the existing frames by the Contractor.
8. Locations to be replaced and dimensions:
· Saturn Dormitory: 1- 61” x 47 ¼”
· Saturn Dormitory: 2- 73 ½” x 47 ½”
· Mercury Dormitory: 1- 73 ½” x 47 ¼”
· Mercury Dormitory: 2- 70 ½” x 47 ¼”
· Earth Dormitory: 1- 47 ½” x 63”
· Earth Dormitory: 2- 47 ½” x 60 ½”
· Earth Dormitory: 3- 73 ½” x 47”
· Jupiter Dormitory: 1- 61 ¼” x 47 ¼”
· Mars Cellblock: 1- 31 1/8” x 37 1/8”
· Mars Cellblock: 2- 47 ½” x 61 ½”
General Notes/Terms:
· All work being performed is required during normal business hours Monday through Friday 08:30 A.M. to 4:30 P.M.
· Upon completion of work all waste materials shall be removed and disposed of by the Contractor.
· Work to be performed according to industry standard, and meet all federal, state and local codes.
· The Contractor’s employees are subject to passing a background check.
· The Contractor’s vehicles and equipment are subject to searches.
· The Contractor must follow all policy and procedures while performing work on facility grounds.