This document set contains construction drawings for the Oregon Department of Public Safety Standards and Training (DPSST) Domestic Water Heater (DWH) Replacement project located at 4190 Aumsville Highway SE, Salem, Oregon. The project involves replacement of two parallel domestic hot water boilers, associated storage tanks, recirculation pumps, piping systems, and related mechanical and electrical equipment at the North Eugene facility. The construction documents are 100% complete design drawings dated June 1, 2026, prepared by Systems West Engineers. The scope includes demolition of existing equipment, installation of new equipment in phases to maintain facility operations, and integration with building automation systems. Two boiler options are specified: RBI Dominator 1350 non-condensing multi-stage boilers with 1,350,000 BTU/hour input and 1,134,000 BTU/hour output. The base bid scope retains existing domestic hot water storage tanks for reuse, while Alternate #1 includes replacement of both storage tanks with new Niles Steel Tank S-48-120 units (860-gallon capacity each). Construction is phased to maintain one operational boiler system throughout the work, with new equipment tested and connected before demolition of existing parallel systems.
The project includes comprehensive plumbing, mechanical, and electrical work with detailed specifications for piping materials, sizing calculations, equipment schedules, and control systems integration. Plumbing design follows the 2023 Oregon Plumbing Specialty Code with Type L copper piping as the basis of design and pressure drop calculations at 4 feet water column per 100 feet. Mechanical systems include two Greenheck SQ-7-M1-VG combustion air fans (500 CFM each) and associated ductwork. Electrical work provides dedicated circuits and connections for two RBI Dominator 1350 boilers, circulation pumps, mixing valve (Leonard Nucleus NV-300-LF), and building automation system integration through panelboard E-L1S. The contractor is responsible for site verification of existing conditions, necessary cutting and patching, protection of operational systems during construction, and fire protection treatment repairs. All work coordinates with the facility remaining operational, requiring facility staff coordination for all shutdowns.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment B-Technical Specs~1.pdf | ||
| S-DASOBO-00017465-ITB.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
725 A Street Springfield, OR 97477 541.342.7210 systemswestengineers.com
NORTH
EUGENE, OREGON
JUNE 2026
OWNER:
Oregon DPSST
4190 Aumsville Hwy SE Salem, OR 97317
p. 503.385.7849 Operation Planner & Fleet Manager Contact: Michael Anderson Michael.anderson@dpsst.oregon.gov
MECHANICAL & ELECTRICAL:
Systems West Engineers
725 A Street Springfield, OR 97477
p. 541.342.7210 www.systemswestengineers.com Contact: Steven Savich, PM ssavich@systemswestengineers.com
V I C I N I T Y M A P
NOT TO SCALE
DATE:
DRAWN:
CHECKED:
PROJECT:
DESIGNED:
OWNER:
LOCATION:
MARK DATE DESCRIPTION
/3
/2
:0 :4
A
M P
LO
T
T E
D B
Y J
S H
O N
Oregon Department of Public Safety Standards and Training
100% CONSTRUCTION DOCUMENTS
DPSST DWH REPLACEMENT
DPSST DWH
REPLACEMENT
4190 Aumsville Hwy SE, Salem, OR 97317
Oregon Department of Public Safety Standards and Training
COVER SHEET
- CONTACTS,
VICINITY MAP,
& SHEET LIST
06.01.2026
250024.01
G001
JSH
JSH
GNL
100%
CONSTRUCTION
DOCUMENTS
SHEET LIST
G001 COVER SHEET - CONTACTS, VICINITY MAP, & SHEET LIST
P001 LEGEND, GENERAL NOTES, & SHEET LIST
P121 FLOOR PLAN - LEVEL 1 - PLUMBING
P401 ENLARGED PLANS - PLUMBING
P501 PLUMBING DETAILS & DIAGRAMS
P601 PLUMBING SCHEDULES
M001 LEGEND, GENERAL NOTES, & SHEET LIST
M401 ENLARGED PLANS - MECHANICAL
M601 DETAILS, DIAGRAMS, AND SCHEDULES
E001 LEGEND, GENERAL NOTES, SCHEDULES, DIAGRAMS, & SHEET LIST
E101 DEMOLITION PLAN - LEVEL 1
E121 FLOOR PLAN - LEVEL 1
© Systems West Engineers, Inc. 2026. The signature in this document is encrypted. Editing this document is prohibited. (OAR 820)
EXPIRES: 06-30-2027
JA NUA RY 14 , 2020
DIGITALLY SIGNED
RE
GI
STERED PROFESSIONALENGINEER# 95772
OREGONN
A
T
E
J . J E NK
I N S
P L U M B I N G L E G E N D
PIPING GENERAL ABBREVIATIONS
SYMBOL ABBREV. DESCRIPTION
PLUMBING PIPING:
FUEL PIPING:
FI
DV
BV
BFV
CHV
GV
GBV
PRV
AV
SV
AV
RV
TPS
COTG, FCO
WCO
FD
HB
HB
PIPING UP
PIPING DOWN
SLOPE OF PIPE IN DECIMALS OF FEET
CAPPED PIPE
PIPE REDUCING FITTING: CONCENTRIC,
ECCENTRIC
DIRECTION OF FLOW
DRAIN VALVE
UNION
PUMP
BALL VALVE
BUTTERFLY VALVE
CHECK VALVE
GATE VALVE
GLOBE VALVE
ECCENTRIC PLUG VALVE
AUTOMATIC CONTROL
VALVE: 2-WAY
AUTOMATIC CONTROL
VALVE: 3-WAY
FLEXIBLE PIPE CONNECTION
WYE STRAINER
PRESSURE REGULATING VALVE
SOLENOID VALVE
RELIEF VALVE
TEMPERATURE/PRESSURE
SAFETY VALVE
THERMOMETER
PRESSURE GAUGE
TEST PLUG
FLOW INDICATOR
METER, SELF-CONTAINED
CLEANOUT TO GRADE, FLOOR
CLEANOUT
WALL CLEANOUT
FLOOR DRAIN
HOSE BIBB (DIAGRAM)
WATER HAMMER ARRESTOR
REDUCED-PRESSURE PRINCIPLE
BACKFLOW PREVENTER
DOUBLE CHECK
BACKFLOW PREVENTER
HOSE BIBB (PLAN)
SYMBOL ABBREV. DESCRIPTION SYMBOL ABBREVIATION DESCRIPTION
ø
SHEET NUMBER
SECTION LETTER
SHEET NUMBER
DIAMETER
NEW TO EXISTING POINT OF CONNECTION
NOTE REFERENCE MARKER
PLAN OR DETAIL REFERENCE MARKER
SECTION REFERENCE MARKER
EQUIPMENT MARKER
EXISTING SHOWN LIGHT
NEW WORK SHOWN BOLD
EXISTING TO BE REMOVED
P301
PLAN OR DETAIL NUMBER
S=0.01
ABC ABOVE CEILING
ABS ACRYLONITRILE BUTADIENE STYRENE
AC AIR COMPRESSOR
ACFM ACTUAL CUBIC FEET PER MINUTE
ACT ACOUSTICAL CEILING TILE
AD AREA DRAIN
ADA AMERICANS WITH DISABILITY ACT
AFF ABOVE FINISHED FLOOR
AFG ABOVE FINISHED GRADE
AFS AUTOMATIC FIRE SPRINKLER
AHJ AUTHORITY HAVING JURISDICTION
ALT ALTERNATE
ANSI AMERICAN NATIIONAL STANDARDS
INSTITUTE
ARCH ARCHITECT/ARCHITECTURAL
ASHRAE AMERICAN SOCIETY OF HEATING,
REFRIGERATING, & AIR-CONDITIONING
ASME AMERICAN SOCIETY OF MECHANICAL
ENGINEERS
ASPE AMERICAN SOCIETY OF PLUMBING
ENGINEERS
ASSE AMERICAN SOCIETY OF SANITARY
ENGINEERING
AVTR ACID VENT THROUGH ROOF
AWWA AMERICAN WATER WORKS ASSOCIATION
BAS BUILDING AUTOMATION SYSTEM
BFF BELOW FINISHED FLOOR
BFP BACKFLOW PREVENTER
BLDG BUILDING
BHP BRAKE HORSEPOWER
BOP BOTTOM OF PIPE
BTUH BRITISH THERMAL UNITS PER HOUR
CFCI CONTRACTOR FURNISHED/
CONTRACTOR INSTALLED
CFH CUBIC FEET PER HOUR
CFM CUBIC FEET PER MINUTE
CFOI CONTRACTOR FURNISHED/
OWNER INSTALLED
CGA COMPRESSED GAS ASSOCIATION
CI CAST IRON
CLG CEILING
CMU CONCRETE MASONRY UNIT
CO CLEANOUT
CONC CONCRETE
CONT CONTINUATION
COTG CLEANOUT TO GRADE
CPVC CHLORINATED POLYVINYL CHLORIDE
CR CONTROL RELAY
(D) DEMOLISH, DEMOLITION
DBA DECIBELS ACOUSTIC
DCDA DOUBLE CHECK DETECTOR ASSEMBLY
DCV DOUBLE CHECK VALVE
DF DRINKING FOUNTAIN
DFU DRAINAGE FIXTURE UNIT
DIA DIAMETER
DI DUCTILE IRON
DI WATER DEIONIZED WATER
DN DOWN
DW DISTILLED WATER
DWG DRAWING
(E) EXISTING
ECM ELECTRONICALLY COMMUTATED MOTOR
EEM ENERGY EFFICIENCY MEASURE
ELEC ELECTRICAL
EPDM ETHYLENE PROPYLENE-DIENE MONOMER
EWT ENTERING WATER TEMPERATURE
FA FIRE ALARM
FD FLOOR DRAIN
FDC FIRE DEPARTMENT CONNECTION
FFE FINISHED FLOOR ELEVATION
FLA FULL LOAD AMPS
FPM FEET PER MINUTE
FS FLOOR SINK
FT FEET
FT WC FEET WATER COLUMN
FU FIXTURE UNIT
GAL GALLON
GALV GALVANIZED
GI GREASE INTERCEPTOR
GPD GALLONS PER DAY
GPF GALLONS PER FLUSH
GPH GALLONS PER HOUR
GPM GALLONS PER MINUTE
HDPE HIGH-DENSITY POLYETHYLENE
HOA HAND-OFF-AUTOMATIC
HP HORSEPOWER
HVAC HEATING, VENTILATING, &
AIR CONDITIONING
HZ HERTZ
IAPMO INTERNATIONAL ASSOCIATION OF
PLUMBING, MECHANICAL OFFICIALS
ID INSIDE DIAMETER
IE INVERT ELEVATION
IN INCH, INCHES
IN WC INCHES WATER COLUMN
IPS IRON PIPE SIZE
IW INDIRECT WASTE
KW KILOWATT
KWH KILOWATT-HOUR
LBS POUNDS
LAV LAVATORY
LF LINEAR FEET
LPG LIQUIFIED PETROLEUM GAS
LWT LEAVING WATER TEMPERATURE
MAX MAXIMUM
MBH THOUSAND BTUS PER HOUR
MCA MINIMUM CIRCUIT AMPACITY
MECH MECHANICAL
MFR MANUFACTURER
MIN MINIMUM
MOP MAXIMUM OVERCURRENT PROTECTION
MS MOTOR STARTER
(N) NEW
NA NOT APPLICABLE
NC NORMALLY CLOSED
NEMA NATIONAL ELECTRICAL
MANUFACTURERS ASSOCIATION
NFPA NATIONAL FIRE PROTECTION ASSOCIATION
NIC NOT IN CONTRACT
(NL) NEW LOCATION
NO NORMALLY OPEN
NPSH NET POSITIVE SUCTION HEAD
NPT NATIONAL PIPE THREAD
NTS NOT TO SCALE
OD OUTSIDE DIAMETER
OFCI OWNER FURNISHED/
CONTRACTOR INSTALLED
OFOI OWNER FURNISHED/
OWNER INSTALLED
OH OVERHEAD
OPSC OREGON PLUMBING SPECIALTY CODE
OSHA OCCUPATION SAFETY AND HEALTH
ADMINISTRATION
PD PRESSURE DROP
PDI PLUMBING & DRAINAGE INSTITUTE
PE POLYETHELENE
PEX CROSS-LINKED POLYETHELENE
PLBG PLUMBING
POC POINT OF CONNECTION
PH PHASE
PP POLYPROPYLENE
PPH POUNDS PER HOUR
PPM PARTS PER MILLION
PRV PRESSURE REGULATING VALVE
PSI POUNDS PER SQUARE INCH
PSIG POUNDS PER SQUARE INCH GAUGE
PTFE POLYTETRAFLUOROETHYLENE (TEFLON)
PVC POLYVINYL CHLORIDE
PVDF POLYVINYLIDENE FLUORIDE
(R) RELOCATE
RD ROOF DRAIN
REQ'D REQUIRED
RO REVERSE OSMOSIS
RP/RPBP REDUCED PRESSURE PRINCIPLE
BACKFLOW PREVENTER
RPM REVOLUTIONS PER MINUTE
SCCR SHORT CIRCUIT CURRENT RATING
SCFM STANDARD CUBIC FEET PER MINUTE
SCH SCHEDULE
SDR STANDARD DIMENSIONAL RATIO
SPKR SPRINKLER
SQFT SQUARE FEET
SS STAINLESS SEEL
TMV THERMOSTATIC MIXING VALVE
TP TRAP PRIMER
TPA TRAP PRIMER ARRAY
TSP TOTAL STATIC PRESSURE
TYP TYPICAL
U URINAL
UG UNDERGROUND
UL UNDERWRITERS LABORATORY
UON UNLESS OTHERWISE NOTED
UPC UNIFORM PLUMBING CODE
UV ULTRAVIOLET
V VOLTAGE
VFD VARIABLE FREQUENCY DRIVE
VTR VENT THROUGH ROOF
W WATT
WB WET BULB
WC WATER CLOSET
WG WATER GAUGE
WH WALL HYDRANT
WHA WATER HAMMER ARRESTOR
WSFU WATER SUPPLY FIXTURE UNITS
DIA
P521
P101
GENERAL NOTES
A. THE FACILITY WILL REMAIN IN OPERATION DURING CONSTRUCTION. COORDINATE ALL SHUTDOWNS
AND CONSTRUCTION ACTIVITY WITH FACILITIES STAFF.
B. SIZE AND LOCATION OF ALL PIPING AND OTHER MECHANICAL EQUIPMENT IS APPROXIMATE.
CONTRACTOR SHALL SITE VERIFY THE LOCATION OF EXISTING PIPING AND EQUIPMENT AND
CONSTRUCT WORK FROM FIELD DIMENSIONS. CONTRACTOR SHALL MAKE ADJUSTMENTS NECESSARY
TO ACCOMMODATE MINOR DEVIATIONS AT NO COST TO OWNER.
C. FINE (LIGHT) LINE WORK INDICATES EXISTING PIPING AND OTHER MECHANICAL EQUIPMENT. BOLD
(HEAVY) LINE WORK INDICATES NEW PIPING AND OTHER MECHANICAL EQUIPMENT.
D. IT IS RESPONSIBILITY OF THE CONTRACTOR TO PROVIDE CUTTING AND PATCHING TO ALLOW THE
INSTALLATION OF MATERIALS AND EQUIPMENT AS SPECIFIED AND SHOWN ON DRAWINGS.
E. WHERE (E) FIRE PROTECTIVE TREATMENT ON STRUCTURAL MEMBERS IS DAMAGED OR REMOVED AS A
RESULT OF WORK, REPAIR TREATMENT TO MATCH (E).
DEMOLITION NOTES
A. REVIEW DEMOLITION DRAWINGS FOR ITEMS TO REMAIN, TO BE RETAINED FOR RELOCATION, OR TO BE SALVAGED TO THE OWNER. REFER TO ARCHITECTURAL DOCUMENTS FOR ADDITIONAL REQUIREMENTS.
B. DEMOLISH EQUIPMENT, FIXTURES, DEVICES, PIPING, CONDUIT, FITTINGS, AND APPURTENANCES INTERIOR TO THE BUILDING THAT ARE MADE OBSOLETE BY THE NEW WORK AND/OR ARE ABANDONED
AND NO LONGER IN USE.
C. PROTECT AND MAINTAIN OPERABLE EXISTING EQUIPMENT, FIXTURES, OR SYSTEMS THAT ARE
INDICATED TO REMAIN, INCLUDING ELECTRICAL POWER, CONTROLS, AND RELATED SYSTEMS
REQUIRED TO MAINTAIN OPERABILITY.
D. EXISTING CONDITIONS SHOWN ARE BASED ON RECORD DOCUMENTS AND LIMITED FIELD
OBSERVATIONS OF ACCESSIBLE AREAS AND MAY NOT SHOW THE ENTIRE SCOPE OF DEMOLITION
WORK. OMISSION OF EXISTING EQUIPMENT, FIXTURES, DEVICES, PIPING, CONDUIT, FITTINGS, AND APPURTENANCES FROM THE DEMOLITION DRAWINGS DOES NOT RELIEVE THE CONTRACTOR OF THE RESPONSIBILITY TO PROVIDE DEMOLITION OF SYSTEMS THAT ARE MADE OBSOLETE BY THE NEW WORK, ARE ABANDONED, OR AS OTHERWISE REQUIRED TO PERFORM THE WORK DESCRIBED HEREIN.
E. PROTECT AND MAINTAIN SERVICES TO REMAIN OPERATIONAL THAT PASS THROUGH THE AREA OF CONSTRUCTION. WHERE IT IS NOT POSSIBLE TO MAINTAIN THESE SERVICES INTACT, REPLACE, REROUTE, MODIFY, OR PROVIDE NEW AS REQUIRED TO MAINTAIN SERVICES.
CONTROLS
SYMBOL DESCRIPTION
DP
P
PROCESS PIPING SIGNAL
ELECTRICAL SIGNAL
PRESSURE MEASUREMENT
TEMPERATURE MEASUREMENT
FLOW MEASUREMENT
ELECTRICAL CURRENT/POWER
S = SENSOR
T = TRANSMITTER
RELAY OR SWITCH
C = ELECTRIC CURRENT
FS = FLOW SWITCH
HP = HIGH PRESSURE
LP = LOW PRESSURE
A ACTUATOR - ELECTRIC
ES
AI
ALARM
VFD
CWP-2
INPUT/OUTPUT POINT
EMERGENCY STOP SWITCH
AI = ANALOG INPUT
AO = ANALOG OUTPUT
DI = DIGITAL INPUT
DO = DIGITAL OUTPUT
FUNCTION DESIGNATION
S/S = START/STOP
EQUIPMENT CONTROL PANEL
(W/EQUIP. INDICATED UNDERLINED)
CP = CONTROL PANEL
FAP = FIRE ALARM PANEL
MC = MOTOR CONTROLLER
VFD = VARIABLE FREQUENCY DRIVE
ECM = ELECTRICALLY COMMUTATED MOTOR
T
P
F S
HP
R
E C
RELAY
DP = DIFFERENTIAL POWER
1C LAB SINK SERVICE FITTING TAG
CW POTABLE COLD WATER
HW POTABLE HOT WATER
HWR POTABLE HOT WATER RETURN
NP NON-POTABLE COLD WATER
W SANITARY WASTE
PW PUMPED SANITARY WASTE
V SANITARY PLUMBING VENT
G NATURAL GAS
HTHW POTABLE HOT WATER - HIGH TEMP (140°F OR HIGHER)
IW SANITARY INDIRECT WASTE
FIRE SPRINKLER ZONE BOUNDARY
ROOM NUMBER
Room Name
ROOM MARKER
ROOM NAME
A
A
S
TPS
M
RP
DCV
AHU-12 TYPE - NUMBER
FIXTURE MARKERTYPE - NUMBERS-1
PHASING AND ALTERNATE SCOPE:
DEMOLITION & NEW WORK WILL BE PERFORMED IN PHASES & INCLUDES BASE & ALTERNATE SCOPE
OPTIONS.
ALTERNATE #1: ALTERNATE SCOPE INCLUDES REPLACING THE TWO (E) HOT WATER STORAGE TANKS WITH NEW. CONFIRM ALTERNATE SCOPE PRIOR TO STARTING DEMOLITION. ISOLATE & DRAIN ONE OF THE EXISTING STORAGE TANKS & EXAMINE TANK INTERIOR TO DETERMINE CONDITION OF THE TANK LINER & GENERAL INSIDE WALL CONDITION. IF THE (E) TANK CONDITION IS NOT ADEQUATE, REPLACE BOTH TANKS
WITH (N).
CONSTRUCTION PHASING - BASE SCOPE:
PHASE 1 : (D) ONE OF THE TWO PARALLEL DOMESTIC HOT WATER BOILERS, STORAGE TANK
RECIRCULATION PUMP, & ASSOCIATED PIPING WHILE THE SECOND BOILER & STORAGE TANK
RECIRCULATION PUMP REMAINS FULLY OPERATIONAL. PROTECT (E) FULLY OPERATIONAL BOILER SYSTEM
DURING CONSTRUCTION PROCESS.
PHASE 2: INSTALL (N) BOILERS, (N) BOILER PUMPS, (N) MASTER MIXING VALVE, (N) DHW RECIRCULATION PUMP AND ALL ASSOCIATED PIPING ACCORDING TO THE NEW WORK PLUMBING PLANS AND DIAGRAMS.
TEST AND CLEAN THE (N) INSTALLED EQUIPMENT AND PIPING. CONNECT NEW BOILERS SYSTEM TO THE
BUILDING (E) DOMESTIC HOT WATER DISTRIBUTION SYSTEM.
PHASE 3: (D) THE SECOND DOMESTIC HOT WATER BOILER, STORAGE TANK RECIRCULATION PUMP, &
ASSOCIATED PIPING ONCE THE (N) BOILER SYSTEM IS FULLY OPERATIONAL.
CONSTRUCTION PHASING -
ALTERNATE #1 SCOPE:
PHASE 1 : (D) ONE OF THE TWO PARALLEL DOMESTIC HOT WATER BOILERS, STORAGE TANK
RECIRCULATION PUMP, STORAGE TANK, & ASSOCIATED PIPING WHILE THE SECOND BOILER & STORAGE TANK RECIRCULATION PUMP REMAINS FULLY OPERATIONAL. PROTECT (E) FULLY OPERATIONAL BOILER
SYSTEM DURING CONSTRUCTION PROCESS.
PHASE 2: INSTALL (N) BOILERS, (N) BOILER PUMPS, ONE (N) STORAGE TANK, (N) MASTER MIXING VALVE, (N) DHW RECIRCULATION PUMP AND ALL ASSOCIATED PIPING ACCORDING TO THE NEW WORK PLUMBING PLANS AND DIAGRAMS. TEST AND CLEAN THE (N) INSTALLED EQUIPMENT AND PIPING. CONNECT NEW
BOILERS SYSTEM TO THE BUILDING (E) DOMESTIC HOT WATER DISTRIBUTION SYSTEM.
PHASE 3: (D) THE SECOND DOMESTIC HOT WATER BOILER, STORAGE TANK RECIRCULATION PUMP, STORAGE TANK, & ASSOCIATED PIPING ONCE THE (N) BOILER SYSTEM IS FULLY OPERATIONAL.
PHASE 4: INSTALL THE SECOND (N) HOT WATER STORAGE TANK IN PLACE OF (D) STORAGE TANK AND CONNECT IT TO THE NEW BOILER SYSTEM ACCORDING TO THE PLUMBING PLANS AND DIAGRAMS.
BALANCING VALVE
725 A Street Springfield, OR 97477 541.342.7210 systemswestengineers.com
DATE:
DRAWN:
CHECKED:
PROJECT:
DESIGNED:
OWNER:
LOCATION:
MARK DATE DESCRIPTION
/1
/2
:3
:0
P M
DPSST DWH
REPLACEMENT
P L O
T T
E D
B Y
A
L P
O
N
4190 Aumsville Hwy SE, Salem, OR 97317
Oregon Department of Public Safety Standards and Training
LEGEND,
GENERAL
NOTES, &
SHEET LIST
06.01.2026
250024.01
P001
ALP
ALP
SJS
100%
CONSTRUCTION
DOCUMENTS
SHEET LIST - PLUMBING
P001 LEGEND, GENERAL NOTES, & SHEET LIST
P121 FLOOR PLAN - LEVEL 1 - PLUMBING
P401 ENLARGED PLANS - PLUMBING
P501 PLUMBING DETAILS & DIAGRAMS
P601 PLUMBING SCHEDULES
P L U M B I N G S Y S T E M S B A S I S O F D E S I G N
BASIS OF DESIGN: 2023 OREGON PLUMBING SPECIALTY CODE, APPENDIX A 'RECOMMENDED RULES FOR SIZING THE WATER SUPPLY SYSTEM' PIPING SIZED ON 4 FT W.C./100 FT DROP UNLESS OTHERWISE NOTED, VELOCITIES NOT TO EXCEED 8 FT/S FOR COLD WATER, 5 FT/S FOR HOT WATER, OR 4 FT/S FOR
HOT WATER RETURN. WATER PIPING SIZING ASSUMES TYPE L COPPER AS BASIS OF DESIGN.
DOMESTIC WATER PIPING SYSTEM:
BASIS OF DESIGN: 2023 OREGON PLUMBING SPECIALTY CODE, CHAPTER 7 - 'SANITARY DRAINAGE' AND CHAPTER 9 - 'VENTS'
ALL WASTE PIPING SLOPED AT 1/4-INCH/FT UNLESS OTHERWISE NOTED.
ALL VENT PIPING INSTALLED HORIZONTAL OR SLOPED UPWARDS AT 1/8-INCH/FT UNLESS OTHERWISE NOTED.
SANITARY WASTE AND VENT PIPING SYSTEM:
BASIS OF DESIGN: 2025 OREGON MECHANICAL SPECIALTY CODE, APPENDIX C - 'FUEL GAS'
INDOOR PIPING SIZES SHOWN ON DRAWINGS ASSUMES SCHEDULE 40 BLACK STEEL PIPING WITH THREADED JOINTS AS BASIS OF DESIGN.
NATURAL GAS PIPING SYSTEM:
© Systems West Engineers, Inc. 2026. The signature in this document is encrypted. Editing this document is prohibited. (OAR 820)
EXPIRES: 06-30-2027
JA NUA RY 14 , 2020
DIGITALLY SIGNED
RE
GI
STERED PROFESSIONALENGINEER# 95772
OREGONN
A
T
E
J . J E NK
P401
P401
(E) 3" G
(E) 3" CW
(E) 3" HW
(E) 1" HWR
DEMO SCOPE
NEW SCOPE
(E) 1 1/2" G
(E) 3" G
(E) 3" G
(E) NG UTILITY DN
REFER TO (E) CIVIL PLANS
FOR COORDINATION.
(E) NG METER BY
UTILITY PROVIDER
NORTH
KEY PLAN
NOT TO SCALE
725 A Street Springfield, OR 97477 541.342.7210 systemswestengineers.com
DATE:
DRAWN:
CHECKED:
PROJECT:
DESIGNED:
OWNER:
LOCATION:
MARK DATE DESCRIPTION
AREA OF WORK
/1
/2
:3
:0
P M
DPSST DWH
REPLACEMENT
P L O
T T
E D
4190 Aumsville Hwy SE, Salem, OR 97317
Oregon Department of Public Safety Standards and Training
FLOOR PLAN -
LEVEL 1 -
PLUMBING
06.01.2026
250024.01
P121
ALP
ALP
SJS
100%
CONSTRUCTION
DOCUMENTS
R E F E R E N C E N O T E S :
1 INSTALL NEW 3” NATURAL GAS SEISMIC SHUT OFF VALVE ( BOD: 3” PSC-315 )
DOWNSTREAM OF THE UTILITY GAS METER. MODIFY EXISTING NATURAL GAS PIPING
AS NEEDED TO ACCOMMODATE THE SEISMIC VALVE INSTALLATION. COORDINATE
AND SCHEDULE NATURAL GAS UTILITY SHUT OFF WITH DPSST AND GENERAL
CONTRACTOR PRIOR TO BEGINNING OF WORK.
NORTH
1/4" = 1'-0"1
LEVEL 1 - PLUMBING FLOOR PLAN
© Systems West Engineers, Inc. 2026. The signature in this document is encrypted. Editing this document is prohibited. (OAR 820)
EXPIRES: 06-30-2027
JA NUA RY 14 , 2020
DIGITALLY SIGNED
RE
GI
STERED PROFESSIONALENGINEER# 95772
OREGONN
A
T
E
J . J E NK
(E ) R
P B
P
(E ) R
P B
P
3 4
(E) 3" G
(E) 3" CW
(E) 3" CW
(E) 1" HWR
(E) 3" HW
(E) 1" CW
(E) 1" HW
(E) 1 1/2" G
(E) 1 1/2" CW
(E) 1 1/2" G
(E) 1 1/2" CW
(E) 1 1/2" CW
(E) 1 1/2" CW
(E) 1" HWR
(E) 3" CW
(E) 1 1/2" G
(E) 2" CW (E) 2" CW
(E) 1" HWR
(E) 1 1/4" HW
(E) 2" HW (E) 2" HW
(E) FS
(E) FS 6
(D) B-2
(D) B-2 GAS
SUPPLY
EQUIPMENT
HWST-2 HWST-1
(D)BP-2 (D)BP-1 (D) B-1 GAS
SUPPLY
EQUIPMENT
(D) B-1
(D)RCP-1
(D) ET-1
(E) MOP SINK
(E)
RPBP
(E) EMERGENCY
SHUTOFF BUTTON
(TOP)
B-2
(ABOVE)
B-1
(BELOW)
HWRCP-1
P501
P501
P501
MMV-1
P501
ET-1
HWST-1HWST-2
1 1/2" G
(E) 1 1/2" G
(E) 1 1/2" G
NG PRV
SET @
11" W.C.
1 1/2" NG DN
TO B-1
1 1/2" NG DN
TO B-2
1 1/2" G
NG PRV SET
@ 11" W.C.
BP-1
BP-2
2 1/2" HW
2 1/2" HW
2 1/2" HW TO B-1
2 1/2" HW
2 1/2" HW
2 1/2" HW TO B-2
3" CW
1" HWR
3" HW (140)
3" HW (120)
3" H
W
E
(E
1" H
W R
(E
3" C
W (E
3"
C W
(E
3" C
W
(E) 1 1/2" CW
(E
1/
2" C
W
(E
3" G
(E
3" H
W
(E
1" H
W R
(E
3" C
W
(E
3" G
(E) 1" HWR
(E) EMERGENCY
SHUTOFF BUTTON
P501
P501
P501
P501
NORTH
KEY PLAN
NOT TO SCALE
725 A Street Springfield, OR 97477 541.342.7210 systemswestengineers.com
DATE:
DRAWN:
CHECKED:
PROJECT:
DESIGNED:
OWNER:
LOCATION:
MARK DATE DESCRIPTION
AREA OF WORK
/1
/2
:3
:1
P M
DPSST DWH
REPLACEMENT
P L O
T T
E D
4190 Aumsville Hwy SE, Salem, OR 97317
Oregon Department of Public Safety Standards and Training
ENLARGED
PLANS -
PLUMBING
06.01.2026
250024.01
P401
ALP
ALP
SJS
100%
CONSTRUCTION
DOCUMENTS
NORTH
1/2" = 1'-0"1
LEVEL 1 - ENLARGED PLUMBING DEMOLITION PLAN
NORTH
1/2" = 1'-0"2
LEVEL 1 - ENLARGED PLUMBING FLOOR PLAN
S H E E T N O T E S :
R E F E R E N C E N O T E S :
1 REMOVE (E) BOILER, (E) RECIRCULATION PUMP WITH ASSOCIATED PIPING AND (E)
GAS SUPPLY REGULATOR. CAP OFF THE ASSOCIATED PIPING. .
BASE BID: RETAIN (E) DOMESTIC HOT WATER STORAGE TANK & REUSE WITH
CONNECTED (N) DOMESTIC HOT WATER BOILER.
ALTERNATE #1: (D) DOMESTIC HOT WATER STORAGE TANK & PROVIDE (N).
DEMOLISH (E) DOMESTIC HOT WATER RECIRCULATION PUMP.
DEMOLISH (E) DOMESTIC HOT WATER EXPANSION TANK.
KEEP (E) PLUMBING FIXTURE / DEVICE IN PLACE. PROTECT PLUMBING FIXTURE /
DEVICE AND ASSOCIATED PIPING DURING THE CONSTRUCTION PROCESS.
(E) FLOOR SINK TO BE REUSED FOR NEW BOILERS DRAINAGE. PROTECT (E) FLOOR
SINK DURING CONSTRUCTION PROCESS.
PROVIDE NEW 3'-2" (W) X 6'-4" (L) X 6" (H) CONCRETE HOUSING PAD TO
ACCOMMODATE NEW BOILERS.
RELOCATE (E) FIRE SPRINKLER PIPING & SPRINKLER HEADS IN THIS AREA AS
NECESSARY TO ACCOMMODATE DEMOLITION & NEW WORK.
EXISTING EMERGENCY SHUT OFF BUTTON TO SHUT OFF THE NATURAL GAS SUPPLY
AND ELECTRICAL POWER SUPPLY TO THE NEW BOILERS. COORDINATE SCOPE OF
WORK WITH ELECTRICAL CONTRACTOR.
1. REFER TO PHASING & ALTERNATE SCOPE NARRATIVE ON P001.
2. EXAMINE ALL EXISTING PIPE PENETRATIONS THROUGH BOILER ROOM WALLS AND
CEILING FOR ASSOCIATED FIRE RATING. REPLACE OR ADD NEW FIRE STOPPING AS
REQUIRED TO PROVIDE 2 HOUR FIRE RATING OF THE EXISTING BOILER ROOM.
© Systems West Engineers, Inc. 2026. The signature in this document is encrypted. Editing this document is prohibited. (OAR 820)
EXPIRES: 06-30-2027
JA NUA RY 14 , 2020
DIGITALLY SIGNED
RE
GI
STERED PROFESSIONALENGINEER# 95772
OREGONN
A
T
E
J . J E NK
HOT WATER
STORAGE
TANK
HOT WATER
STORAGE
TANK
EXP.
TANK
RVRV
HWST-1 HWST-2
BP-1
HWRCP-1
HEAT TRAP
MIN 24"
(E) 3" 120 HW TO FIXTURES
(E) 3" CW
MMV-1
AI
AI
AI
AI
(E) 1" HWR
BOILER
B-1
BOILER
B-2
BP-2
3" NG (2PSI)
1 1/4" NG
1 1/4" NG
2 1/2" HW
2 1/2" HW
2 1/2" HW
2 1/2" HW
(E) 3" NG
2" N
G
2 1/2" HW
2 1/2" HW
(E) 2" 140 HW (E) 3" 140 HW
(E) 2" CW (E) 3" CW
2" C
W
2" C
W 3"
H
W
3" H
W
3" C
W
1" H
W R
3" CW
BOILER
MANUFACTURER
RACK ASSEMBLY
NEW 6" HIGH
CONCRETE
HOUSING PAD.
BALANCING
VALVEET-1
R V
R V
(E)FS (E)FS
T
T
T T
NG PRV SET
AT 11" W.C.
(TYP 2)
AI AI AI
AI
DI
AI
T
AI
T
T
AIAI
AI AI
T T
2 2
POWER
E C
HWRCP-1
DI
B-1 POWER
R
POWER
BY DIV. 26
POWER
TO BOILER
DO
ENABLE/DISABLE
B-2 POWER
R
POWER
BY DIV. 26
DO
ENABLE/DISABLE
POWER
TO BOILER
AO
A. REFER TO PLANS FOR SIZES, LOCATION AND CONTINUATION
FLOOR SINK
INDIRECT DRAIN PIPE
STEEL CHANNEL SUPPORT
AND PIPE CLAMP TYP
1" MIN AIR GAP ABOVE
FLOOD RIM OF FIXTURE
SLOPE
D E T A I L G E N E R A L N O T E S :
EQUIPMENT
ISOLATION
VALVE
MIN 4" DIRT LEG, LINE SIZE.
PROVIDE A MIN OF 6"
CLEARANCE BELOW THE CAP
FOR MAINTENANCE ACCESS
PRV LINE SIZE AS
SHOWN ON PLANS
RECOMMENDED BY THE PRV MFGR
MIN DISTANCE: 3 FEET OR AS
CAPPED
TEE
FLEXIBLE CONNECTOR
EXCEPT WHERE THE GAS APPLIANCE IS SUPPLIED WITH A PRESSURE TEST PORT
ON THE GAS INLET, PROVIDE A CAPPED TEE A MINIMUM OF 10 PIPE DIAMETERS
DOWNSTREAM OF THE PRV.
VENT TO OUTDOORS. TERMINATE WITH SCREENED, DOWNWARD FACING OPENING.
DO NOT REUSE (E) GAS VENT PIPING. UON BY GAS EQUIPMENT OR PRV
MANUFACTURERS, INCREASE PRV VENT SIZE BY ONE SIZE FOR EVERY 10
EQUIVALENT FEET OF LENGTH BEYOND THE FIRST 10 EQUIVALENT FEET. (TYP)
D E T A I L R E F E R E N C E N O T E S :
PIPE HANGER SUPPORT
ADJACENT TO PUMP FLANGE
OR UNION, TYP
VIBRATION ISOLATORS
WHERE SPECIFIED
A. PROVIDE A MINIMUM OF 5 PIPE DIAMETERS BETWEEN BOTH SUCTION AND DISCHARGE
SIDES OF PUMP & TEE, STRAINERS, VALVES, OR 90 DEGREE FITTINGS.
B. ORIENT MOTOR PER MANUFACTURER'S RECOMMENDATIONS.
C. WHERE PUMP DOES NOT HAVE INTEGRAL TAPS FOR PRESSURE PORTS, PROVIDE 1/4-
INCH PIPE WITH ISOLATION VALVE ON EITHER SIDE OF PUMP AS SHOWN AS CLOSE TO
PUMP FLANGES AS POSSIBLE.
PIPE & ISOLATION VALVE WITH
FEMALE THREADING & THREADED
PLUG IN OPEN END
5 PIPE DIAMETERS MIN
D E T A I L G E N E R A L N O T E S :
ROUGHEN SURFACE OF FLOOR AND COAT WITH
EPOXY BONDING AGENT BEFORE CASTING NEW PAD.
PUMP BASES: MIN (6)
1/2"Ø EXP. ANCHORS,
2-1/2" EMBEDMENT
#4 @ 18" O.C. EACH WAYPROVIDE 1/2" MIN TO 1" MAX THICKNESS
OF NON-SHRINK GROUT UNDER PUMP
BASE AFTER ALIGNING PUMP.
SIZE PAD MINIMUM 2"
LARGER THAN EQUIP.
BASE, ALL SIDES
45° CHAMFER
CONCRETE FLOOR#4 (GR 60) DOWELS AT 18" O.C.
EACH WAY, SET IN EPOXY
3000 PSI MIN
6"
1/
2"
725 A Street Springfield, OR 97477 541.342.7210 systemswestengineers.com
DATE:
DRAWN:
CHECKED:
PROJECT:
DESIGNED:
OWNER:
LOCATION:
MARK DATE DESCRIPTION
/1
/2
:3
:1
P M
DPSST DWH
REPLACEMENT
P L O
T T
E D
4190 Aumsville Hwy SE, Salem, OR 97317
Oregon Department of Public Safety Standards and Training
PLUMBING
DETAILS &
DIAGRAMS
06.01.2026
250024.01
P501
ALP
ALP
SJS
100%
CONSTRUCTION
DOCUMENTS
NOT TO SCALE
DHW BOILER SYSTEM DIAGRAM
B A S - DPSST DWH SYSTEM
POINT TYPE POINT NAME
BAS POINT
COMMUNICATION
POINT SOURCE
AI BOILER # 1 FLAME FAIL ALARM PTP B-1
AI BOILER # 1 STAGE CONTROL ALARM PTP B-1
AI BOILER # 1 TEMP IN PTP
AI BOILER # 1 TEMP OUT PTP
AI BOILER # 2 FLAME FAIL ALARM PTP B-2
AI BOILER # 2 STAGE CONTROL ALARM PTP B-2
AI BOILER # 2 TEMP IN PTP
AI BOILER # 2 TEMP OUT PTP
AI BUILDING HOT WATER SUPPLY TEMP PTP
AI MIXING VALVE TEMP COLD IN C MMV-1
AI MIXING VALVE TEMP HOT IN C MMV-1
AI MIXING VALVE TEMP RETURN C MMV-1
AI STORAGE TANK # 1 TEMP PTP
AI STORAGE TANK # 2 TEMP PTP
AO DHW RECIRCULATION PUMP SPEED PTP HWRCP-1
DI DHW RECIRCULATION PUMP STATUS PTP
DI MIXING VALVE ALARM STATUS C MMV-1
DO BOILER # 1 ENABLE/DISABLE PTP
DO BOILER # 2 ENABLE/DISABLE PTP
R E F E R E N C E N O T E S :
1 BOILER RECIRCULATION PUMP CONTROLLED BY THE INTEGRAL BOILER CONTROLS
SYSTEM.
BOILER MANUFACTURER PROVIDED AQUASTAT AND INTERCONNECTED WITH
INTEGRAL BOILER CONTROLS SYSTEM.
S H E E T N O T E S :
1. REFER TO PHASING & ALTERNATE SCOPE NARRATIVE ON P001.
© Systems West Engineers, Inc. 2026. The signature in this document is encrypted. Editing this document is prohibited. (OAR 820)
NOT TO SCALE
FLOOR SINK
NOT TO SCALE
GAS PIPING CONNECTION
NOT TO SCALE
IN-LINE CIRCULATION PUMP
NOT TO SCALE
EQUIPMENT PAD
EXPIRES: 06-30-2027
JA NUA RY 14 , 2020
DIGITALLY SIGNED
RE
GI
STERED PROFESSIONALENGINEER# 95772
OREGONN
A
T
E
J . J E NK
725 A Street Springfield, OR 97477 541.342.7210 systemswestengineers.com
DATE:
DRAWN:
CHECKED:
PROJECT:
DESIGNED:
OWNER:
LOCATION:
MARK DATE DESCRIPTION
/1
/2
:3
:1
P M
DPSST DWH
REPLACEMENT
P L O
T T
E D
4190 Aumsville Hwy SE, Salem, OR 97317
Oregon Department of Public Safety Standards and Training
PLUMBING
SCHEDULES
06.01.2026
250024.01
P601
ALP
ALP
SJS
100%
CONSTRUCTION
DOCUMENTS
NOTES:
1.BOILERS B-1 AND B-2 ARE INTENDED TO BE STACKED. PROVIDE BOILER MANUFACTURER'S RACK ASSEMBLY FOR STACKED BOILERS INSTALLATION.
B O I L E R - H O T W A T E R
TAG MANUFACTURER MODEL TYPE
CAPACITY DESIGN
FLOW
(GPM)
MIN FLOW
[GPM]
DESIGN
PRESS DROP
[ FT WC]
EWT
(°F)
LWT
(°F)
NATURAL GAS OPERATING
WEIGHT
(LBS)
ELECTRICAL
NOTESINPUT
(BTU/HR)
OUTPUT
(BTU/HR)
INPUT
(CFH)
PRESSURE
(IN WC)
VOLTS PHASE MCA MOP
B-1 RBI DOMINATOR 1350 NON
CONDENSING,
MULTI
STAGEBOILER
1,350,000 1,134,000 65 5 2.48 50 140 1,350,000 11.0 805 120 1 11 20 1
B-2 RBI DOMINATOR 1350 NON
CONDENSING,
MULTI
STAGEBOILER
1,350,000 1,134,000 65 5 2.48 50 140 1,350,000 11.0 805 120 1 11 20 1
M I X I N G V A L V E S
TAG MANUFACTURER MODEL TYPE SERVICE LOCATION
FLOW
(GPM)
PRESSURE
DROP
(PSI)
TEMPERATURES (°F) CONNECTIONS (IN) ELECTRICAL
NOTES
EWT LWT
HOT
INLET
COLD
INLET
OUTLET VOLTS PHASE
MMV-1 LEONARD
NUCLEUS
NV-300-LF
DIGITALLY CONTROLLED MIXING
VALVE
DHW BOILER ROOM 135 10 140 120 3 3 3
120 1
P L U M B I N G E X P A N S I O N T A N K S
TAG MANUFACTURER MODEL SERVICE TYPE ORIENTATION LOCATION
VOLUME (GAL) PRESSURE (PSIG)
TEMPERATURE
(°F)
CONNECTIONS (IN) DIMENSIONS
NOTES
TANK ACCEPTANCE MAX PRECHARGE SYSTEM EWT LWT INLET DRAIN
DIA
(IN)
LENGTH
(IN)
WEIGHT
(LBS)
ET-1 AMTROL ST-80VC DHW DIAPHRAGM VERTICAL BOILER ROOM 53 35 175 55 60 50 140 1 1/4 3/4 24 37 296
1. PROVIDE BAS TEMPERATURE SENSORS AND BOILER AQUASTAT TANK CONNECTION.
NOTES:
GENERAL NOTES:
A. SEE SPECIFICATION SECTION FOR ADDITIONAL CONNECTIONS.
P L U M B I N G D H W S T O R A G E T A N K S - A L T E R N A T E # 1
TAG MANUFACTURER MODEL SERVICE LOCATION
VOLUME
(GAL)
PRESSURE
RATING
(PSI)
ASME
STAMP
ORIENTATION
WEIGHT
(LBS)
DIMENSIONS (IN) CONNECTIONS (IN)
NOTESDIA
(IN)
LENGTH
HEIGHT
LEG /
PAD
HEIGHT
INLET OUTLET DRAIN CIRC IN CIRC OUT
HWST-1 NILES STEEL
TANK
S-48-120
DHW
BOILER ROOM 860 125 YES VERTICAL 1567 48 72 - 3 3 1 1/4 2 1/2 2 1/2 1
HWST-2 NILES STEEL
TANK
S-48-120
DHW
BOILER ROOM 860 125 YES VERTICAL 1567 48 72 - 3 3 1 1/4 2 1/2 2 1/2 1
GENERAL NOTES:
A. MOTOR CONTROL FURNISHED BY DIVISION 22.
B. MOTOR CONTROL TYPE: ECM: ECM MOTOR CONTROLLER
C. REFER TO SCHEMATIC DIAGRAMS FOR PUMP CONTROL CONNECTIONS TO BUILDING BAS.
D. REFER TO SECTION 22 11 23 FOR PUMP CONTROLS.
P U M P S
TAG MANUFACTURER MODEL TYPE SERVICE LOCATION
FLOW
(GPM)
HEAD
(FT WC)
DISCHARGE
SIZE
(IN)
WEIGHT
(LBS)
ELECTRICAL
MOTOR
CONTROL
NOTES
HP RPM VOLTS PHASE
HWRCP-1 BELL AND GOSSETT ECOCIRC XL 55-45 ECM DHW RECIRCULATION BOILER ROOM 15 34 1" 22 0.34 3782 208 1
TEMPERATURE SENSOR / TIME CONTROL
BY BAS
BP-1 TACO 1911ECM-SF ECM B-1 TO HWST-1 DHW CIRCULATION BOILER ROOM 65 12 1 1/2" 32 0.60 120 1 TEMPERATURE SENSOR / B1
BP-2 TACO 1911ECM-SF ECM B-2 TO HWST-2 DHW CIRCULATION BOILER ROOM 65 12 1 1/2" 32 0.60 120 1 TEMPERATURE SENSOR / B2
© Systems West Engineers, Inc. 2026. The signature in this document is encrypted. Editing this document is prohibited. (OAR 820)
EXPIRES: 06-30-2027
JA NUA RY 14 , 2020
DIGITALLY SIGNED
RE
GI
STERED PROFESSIONALENGINEER# 95772
OREGONN
A
T
E
J . J E NK
M E C H A N I C A L L E G E N D
DUCTWORK GENERAL GENERAL NOTES
ABBREV ABBREVIATION
ACH AIR CHANGES PER HOUR
AD ACCESS DOOR
AFF ABOVE FINISHED FLOOR
AI ANALOG INPUT
AL ALUMINUM
ALT ALTERNATE
AMP AMPERE
AO ANALOG OUTPUT
APD AIR PRESSURE DROP
BAS BUILDING AUTOMATION SYSTEM
BHP BRAKE HORSEPOWER
BOD BOTTOM OF DUCT
BTUH BRITISH THERMAL UNITS PER HOUR
CFH CUBIC FEET per HOUR CFM CUBIC FEET per MINUTE
CMU CONCRETE MASONRY UNIT
CONC CONCRETE
CONT CONTINUATION
CU FT CUBIC FEET
D DEPTH
(D) DEMOLITION
DB DRY BULB
dBa DECIBELS ACOUSTIC
DDC DIRECT DIGITAL CONTROL
DEMO DEMOLITION
DI DIGITAL INPUT
DN DOWN
DO DIGITAL OUTPUT
DP DIFFERENTIAL PRESSURE
(E) EXISTING
EA EXHAUST AIR
EAT ENTERING AIR TEMPERATURE
ECM ELECTRONICALLY COMMUTATED MOTOR
EER ENERGY EFFICIENCY RATIO
EFF EFFICIENCY
EG EXHAUST GRILLE
ENT ENTERING
ESP EXTERNAL STATIC PRESSURE
EWT ENTERING WATER TEMPERATURE
°F DEGREES FAHRENHEIT
FLA FULL LOAD AMPS
FP FIRE PROTECTION
FPM FEET PER MINUTE
FPS FEET PER SECOND
FT FEET
FT2 SQUARE FEET
FT WC FEET WATER COLUMN
FUT FUTURE
GALV GALVANIZED
GPM GALLONS PER MINUTE
GYPBD GYPSUM WALL BOARD
H HEIGHT
HP HORSEPOWER
HVAC HEATING, VENTILATING,
& AIR CONDITIONING
HZ HERTZ (CYCLES PER SECOND)
IAQ INDOOR AIR QUALITY
IN INCHES
IN WC INCHES WATER COLUMN
A. THE FACILITY WILL REMAIN IN OPERATION DURING CONSTRUCTION. COORDINATE ALL SHUTDOWNS
AND CONSTRUCTION ACTIVITY WITH FACILITIES STAFF.
B. SIZE AND LOCATION OF ALL PIPING AND OTHER MECHANICAL EQUIPMENT IS APPROXIMATE.
CONTRACTOR SHALL SITE VERIFY THE LOCATION OF EXISTING PIPING AND EQUIPMENT AND
CONSTRUCT WORK FROM FIELD DIMENSIONS. CONTRACTOR SHALL MAKE ADJUSTMENTS
NECESSARY TO ACCOMMODATE MINOR DEVIATIONS AT NO COST TO OWNER.
C. FINE (LIGHT) LINE WORK INDICATES EXISTING PIPING AND OTHER MECHANICAL EQUIPMENT. BOLD
(HEAVY) LINE WORK INDICATES NEW PIPING AND OTHER MECHANICAL EQUIPMENT.
D. IT IS RESPONSIBILITY OF THE CONTRACTOR TO PROVIDE CUTTING AND PATCHING TO ALLOW THE
INSTALLATION OF MATERIALS AND EQUIPMENT AS SPECIFIED AND SHOWN ON DRAWINGS.
SYMBOL DESCRIPTION SYMBOL DESCRIPTION
(E) ø OR dia
SHEET NUMBER
SECTION LETTER
SHEET NUMBER
EXISTING
DIAMETER
NEW TO EXISTING POINT OF CONNECTION
NOTE REFERENCE MARKER
PLAN OR DETAIL REFERENCE MARKER
SECTION REFERENCE MARKER W/VIEW DIRECTION
EQUIPMENT MARKER
ROOM NUMBER
EXISTING SHOWN LIGHT
NEW WORK SHOWN BOLD
EXISTING TO BE REMOVED
M-301
Room Name
PLAN OR DETAIL NUMBER
EXHAUST AIR UP
OUTSIDE AIR UP
SUPPLY AIR, & MAKE-UP AIR DUCT DOWN
EXHAUST AIR or OUTSIDE AIR DOWN
EA
OSA
DUCT SIZE
RECTANGLE: WIDTH (IN) x DEPTH (IN) ROUND: DIAMETER(IN) ø
12x6
CONCENTRIC TRANSITION
ECCENTRIC TRANSITION
LATERAL BRANCH
(ROUND OR OVAL)
BEVELED BRANCH
(RECTANGULAR, ROUND, OR OVAL)
RECTANGULAR DUCT ANGLED
CHANGE IN ELEVATION
ROUND DUCT ANGLED
CHANGE IN ELEVATION
DEMOLITION NOTES
A. REVIEW DEMOLITION DRAWINGS FOR ITEMS TO REMAIN, TO BE RETAINED FOR RELOCATION, OR TO
BE SALVAGED TO THE OWNER.
B. DEMOLISH EQUIPMENT, FIXTURES, DEVICES, PIPING, CONDUIT, FITTINGS, AND APPURTENANCES INTERIOR TO THE BUILDING THAT ARE MADE OBSOLETE BY THE NEW WORK AND/OR ARE ABANDONED
AND NO LONGER IN USE.
C. PROTECT AND MAINTAIN OPERABLE EXISTING EQUIPMENT, FIXTURES, OR SYSTEMS THAT ARE
INDICATED TO REMAIN, INCLUDING ELECTRICAL POWER, CONTROLS, AND RELATED SYSTEMS
REQUIRED TO MAINTAIN OPERABILITY.
D. EXISTING CONDITIONS SHOWN ARE BASED ON RECORD DOCUMENTS AND LIMITED FIELD
OBSERVATIONS OF ACCESSIBLE AREAS AND MAY NOT SHOW THE ENTIRE SCOPE OF DEMOLITION
WORK. OMISSION OF EXISTING EQUIPMENT, FIXTURES, DEVICES, PIPING, CONDUIT, FITTINGS, AND APPURTENANCES FROM THE DEMOLITION DRAWINGS DOES NOT RELIEVE THE CONTRACTOR OF THE RESPONSIBILITY TO PROVIDE DEMOLITION OF SYSTEMS THAT ARE MADE OBSOLETE BY THE NEW WORK, ARE ABANDONED, OR AS OTHERWISE REQUIRED TO PERFORM THE WORK DESCRIBED HEREIN.
E. PROTECT AND MAINTAIN SERVICES TO REMAIN OPERATIONAL THAT PASS THROUGH THE AREA OF CONSTRUCTION. WHERE IT IS NOT POSSIBLE TO MAINTAIN THESE SERVICES INTACT, REPLACE, REROUTE, MODIFY, OR PROVIDE NEW AS REQUIRED TO MAINTAIN SERVICES.
M-521
M101
MAKE-UP AIR DUCT UPMAS
ABBREV. AAV AUTOMATIC AIR VENT
AC AIR CONDITIONER
ACB ACTIVE CHILLED BEAM
AD AUTOMATIC DAMPER
AF AIR CURTAIN
AHU AIR HANDLING UNIT
AS AIR SEPARATOR
B BOILER
BD BALANCING DAMPER
BDD BACK DRAFT DAMPER
BF BOILER FEED
BF BOOSTER FAN
CB CHILLED BEAM
CC CHILLED WATER COIL
CFP CHEMICAL FEED PUMP
CFT CHEMICAL FEED TANK
CH CHILLER
CP CIRCULATING PUMP
CT COOLING TOWER
CU CONDENSING UNIT
CRU CONDENSATE RETURN UNIT
CV CONTROL VALVE
CWP CHILLED WATER PUMP
EAL EXHAUST AIR LOUVER
EDH ELECTRIC DUCT HEATER
EF EXHAUST FAN
EH EXHAUST HOOD
ET EXPANSION TANK
FC FAN COIL UNIT
FCD FLOW CONTROL DEVICE
FD FIRE DAMPER
FF FINAL FILTER
FSD FIRE SMOKE DAMPER
GF GLYCOL FEEDER
IW INDIRECT WASTE
KW KILOWATT
L LENGTH
LAT LEAVING AIR TEMPERATURE
LBS POUNDS
LON LOCAL OPERATING NETWORK
LVG LEAVING
LWT LEAVING WATER TEMPERATURE
mA MILLIAMPERE
MA MIXED AIR
MAX MAXIMUM
MBH THOUSAND BTUs per HOUR
MCA MINIMUM CIRCUIT AMPACITY
MFR MANUFACTURER
MIN MINIMUM
MIN EFF MINIMUM EFFICIENCY
MOP MAXIMUM OVERCURRENT PROTECTION
(N) NEW
NC NOISE CRITERIA
NC NORMALLY CLOSED
NIC NOT IN CONTRACT
NO NORMALLY OPEN
NR NOT REQUIRED
OAT OUTSIDE AIR TEMPERATURE
OCC OCCUPIED
OFCI OWNER FURNISHED/
CONTRACTOR INSTALLED
OSA OUTSIDE AIR
PD PRESSURE DROP
PH PHASE
PSI POUNDS per SQUARE INCH PSIG POUNDS per SQUARE INCH GAUGE
REQ'D REQUIRED
RH RELATIVE HUMIDITY
RLA RUNNING LOAD AMPS
RPM REVOLUTIONS PER MINUTE
SA SUPPLY AIR
SAT SUPPLY AIR TEMPERATURE
SCFM STANDARD CUBIC FEET PER MINUTE
SP STATIC PRESSURE
SS STAINLESS STEEL
STL STEEL
TEMP TEMPERATURE
TP TOTAL PRESSURE
TSP TOTAL STATIC PRESSURE
TYP TYPICAL
V VOLT
VP VELOCITY PRESSURE
W WATTS
WB WET BULB
WPD WATER PRESSURE DROP
WC WATER COLUMN
WG WATER GAUGE
ABBREVIATIONS EQUIPMENT ABBREVIATIONS
HC HOT WATER COIL
HP HEAT PUMP
HR HEAT RECOVERY EXCHANGER
HRC HEAT RECOVERY COIL
HRU HEAT RECOVERY UNIT
HRV HEAT RECOVERY VENTILATOR
HUM HUMIDIFER
HWP HEATING WATER PUMP
HX HEAT EXCHANGER
L LOUVER
LEF LABORATORY EXHAUST FAN
MUA MAKE UP AIR UNIT
MZ MULTI-ZONE
OAH OUTSIDE AIR HOOD
OBD OPPOSED BLADE DAMPER
OSAL OUTSIDE AIR LOUVER
P PUMP
PF PREFILTER
PHX POOL HEAT EXCHANGER
PTAC PACKAGED TERMINAL AIR
CONDITIONER
RF RETURN FAN
RH RELIEF HOOD
RTU ROOF TOP UNIT
SA SOUND ATTENUATOR
SF SUPPLY FAN
SG SUPPLY GRILLE
SHX STEAM HEAT EXCHANGER
ST STORAGE TANK
TP TOWER PUMP
TU TERMINAL UNIT
UH UNIT HEATER
VD VOLUME DAMPER
VP VACUUM PUMP
ROOM MARKER
ROOM NAME
AHU-12 TYPE - NUMBER
RADIUS
(RECTANGULAR OR ROUND)
BACKDRAFT DAMPER
BD
12ø
PHASING AND ALTERNATE SCOPE:
1. REFER TO PLUMBING DRAWINGS FOR CONSTRUCTION PHASING AND ALTERNATIVE SCOPE OF WORK
WITH IMPACTS TO MECHANICAL WORK.
725 A Street Springfield, OR 97477 541.342.7210 systemswestengineers.com
DATE:
DRAWN:
CHECKED:
PROJECT:
DESIGNED:
OWNER:
LOCATION:
MARK DATE DESCRIPTION
/1
/2
:5
:2
P M
DPSST DWH
REPLACEMENT
P L O
T T
E D
T
K
4190 Aumsville Hwy SE, Salem, OR 97317
Oregon Department of Public Safety Standards and Training
LEGEND,
GENERAL
NOTES, &
SHEET LIST
06.01.2026
250024.01
M001
TKO
TKO
NJJ
100%
CONSTRUCTION
DOCUMENTS
SHEET LIST - MECHANICAL
M001 LEGEND, GENERAL NOTES, & SHEET LIST
M401 ENLARGED PLANS - MECHANICAL
M601 DETAILS, DIAGRAMS, AND SCHEDULES
© Systems West Engineers, Inc. 2026. The signature in this document is encrypted. Editing this document is prohibited. (OAR 820)
EXPIRES: 06-30-2027
JA NUA RY 14 , 2020
DIGITALLY SIGNED
RE
GI
STERED PROFESSIONALENGINEER# 95772
OREGONN
A
T
E
J . J E NK
BD BD
D
BD
SEF E-S11(E) SEF E-S12(E)
(E) 20" VENT
UP THROUGH
ROOF
(E) 14" COMBUSTION
AIR DOWN FROM
ROOF
12ø EA
B-2
(ABOVE)
B-1
(BELOW)
12ø EA
(E) 20" VENT UP THROUGH ROOF
(E) 14" MAS DOWN FROM ROOF
SEF E-S12SEF E-S11 PROVIDE BAS PANEL FOR NEW BOILER
SYSTEM AND COMBUSTION AIR FANS.
COORDINATE PANEL LOCATION WITH
PLUMBING PIPING ALONG WALL.
14x14 MAS
14x14 MAS TO EACH FAN
NORTH
KEY PLAN
NOT TO SCALE
725 A Street Springfield, OR 97477 541.342.7210 systemswestengineers.com
DATE:
DRAWN:
CHECKED:
PROJECT:
DESIGNED:
OWNER:
LOCATION:
MARK DATE DESCRIPTION
AREA OF WORK
/1
/2
:5
:2
P M
DPSST DWH
REPLACEMENT
P L O
T T
E D
4190 Aumsville Hwy SE, Salem, OR 97317
Oregon Department of Public Safety Standards and Training
ENLARGED
PLANS -
MECHANICAL
06.01.2026
250024.01
M401
TKO
TKO
NJJ
100%
CONSTRUCTION
DOCUMENTS
NORTH
1/2" = 1'-0"1
LEVEL 1 - ENLARGED MECHANICAL DEMOLITION PLAN
NORTH
1/2" = 1'-0"2
LEVEL 1 - ENLARGED MECHANICAL FLOOR PLAN
R E F E R E N C E N O T E S :
1 DEMO EXISTING EXHAUST FLUES AND HOODS BACK TO MAIN AS SHOWN.
CONNECT NEW 12" FLUE TO TOP OUTLET OF BOILER. SEE MANUFACTURERS
VENTING INSTRUCTIONS FOR CONNECTION DETAILS.
CONNECT NEW 12" FLUE TO REAR OUTLET OF BOILER. SEE MANUFACTURERS
VENTING INSTRUCTIONS FOR CONNECTION DETAILS.
PROVIDE BAROMETRIC DAMPERS FOR BOILER VENTING AS REQUIRED BY BOILER
MANUFACTURER. INSTALL PER MANUFACTURER GUIDELINES.
S H E E T N O T E S :
1. REFER TO M601 FOR FAN SCHEDULE, DETAILS AND DIAGRAMS.
2. FOR DIV 22 BAS CONTROL WORK REFER TO PLUMBING DRAWINGS.
© Systems West Engineers, Inc. 2026. The signature in this document is encrypted. Editing this document is prohibited. (OAR 820)
EXPIRES: 06-30-2027
JA NUA RY 14 , 2020
DIGITALLY SIGNED
RE
GI
STERED PROFESSIONALENGINEER# 95772
OREGONN
A
T
E
J . J E NK
UNISTRUT ATTACHED TO
EXISTING STRUCTURE
ABOVE.
BACKDRAFT DAMPER
LOCATE AIRFLOW SWITCH ON
FAN OUTLET OR ON FAN INLET
DUCT
UNIT SUPPORT AND VIBRATION
ISOLATION AS SPECIFIED
SEE PLANS FOR DUCT SIZE
AND CONNECTION TO
COMBUSTION AIR MAIN
FLEX CONNECTOR
PROVIDE WIRE MESH COVER
OVER DUCT OR FAN OUTLET
E C
DI
BACKDRAFT DAMPER
FS
R
POWER FROM
ELECTRICAL
PANEL BY DIV 26
POWER TO COMBUSTION AIR
FAN BY DIV 26R
DI
BAS FAN
ENABLE/DISABLE
SIGNAL WIRING
FROM BOILER
CONTROLLER
BY DIV 26
SIGNAL WIRING
TO BOILER
CONTROLLER
BY DIV 26
E C
DI
R E F E R E N C E N O T E S :
1 PROVIDE AIR FLOW SWITCH FOR FAN PROOFING. WIRE SWITCH TO BOILER
CONTROLLER. COORDINATE LINE VOLTAGE WIRING WITH DIV. 26 CONTRACTOR.
2 PROVIDE RELAYS FOR COMBUSTION AIR FAN CONTROL AND INTERLOCK WITH
BOILER. COORDINATE LINE VOLTAGE WIRING WITH DIV. 26 CONTRACTOR.
725 A Street Springfield, OR 97477 541.342.7210 systemswestengineers.com
DATE:
DRAWN:
CHECKED:
PROJECT:
DESIGNED:
OWNER:
LOCATION:
MARK DATE DESCRIPTION
/1
/2
:5
:2
P M
DPSST DWH
REPLACEMENT
P L O
T T
E D
4190 Aumsville Hwy SE, Salem, OR 97317
Oregon Department of Public Safety Standards and Training
DETAILS,
DIAGRAMS,
AND
SCHEDULES
06.01.2026
250024.01
M601
TKO
TKO
NJJ
100%
CONSTRUCTION
DOCUMENTS
NOT TO SCALE
SUSPENDED FAN
NOT TO SCALE
COMBUSTION AIR FAN
B A S P O I N T S L I S T - C O M B U S T I O N A I R F A N
POINT TYPE POINT NAME
BAS POINT
COMMUNICATION
POINT SOURCE
DI BOILER FAN COMMAND STATUS PTP
DI FAN ENABLE/DISABLE PTP
DI BAS FAN COMMAND STATUS PTP
NOTES:
1.INTERLOCK BOILER OPERATION WITH MAKEUP AIR FANS. BOILERS ARE TO BE DISABLED IF FANS ARE OFF.
C O M B U S T I O N A I R F A N S
TAG MANUFACTURER MODEL TYPE
PERFORMANCE WHEEL
UNIT WEIGHT
(LBS)
SOUND LEVEL
(SONES)
MOTOR
MOTOR CONTROL NOTESAIRFLOW
(CFM)
TSP
(IN WC)
POWER (BHP)
(BHP)
TYPE
DIAMETER
(IN)
VOLTS PHASE HP
SEF E-S12 GREENHECK SQ-7-M1-VG MIXED FLOW INLINE 500 0.75 0.12 MIXED FLOW 9 40 11 120 1 0.3 ECM 1
SEF E-S11 GREENHECK SQ-7-M1-VG MIXED FLOW INLINE 500 0.75 0.12 MIXED FLOW 9 40 11 120 1 0.3 ECM 1
© Systems West Engineers, Inc. 2026. The signature in this document is encrypted. Editing this document is prohibited. (OAR 820)
EXPIRES: 06-30-2027
JA NUA RY 14 , 2020
DIGITALLY SIGNED
RE
GI
STERED PROFESSIONALENGINEER# 95772
OREGONN
A
T
E
J . J E NK
E L E C T R I C A L L E G E N D
CONCEALED RACEWAY AND CONDUCTORS. NUMBER OF SLASHES
INDICATES NUMBER OF CONDUCTORS IF MORE THAN TWO. SIZE
OTHER THAN 12 AWG AS NOTED. (APPLIES TO ALL WIRING SYMBOLS)
UNDERGROUND OR UNDERFLOOR RACEWAY
HOMERUN
OVERHEAD POWER LINE
SPLICE
OHD
GROUND CONNECTION
CONDUIT UP
CONDUIT DOWN
JUNCTION BOX
JUNCTION BOX FLUSH WITH FLOOR OR AT GRADE
CONDUIT STUB
CABLE TRAY
ELECTRICAL EQUIPMENT AS NOTED ON DRAWINGS
SURFACE-MOUNTED CABINET, TYPE AS NOTED
MECHANICAL EQUIPMENT DESIGNATOR, SEE SCHEDULES.
REFERENCE NOTE MARKER
PLAN OR DETAIL NUMBER
SHEET NUMBER
EXISTING WORK SHOWN LIGHT
NEW WORK SHOWN BOLD
EXISTING TO BE REMOVED (APPLIES TO DEMOLITION PLANS ONLY)
E-121
E-501
J
J
PB PULL BOX, SIZE AS NOTED OR AS REQUIRED
FB
FB1
SURFACE-MOUNTED PANELBOARD (120/208V)
SURFACE-MOUNTED PANELBOARD (277/480V)
RECESSED PANELBOARD (120/208V)
RECESSED PANELBOARD (277/480V)
CT
T
DISTRIBUTION TRANSFORMER
GROUNDING BUSBAR
SPECIAL PURPOSE RECEPTACLE WITH NEMA CONFIGURATION AS NOTED.L6-30R
PUSH BUTTON STATION
SIMPLEX RECEPTACLE
DUPLEX RECEPTACLE
QUADPLEX RECEPTACLE
FLUSH FLOOR BOX. REFER TO SPECIFICATIONS AND SCHEDULES FOR
DEVICE QUANTITIES AND TYPES.
FLUSH POKE-THROUGH FLOOR BOX. REFER TO SPECIFICATIONS AND
SCHEDULES FOR DEVICE QUANTITIES AND TYPES.
SPLIT-WIRED RECEPTACLE WITH HALF SWITCHED CONTROL VIA MANUAL
CONTROL, OCCUPANCY SENSING CONTROL, OR TIME BASED CONTROL.
REFER TO SPECIFICATIONS AND DRAWINGS.
RECEPTACLE WITH FULL SWITCHED CONTROL VIA MANUAL CONTROL,
OCCUPANCY SENSING CONTROL, OR TIME BASED CONTROL. REFER TO
SPECIFICATIONS AND DRAWINGS.
FB1 FLUSH FLOOR BOX WITH SWITCHED CONTROL VIA MANUAL CONTROL,
OCCUPANCY SENSING CONTROL, OR TIME BASED CONTROL. REFER TO
SPECIFICATIONS AND DRAWINGS.
PT3 FLUSH POKE-THROUGH FLOOR BOX WITH SWITCHED CONTROL VIA MANUAL
CONTROL, OCCUPANCY SENSING CONTROL, OR TIME BASED CONTROL.
REFER TO SPECIFICATIONS AND DRAWINGS.
LETTER DESIGNATOR(S) INDICATE ADDITIONAL RECEPTACLE
CHARACTERISTICS (APPLIES TO ALL RECEPTACLE AND FLOOR BOX TYPES):
A = INTEGRAL AFCI
B = INTEGRAL WITH USB OUTLET(S)
C = SUPPLIED POWER VIA CRITICAL BRANCH (NEC 517)
E = SUPPLIED POWER VIA LIFE SAFETY BRANCH (NEC 517)
G = INTEGRAL GFCI
IG = SUPPLIED POWER VIA AN ISOLATED GRD SYSTEM
P = INTEGRAL SURGE PROTECTIVE DEVICE
S = SUPPLIED POWER VIA OPTIONAL STANDBY BRANCH (NEC 702)
U = SUPPLIED POWER VIA A UPS
WP = WEATHERPROOF AND INTEGRAL GFCI
A
INDICATES RECEPTACLE ROUGH-IN HEIGHT FROM AFF TO CL OF
RECEPTACLE WHEN NOT AT STANDARD MOUNTING HEIGHT.+48"
INDICATES PANELBOARD AND BRANCH CIRCUIT NUMBER SERVING
RECEPTACLE.
2P1:12
INDICATES BRANCH CIRCUIT NUMBER SERVING RECEPTACLE. REFER TO
SHEET NOTES AND REFERENCE NOTES FOR SOURCE.
SURFACE MOUNTED RACEWAY WITH DUPLEX RECEPTACLES
RACEWAYS, BOXES, AND CONDUCTORS
ELECTRICAL EQUIPMENT - PLANS
WIRING DEVICES GENERAL
ABBREVIATIONS
(#) DESIGNATES QUANTITY
A AMPERE (AMP)
AC ALTERNATING CURRENT
AFC AVAILABLE FAULT CURRENT
AFF ABOVE FINISHED FLOOR
AFG ABOVE FINISHED GRADE
AL ALUMINUM
ARCH ARCHITECT/ARCHITECTURAL
ATS AUTOMATIC TRANSFER SWITCH
AWG AMERICAN WIRE GAUGE
BLDG BUILDING
BOCT BOTTOM OF CABLE TRAY
BSC BIOLOGICAL SAFETY CABINET
C. CONDUIT
CENT CENTRIFUGE
CKT CIRCUIT
CL CENTERLINE
CLG CEILING
CRI COLOR RENDERING INDEX
CU COPPER
DC DIRECT CURRENT
DF DRINKING FOUNTAIN
DW DISHWASHER
(E) EXISTING
ECR ENVIRONMENTAL CONTROL ROOM
ELEC ELECTRICAL
EMERG EMERGENCY
EMT ELECTRICAL METALLIC TUBING
EV ELECTRIC VEHICLE
FA FIRE ALARM
FH FUME HOOD
FLA FULL LOAD AMPS
FTL FEED-THROUGH LUGS
GFCI GROUND FAULT CIRCUIT INTERRUPTER
GFP GROUND FAULT PROTECTION
GND GROUND
HP HORSEPOWER
IDF INTERMEDIATE DISTRIBUTION FRAME
INC INCUBATOR
K KELVIN
KW KILOWATT
KWH KILOWATT-HOUR
KV KILOVOLT
KVA KILOVOLT-AMPERE
KVAR KILOVOLT-AMPERE REACTIVE
LED LIGHT EMITTING DIODE
LM LUMENS
LV LOW VOLTAGE
LSI LSI ELECTRONIC TRIP UNIT
LSI/G LSI/G ELECTRONIC TRIP UNIT
LTG LIGHTING
MCA MINIMUM CIRCUIT AMPACITY
MCB MAIN CIRCUIT BREAKER
MCC MOTOR CONTROL CENTER
MDF MAIN DISTRIBUTION FRAME
MDS MAIN DISTRIBUTION SWITCHBOARD
MDP MAIN DISTRIBUTION PANELBOARD
MECH MECHANICAL
MLO MAIN LUG ONLY
MTS MAIN TRANSFER SWITCH
MVA MEGAVOLT-AMPERE
MW MEGAWATT
(N) NEW
(NL) NEW LOCATION
NA NOT APPLICABLE
NIC NOT IN CONTRACT
PA PUBLIC ADDRESS
PE PHOTOELECTRIC CELL
PF POWER FACTOR
PNL PANELBOARD
PV PHOTOVOLTAIC
PVC POLYVINYL CHLORIDE
PWR POWER
(R) REMOVE
(RL) RELOCATE
REFL REFLECTOR
SCCR SHORT CIRCUIT CURRENT RATING
SDP SUB-DISTRIBUTION PANELBOARD
SWBD SWITCHBOARD
TR TAMPER RESISTANT
TTB TELEPHONE TERMINAL BOARD
TV TELEVISION
TYP TYPICAL
UC UNDER CABINET
UG UNDERGROUND
UON UNLESS OTHERWISE NOTED
UPS UNINTERRUPTIBLE POWER SUPPLY
V VOLTAGE
VA VOLT-AMPERE
VP VAPOR PROOF
W WATT
WP WEATHERPROOF
XFMR TRANSFORMER
PT1
ELECTRICAL EQUIPMENT DESIGNATIONS
4 E - SWB - D1 A
VOLTAGE
POWER SOURCE
EQUIPMENT TYPE
2 - 208Y/120V (3-PHASE)
4 - 480Y/277V (3-PHASE)
N - NORMAL POWER (ELECTRIC UTILITY)
E - EMERGENCY POWER (GENERATOR, NEC 700)
R - REQUIRED STANDBY POWER (GENERATOR, NEC 701)
S - OPTIONAL STANDBY POWER (GENERATOR, NEC 702)
BLANK - PANELBOARD
SWB - SWITCHBOARD
T - TRANSFORMER
ATS - AUTOMATIC TRANSFER SWITCH
MTS - MANUAL TRANSFER SWITCH
GEN - GENERATOR
DS - DISCONNECT SWITCH
LOCATION BY BUILDING AND LEVEL
SERIES INDICATOR
D1 - DISTRICT UTILITY PLAN, LEVEL 1
CW1 - CORDLEY HALL WEST, LEVEL 1
CW2 - CORDLEY HALL WEST, LEVEL 2
CW3 - CORDLEY HALL WEST, LEVEL 3
CW4 - CORDLEY HALL WEST, LEVEL 4
CW5 - CORDLEY HALL WEST, LEVEL 5
A - FIRST IN A SERIES OF EQUIPMENT
B - SECOND IN A SERIES OF EQUIPMENT
ETC.
E1A-1 LAB EQUIPMENT DESIGNATOR, SEE SCHEDULES.
AHU-12FUTURE EV CHARGING STATION (ROUGH-IN ONLY)
WALL-MOUNTED EV CHARGING STATION. SINGLE-PORT, DUAL-PORT.
PEDESTAL-MOUNTED EV CHARGING STATION. SINGLE-PORT, DUAL-PORT.
NUMERICAL DESIGNATOR INDICATES EV CHARGING STATION TYPE.
2 = FUTURE LEVEL 2 EV CHARGING STATION, LEVEL 2 EV CHARGING
STATION
3 = FUTURE LEVEL 3 EV CHARGING STATION, LEVEL 3 EV CHARGING
STATION
2 2
F
CONTINUATION LINE
BY DIVISION 26
BY DIVISION 26 COMBUSTION AIR FAN
BY DIVISION 23CIRCULATION PUMP BY DIVISION 22
FIELD WIRING BY DIVISION 26, UON
TO MANUFACTURER WIRING
TYPICAL
D E T A I L G E N E R A L N O T E S :
A. FIELD WIRING REQUIREMENTS SHOWN ARE AS PROVIDED BY BASIS OF DESIGN
MANUFACTURER. COORDINATE ACTUAL REQUIREMENTS WITH OTHER TRADES AND
WITH EQUIPMENT SUPPLIED PRIOR TO COMMENCING WORK.
725 A Street Springfield, OR 97477 541.342.7210 systemswestengineers.com
DATE:
DRAWN:
CHECKED:
PROJECT:
DESIGNED:
OWNER:
LOCATION:
MARK DATE DESCRIPTION
/1
/2
:3 :2
A
M
DPSST DWH
REPLACEMENT
P L O
T T
E D
J
H
O
N
4190 Aumsville Hwy SE, Salem, OR 97317
Oregon Department of Public Safety Standards and Training
LEGEND,
GENERAL
NOTES,
SCHEDULES,
DIAGRAMS, &
SHEET LIST
06.01.2026
250024.01
E001
AJW
JSH
MBR
100%
CONSTRUCTION
DOCUMENTS
SHEET LIST - ELECTRICAL
E001 LEGEND, GENERAL NOTES, SCHEDULES, DIAGRAMS, & SHEET LIST
E101 DEMOLITION PLAN - LEVEL 1
E121 FLOOR PLAN - LEVEL 1
D. BRANCH CIRCUIT SERVES MULTIPLE PIECES OF EQUIPMENT. FIELD WIRING BY DIVISION 26 IS REQUIRED. REFER TO WIRING DIAGRAM AND COORDINATE WITH EQUIPMENT SUPPLIED.
C. UTILIZE EXISTING BRANCH CIRCUIT AND BREAKER PREVIOUSLY SERVING DEMOLISHED EQUIPMENT.
B. FUSED DISCONNECTS FURNISHED BY DIVISION 23 AND INSTALLED BY DIVISION 26. COORDINATE WITH EQUIPMENT SUPPLIED.
A. EQUIPMENT CONNECTION IS CORD AND PLUG TYPE.
NOTES:
2. WHERE INDICATED IN SCHEDULE ABOVE, DISCONNECTS SHALL BE FURNISHED AND INSTALLED BY DIVISION 26. COORDINATE DISCONNECT REQUIREMENTS WITH MECHANICAL.
1. PROVIDE CONDUCTORS WITH TYPE XHHW INSULATION FOR FEEDERS AND BRANCH CIRCUITS BETWEEN VFDS AND THEIR ASSOCIATED MOTORS.
GENERAL NOTES:
SEF E-S12 COMBUSTION AIR FAN 120 1 0.6 5.0 (2) 12 AWG CU, (1) 12 AWG GND. IN 3/4" C. 15/1 E-L1S SEC 3:101 NA DIV 23 NA B,D
SEF E-S11 COMBUSTION AIR FAN 120 1 0.6 5.0 (2) 12 AWG CU, (1) 12 AWG GND. IN 3/4" C. 15/1 E-L1S SEC 3:88 NA DIV 23 NA B,D
BAS BUILDING AUTOMATION SYSTEM 120 1 0.3 2.5 (2) 12 AWG CU, (1) 12 AWG GND. IN 3/4" C. 20/1 E-L1S SEC 3:103 NA NA NA
MMV-1 MIXING VALVE 120 1 0.1 0.8 (2) 12 AWG CU, (1) 12 AWG GND. IN 3/4" C. 20/1 E-L1S SEC 3:105 NA NA NA A
HWRCP-1 HOT WATER CIRCULATION PUMP 208 1 0.75 3.6 (2) 12 AWG CU, (1) 12 AWG GND. IN 3/4" C. 15/2 E-L1S SEC 3:97,99 NA NA NA
BP-2 CIRCULATION PUMP #2 120 1 0.43 3.6 (2) 12 AWG CU, (1) 12 AWG GND. IN 3/4" C. 15/1 E-L1S SEC 3:101 NA DIV 26 NA D
BP-1 CIRCULATION PUMP #1 120 1 0.43 3.6 (2) 12 AWG CU, (1) 12 AWG GND. IN 3/4" C. 15/1 E-L1S SEC 3:88 NA DIV 26 NA D
B-2 BOILER #2 120 1 1.19 9.9 (2) 12 AWG CU, (1) 12 AWG GND. IN 3/4" C. 20/1 E-L1S SEC 2:72 NA NA NA C
B-1 BOILER #1 120 1 1.19 9.9 (2) 12 AWG CU, (1) 12 AWG GND. IN 3/4" C. 20/1 E-L1S SEC 2:70 NA NA NA C
TAG DESCRIPTION VOLTAGE PHASE HP KW FLA FEEDER DESCRIPTION
CIRCUIT BREAKER
(AMPS/POLES)
PANEL
IDENTIFICATION
STARTER
DIVISION
DISCONNECT
DIVISION
VFD
DIVISION
NOTES
MECHANICAL EQUIPMENT CONNECTION SCHEDULE
DEMAND AMPS 7.6 13.8 9.8
CONNECTED AMPS 5.6 11.8 7.8
DEMAND VA 910 1650 1175
PHASE TOTALS CONNECTED VA 675 1415 940 ** 100% PLUS 25% OF THE LARGEST MOTOR
A B C * 10KVA AT 100%, REMAINDER AT 50%
SPACE 0 125 C 126 0 E-L2S
SPACE 0 123 B 124 0 E-L2S
SPACE 0 121 A 122 0 E-L2S 3 225
SPACE 0 119 C 120 0 SPACE
SPACE 0 117 B 118 0 SPACE
SPACE 0 115 A 116 0 SPACE
SPACE 0 113 C 114 0 SPACE
SPACE 0 111 B 112 0 SPACE
SPACE 0 109 A 110 0 SPACE
SPACE 0 107 C 108 0 SPACE
20 1 (NN) EQ: MMV-1 100 105 B 106 0 SPACE
20 1 (NN) EQ: BAS PANEL 300 103 A 104 0 SPACE
15 1 (NN) EQ: SEF E-S12, BP-2 940 101 C 102 0 SPACE
375 99 B 100 0 SPACE
15 2 (NN) EQ: HWRCP-1 375 97 A 98 0 SPACE
95 C 96 (E) LTG: PIT LIGHTS 1 20
20 2 (E) EUH-E-S2 93 B 94 (E) RCPT: PIT GFCI 1 20
91 A 92 0 (E) SPARE 1 20
20 2 (E) EUH-E-S1 89 C 90 0 (E) SPARE 1 20
87 B 88 940 (EN) EQ: SEF E-S11, BP-1 1 15
20 2 (E) CUH-E-S1 85 A 86 (E) ELEVATOR SUMP PUMP 1 15
A P DESCRIPTION WATTS NO. PHASE NO. WATTS DESCRIPTION P A
BREAKER CIR. CIR. BREAKER
MAXIMUM PHASE AMPS 11.8 13.8
TOTAL VOLT-AMPS 3,030 3,735
CONNECTED DEMAND
SUBFEED BREAKER 0 0
NOTES: EXISTING PANEL SUB-FED FROM (E) E-L1S SEC 2
(E) INDICATES EXISTING BREAKER SERVING EXISTING LOAD
(EN) INDICATES EXISTING BREAKER SERVING NEW LOAD
(NN) INDICATES NEW BREAKER SERVING NEW LOAD
MISC. LOADS 400 100% 400
SUBFEED 0 100% 0
MOUNTING: SURFACE RESISTANCE LOADS 0 100% 0
MAIN: MLO AFC: MOTOR LOADS 2630 ** 3335
LOCATION: RECEPTACLES 0 * 0
PHASE: 3 WIRE: 4 LIGHTING 0 125% 0
VOLTS: 120/208 LOAD CLASS VA FACTOR LOAD VA
TYPE: BOLT ON AMPS: 600 CONN. DEMAND DEMAND
PANEL: (E) E-L1S SEC 3
PANEL SCHEDULE
NOT TO SCALE
PARTIAL BOILER FIELD WIRING DIAGRAM
NOT TO SCALE. BASIS OF DESIGN: RBI DOMINATOR 1350
© Systems West Engineers, Inc. 2026. The signature in this document is encrypted. Editing this document is prohibited. (OAR 820)
EXP IRES : 12 - 3 1- 26
MA Y 21, 2014
RE
GI
STE
RED PROFESSIONALENGINEER# 80,621
OREGONM
A T
THEW B. R
E I
C H
(E) E-H1SA
(E) E-L1S SEC 1
(E) E-L1S SEC 2
(E) E-L1S SEC 3
(E) E-H1S
1 1
(E) BOILER EMERGENCY STOP 4
NORTH
KEY PLAN
NOT TO SCALE
725 A Street Springfield, OR 97477 541.342.7210 systemswestengineers.com
DATE:
DRAWN:
CHECKED:
PROJECT:
DESIGNED:
OWNER:
LOCATION:
MARK DATE DESCRIPTION
AREA OF WORK
/1
/2
:3 :2
A
M
DPSST DWH
REPLACEMENT
P L O
T T
E D
H
O
N
4190 Aumsville Hwy SE, Salem, OR 97317
Oregon Department of Public Safety Standards and Training
DEMOLITION
PLAN - LEVEL 1
06.01.2026
250024.01
E101
SJS
JSH
SJS
100%
CONSTRUCTION
DOCUMENTS
R E F E R E N C E N O T E S :
1 REMOVE CONNECTION TO PLUMBING EQUIPMENT. REFER TO PLUMBING SHEETS
FOR EQUIPMENT IDENTIFICATION. RETAIN BRANCH CIRCUIT FROM PANELBOARD E-
L1S- SEC 2 FOR REUSE WITH NEW EQUIPMENT IN SAME LOCATION.
REMOVE CONNECTION TO PLUMBING EQUIPMENT. REFER TO PLUMBING SHEETS
FOR EQUIPMENT IDENTIFICATION. REMOVE WIRING AND PATHWAY BACK TO
SOURCE.
REMOVE CONNECTION TO MECHANICAL EQUIPMENT. REFER TO MECHANICAL
SHEETS FOR EQUIPMENT IDENTIFICATION. REMOVE WIRING AND PATHWAY BACK
TO SOURCE PANELBOARD E-L1S SEC 1 AND MARK UNUSED CIRCUIT BREAKER AS
SPARE.
RETAIN EXISTING BOILER EMERGENCY STOP SWITCH FOR RECONNECTION TO NEW
EQUIPMENT.
NORTH
1/4" = 1'-0"1
LEVEL 1 - ELECTRICAL DEMOLITION PLAN
© Systems West Engineers, Inc. 2026. The signature in this document is encrypted. Editing this document is prohibited. (OAR 820)
EXP IRES : 12 - 3 1- 26
MA Y 21, 2014
RE
GI
STE
RED PROFESSIONALENGINEER# 80,621
OREGONM
A T
THEW B. R
E I
B-1
(BELOW)
B-2
(ABOVE)
HWRCP-1
1 2
BP-2
BP-1
(E) E-L1S SEC 2
(E) E-L1S SEC 3
(E) E-H1S
(E) E-L1S SEC 1
(E) E-H1SA
MMV-1
3BAS PANEL
SEF E-S11
SEF E-S12 1
(E) BOILER EMERGENCY STOP 4
NORTH
KEY PLAN
NOT TO SCALE
725 A Street Springfield, OR 97477 541.342.7210 systemswestengineers.com
DATE:
DRAWN:
CHECKED:
PROJECT:
DESIGNED:
OWNER:
LOCATION:
MARK DATE DESCRIPTION
AREA OF WORK
/1
/2
:3 :2
A
M
DPSST DWH
REPLACEMENT
P L O
T T
E D
H
O
N
4190 Aumsville Hwy SE, Salem, OR 97317
Oregon Department of Public Safety Standards and Training
FLOOR PLAN -
LEVEL 1
06.01.2026
250024.01
E121
SJS
JSH
SJS
100%
CONSTRUCTION
DOCUMENTS
R E F E R E N C E N O T E S :
1 INTERCEPT AND EXTEND BRANCH CIRCUIT RETAINED DURING DEMOLITION AS
REQUIRED TO SERVE NEW EQUIPMENT. REFER TO SCHEDULES AND WIRING
DIAGRAM FOR ADDITIONAL INFORMATION.
PROVIDE DEDICATED 120V CIRCUIT AND RECEPTACLE FOR MIXING VALVE. REFER
TO SCHEDULES.
PROVIDE CONNECTION TO NEW BAS PANEL. COORDINATE EXACT LOCATION WITH
MECHANICAL PRIOR TO COMMENCING WORK.
CONNECT EXISTING BOILER EMERGENCY STOP SWITCH TO NEW BOILER
EQUIPMENT. RETAIN EXISTING FUNCTIONALITY OF SHUTTING OFF FUEL AND
POWER TO BOTH BOILERS. COORDINATE CONNECTION REQUIREMENTS WITH
DIVISION 22 AND WITH EQUIPMENT SUPPLIED PRIOR TO COMMENCING WORK.
NORTH
1/4" = 1'-0"1
LEVEL 1 - POWER DISTRIBUTION FLOOR PLAN
© Systems West Engineers, Inc. 2026. The signature in this document is encrypted. Editing this document is prohibited. (OAR 820)
EXP IRES : 12 - 3 1- 26
MA Y 21, 2014
RE
GI
STE
RED PROFESSIONALENGINEER# 80,621
OREGONM
A T
THEW B. R
E I
| GENERAL SHEET |
| PLUMBING SET |
| P001_LEGEND, GENERAL NOTES, & SHEET LIST |
| P121_FLOOR PLAN - LEVEL 1 - PLUMBING |
| P401_ENLARGED PLANS - PLUMBING |
| P501_PLUMBING DETAILS & DIAGRAMS |
| P601_PLUMBING SCHEDULES |
| MECHANICAL SET |
| M001_LEGEND, GENERAL NOTES, & SHEET LIST |
| M401_ENLARGED PLANS - MECHANICAL |
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .