Attachment B - Specifications.pdf
PDF 6 MB Posted
- Attached to
- Red Bluff Campground Rehabilitation Federal contract opportunity
- Solicitation number
- 12445521B0005
- Issued by
- Department of Agriculture Forest Service
About this file
This solicitation is for the Red Bluff Campground Rehabilitation project located in Crawford County, Missouri. Work includes construction of campground sites, an RV dump station, shower/toilet building, CXT toilets and a host site. Types of work include grading, erosion control, installation of a water well and distribution system, wastewater collection systems, asphalt pavement, electrical distribution, planting, and other work as indicated in the contract documents. Interested parties may coordinate a pre-bid site visit by contacting the project contact by July 26, 2021. The selected contractor will be responsible for construction under a single prime contract.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Pre-Bid Q-A.docx | DOCX document | |
| 12445521B0005.pdf | ||
| Attachment D - Plans - Part 1B.pdf | ||
| Attachment E - Plans - Part 2.pdf | ||
| Attachment C - Plans - Part 1A.pdf | ||
| Attachment G - Davis Bacon Wage Determination - Building.pdf | ||
| Attachment A - Schedule of Items.xlsx | XLSX spreadsheet | |
| Attachment F - Davis Bacon Wage Determination - Highway.pdf | ||
| Attachment H - Davis Bacon Wage Determination - Heavy.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MARK TWAIN NATIONAL FOREST
RED BLUFF RECREATION AREA
REHABILITATION PROJECT
CONTRACT #
PROJECT SPECIFICATIONS
USDA- Forest Service
R9 Technical Services Team- TST April 30, 2021
MARK TWAIN NATIONAL FOREST, 1
RED BLUFF RECREATION AREA REHABILITATION
TABLE OF CONTENTS
USFS DIVISION 1 - GENERAL REQUIREMENTS
011000 Summary 012700 Measurement and Payment Procedures 012800 Mobilization 013100 Project Management 013300 Submittals 014000 Quality Control 014200 References 015000 Temporary Facilities and Controls 017000 Execution 017700 Closeout Procedures
CSI MASTER SPECIFICATIONS
031000 Concrete Forming and Accessories 032000 Concrete Reinforcement 033000 Cast-in-Place Concrete 033500 Concrete Finishing 061000 Rough Carpentry 061323 Heavy Carpentry Construction 061516 Wood Roof Decking
074113.16 Standing Seam Metal Roof Panels
076200 Sheet Metal /Flashing and Trim 099300 Staining and Transparent Finishing 265619 LED Exterior Lighting 221114 Water Distribution 221353 Facility Holding, Septic, Pump Tanks, Pipe, Pumps & Distribution Cells 260010 General-Technical-Provisions 260050 Basic Methods and Materials 260400 Underground Power Distribution 329200 Seeding and Mulching 329300 Plants………… 332100 Water Supply Well
FP14 SUPPLEMENTAL SPECIFICATIONS
Preface 101 - Terms¸ Format¸ and Definitions 104 - Control of Work 106 - Acceptance of Work 152 - Construction Survey and Staking 157 - Soil Erosion and Sediment Control 204 - Excavation and Embankment 301 - Untreated Aggregate Courses 401-Asphalt Concrete Pavements……………………………………………………………………… 173 403 – MoDOT Mixture BP-1, Hot Asphalt Concrete Pavements 602 - Culverts and Drains 633 - Permanent Traffic Control 704 - Soil
MARK TWAIN NATIONAL FOREST, 2
APPENDIX 1 -- Well Information
APPENDIX 2 -- Specifications for Testing
SECTION 011000 - SUMMARY
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Project information.
2. Work covered by Contract Documents.
3. Contractor's use of site and premises.
4. Work restrictions.
5. Specification and Drawing conventions.
B. Related Requirements:
1. Section 015000 "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.
1.2 PROJECT INFORMATION
A. Project Identification: Red Bluff Recreation Area Rehabilitation
1. Project Location: The project is located in Crawford County Missouri, approximately one mile from Davisville, Missouri in the Mark Twain National Forest, Potosi-Fredericktown Ranger District. 37.8137, -91.1730
B. Owner: Government or Owners refers to the USDA Forest Service
1. Owner's Representative: The Federal Contracting Officer (CO) and his/her designated representative(s), as named in writing. Contracting Officer (CO) refers to the person assigned by the USDA Forest Service to administer the Contract. Soon after Contract award, the Contracting Officer will designate a Contracting Officers Representative (COR).
1.3 WORK COVERED BY CONTRACT DOCUMENTS
A. The Work of Project is defined by the Contract Documents and consists of the following:
1. Construction of campground sites, RV dump station, shower/toilet building, CXT toilets and host site. Types of work include grading, erosion control, install water well and distribution system, install wastewater collection systems, install AC pavement, install electrical distribution system, planting, and other Work indicated in the Contract Documents.
MARK TWAIN NATIONAL FOREST, 3
B. Type of Contract:
1. Project will be constructed under a single prime contract.
1.4 CONTRACTOR'S USE OF SITE AND PREMISES
A. The Government will conduct a pre-construction survey with the Contractor to review and document the existing project conditions prior to construction.
B. Restricted Use of Site: Contractor shall have limited use of Project site for construction operations as indicated on Drawings by the Contract limits and as indicated by requirements of this Section.
C. Limits on Use of Site: Limit use of Project site to areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Limited space on the premises is available for the Contractor's storage and related activities, as staked by the Government. Schedule deliveries to minimize on-site storage of material and equipment.
2. Existing materials and equipment that are removed as part of the construction operations, and that are not reused or salvaged as Government property, shall become the property of the Contractor and shall be promptly removed from the site.
1.5 WORK RESTRICTIONS
A. Comply with restrictions on construction operations.
1. Comply with limitations on use of public streets, work on public streets, rights of way, and other requirements of authorities having jurisdiction.
2. The Contractor may restrict public access on the North Loop, Group Loop, and Pine Bluff Overlook roads. The portion of the South Loop without any current camping spurs may also be restricted. All other roads shall not restrict access to the recreation area and shall remain open for public use, excepted when coordinated and approved by the COR. The Contractor shall provide safety barriers and provide traffic control as required in order to maintain safe access by the public.
B. Work Hours: Limit work in all project areas to normal business working hours of 7 a.m. to 6 p.m., Monday through Friday, unless otherwise indicated.
1. No work is permitted without written authorization on Government Holidays or weekends.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:
1. Notify Owner not less than two days in advance of proposed utility interruptions.
2. Obtain Owner's written permission before proceeding with utility interruptions.
MARK TWAIN NATIONAL FOREST, 4
1.
3. Monday – Thursday both water and electric service maybe disconnected/shutoff for up to 8 hours when at least 48 hours of advance notice is provided to the COR. Additional requirements to interrupt electric or water service may be granted with prior COR approval.
D. Noise, Vibration, Dust, and Odors: Coordinate operations that may result in high levels of noise and vibration, dust, odors, or other disruption to Owner occupancy with Owner.
1. Notify Owner not less than two days in advance of proposed disruptive operations.
2. Obtain Owner's written permission before proceeding with disruptive operations.
E. Smoking and Controlled Substance Restrictions: Use of tobacco products, alcoholic beverages, and other controlled substances on Project site is not permitted. Use of any type of marijuana on federal property is illegal.
F. Site Cleanup: Before leaving the Site each day the Contractor shall secure equipment, tools, and materials; pickup and dispose of paper and other debris/construction waste. The Site shall be left in a safe and secure manner with the public protected from construction hazards.
G. Before leaving the Site on Fridays a more complete policing, pickup and securing of the Site shall be performed. The Site shall be left in a neat and orderly manner as determined by the COR with the public protected from construction related hazards.
1.6 SPECIFICATION AND DRAWING CONVENTIONS
A. Division 00 Contracting Requirements: General provisions of the Contract, including General and Supplementary Conditions, apply to all Sections of the Specifications.
B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications not listed as being covered by FP-14.
C. FP-14 sections apply to all clearing and grubbing, disposal of excess soils at off site location, installation of culverts and associated features, providing, placing and compacting of aggregate base and surfacing materials and providing and installing asphalt concrete.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 011000
MARK TWAIN NATIONAL FOREST, 5
SECTION 012700 - MEASUREMENT AND PAYMENT
1.1 RELATED DOCUMENTS
A. Drawings entitled “Red Bluff Recreation Area Rehabilitation” and applicable provisions of the Solicitation/Contract including but not limited to: Section B - Schedule of Items (and associated Schedule of Values), Section C - Statement of Work, Section G - Contract Administration Data/Invoices and Payments and Section I - Contract Clauses.
1.2 SUMMARY
A. This Section includes:
1. Measurement and payment criteria applicable to the work performed.
2. Administrative and procedural requirements necessary to prepare and process Applications for
Payment.
3. Defect assessment and non-payment for rejected work.
4. General description of work included under each pay item.
B. Related Requirements:
1. Schedule of Values Form (SOV): The Contractor is required to complete the SOV Form, provided by the Government, as part of their Proposal or Bid together with the completed Section B – Schedule of Items. Totals from the SOV Form must agree exactly with the corresponding item totals on the Schedule of Items.
2. Invoice Processing Platform (IPP) System: All invoices are to be submitted via the electronic IPP System. The contractor must follow the instructions on how to register and submit invoices via IPP as prescribed in communications from USDA and Treasury. This is a mandatory requirement initiated by the U.S. Department of Treasury and you can find more information at this website https://www.ipp.gov/index.htm. Ensure your company has registered at https://www.ipp.gov/vendors/enrollmentvendors.htm to establish your account. Offeror must have an established account prior to commencement of work.
3. Certified Payrolls: Certified payrolls for construction work must be submitted to the CO/COR for review at regular intervals as work progresses. At least one week prior to Contractor requesting payment via IPP, all certified payrolls related to the subject pay request work must have been received by the CO/COR. Incomplete or inaccurate payroll submittal will result in rejection of the IPP invoice. Contractor and all subcontractors, through the contractor, shall furnish all certified payrolls covering payments to laborers and mechanics for on-site work. Payroll hourly rates and fringe benefits must be in accordance with the established Wage Determination for the project.
1.3 AUTHORITY
A. The Contracting Officer’s Representative (COR) will take all measurements and compute quantities accordingly.
1.4 MEASUREMENT OF QUANTITIES
A. Linear Measurement: Measured by the linear dimension, (i.e. LF = lineal foot), at the item centerline or mean chord. Measurement will be made to the nearest given linear unit.
https://www.ipp.gov/index.htm https://www.ipp.gov/vendors/enrollmentvendors.htm
MARK TWAIN NATIONAL FOREST, 6
B. Each: Measured by the number of individual items of work completed.
C. Lump Sum Quantities (LSQ): These quantities denote one complete unit of work as required by or described in the Contract, including all necessary materials, equipment, and labor to complete the job.
They will not be measured.
D. Actual Quantities (AQ): These quantities denote completed units of work, as described in the Contract, including all necessary materials, equipment, and labor, to complete the job. They will be measured in the field.
E. Designed Quantities (DQ) - These quantities denote the final number of units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the quantity of units SHOWN in the SCHEDULE OF ITEMS may be authorized under any of the following conditions:
1. As a result of changes in the work authorized by the Contracting Officer.
2. As a result of the Contracting Officer determining that errors exist in the original design data used to determine designed quantities, which cause a pay item to change by 15 percent or more.
3. As a result of the Contractor submitting to the Contracting Officer a written request showing evidence of errors in the original design data used to determine design quantities that cause a pay item total to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.
1.5 PAYMENT
A. Pay Request Documentation from Contractor: Contractor must submit the following documentation to the CO/COR for review and approval at least seven (7) days prior to requesting a payment via IPP.
1. All Certified Payroll forms from the general contractor (including payrolls from all sub-contractors) for work covered by the pay request.
2. A completed draft Schedule of Values (SOV) Form for work covered by the pay request, indicating the percent complete for each line item in the SOV.
3. Written Quality Control testing results if applicable to items in the payment request.
B. Payment Includes: Full compensation for all required labor, products, tools, equipment, plant, transportation, services, and incidentals; erection, application, or installation of an item of the Work;
overhead and profit.
1. "Incidentals" are to be considered as an additional obligation to the other work required for the item(s). Incidental work is not payable directly but is to be considered included in the contract price for the item(s) of work specified.
2. All work not specifically identified as a separate bid item is "Incidental".
C. The accepted quantities will be paid for at the contract unit price for each item as shown in the Schedule of Items.
D. Payment will not be made for any of the following:
1. Products or construction placed beyond the lines and levels of the required work.
2. Products or construction determined as unacceptable before or after placement.
3. Products wasted or disposed of in a manner that is not acceptable.
4. Products remaining on hand after completion of the Work.
5. Loading, hauling, and disposing of rejected products.
MARK TWAIN NATIONAL FOREST, 7
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION (Not Applicable)
END OF SECTION 012700
MARK TWAIN NATIONAL FOREST, 8
SECTION 012800 - MOBILIZATION
PART 1 - GENERAL
1.1 SUMMARY
A. This work consists of mobilization of personnel, equipment, materials and supplies. Other items included but not limited to: construction surveying and staking, temporary erosion control, bonding, insurance, permit fees, closeout procedures including record drawings, submittals, operations and maintenance manuals and material submittal and final cleaning, field office and staff, temporary utilities, site clean-up, waste disposal, field office vehicles and their operational costs, superintendent, safety and QC costs.
1.2 MEASUREMENT AND PAYMENT
A. Method of Measurement will be by Lump Sum Quantity (LSQ).
B. The maximum Mobilization bid price shall not exceed fifteen percent (15%) of the total base bid contract price or optional bid contract price (not including Mobilization).
C. Progress Payments for Mobilization will be in accordance with the following schedule:
1. The cost of premiums paid for performance and payment bonds are considered incidental to Mobilization and will not be paid for separately. Payment for bond premiums will be in accordance with FAR Clause 52.232-5, Payments under Fixed-Price Construction Contracts, after receipt of the evidence of payment.
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION (Not Applicable)
END OF SECTION 012800
MARK TWAIN NATIONAL FOREST, 9
SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. This section includes certain administrative provisions for managing and coordinating construction operations.
1.2 GENERAL PROJECT COORDINATION
A. Coordination of Trades: Coordinate construction operations to provide an efficient and orderly installation of each part of the Work.
1.3 SPILL AND EROSION CONTROL
A. Spill and Erosion Control Plans: At a minimum, the contractor shall install erosion control devises as indicated on the erosion control plans. The Contractor shall install additional erosion control features to prevent sediment from entering wetlands or waters of the United States and to provide for containment of hazardous materials and unplanned spills in accordance with all applicable federal, state and local laws. Submit a plan in accordance with paragraph 1.7 in this section. Permit will not be required for work on federal land.
1.4 ADMINISTRATIVE AND SUPERVISORY PERSONNEL
A. In addition to meeting the requirements of FAR 52.236-6 for an on-site Project Superintendent, the Contractor shall provide other administrative and supervisory personnel as required for performance of the Work.
1.5 CONFERENCES AND MEETINGS
A. Pre-construction Conference: The Contracting Officer or Contracting Officer’s Representative will schedule a pre-construction conference before starting construction at a time and place agreeable and convenient to both the Contractor and Government and will review responsibilities and personnel assignments in accordance with FAR 52.236-
B. Progress Meetings: Progress meetings at the Project Site shall be conducted at regular intervals. Dates of meetings shall be coordinated with preparation of the payment request in accordance with FAR 52.232-5.
1. Agenda: Include topics for discussion as appropriate to the status of the Project.
Include review of the Contractor's Construction Schedule and of the present and future needs of each entity present.
2. Schedule Updating: If the progress of the work falls behind the approved Contractor’s Construction Schedule, the Contractor shall submit a supplementary schedule for approval by the Contracting Officer in accordance with FAR 52.236-
15. The COR will keep the Contractor informed of any scheduled events that
MARK TWAIN NATIONAL FOREST, 10
may impact the contractor’s work schedule. It is imperative the Contractor provide an accurate Work Schedule to the COR and shall update it whenever the current Work Schedule is not accurate.
1.6 SUBMITTALS
A. Spill and Erosion Control Plans shall be submitted within 5 calendar days after Notice to Proceed.
B. Staff Names: Within 5 calendar days after Notice to Proceed, submit a list of principal staff assignments, including the Superintendent and other primary personnel. Identify individuals by name, duties and responsibilities, home address, and business/cell and home (in case of emergencies after hours) telephone numbers. Post copies of this list in the temporary field office (if present).
C. Construction Schedules shall be submitted as directed in FAR 52.236-15, Schedules for Construction.
PART 2 - PRODUCTS (Not applicable)
PART 3 - EXECUTION
3.1 GENERAL COORDINATION PROVISIONS
A. Inspection of Conditions: Prior to installations, require the installer of each major component to inspect both the substrate and conditions under which work is to be performed.
B. Construction in Progress: Keep construction in progress, adjoining materials in place, and clean during handling and installation. Apply protective enclosures or coverings for protection from damage or deterioration.
C. Completed Construction: Clean completed construction and provide maintenance to prevent damage, soiling or other deterioration through the remainder of the construction period. Adjust and lubricate operable components to assure operability without damage.
D. Limiting Exposures: Supervise construction operations to prevent exposure of any part of construction, completed or in progress, to harmful, dangerous, damaging or otherwise deleterious conditions during the construction period.
END OF SECTION 013100
MARK TWAIN NATIONAL FOREST, 11
SECTION 013300 - SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. This Section and FAR 52.236-21 include requirements for Shop Drawings, as defined by
FAR 52.236-21 and Designs. Shop drawings and Designs may include drawings, specifications, diagrams, layouts, schematics, descriptive literature, illustrations, schedules, performance and test data furnished by the Contractor to explain in detail specific portions of the work required by the Contract.
B. This section includes requirements for Samples. Samples may include mailed samples, field samples or mock-ups of full-size physical examples erected on-site or elsewhere.
C. This section includes requirements for Product Data. Product Data includes manufacturer's standard catalogs, manuals, pamphlets and other printed materials, and includes but is not limited to the following: product specifications and installation instructions, color charts and catalog cuts, rough-in diagrams and templates, wiring diagrams, performance curves, operational range diagrams, mill reports, test reports, shop drawings and code approvals.
D. This section includes other quality assurance submittals such as certifications of compliance or conformance, manufacturer's instructions and field reports, and mix designs.
1.2 GENERAL SUBMITTAL REQUIREMENTS
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities and with the schedule.
1. Allow 15 calendar days each for submittal review, corrections following the initial review and re-submittal review before activities scheduled after the submittal approval.
2. Incomplete submittals will be returned to the Contractor with no further review. Delays due to incomplete or rejected submittals will not be excused and no compensation in the form of monetary or time will be provided to the Contractor.
3. When the Contractor desires to submit for approval a product for an “approved equal”, the Contractor MUST provide documentation of the original specified product and the Contractor proposed product in a side-by-side comparison, such as a table, which clearly demonstrates the Contractor proposed product meets or exceeds the originally specified product. If this product comparison is not done the first time it is submitted, the proposed product will be rejected, and the Contractor will be required to provide the specified product. The Government is not obligated to review a re-submittal for a rejected product.
4. Submittal Transmittal: Transmit each submittal from the Contractor to the Government by use of one transmittal form per submittal. Transmittal format to be approved by COR and shall include the following information on the transmittal form.
a. Project name and Forest Service contract number.
b. Date.
c. Name, address and telephone number of firm or entity that prepared the submittal
d. Names of subcontractor, manufacturer, supplier, etc. as applicable.
MARK TWAIN NATIONAL FOREST, 12
e. Category and description of submittal.
f. Section of Specifications or Drawing sheet number the Submittal is representing.
g. Certification by Contractor stating that submittal complies with the Contract, or statement of deviations from the requirements of the Contract.
h. Signature of transmitter.
i. Space to record Contractor's review and approval markings, and for Government response.
B. Submit 3 hardcopies of each submittal to the COR for review unless otherwise stated. One copy will be returned to the Contractor and two copies will be retained, one for the COR and one for the Inspector.
1.3 SHOP DRAWINGS AND DESIGNS
A. Submit originally prepared information, drawn accurately to scale.
B. Submittals: Submit three blue-line or black-line prints of each drawing submittal. One print will be marked with action taken and returned. Distribution: When submittal is approved, the Contractor shall prepare and submit three final copies.
C. Shop drawings shall be done in AutoCAD format. Upon final approval the drawings shall be sent on a thumb drive or via email to the COR.
D. Specifications shall be done in Microsoft Word format and a copy sent on a thumb drive or via email to the COR.
1.4 PRODUCT DATA
A. Collect Product Data into a single submittal for each system or element of construction.
Mark each copy to show specific product choices and options applicable to the project.
Product Data shall include the following information, where applicable:
1. Manufacturer's printed recommendations.
2. Compliance with recognized trade association standards.
3. Compliance with recognized testing standards.
4. Applicability of testing agency labels and seals.
5. Notation of dimensions verified for fit by field measurements.
6. Notation of coordination requirements.
B. Preliminary Submittal: Prior to submittal of complete Product Data, submit a preliminary single copy of that part of Product Data when selection of options is required, such as for color charts. Preliminary submittal will be returned, with selection noted, for the Contractor's use in subsequent submittals.
C. Submittals: Unless otherwise indicated, submit 3 copies of each Product Data submittal.
Two copies will be retained, and the remaining copy will be marked with action taken and returned. The COR may allow electronic copies to be transmitted in lieu of hard copies.
D. Material and Product substitution shall be in accordance with FAR 52.211-6 and Section 013300-1.2. A.3.
MARK TWAIN NATIONAL FOREST, 13
1.5 SAMPLES
A. Submit full-size, fully fabricated samples, cured and finished in the manner specified.
Samples shall be physically identical to the material or product proposed for use.
B. Preliminary Submittal: Where color, pattern, texture or similar characteristics are to be selected from a manufacturer's range of standard choices, submit a preliminary single set sample of available choices when required by the CO.
1.6 OTHER QUALITY ASSURANCE SUBMITTALS
A. Submit other quality assurance submittals in compliance with requirements in the individual specification sections.
1.7 REVIEW ACTION ON SUBMITTALS
A. Except for submittals for the record or for information or for another purpose where no action and return is required, the Government will review submittals and mark returned copies to indicate action taken within a maximum time period of 15 calendar days.
B. Submittals that do not contain an appropriate marking of approval by the Government shall not be used for construction.
PART 2 - PRODUCTS (Not applicable)
PART 3 - EXECUTION (Not applicable)
END OF SECTION 013300
MARK TWAIN NATIONAL FOREST, 14
SECTION 014000 - QUALITY CONTROL
PART 1 - GENERAL
1.1 SUMMARY
A. This section, FAR 52.246-1 Contractor Inspection Requirements and FAR 52.246-12 Inspection of Construction, include requirements for Contractor quality control services used to verify quality assurance requirements specified elsewhere in the Contract.
B. The Government reserves the right to conduct independent tests.
C. This section includes requirements for quality control services such as soil density compaction, concrete mix and strength testing, sewer line pressure tests and bedding and sand gradation tests (this is not an all-inclusive list of tests that may be required) per State of Missouri Agency Requirements – MO DOT and MO DNR– as they apply to the work being performed.
D. The quality control services include tests and related actions, including reports, performed by the Contractor, independent testing agencies or governing authorities.
1.2 QUALIFICATIONS OF INDEPENDENT TESTING AGENCIES
A. A qualified independent testing Agency shall be an accredited entity engaged to perform tests or inspections, and to report on and, if required, to interpret results of those tests or inspections.
1.3 SUBMITTALS
A. Reports: The Contractor shall submit a certified written report, in duplicate (or electronic format), of each test, inspection or other quality control service to the Government.
B. Written reports shall include but not be limited to the following:
Date of issue.
Project title and number.
Name, address, and telephone number of testing agency.
Dates and locations of samples and tests or inspections.
Names of individuals making the test or inspection.
Designation of the work and test method.
Identifications of product and specification section.
Complete test or inspection data.
Test results and an interpretation of test results.
Ambient conditions at the time of sample taking and testing.
Comments or professional opinion on whether tested or inspected Work complies with Contract
Document requirements.
Name and signature of laboratory inspector.
Recommendations on retesting.
1.4 MEASUREMENT AND PAYMENT
MARK TWAIN NATIONAL FOREST, 15
A. Method of Measurement will be by Lump Sum Quantity (LSQ).
B. Payment will be full compensation for the work prescribed in this Section. Payment for lump sum pay items will be prorated based on the progress of the work under this Section.
C. Progress Payments and Final Payment for Quality Control will be in accordance with FAR 52.232-5 Payments under Fixed-Price Construction Contracts. The Government shall make progress payments monthly as the work proceeds on estimates of work accomplished which meets the standards of quality established under the contract, as approved by the Contracting Officer.
1.5 RESPONSIBILITIES
A. Contractor Responsibilities: The Contractor shall provide for tests, inspections and other quality control services (such as water/wastewater, well water, electrical, etc. tests and inspections) where specified in the Contract or when required by authorities having jurisdiction such as the State of Missouri Agencies—MODOT and MODNR. Costs for these services are included in the Contract price. The Contractor shall maintain complete inspection records and make them available to the Government.
B. The Contractor shall employ and pay for a qualified independent testing agency (Agency) to perform the quality control services.
C. Associated Services: The Contractor shall cooperate with others performing required tests, inspections and other quality control services, shall provide access to the work, and shall furnish incidental labor and facilities necessary to facilitate inspections and tests.
PART 2 PRODUCTS (Not applicable)
PART 3 EXECUTION (Not applicable)
END OF SECTION 014000
MARK TWAIN NATIONAL FOREST, 16
SECTION 014200 - REFERENCES
PART 1 - GENERAL
1.1 DEFINITIONS
A. General Explanation: Specification language often includes terms that are defined elsewhere in the Contract including the Construction Clauses. Certain terms are defined in this section. These definitions or explanations are not necessarily complete or exclusive but are general for the Work and may be explained more explicitly in other sections.
B. "General Conditions" refer collectively to the Construction Contract Clauses, Labor Standards and the U.S. Department of Labor Wage Decision bound into the specifications.
C. "Indicated" refers to graphic representations, notes or schedules on the Drawings, or to requirements elsewhere in the Specifications or other Contract Documents. Terms such as "shown", "noted", "scheduled" and "specified" have the same meaning as "indicated" and are used to further help locate the reference, but no limitation on location is intended except as specifically stated.
D. Where "directed", "authorized", "selected", "approved", or a similar term is used in conjunction with the Contractor's submittals, applications, requests and other activities, and the specifications state that an individual other than the Contracting Officer (CO) shall provide this action, it is understood that only the CO has this authority unless the individual stated is so authorized in writing by the CO.
1. When the individual is so authorized by the CO, the Contractor may still appeal the action to the CO.
2. The CO’s decision will be final.
3. In no case shall the CO action be interpreted as releasing the Contractor from responsibility to fulfill the requirements of the Contract.
E. "Regulations" include laws, ordinances, statutes and lawful orders issued by authorities having jurisdiction, as well as rules, conventions and agreements within the construction industry that control performance of the Work.
F. "Project site" refers to the space available to the Contractor for performance of the Work, either exclusively or in conjunction with others performing other work.
G. "Furnish" means to supply and deliver to the Project site, ready for unloading, unpacking, assembling, installation and similar operations.
H. "Install" describes operations at the Project site, including unloading, temporary storage, unpacking, assembling, erecting, placing, anchoring, applying, working to dimension, finishing, curing, protecting, cleaning and similar operations.
I. "Provide" means to furnish and install, complete in place and ready for full use.
J. "Cutting" refers to removal of material by cutting, sawing, drilling, coring, breaking, chipping, grinding, excavating and similar operations.
MARK TWAIN NATIONAL FOREST, 17
K. "Patching" refers to restoration of a surface to its original completed condition by filling, repairing, refinishing, closing and similar operations.
L. "Installer" is the Contractor or another entity engaged by the Contractor, either directly or indirectly through subcontracting, to perform a particular construction operation at the Project site, including installation, erection, application and similar operations. Installers shall be skilled in the operations they perform.
M. "Testing agency" or "testing laboratory" is an independent entity engaged to perform specific inspections or tests, either at the Project site or elsewhere, and to report the results of those inspections and tests.
N. "Notice to Proceed" is the CO’s notification by letter to the Contractor to proceed with the Contract, activating the time period for construction and establishing the completion date.
1.2 CODES AND STANDARDS
A. Applicability of Standards: Unless the Contract includes more stringent requirements, applicable construction industry standards have the same force and effect, to the extent referenced, as if bound or copied directly into the Contract. Such standards are made a part of the Contract by reference.
B. Codes: The Work shall be performed in compliance with the latest editions of the following codes: IMC, NEC, IBC and IPC.
C. All septic system work shall comply with the latest edition of applicable Missouri Department of Natural Resources Rules and Publications. The USFS is obtaining the Construction Permit for Wastewater Treatment Facility. The Contractor is required to be a licensed septic installer with the State of Missouri for ALL septic work, including holding tanks. Any proposed deviation from the approved septic system design (holding tanks or pressure distribution system) must be submitted in writing to the CO who will consult with the design engineer. The design engineer has the final word on whether or not to allow a design change.
D. All water system work shall comply with the latest edition of applicable Missouri Department of Natural Resources Rules and Publications. The Contractor shall fully comply with the USFS water design as shown on the drawings and in the specifications, which were used to obtain the Missouri Department of Natural Resources Water System Construction Permit (review No. 4000035-20 on June 15, 2020). Any proposed deviation from the approved water system design must be submitted in writing to the CO who will consult with the design engineer. The design engineer has the final word on whether or not to allow a design change.
E. The Contractor shall comply with the Forest Service Health and Safety Code Handbook, FSH
6709.11 available at http://www.fs.fed.us/im/directives/fsh/6709.11/FSH6709.pdf.
F. Conflicting Requirements. Where compliance with two or more standards is specified, comply with the most stringent requirement. Refer uncertainties, and requirements that are different but apparently equal, to the CO in writing for a decision before proceeding.
http://www.fs.fed.us/im/directives/fsh/6709.11/FSH6709.pdf
MARK TWAIN NATIONAL FOREST, 18
G. Abbreviations: Names and titles of standards are frequently abbreviated. Abbreviations and acronyms used in the Contract mean the associated names. The following names may be referenced in the Contract:
1. AASHTO - American Association of State Highway and Transportation
2. ACI - American Concrete Institute
3. ADA – American’s with Disabilities Act
4. ADAAG – Americans with Disabilities Act Accessibility Guidelines
5. AI - Asphalt Institute
6. AISC - American Institute of Steel Construction
7. AITC - American Institute of Timber Construction
8. ALSC – American Lumber Standard Committee
9. ANSI - American National Standards Institute
10. ASME – American Society of Mechanical Engineers International
11. ASTM - American Society for Testing and Materials
12. AWPA - American Wood-Preservers' Association
13. AWS - American Welding Society
14. AWWA - American Water Works Association
15. CABO - Council of American Building Officials
16. CFR - Code of Federal Regulations
17. CRSI - Concrete Reinforcing Steel Institute
18. CS - Commercial Standard (U.S. Dept. of Commerce)
19. CSI - Construction Specifications Institute
20. DOT – Department of Transportation
21. EIA - Electronic Industries Association
22. EPA - Environmental Protection Agency
23. FS - Federal Specification (Publications available from GSA)
24. GSA - General Services Administration
25. IBC – International Building Code
26. IFC – International Fire Code
27. IPC – International Plumbing Code
28. ICBO – International Conference of Building Officials
29. MCAA – Mechanical Contractors Association of America
30. MSS-Manufacturers Standardization Society of the Valve and Fittings Industry Inc.
31. NECA – National Electrical Contractors Association
32. NEMA - National Electrical Manufacturers Association
33. NEC – National Electrical Code
34. NFPA - National Fire Protection Association
35. OSHA - Occupational Safety and Health Administration (U.S. Dept. of Labor)
36. PCA - Portland Cement Association
37. SSPC - Steel Structures Painting Council - The Society for Protective Coatings
38. UFAS – Uniform Federal Accessibility Standards
39. UL - Underwriters Laboratories Inc.
40. IMC – International Mechanical Code
41. IPC – International Plumbing Code
42. USDA - U.S. Department of Agriculture
MARK TWAIN NATIONAL FOREST, 19
PRODUCTS (Not applicable)
EXECUTION (Not applicable)
END OF SECTION 014200
MARK TWAIN NATIONAL FOREST, 20
SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes requirements for temporary utilities, support facilities, and security and protection facilities.
B. Related Requirements:
1. Section 011000 "Summary" for work restrictions and limitations on utility interruptions.
1.2 USE CHARGES
A. Installation, removal, and use charges for temporary facilities shall be included in the Contract Sum unless otherwise indicated.
B. Water from Existing System: Water from Owner's existing water system near the south is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations.
C. Electric Power Service from Existing System: Electric power from Owner's existing system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations.
1.3 INFORMATIONAL SUBMITTALS
A. Site Utilization Plan: Show temporary facilities, temporary utility lines and connections, staging areas, construction site entrances, vehicle circulation, and parking areas for construction personnel.
B. Fire-Safety Program: Show compliance with requirements of NFPA 241 and authorities having jurisdiction. Indicate Contractor personnel responsible for management of fire-prevention program.
C. Moisture- and Mold-Protection Plan: Describe procedures and controls for protecting materials and construction from water absorption and damage and mold. Describe delivery, handling, storage, installation, and protection provisions for materials subject to water absorption or water damage.
1. Indicate procedures for discarding water-damaged materials, protocols for mitigating water intrusion into completed Work, and requirements for replacing water-damaged Work.
1.4 QUALITY ASSURANCE
A. Electric Service: Comply with NECA, NEMA, and UL standards and regulations for temporary electric service. Install service to comply with NFPA 70.
B. Tests and Inspections: Arrange for authorities having jurisdiction to test and inspect each temporary utility before use. Obtain required certifications and permits.
MARK TWAIN NATIONAL FOREST, 21
1.5 PROJECT CONDITIONS
A. Temporary Use of Permanent Facilities: Engage Installer of each permanent service to assume responsibility for operation, maintenance, and protection of each permanent service during its use as a construction facility before Owner's acceptance, regardless of previously assigned responsibilities.
PART 2 - PRODUCTS – (Not Applicable)
PART 3 - EXECUTION
3.1 TEMPORARY FACILITIES, GENERAL
A. Conservation: Coordinate construction and use of temporary facilities with consideration given to conservation of energy, water, and materials. Coordinate use of temporary utilities to minimize waste.
3.2 TEMPORARY UTILITY INSTALLATION
A. General: Install temporary service or connect to existing service.
1. Arrange with utility company, Owner, and existing users for time when service can be interrupted, if necessary, to make connections for temporary services.
B. Sanitary Facilities: Provide temporary toilets and drinking water for use of construction personnel.
Comply with requirements of authorities having jurisdiction for type, number, location, operation, and maintenance of fixtures and facilities.
3.3 SUPPORT FACILITIES INSTALLATION
A. Traffic Controls: Comply with requirements of authorities having jurisdiction.
1. Protect existing site improvements to remain including curbs, pavement, and utilities.
2. Maintain access for fire-fighting equipment and access to fire hydrants.
B. Dewatering Facilities and Drains: Comply with requirements of authorities having jurisdiction. Maintain Project site, excavations, and construction free of water.
1. Dispose of rainwater in a lawful manner that will not result in flooding Project or adjoining properties or endanger permanent Work or temporary facilities.
2. Remove snow and ice as required to minimize accumulations.
C. Waste Disposal Facilities: Provide waste-collection containers in sizes adequate to handle waste from construction operations. Comply with requirements of authorities having jurisdiction. Comply with progress cleaning requirements in Section 017300 "Execution."
1. Truck cranes and similar devices used for hoisting materials are considered "tools and equipment" and not temporary facilities.
MARK TWAIN NATIONAL FOREST, 22
3.4 SECURITY AND PROTECTION FACILITIES INSTALLATION
A. Protection of Existing Facilities: Protect existing vegetation, equipment, structures, utilities, and other improvements at Project site and on adjacent properties, except those indicated to be removed or altered.
Repair damage to existing facilities.
1. Where access to adjacent properties is required in order to affect protection of existing facilities, obtain written permission from adjacent property owner to access property for that purpose.
B. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction as required to comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.
C. Temporary Erosion and Sedimentation Control: Comply with requirements of EPA Construction General Permit or authorities having jurisdiction, whichever is more stringent, and requirements specified in Section 311000 "Site Clearing."
D. Temporary Erosion and Sedimentation Control: Provide measures to prevent soil erosion and discharge of soil-bearing water runoff and airborne dust to undisturbed areas and to adjacent properties and walkways, according to erosion- and sedimentation-control Drawings, requirements of EPA Construction General Permit or authorities having jurisdiction, whichever is more stringent.
1. Verify that flows of water redirected from construction areas or generated by construction activity do not enter or cross tree- or plant-protection zones.
2. Inspect, repair, and maintain erosion- and sedimentation-control measures during construction until permanent vegetation has been established.
3. Clean, repair, and restore adjoining properties and roads affected by erosion and sedimentation from Project site during the course of Project.
4. Remove erosion and sedimentation controls and restore and stabilize areas disturbed during removal.
E. Stormwater Control: Comply with requirements of authorities having jurisdiction. Provide barriers in and around excavations and subgrade construction to prevent flooding by runoff of stormwater from heavy rains.
F. Tree and Plant Protection: Coordinate removal and protection of trees with COR.
G. Protect tree root systems from damage, flooding, and erosion. Security Enclosure and Lockup: Install temporary enclosure around partially completed areas of construction. Provide lockable entrances to prevent unauthorized entrance, vandalism, theft, and similar violations of security. Lock entrances at end of each workday.
H. Barricades, Warning Signs, and Lights: Comply with requirements of authorities having jurisdiction for erecting structurally adequate barricades, including warning signs and lighting.
3.5 OPERATION, TERMINATION, AND REMOVAL
A. Supervision: Enforce strict discipline in use of temporary facilities. To minimize waste and abuse, limit availability of temporary facilities to essential and intended uses.
B. Termination and Removal: Remove each temporary facility when need for its service has ended, when it has been replaced by authorized use of a permanent facility, or no later than Substantial Completion.
MARK TWAIN NATIONAL FOREST, 23
Complete or, if necessary, restore permanent construction that may have been delayed because of interference with temporary facility. Repair damaged Work, clean exposed surfaces, and replace construction that cannot be satisfactorily repaired.
1. Materials and facilities that constitute temporary facilities are property of Contractor. Owner reserves right to take possession of Project identification signs.
2. At Substantial Completion, repair, renovate, and clean permanent facilities used during construction period. Comply with final cleaning requirements specified in Section 017700 "Closeout Procedures."
END OF SECTION 015000
MARK TWAIN NATIONAL FOREST, 24
SECTION 017000 - EXECUTION REQUIREMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. This section, FAR 52.236-5, FAR 52.236-12 and FAR 52.236.17 include certain general procedural requirements governing the Contractor's execution of the Work, including, but not limited to laying out the Work, general installation of products, correction of defective Work, and cleaning.
1.2 QUALITY ASSURANCE
A. Workmanship Standards: Initiate and maintain procedures to ensure personnel performing the Work are skilled and knowledgeable in the methods and craftsmanship needed to produce the required levels of workmanship. Remove and replace Work that does not comply with workmanship specified and standards recognized in the construction industry for the applications indicated. Remove and replace Work damaged or deteriorated by faulty workmanship or replacement of other Work.
B. Manufacturer's Instructions: Where installations include manufactured products, comply with manufacturer's applicable installation instructions and recommendations to the extent that those instructions and recommendations are more explicit or stringent than requirements contained in the Contract. The Contracting Officer’s Representative shall be immediately notified of conflicts between manufacturer’s instructions and the Contract.
C. Minimum Quality and Quantity: The quality level or quantity shown or specified shall be the minimum required for the Work. Except as otherwise indicated, the Work shall comply exactly with that minimum or may be superior to that minimum. Specified numeric values are either minimums or maximums as indicated or as appropriate for the context of the requirements.
D. Septic system and all holding tank installations must be performed by a State of Missouri licensed septic installer.
E. Water well installation must be performed by a State of Missouri licensed well driller.
F. Electrical work must be performed by a State of Missouri licensed electrician.
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION
3.1 LAYING OUT THE WORK
A. Before proceeding to lay out the Work, verify layout information shown on the Drawings, in relation to the property survey and existing benchmarks. If discrepancies are discovered notify the Contracting Officer's Representative promptly.
MARK TWAIN NATIONAL FOREST, 25
B. Maintain existing benchmarks at the sites as indicated on the Drawings or replace at new locations.
C. Existing Utilities and Equipment: The existence and location of underground and other utilities and construction indicated as existing are not guaranteed. Before beginning site work, investigate and verify the existence and location of underground utilities and other construction.
3.2 PREPARATION
A. Site Improvements: The Contractor is responsible for all staking, maintaining and replacing of staking, except: The Government will establish (one time only) a minimum of 2 control points and 1 benchmark at each of the major project areas.
B. Existing Utilities: Furnish information necessary to adjust, move, or relocate existing structures, utility poles, lines, services, or other appurtenances located in or affected by construction.
Coordinate with local authorities having jurisdiction. The Contractor is responsible for contacting the appropriate state agency for locating underground utilities.
C. Take field measurements as required to fit the Work properly.
3.3 INSTALLATION
A. Locate the Work and components of the Work accurately. Make vertical work plumb and horizontal work level. This is imperative for the drain field.