Attachment_B_Contract_Clauses.pdf

PDF 322 KB Posted

Attached to
USGS FLAGPOLE LIGHTING INSTALLATION Federal contract opportunity
Solicitation number
140G0126R0006
Issued by
Department of the Interior US Geological Survey Office of Acquisitions and Grants

About this file

This is Attachment B to a federal construction solicitation containing contract clauses incorporated by reference for USGS Flagpole Lighting Installation (Solicitation 140G0126R0006). The document is a comprehensive listing of standard FAR clauses and Department of Interior-specific clauses that apply to the contract, rather than a statement of work or requirements document.

The clauses cover standard federal contracting requirements including ethics and compliance (code of business ethics, anti-kickback procedures, whistleblower rights), small business provisions (small business set-aside notice, subcontracting limitations, post-award re-representation), labor standards (prevailing wage requirements, apprentices and trainees, equal opportunity for veterans and workers with disabilities), procurement requirements (Buy American for construction materials effective October 2022, restrictions on certain telecommunications equipment), and performance requirements (differing site conditions, changes, inspection of construction, termination for convenience). Department of Interior-specific clauses address restriction on endorsements, release of claims requirements, liability insurance minimums of $1,000,000 per person/$500,000 per occurrence/$300,000 property damage, service of protest procedures requiring notification to the Assistant Solicitor for Procurement and Patents within one day of GAO filing, and prohibition on lead-based paint exceeding 0.06 percent by weight in residential structures. The clauses are incorporated by full reference with electronic access available at http://www.acquisition.gov/far/, allowing incorporation by reference rather than full text reproduction in the solicitation.

View the file

Other files for this federal contract opportunity

Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment B Solicitation

140G0126R0006 USGS Flagpole Lighting Installation Page 1 of 13

Attachment B – Contract Clauses

I.1 52.252-02 CLAUSES INCORPORATED BY REFERENCE FEB 1998

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this address:

http://www.acquisition.gov/far/

Clause Title Date 52.202-01 Definitions June 2020 52.203-03 Gratuities April 1984 52.203-05 Covenant Against Contingent Fees May 2014 52.203-06 Restrictions on Subcontractor Sales to the Government June 2020 52.203-07 Anti-Kickback Procedures June 2020 52.203-08 Cancellation, Rescission, and Recovery of Funds for

Illegal or Improper Activity May 2014

52.203-10 Price or Fee Adjustment for Illegal or Improper Activity May 2014 52.203-12 Limitation on Payments to Influence Certain Federal

Transactions June 2020

52.203-13 Contractor Code of Business Ethics and Conduct November 2021 52.203-14 Display of Hotline Poster(s) November 2021 52.203-16 Preventing Personal Conflicts of Interest June 2020 52.203-17 Contractor Employee Whistleblower Rights and

Requirement to Inform Employees of Whistleblower Rights

June 2020

52.204-04 Printed or Copied Double-Sided on Recycled Paper May 2011 52.204-09 Personal Identity Verification of Contractor Personnel January 2011 52.204-10 Reporting Executive Compensation and First-Tier

Subcontract Awards

June 2020

52.204-13 System for Award Management Maintenance October 2018 52.204-14 Service Contract Reporting Requirements October 2016 52.204-18 Commercial and Government Entity Code Maintenance August 2020 52.204-19 Incorporation by Reference of Representations and

Certifications December 2014

52.209-06 Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment

November 2021

52.209-10 Prohibition on Contracting with Inverted Domestic Corporations

November 2015

52.211-10 Commencement, Prosecution, and Completion of Work April 1984 52.211-10 Alternate I Commencement, Prosecution, and Completion of Work April 1984 52.211-13 Time Extensions September 2000 52.215-02 Audit and Records - Negotiation June 2020 52.219-06 Notice of Total Small Business Set-Aside November 2020 http://www.acquisition.gov/far/

USGS Flagpole Lighting Installation Page 2 of 13

52.219-08 Utilization of Small Business Concerns October 2018 52.219-14 Limitations on Subcontracting September 2021 52.219-28 Post-Award Small Business Program Re-representation September 2021 52.222-01 Notice to the Government of Labor Disputes February 1997 52.222-03 Convict Labor June 2003 52.222-04 Contract Work Hours and Safety Standards Act –

Overtime Compensation May 2018

52.222-06 Construction Wage Rate Requirements August 2018 52.222-07 Withholding of Funds May 2014 52.222-08 Payrolls and Basic Records July 2021 52.222-09 Apprentices and Trainees July 2005 52.222-10 Compliance with Copeland Act Requirements February 1988 52.222-11 Subcontracts (Labor Standards) May 2014 52.222-12 Contract Termination – Debarment May 2014 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations May 2014

52.222-14 Disputes Concerning Labor Standards February 1988 52.222-15 Certification of Eligibility May 2014 52.222-21 Prohibition of Segregated Facilities April 2015 52.222-26 Equal Opportunity September 2016 52.222-27 Affirmative Action Compliance Requirements for

Construction April 2015

52.222-32 Construction Wage Rate Requirements-Price Adjustment (Actual Method)

August 2018

52.222-37 Employment Reports on Veterans June 2020 52.222-50 Combating Trafficking in Persons October 2025 52.222-55 Minimum Wages Under Executive Order 13658 January 2022 52.223-02 Affirmative Procurement of Biobased Products Under

Service and Construction Contracts May 2024

52.223-03 Hazardous Material Identification and Material Safety Data

February 2021

52.223-05 Pollution Prevention and Right-to-Know Information May 2024 52.223-06 Drug-Free Workplace May 2001 52.223-10 Waste Reduction Program May 2024 52.223-11 Ozone-Depleting Substances and High Global Warming

Potential Hydrofluorocarbons May 2024

20.223-12 Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners

June 2016

52.223-15 Energy Efficiency in Energy-Consuming Products May 2020 52.223-17 Affirmative Procurement of EPA-designated Items in

Service and Construction Contracts August 2018

52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving

June 2020

52.223-20 Aerosols June 2016 52.223-21 Foams June 2016 52.225-13 Restrictions on Certain Foreign Purchases February 2021 52.228-01 Bid Guarantee September 1996

USGS Flagpole Lighting Installation Page 3 of 13

52.228-02 Additional Bond Security October 1997 52.228-05 Insurance – Work on a Government Installation January 1997 52.228-11 Individual Surety - Pledges of Assets February 2021 52.228-12 Prospective Subcontractor Requests for Bonds May 2014 52.228-14 Irrevocable Letter of Credit November 2014 52.229-03 Federal, State, and Local Taxes February 2013 52.232-05 Payments under Fixed-Price Construction Contracts May 2014 52.232-17 Interest May 2014 52.232-23 Assignment of Claims May 2014 52.232-27 Prompt payment for construction contracts January 2017 52.232-33 Payment by Electronic Funds Transfer - System for

Award Management October 2018

52.232-39 Unenforceability of Unauthorized Obligations June 2013 52.232-40 Providing Accelerated Payments to Small Business

Subcontractors December 2013

52.233-01 Disputes May 2014 52.233-03 Protest after Award August 1996 52.233-04 Applicable Law for Breach of Contract Claim October 2004 52.236-02 Differing Site Conditions April 1984 52.236-03 Site Investigation and Conditions Affecting the Work April 1984 52.236-05 Material and Workmanship April 1984 52.236-06 Superintendence by the Contractor April 1984 52.236-07 Permits and Responsibilities November 1991 52.236-08 Other Contracts April 1984 52.236-09 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements April 1984

52.236-10 Operations and Storage Areas April 1984 52.236-11 Use and Possession Prior to Completion April 1984 52.236-12 Cleaning Up April 1984 52.236-13 Accident Prevention November 1991 52.236-14 Availability and Use of Utility Services April 1984 52.236-15 Schedules for Construction Contracts April 1984 52.237-02 Protection of Government Buildings, Equipment, and

Vegetation April 1984

52.242-02 Production Progress Reports April 1991 52.242-05 Payments to Small Business Subcontractors January 2017 52.242-13 Bankruptcy July 1995 52.242-14 Suspension of Work April 1984 52.243-04 Changes June 2007 52.243-05 Changes and Changed Conditions April 1984 52.244-06 Subcontracts for Commercial Products and Commercial

Services January 2022

52.246-12 Inspection of Construction August 1996 52.249-02 Termination for Convenience of the Government (Fixed-

Price)(Alternate I) April 2012

52.249-10 Default (Fixed-Price Construction) April 1984 52.253-01 Computer Generated Forms January 1991

USGS Flagpole Lighting Installation Page 4 of 13

52.204-25 Prohibition on Contracting for Certain Telecommunications (November 2021) and Video Surveillance Services or Equipment

(a) Definitions. As used in this clause— Backhaul means intermediate links between the core network, or backbone network, and the small subnetworks at the edge of the network (e.g., connecting cell phones/towers to the core telephone network). Backhaul can be wireless (e.g., microwave) or wired (e.g., fiber optic, coaxial cable, Ethernet).

Covered foreign country means The People’s Republic of China.

Covered telecommunications equipment or services means–

(1) Telecommunications equipment produced by Huawei Technologies Company or ZTE Corporation (or any subsidiary or affiliate of such entities);

(2) For the purpose of public safety, security of Government facilities, physical security surveillance of critical infrastructure, and other national security purposes, video surveillance and telecommunications equipment produced by Hytera Communications Corporation, Hangzhou Hikvision Digital Technology Company, or Dahua Technology Company (or any subsidiary or affiliate of such entities);

(3) Telecommunications or video surveillance services provided by such entities or using such equipment; or

(4) Telecommunications or video surveillance equipment or services produced or provided by an entity that the Secretary of Defense, in consultation with the Director of National Intelligence or the Director of the Federal Bureau of Investigation, reasonably believes to be an entity owned or controlled by, or otherwise connected to, the government of a covered foreign country.

Critical technology means–

(1) Defense articles or defense services included on the United States Munitions List set forth in the International Traffic in Arms Regulations under subchapter M of chapter I of title 22, Code of Federal Regulations;

(2) Items included on the Commerce Control List set forth in Supplement No. 1 to part 774 of the Export Administration Regulations under subchapter C of chapter VII of title 15, Code of Federal Regulations, and controlled-

(i) Pursuant to multilateral regimes, including for reasons relating to national security, chemical and biological weapons proliferation, nuclear nonproliferation, or missile technology; or

(ii) For reasons relating to regional stability or surreptitious listening;

(3) Specially designed and prepared nuclear equipment, parts and components, materials, software, and technology covered by part 810 of title 10, Code of Federal Regulations (relating to assistance to foreign atomic energy activities);

(4) Nuclear facilities, equipment, and material covered by part 110 of title 10, Code of Federal Regulations (relating to export and import of nuclear equipment and material);

(5) Select agents and toxins covered by part 331 of title 7, Code of Federal Regulations, part 121 of title 9 of such Code, or part 73 of title 42 of such Code; or

(6) Emerging and foundational technologies controlled pursuant to section 1758 of the Export Control Reform Act of 2018 (50 U.S.C. 4817).

Interconnection arrangements means arrangements governing the physical connection of two or more networks to allow the use of another's network to hand off traffic where it is ultimately delivered (e.g., connection of a customer of telephone provider A to a customer of telephone company B) or sharing data and other information resources.

Reasonable inquiry means an inquiry designed to uncover any information in the entity's possession about the identity of the producer or provider of covered telecommunications equipment or services used by the entity that excludes the need to include an internal or third-party audit.

Roaming means cellular communications services (e.g., voice, video, data) received from a visited network when unable to connect to the facilities of the home network either because signal coverage is too weak or because traffic is too high.

Substantial or essential component means any component necessary for the proper function or performance of a piece of equipment, system, or service.

(b) Prohibition.

USGS Flagpole Lighting Installation Page 5 of 13

(1) Section 889(a)(1)(A) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L. 115-

232) prohibits the head of an executive agency on or after August 13, 2019, from procuring or obtaining, or extending or renewing a contract to procure or obtain, any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system. The Contractor is prohibited from providing to the Government any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system, unless an exception at paragraph (c) of this clause applies or the covered telecommunication equipment or services are covered by a waiver described in FAR 4.2104.

(2) Section 889(a)(1)(B) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L.

115-232) prohibits the head of an executive agency on or after August 13, 2020, from entering into a contract, or extending or renewing a contract, with an entity that uses any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system, unless an exception at paragraph (c) of this clause applies or the covered telecommunication equipment or services are covered by a waiver described in FAR 4.2104. This prohibition applies to the use of covered telecommunications equipment or services, regardless of whether that use is in performance of work under a Federal contract.

(c) Exceptions. This clause does not prohibit contractors from providing—

(1) A service that connects to the facilities of a third-party, such as backhaul, roaming, or interconnection arrangements; or

(2) Telecommunications equipment that cannot route or redirect user data traffic or permit visibility into any user data or packets that such equipment transmits or otherwise handles.

(d) Reporting requirement.

(1) In the event the Contractor identifies covered telecommunications equipment or services used as a substantial or essential component of any system, or as critical technology as part of any system, during contract performance, or the Contractor is notified of such by a subcontractor at any tier or by any other source, the Contractor shall report the information in paragraph (d)(2) of this clause to the Contracting Officer, unless elsewhere in this contract are established procedures for reporting the information; in the case of the Department of Defense, the Contractor shall report to the website at https://dibnet.dod.mil. For indefinite delivery contracts, the Contractor shall report to the Contracting Officer for the indefinite delivery contract and the Contracting Officer(s) for any affected order or, in the case of the Department of Defense, identify both the indefinite delivery contract and any affected orders in the report provided at https://dibnet.dod.mil.

(2) The Contractor shall report the following information pursuant to paragraph (d)(1) of this clause

(i) Within one business day from the date of such identification or notification: the contract number; the order number(s), if applicable; supplier name; supplier unique entity identifier (if known); supplier Commercial and Government Entity (CAGE) code (if known); brand; model number (original equipment manufacturer number, manufacturer part number, or wholesaler number); item description; and any readily available information about mitigation actions undertaken or recommended.

(ii) Within 10 business days of submitting the information in paragraph (d)(2)(i) of this clause: any further available information about mitigation actions undertaken or recommended. In addition, the Contractor shall describe the efforts it undertook to prevent use or submission of covered telecommunications equipment or services, and any additional efforts that will be incorporated to prevent future use or submission of covered telecommunications equipment or services.

(e) Subcontracts. The Contractor shall insert the substance of this clause, including this paragraph (e) and excluding paragraph (b)(2), in all subcontracts and other contractual instruments, including subcontracts for the acquisition of commercial items.

(End of clause) https://www.acquisition.gov/content/42104-waivers#id1989GI040ZO https://dibnet.dod.mil/ https://dibnet.dod.mil/

USGS Flagpole Lighting Installation Page 6 of 13

52.215-19 NOTIFICATION OF OWNERSHIP CHANGES OCTOBER 1997

(a) The Contractor shall make the following notifications in writing:

(1) When the Contractor becomes aware that a change in its ownership has occurred, or is certain to occur, that could result in changes in the valuation of its capitalized assets in the accounting records, the Contractor shall notify the Administrative Contracting Officer (ACO) within 30 days.

(2) The Contractor shall also notify the ACO within 30 days whenever changes to asset valuations or any other cost changes have occurred or are certain to occur as a result of a change in ownership.

(b) The Contractor shall--

(1) Maintain current, accurate, and complete inventory records of assets and their costs;

(2) Provide the ACO or designated representative ready access to the records upon request;

(3) Ensure that all individual and grouped assets, their capitalized values, accumulated depreciation or amortization, and remaining useful lives are identified accurately before and after each of the Contractor's ownership changes; and

(4) Retain and continue to maintain depreciation and amortization schedules based on the asset records maintained before each Contractor ownership change.

(c) The Contractor shall include the substance of this clause in all subcontracts under this contract that meet the applicability requirement of FAR 15.408(k).

(End Clause)

52.222-35 Equal Opportunity for Veterans June 2020

(a) Definitions. As used in this clause--

“Active duty wartime or campaign badge veteran,” “Armed Forces service medal veteran,” “disabled veteran,” “protected veteran,” “qualified disabled veteran,’ and “recently separated veteran” have the meanings given at FAR 22.1301.

(b) Equal opportunity clause. The Contractor shall abide by the requirements of the equal opportunity clause at 41 CFR 60-300.5(a), as of March 24, 2014. This clause prohibits discrimination against qualified protected veterans and requires affirmative action by the Contractor to employ and advance in employment qualified protected veterans.

(c) Subcontracts. The Contractor shall insert the terms of this clause in subcontracts of $150,000 or more unless exempted by rules, regulations, or orders of the Secretary of Labor. The Contractor shall act as specified by the Director, Office of Federal Contract Compliance Programs, to enforce the terms, including action for noncompliance. Such necessary changes in language may be made as shall be appropriate of identify properly the parties and their undertakings.

[Class Deviation- 2017-O0008, Office of Federal contract Compliance Programs Waiver of Certain Clause Requirements in Contracts for Hurricane Harvey Relief Efforts. This clause deviation is effective on Sept 01, 2017, and remains in effect until incorporated into the FAR, or otherwise rescinded.

USGS Flagpole Lighting Installation Page 7 of 13

(d) Notwithstanding the provisions of this section, the Contractor will not be obligated to develop the written affirmative action program required under the regulations implementing the Vietnam Era Veterans’ Readjustment Assistance Act

(VEVRAA).

(End of Clause)

52.222-36 Equal Opportunity for Workers With Disabilities June 2020

(a) Equal opportunity clause. The Contractor shall abide by the requirements of the equal opportunity clause at 41 CFR 60.741.5(a), as of March 24, 2014. This clause prohibits discrimination against qualified individuals on the basis of disability, and requires affirmative action by the Contractor to employ and advance in employment qualified individuals with disabilities.

(b) Subcontracts. The Contractor shall include the terms of this clause in every subcontract or purchase order in excess of $15,000 unless exempted by rules, regulations, or orders of the Secretary, so that such provisions will be binding upon each subcontractor or vendor. The Contractor shall act as specified by the Director, Office of Federal Contract Compliance Programs of the U.S. Department of Labor, to enforce the terms, including action for noncompliance. Such necessary changes in language may be made as shall be appropriate to identify properly the parties and their undertakings.

[Class Deviation- 2017-O0008, Office of Federal contract Compliance Programs Waiver of Certain Clause Requirements in Contracts for Hurricane Harvey Relief Efforts. This clause deviation is effective on Sept 01, 2017, and remains in effect until incorporated into the FAR, or otherwise rescinded.

(c) Notwithstanding the provisions of this section, the Contractor will not be obligated to develop the written affirmative action program required under the regulations implementing section 503 of the Rehabilitation Act of 1973, as amended.

52.225-09 Buy American - Construction Materials. October 2022

(a) Definitions. As used in this clause—

Commercially available off-the-shelf (COTS) item—

(1) Means any item of supply (including construction material) that is–

(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation (FAR) 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

https://www.acquisition.gov/far/2.101#FAR_2_101 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title46-section40102(4)&num=0&edition=prelim

USGS Flagpole Lighting Installation Page 8 of 13

"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

Cost of components means—

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.

Critical item means a domestic construction material or domestic end product that is deemed critical to U.S. supply chain resiliency. The list of critical items is at FAR 25.105.

Domestic construction material means—

(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-

(i) An unmanufactured construction material mined or produced in the United States; or

(ii) A construction material manufactured in the United States, if–

(A) The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or

(B) The construction material is a COTS item; or

(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".

https://www.acquisition.gov/far/25.105#FAR_25_105

USGS Flagpole Lighting Installation Page 9 of 13

Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.

Foreign construction material means a construction material other than a domestic construction material.

Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives.

The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.

Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.

Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.

"United States" means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:

________________________________________________[Contracting Officer to list applicable excepted materials or indicate "none"]

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-

(i) The cost of domestic construction material would be unreasonable.

(A) For domestic construction material that is not a critical item or does not contain critical components.

(1) The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;

(2) For construction material that is not a COTS item and does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is http://uscode.house.gov/view.xhtml?req=granuleid%3AUSC-prelim-title41-chapter83&saved=%7CZ3JhbnVsZWlkOlVTQy1wcmVsaW0tdGl0bGU0MC1jaGFwdGVyMzctZnJvbnQ%3D%7C%7C%7C0%7Cfalse%7Cprelim&edition=prelim http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title41-section1907&num=0&edition=prelim https://www.acquisition.gov/far/12.505#FAR_12_505

USGS Flagpole Lighting Installation Page 10 of 13 no domestic offer received, and the low offer is for foreign construction material that is manufactured in the United States and does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest offer of foreign construction material that exceeds 55 percent domestic content as a domestic offer and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(A)(1) of this clause.

(3) The procedures in paragraph (b)(3)(i)(A)(2) of this clause will no longer apply as of January 1, 2030.

(B) For domestic construction material that is a critical item or contains critical components.

(1) The cost of a particular domestic construction material that is a critical item or contains critical components, subject to the requirements of the Buy American statute, is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent plus the additional preference factor identified for the critical item or construction material containing critical components listed at FAR 25.105.

(2) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest foreign offer of construction material that is manufactured in the United States and exceeds 55 percent domestic content as a domestic offer, and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(B)(1) of this clause.

(3) The procedures in paragraph (b)(3)(i)(B)(2) of this clause will no longer apply as of January 1, 2030.

(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American statute.

(1)

(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

USGS Flagpole Lighting Installation Page 11 of 13

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award.

If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.

(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:

Foreign and Domestic Construction Materials Price Comparison Construction Material Description Unit of Measure Quantity Price (dollars)* Item1:

Foreign construction material _______ _______ _______ Domestic construction material _______ _______ _______

Item2:

Foreign construction material _______ _______ _______ Domestic construction material _______ _______ _______

[* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued)].

[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.]

[Include other applicable supporting information.]

USGS Flagpole Lighting Installation Page 12 of 13

1452.203-70 RESTRICTION ON ENDORSEMENTS—DEPARTMENT JULY 1996

OF THE INTERIOR

The Contractor shall not refer to contracts awarded by the Department of the Interior in commercial advertising, as defined in FAR 31.205-1, in a manner which states or implies that the product or service provided is approved or endorsed by the Government, or is considered by the Government to be superior to other products or services. This restriction is intended to avoid the appearance of preference by the Government toward any product or service. The Contractor may request the Contracting Officer to make a determination as to the propriety of promotional material.

1452.204-70 RELEASE OF CLAIMS – DEPARTMENT OF THE INTERIOR JULY 1996

After completion of work and prior to final payment, the Contractor shall furnish to the Contracting Officer a release of claims against the United States relating to this contract. The Release of Claims form (DI-137) shall be used for this purpose. The form provides for exception of specified claims from operation of the release.

1452.228-70 LIABILITY INSURANCE - DEPARTMENT OF THE INTERIOR JULY 1998

(a) The Contractor shall procure and maintain during the term of this contract and any extension there of liability insurance in form satisfactory to the Contracting Officer by an insurance company which is acceptable to the Contracting Officer. The named insured parties under the policy shall be the Contractor and the United States of America. The amounts of the insurance shall be not less than as follows:

$1,000,000.00 each person $500,000.00 each occurrence $300,000.00 property damage

(a) Each policy shall have a certificate evidencing the insurance coverage. The insurance company shall provide an endorsement to notify the Contracting Officer 30 days prior to the effective date of cancellation or termination of the policy or certificate; or modification of the policy or certificate which may adversely affect the interest of the Government in such insurance. The certificate shall identify the contract number, the name and address of the Contracting Officer, as well as the insured, the policy number and a brief description of contract services to be performed. The contractor shall furnish the Contracting Officer with a copy of an acceptable insurance certificate prior to beginning the work.

1452.233-2 SERVICE OF PROTEST -- DEPARTMENT OF THE

INTERIOR (JUL 1996) (DEVIATION)

JULY 1996

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from Department of the Interior Assistant Solicitor for Procurement and Patents, 1849 C Street, NW, Room 6511, Washington, D.C. 20240.

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the

GAO.

USGS Flagpole Lighting Installation Page 13 of 13

c) A copy of the protest served on the Contracting Officer shall be simultaneously furnished by the protester to the Department of the Interior Assistant Solicitor for Procurement and Patents, 1849 C Street, NW, Room 6511, Washington, D.C. 20240.

I.12 1452.236-70 PROHIBITION AGAINST USE OF LEAD-BASED PAINT JULY 1996

Paint containing more than .06 percent by weight of lead in paint, or the equivalent measure of lead in the dried film of paint already applied, shall not be used in the construction or rehabilitation of residential structures under this contract or any resulting subcontracts.

(End of Contract Clauses)

File details come from the government source that posted it. Updated .