ATTACHMENT B - Beaumont Activation Project Timelines.xlsx
XLSX spreadsheet 15 KB Posted
- Attached to
- Q702--Beaumont CBOC IOT&A
- Solicitation number
- 36C77624Q0257
About this file
This document appears to be an attachment containing a timeline for the Beaumont CBOC IOT&A project. The timeline provides details on the period of performance, deliverables, and contract line items (CLINs) for this federal contract opportunity.
The timeline shows a base period of performance from 10/15/2024 to 10/14/2025, with two 1-year option periods. The base period includes CLINs for Project Management Support, Interior Design/FF&E/Space Planning, Concept of Operations and Transition Planning, and Acquisition Planning Services. There are also optional CLINs for Acquisition Packages Development, Warehousing Services, Relocation of Files, Activation Services, and Staff Training. The contract is managed by the Department of Veterans Affairs Technology Acquisition Center Austin.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Timeline
| Beaumont CBOC IOT&A | ||||||||||||||||||||||||||||||||||||||||||
| 09/24 | 10/24 | 11/24 | 12/24 | 01/25 | 02/25 | 03/25 | 04/25 | 05/25 | 06/25 | 07/25 | 08/25 | 09/25 | 10/25 | 11/25 | 12/25 | 01/26 | 02/26 | 03/26 | 04/26 | 05/26 | 06/26 | 07/26 | 08/26 | 09/26 | 10/26 | 11/26 | 12/26 | 01/27 | 02/27 | 03/27 | 04/27 | 05/27 | 06/27 | 07/27 | 08/27 | 09/27 | 10/27 | |||||
| Task Order Number | CLIN | Task Order Title | Period of Performance | Lease Award | BOD | FPD | ||||||||||||||||||||||||||||||||||||
| PWS 16.1 | Base | CLIN 0001 | PM Support Base Year | 10/15/2024 - 10/14/2025 | ||||||||||||||||||||||||||||||||||||||
| PWS 16.1 | Option Year | CLIN 1001 | PM Support Option Year 1 | 10/15/2025 - 10/14/2026 | ||||||||||||||||||||||||||||||||||||||
| PWS 16.1 | Option Year | CLIN 2001 | PM Support Option Year 2 | 10/15/2026 - 10/14/2027 | ||||||||||||||||||||||||||||||||||||||
| PWS 16.2 | Base | CLIN 0002 | Interior Design, FF&E and Space Planning | 10/15/2024 - 10/14/2025 | ||||||||||||||||||||||||||||||||||||||
| PWS 16.3 | Base | CLIN 0003 | Concept of Operations andTransition Planning | 10/15/2024 - 10/14/2025 | ||||||||||||||||||||||||||||||||||||||
| PWS 16.4 | Base | CLIN 0004 | Acquisition Planning Services | 10/15/2024 - 10/14/2025 | ||||||||||||||||||||||||||||||||||||||
| PWS 17.1 | Optional Task | CLIN 0007 | Acquisition Packages Development | 03/15/2026 - 01/14/2027 | ||||||||||||||||||||||||||||||||||||||
| PWS 17.2 | Optional Task | CLIN 0008 | Warehousing and Warehousing Management Services | 10/15/2026 - 04/14/2027 | ||||||||||||||||||||||||||||||||||||||
| PWS 17.3 | Optional Task | CLIN 0009 | Relocation of Reuse and Personnel Files | 01/11/2027 - 07/14/2027 | ||||||||||||||||||||||||||||||||||||||
| PWS 17.4 | Optional Task | CLIN 0010 | Activation Services and Post Occupancy Support | 01/11/2027 - 10/14/2027 | ||||||||||||||||||||||||||||||||||||||
| PWS 17.5 | Optional Task | CLIN 0011 | Staff Training and Orientation | 01/11/2027 - 10/14/2027 |
CLINs
| Period | CLIN NO. | TASK | Est. PoP | FY | Duration |
| Base | 0001 | PM Support | 10/15/2024 - 10/14/2025 | 25 | 12 MO |
| Base | 0002 | Interior Design, FF&E and Space Planning | 10/15/2024 - 10/14/2025 | 25 | 12 MO |
| Base | 0003 | Concept of Operations (CONOPS) and Transition Planning | 10/15/2024 - 10/14/2025 | 25 | 12 MO |
| Base | 0004 | Acqusition Planning Services | 10/15/2024 - 10/15/2025 | 25 | 12 MO |
| Base | 0005 | Cost Reiumbursable Travel | 10/15/2024 - 10/14/2025 | 25 | 12 MO |
| Base | 0006 | Other Direct Costs-Cost Reimbursable | 10/15/2024 - 10/14/2025 | 25 | 12 MO |
| Optional Task 1 | 0007 | Acquisition Packages Development | 03/15/2026 - 01/14/2027 | 26 | 10 MO |
| Optional Task 2 | 0008 | Warehousing and Warehousing Management Services | 10/15/2026 - 04/14/2027 | 27 | 6 MO |
| Optional Task 3 | 0009 | Relocation of Reuse and Personnel Files | 01/11/2027 - 07/14/2027 | 27 | 6 MO |
| Optional Task 4 | 0010 | Activation Services and Post Occupancy Support | 01/11/2027 - 10/14/2027 | 27 | 9 MO |
| Optional Task 5 | 0011 | Staff Training and Orientation | 01/11/2027 - 10/14/2027 | 27 | 9 MO |
| Option Year 1 | 1001 | PM Support | 10/15/2025 - 10/14/2026 | 26 | 12 MO |
| Option Year 1 | 1005 | Cost Reiumursable Travel | 10/15/2025 - 10/14/2026 | 26 | 12 MO |
| Option Year 1 | 1006 | Other Direct Costs | 10/15/2025 - 10/14/2026 | 26 | 12 MO |
| Option Year 2 | 2001 | PM Support | 10/15/2026 - 10/14/2027 | 27 | 12 MO |
| Option Year 2 | 2005 | Cost Reiumursable Travel | 10/15/2026 - 10/14/2027 | 27 | 12 MO |
| Option Year 2 | 2006 | Other Direct Costs | 10/15/2026 - 10/14/2027 | 27 | 12 MO |