The document is a set of Special Provisions for the Oregon Department of Transportation (ODOT) for the Highway 29 Over PNWR Deck Resurfacing Project located on the Tualatin Valley Highway in Washington County, scheduled for July 2025. The project involves bridge surfacing, asphalt concrete pavement construction, waterproof membrane and joint seal installation, and permanent pavement markings. The work will be performed on Bridge No. 16185, with specific requirements for traffic control, lane closures, and pedestrian routing during construction. The project includes detailed specifications for surface preparation, joint replacement, and pavement marking.

The special provisions outline technical requirements, equipment specifications, and performance standards for the project. Materials will include emulsified asphalt tack coat (approximately 3.11 tons), asphalt concrete pavement, and expansion joint seals. The contract uses statistical acceptance methods for pavement quality and includes provisions for environmental protection, erosion control, and water quality management. The document provides comprehensive guidelines for contractors, including safety policies, equipment conditions, and specific technical requirements for bridge deck resurfacing, with estimated joint seal quantities of 189.0 linear feet for the bridge.

View the file

Other files

File Type Posted
Attachment C - Bid Pricing Form~51.xlsx XLSX spreadsheet
Attachment B - Plans~3.pdf PDF
00014236_Invitation To Bid.docx DOCX document
Attachment D - Standard Drawings~6.pdf PDF
PW-25-08 Addendum 1-Plan Sheets.pdf PDF
Preliminary Bid Results~65.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIAL PROVISIONS

FOR HIGHWAY MAINTENANCE CONSTRUCTION

OREGON DEPARTMENT OF TRANSPORTATION

SALEM, OREGON

STRUCTURE AND PAVING

HWY 29 OVER PNWR DECK RESURFACING PROJECT

TUALATIN VALLEY HIGHWAY

WASHINGTON COUNTY

JULY 2025

FOR

Structure and Paving Hwy 29 Over PNWR Deck Resurfacing Project

Tualatin Valley Highway Washington County

PROFESSIONAL OF RECORD CERTIFICATION:

Seal w/signature I certify the Special Provision Sections listed below are applicable to the design for the subject project for traffic control. Modified Special Provisions were prepared by me or under my supervision.

Sections: 00220, 00221, 00222, 00223, 00224, 00225, 00226, and 00228.

FINAL ELECTRONIC DOCUMENT AVAILABLE UPON REQUEST

2025.06.16 09:19:51 -07'00'

FOR

Structure and Paving

Hwy 29 Over PNWR Deck Resurfacing Project Tualatin Valley Highway

Washington County

PROFESSIONAL OF RECORD CERTIFICATION:

Seal w/signature I certify the Special Provision Sections listed below are applicable to the design for the subject project for pavement and roadway.

Modified Special Provisions were prepared by me or under my supervision.

Sections: 00280, 00305, 00620, 00730, and 00745.

FINAL ELECTRONIC DOCUMENT AVAILABLE UPON REQUEST

2025.06.16 16:12:45 -07'00'

FOR

Structure and Paving Hwy 29 Over PNWR Deck Resurfacing Project

Tualatin Valley Highway Washington County

PROFESSIONAL OF RECORD CERTIFICATION:

I certify the Special Provision Sections listed below are applicable to the design for the subject project for structures. Modified Special Provisions were prepared by me or under my supervision.

Sections: 00503, 00504, 00585, and 00590.

FINAL ELECTRONIC DOCUMENT AVAILABLE UPON REQUEST

06:57:19-07'00'

FOR

Structure and Paving

Tualatin Valley Highway

Washington County

PROFESSIONAL OF RECORD CERTIFICATION:

Seal w/signature

I certify the Special Provision Sections listed below are applicable to the design for the subject project for permanent pavement markings. Modified Special Provisions were prepared by me or under my supervision.

Sections: 00850, 00855, 00865, and 00867.

FINAL ELECTRONIC DOCUMENT AVAILABLE UPON REQUEST

15:28:00 -07'00' iii

TABLE OF CONTENTS FOR SPECIAL PROVISIONS

WORK TO BE DONE

SUPPLEMENTAL SPECIAL PROVISIONS

UTILITY INFORMATION

APPLICABLE SPECIFICATIONS

CLASS OF PROJECT

SECTION 00210 - MOBILIZATION

SECTION 00220 - ACCOMMODATIONS FOR PUBLIC TRAFFIC

SECTION 00221 - COMMON PROVISIONS FOR WORK ZONE TRAFFIC

CONTROL

SECTION 00222 – TEMPORARY TRAFFIC CONTROL SIGNS

SECTION 00223 - WORK ZONE TRAFFIC CONTROL LABOR AND VEHICLES

SECTION 00224 - TEMPORARY TRAFFIC CHANNELIZING DEVICES

SECTION 00225 - TEMPORARY PAVEMENT MARKINGS

SECTION 00226 - TEMPORARY ROADSIDE BARRIERS AND IMPACT

ATTENUATORS

SECTION 00228 - TEMPORARY PEDESTRIAN AND BICYCLIST ROUTING

SECTION 00280 - EROSION AND SEDIMENT CONTROL

SECTION 00290 - ENVIRONMENTAL PROTECTION

SECTION 00305 - CONSTRUCTION SURVEY WORK

SECTION 00503 - BRIDGE DECK COLD PLANE PAVEMENT REMOVAL

SECTION 00504 - CONCRETE DECK SURFACE PREPARATION

SECTION 00585 - EXPANSION JOINTS

SECTION 00590 - POLYMER MEMBRANE

SECTION 00620 - COLD PLANE PAVEMENT REMOVAL

SECTION 00730 - EMULSIFIED ASPHALT TACK COAT

SECTION 00745 - ASPHALT CONCRETE PAVEMENT - STATISTICAL

ACCEPTANCE

SECTION 00850 - COMMON PROVISIONS FOR PAVEMENT MARKINGS

SECTION 00855 - PAVEMENT MARKERS

SECTION 00865 - LONGITUDINAL PAVEMENT MARKINGS - DURABLE

SECTION 00867 - TRANSVERSE PAVEMENT MARKINGS - LEGENDS AND

BARS

WORK TO BE DONE

The Work to be done under this Contract consists of the following:

1. Construct bridge surfacing.

2. Construct asphalt concrete pavement.

3. Install waterproof membrane and joint seals.

4. Install permanent pavement markings.

5. Perform additional and Incidental Work as called for by the Specifications and Plans.

SUPPLEMENTAL SPECIAL PROVISIONS

1. The quantities in the bid item list are intended to serve only as a guide to bidders, and are not to be construed as a guarantee. All quantities are estimated, and are for bid purposes only. The quantity for each bid item includes all labor, equipment and materials for all activities associated with this project. The Oregon Department of Transportation (ODOT) reserves the right to adjust quantities and add or delete, as needed.

2. Contractor shall provide a schedule to the Project Manager seven (7) days prior to the pre-construction meeting to allow for review.

3. Contractor shall schedule a pre-construction meeting with the Project Manager seven (7) days prior to the proposed start of construction.

4. The Engineer will perform the Agency responsibilities described in the Construction Surveying Manual for Contractors, Chapter 1.5 (see Section 00305).

5. The Contractor shall perform the Contractor responsibilities described in the Construction Surveying Manual for Contractors, Chapter 1.6 (see Section 00305). The Contractor shall perform slope staking including intersections and set stakes defining limits for clearing which approximate Right-of-Way and easements.

6. The Contractor shall contact Dennis Hannahs of PNWR by email: dhannahs@gwrr.com or phone number: (503) 508-7440 at least one business day prior to when Work is scheduled to begin on the bridge over the RR.

7. Cooperation with Other Contractors – The Agency reserves the right to perform other work on or near the Project Site, including, without limitation, any Materials site, with forces other than those of the Contractor.

If such work takes place on or near the Project Site, the Contractor shall have the following obligations:

• The Contractor shall coordinate Work with other contractors or forces.

mailto:dhannahs@gwrr.com

• The Contractor shall cooperate in good faith with all other contractors or forces.

• The Contractor shall perform the Work specified in the Contract in a way that will minimize interference and delay for all forces involved.

• The Contractor shall place and dispose of the Materials being used so as not to interfere with the operations of other forces.

• The Contractor shall join the Work with that of all other forces in a manner acceptable to the Engineer or the Agency, and shall perform it in the accepted sequence with the work of the other force.

The Project Manager will resolve any disagreements under this supplemental special provision that may arise among the Contractor and other work forces, or between the Contractor and the Agency. The Project Managers decision in these matters is final.

When the schedules for Work of the Contractor and the work of other forces overlap, each contractor involved shall submit a current, realistic progress schedule to the Project Manager.

Before the Project Manager accepts the schedule, each party shall have the opportunity to review all schedules. After this review and any necessary consultations, the Project Manager will determine acceptable schedules.

The Contractor waives any right it may have to make claims against the Agency for any damages or claims that may arise because of inconvenience, delay, or loss due solely to the presence of other contractors working on or near the Project Site.

8. Contractor shall provide weigh slips for each load of material measured on the weight basis placed in performance of Work under the Contract. Contractor to collect all weigh slips during the shift and give the group of them to the inspector at the end of the shift.

9. Contractor is responsible for providing quality control and quality assurance for the project.

The Project Manager reserves the right to take and re-test material samples, and based upon such test results, to reject any material not meeting the referenced Specifications. It is agreed and understood that the Contractor shall replace all rejected material with material meeting the Specifications at no additional cost to the State.

10. Changes to the scope and/or limits of work are to be requested in writing to the Owners Authorized Representative. The Owners Authorized Representative will respond in writing with approval or denial of the change(s). ADA ramp upgrades that are triggered due to unauthorized changes to the scope and/or limits of work are the Contractors responsibility to remedy. Contractor, or their designated representative, will design and construct the ADA ramp upgrades per ODOT standards at no expense to the Agency. ADA ramp upgrades must follow the triggering activity in a timely manner.

11. Contractor’s employees and their subcontractors may not wear clothing, hats, vests, etc. that have the ODOT name or “flying T” symbol.

12. There is public interest in the work. Contractor is advised to use courtesy and respect in any work site interaction with the public and to refer all public relations matters to the ODOT Project Manager.

13. Contractor shall implement safety policies, procedures and practices in conformance with all applicable local, state and federal laws, rules and regulations including but not limited to:

a. Applicable OSHA safety regulations

b. ANSI Z 133.1 Safety standards agreed upon by ODOT and local jurisdiction

c. The Manual of Uniform Traffic Control Devices (MUTCD)

d. Any other applicable safety laws, regulations and codes.

14. All equipment utilized during this contract shall be in good and serviceable condition.

15. Correspondence for the project is required to have the project name in the subject line.

16. The invoices, certified payrolls (if applicable) and project submittals are to be submitted via email to the Agency Authorized Representative.

17. Invoices must have the following certified statement on them along with a signature by the Contractor’s Authorized Representative.

“I the undersigned, hereby certify that the above bill is true and correct and that payment has not been received. Signature: _______________________”

18. Invoices are to have the contract number and service period listed on them and the following billing address:

ODOT Region 1 123 NW Flanders St Portland, OR 97209

19. Responsibility for Damage to Property and Facilities – In addition to the provisions of the State of Oregon General Conditions for Public Improvement Contracts January 1, 2012 Edition Section G.1, the Contractor, Contractor’s agents, Subcontractors, and all workers performing Work under the Contract (collectively, the “Contractor”), shall:

a. Determine the location of all properties and facilities, Agency and Non-Agency, that could be damaged by the Contractor’s operation, and protect them from damage;

b. Provide adequate protection to avoid damaging Agency and Non-Agency property and facilities;

c. Be responsible for damage to Agency and Non-Agency property and facilities caused by or resulting from the Contractor’s operations;

d. Clean up and restore such damage to the condition that existed before the damage, by repair, rebuilding, replacement, or compensation, as determined by the Engineer;

e. Protect monuments and property marks until the Engineer has authorized their removal;

f. Provide temporary facilities when needed until the required repair, rebuilding, or replacement is accomplished.

UTILITY INFORMATION

The Project is located within the area served by the Oregon Utility Notification Center, which operates a Utilities notification system for notifying owners of Utilities about Work being performed in the vicinity of their facilities. The Contractor shall notify owners of Utilities prior to the performance of Work in the vicinity of their facilities. The Utilities notification system telephone number is 811 or 1-800-332-2344.

The Contractor shall comply with the rules of the Oregon Utility Notification Center, OAR 952-001-0010 through OAR 952-001-0090, and ORS 757.993. The Contractor may contact the Oregon Utility Notification Center at 503-232-1987 about these rules.

Within the Project limits, there are no anticipated Utility relocations or conflicts.

APPLICABLE SPECIFICATIONS

The 2024 Oregon Standard Specifications for Construction (“Standard Specifications”) include detailed technical specifications in Sections 00200 and beyond that apply to this ITB and any resulting Contract. Some sections of the technical specifications may be identified and modified in the Plans and Special Provisions. Sections of the technical specifications not identified in the Plans and Special Provisions remain applicable to the Contract according to their original terms.

Sections in Part 00100 of the Standard Specifications (General Conditions) are not applicable to the Contract unless they are specifically identified in the Plans and Special Provisions as being applicable. However, if a Part 00100 section that has been identified as being applicable references another section in Part 00100, or a technical specification (Parts 00200 and beyond) references a section from Part 00100, that section from Part 00100 applies to the Contract for purposes of supporting and giving full effect to the specification that referenced it. Bidders can access the Standard Specifications online at:

http://www.oregon.gov/ODOT/Business/Pages/Standard_Specifications.aspx

All number references in these Special Provisions shall be understood to refer to the Sections and subsections of the Standard Specifications bearing like numbers and to Sections and subsections contained in these Special Provisions in their entirety.

Conventions Used Throughout the Specifications - The "2024 Oregon Standard Specifications for Construction", Parts 00200 through 03000, the detailed "Technical Specifications", are generally written in the imperative mood, in which the subject is implied.

Therefore, throughout these Specifications, Parts 00200 through 03000, and on the Plans:

• The subject, "the Contractor", is implied.

• "Shall" refers to action required of the Contractor, and is implied.

• "Will" refers to decisions or actions of the Agency and/or the Engineer.

• “The Engineer” refers to The Chief Engineer of the Agency acting either directly or through authorized representatives. If the Agency has not designated a Chief Engineer, this term denotes the person responsible for administering its public works program.

• The following words, or words of equivalent meaning, refer to the actions of the Agency and/or the Engineer, unless otherwise stated: "allowed", "directed", "established", "permitted", "ordered", "designated", "prescribed", "required", "determined".

http://www.oregon.gov/ODOT/Business/Pages/Standard_Specifications.aspx

• The words "approved", "acceptable", "authorized", "satisfactory", "suitable", "considered", and "rejected", "denied", "disapproved", or words of equivalent meaning, mean by or to the Agency and/or the Engineer, subject in each case to Section 00150 of the General Conditions.

• The words "as shown", "shown", "as indicated", or "indicated" mean "as indicated on the Plans".

CLASS OF PROJECT

This is a State Project.

SECTION 00210 - MOBILIZATION

Comply with Section 00210 of the Standard Specifications.

SECTION 00220 - ACCOMMODATIONS FOR PUBLIC TRAFFIC

Comply with Section 00220 of the Standard Specifications modified as follows:

00220.02(a) General Requirements - Add the following bullet to the end of the bullet list:

• When paving operations create an abrupt edge, protect traffic by installing a "DO NOT PASS" (R4-1) sign before the Work Area at sign spacing "A" from the TCD Spacing Table" shown on the Standard Drawings. Alternate "ABRUPT EDGE" (CW21-7) signs with appropriate (CW21-8) rider and "DO NOT PASS" (R4-1) signs at 1/2 mile spacings. Install a "BUMP" (W8-1) sign 100 feet prior to the transverse paving edge.

00220.40(e)(1) Closed Lanes - Replace this subsection, except for the subsection number and title, with the following:

Traffic Lanes may be closed on the Tualatin Valley Highway (OR8) when allowed, shown, or directed during the following periods of time except as specified in 00220.40(e)(2):

Single Lane Closures – One Traffic Lane in each direction on the Tualatin Valley Highway (OR8) may be closed during the following times:

• Daily, Monday through Friday, between 9:00 a.m. and 3:00 p.m.

• Nightly, Monday night through Friday morning, between 7:00 p.m. and 7:00 a.m.

• Friday night through Saturday morning, between 7:00 p.m. and 9:00 a.m.

• Saturday night through Sunday morning, between 6:00 p.m. and 10:00 a.m.

• Sunday night through Monday morning, between 6:00 p.m. and 7:00 a.m.

Three Lane Closures – One Traffic Lane in each direction plus a two-way left turn lane on the Tualatin Valley Highway (OR8) may be closed during the following times:

• Daily, Monday through Friday, between 9:00 a.m. and 3:00 p.m.

• Nightly, Monday night through Friday morning, between 7:00 p.m. and 7:00 a.m.

• Friday night through Saturday morning, between 7:00 p.m. and 9:00 a.m.

• Saturday night through Sunday morning, between 6:00 p.m. and 10:00 a.m.

• Sunday night through Monday morning, between 6:00 p.m. and 7:00 a.m.

Multiple lane Closures – One or more Traffic Lanes on the Tualatin Valley Highway (OR8) may be closed while maintaining one-lane, two-way traffic under temporary traffic control, during the following times:

• Nightly, Sunday night through Friday morning, between 10:00 p.m. and 5:00 a.m.

• Friday night through Saturday morning, between 10:00 p.m. and 7:00 a.m.

• Saturday night through Sunday morning, between 10:00 p.m. and 8:00 a.m.

One Traffic Lane may be closed on all other adjacent Roadways within the Project Site not listed above, when allowed, shown, or directed during the following periods of time except as specified in 00220.40(e)(2):

• Daily, Monday through Thursday, between 9:00 a.m. and 4:00 p.m.

• Friday, between 9:00 a.m. and 3:00 p.m.

• Nightly, Sunday night through Friday morning, between 6:00 p.m. and 7:00 a.m.

Add the following subsection:

00220.41 Bridge Work - Before starting any grading or Pavement removal at Bridge ends or removal of Pavement from Bridge decks, arrange so that all Equipment, labor, and Materials required to complete the Pavement replacement Work and Bridge deck waterproofing Work are on hand or are guaranteed to be delivered. Once grading and Pavement removal begins, vigorously prosecute and complete this Work. Complete paving and membrane waterproofing Work in the shortest possible time.

Temporarily taper or bevel longitudinal and transverse grade changes or drop-offs resulting from grading and Pavement removal and membrane waterproofing Work with asphalt concrete mixture to provide a smooth and safe transition. Construct tapers according to 00620.40.

Add the following subsection:

00220.45 Load Restrictions on Bridges -

For Structure(s) No.16185, limit the combined weight of construction vehicles, Equipment, and daily Material usage to 65,000 pounds for every 1,000 square feet of surface area plus the weight of long term storage of Materials to 25,000 pounds for every 100 square feet of surface area of the Bridge or a total of 200,000 pounds for each span of the Bridge, whichever is less.

The Contractor may request alternate loadings by submitting, 30 Calendar Days before proposed loadings, stamped loading calculations and data according to 00150.35.

SECTION 00221 - COMMON PROVISIONS FOR WORK ZONE TRAFFIC CONTROL

Comply with Section 00221 of the Standard Specifications modified as follows:

00221.06 Traffic Control Plan - Replace this subsection with the following subsection:

00221.06 Traffic Control Plan and Tourist-Oriented Directional and Business Logo Signs –

(a) Traffic Control Plan - Submit one of the following, 5 Calendar Days before the preconstruction conference:

(1) Agency Traffic Control Plan - If the Contractor intends to use the Agency TCP without modification, a written notification indicating that the Agency TCP will be used without modification.

(2) Contractor-Modified Traffic Control Plan - The Contractor may request to use a Contractor-modified Agency TCP, or a TCP developed by the Contractor. Do not use a modified TCP, or a TCP developed by the Contractor, unless approved by the Engineer. Use the Agency TCP unless a modified TCP, or a TCP developed by the Contractor is accepted.

The Engineer is not obligated to consider any modified Agency TCP or a TCP developed by the Contractor. The Agency will not be liable to the Contractor for failure to accept or act upon any request for a modified Agency TCP or a TCP developed by the Contractor.

To conserve time and funds, the Contractor may first submit a written request for a preliminary review by the Engineer. The request should contain a description of the proposal together with a rough estimate of anticipated dollar and time impacts. The Engineer will, within a reasonable time, respond to the Contractor in writing whether or not the request would be considered by the Agency.

If requesting a Contractor-modified Agency TCP, or a TCP developed by the Contractor, at a minimum the request shall meet all requirements of the Contract documents and comply with the Project transportation management plan (TMP).

Provide the following information:

• Stamped Working Drawings according to 00150.35 that include the proposed TCP showing all TCM and quantities of TCD.

• A TPAR plan that includes:

• Details and features used to provide pedestrian accessibility.

• Pedestrian staging Plans at a scale no smaller than 1 inch = 50 feet.

• Temporary alternate facilities or detour routes for pedestrian traffic.

• Staging sequences and details for Work affecting vehicular, pedestrian, and bicycle traffic.

• Proposed order and duration of the TCM.

• A detailed temporary striping plan.

If the Contractor’s request to use a Contractor-modified Agency TCP, or a TCP developed by the Contractor is approved in whole or in part, acceptance will be made by a Change Order.

The Engineer will establish prices that represent a fair measure of the value of Work to be added, changed, or deleted as a result of any accepted modifications to the Agency TCP or an accepted TCP developed by the Contractor.

Once a TCP has been accepted by the Engineer, any additional modifications must be submitted by the Contractor for Agency review following the procedure described above. The Engineer is not obligated to consider additional modifications to a previously approved TCP.

(b) Tourist-Oriented Directional and Business Logo Signs - Submit one of the following for approval, at least 5 Calendar Days before the preconstruction conference:

(1) No Signs - If there are no tourist-oriented directional (TOD) or business logo signs on the Project, a written notification that no TOD or business logo signs exist within the Project limits or

(2) Signs - Submit one copy of a sketch map of the Project showing all existing TOD and business logo signs and a written narrative describing how these signs will be kept in service and protected throughout all the construction stages. If modifications are necessary, submit updated information to the Engineer for approval at least 21 Calendar Days before the change is needed.

00221.90(b) Temporary Protection and Direction of Traffic – Replace the bullet that begins “Providing, Surfacing, maintain…” with the following bullet:

• Providing, surfacing, maintaining, removing, and restoring the TPAR.

SECTION 00222 – TEMPORARY TRAFFIC CONTROL SIGNS

Comply with Section 00222 of the Standard Specifications modified as follows:

00222.40(e) Temporary Sign Placement - Add the following to the end of the bullet list:

• Place a “WAIT FOR FLAGGER” (CR4-23) sign approximately 50 feet in advance of each flagger station, facing incoming pedestrian traffic. Install the sign on a conical marker or other temporary sign support, as shown or as directed. Do not allow the sign installation height or location to block the visibility of the flagger for incoming Public Traffic.

• At least ten Calendar Days before closing the sidewalk at work area along Tualatin

Valley Highway (OR8), place a “SIDEWALK CLOSED, Daily” (CW11-5) sign in advance of each future closure point. Locate the sign so it is legible from the nearest alternate pedestrian pathway facing incoming pedestrian traffic. The sign may be mounted between the panels of a Type II barricade, or on a single-post TSS. Do not place the sign or sign support such that it narrows the pedestrian pathway to a width of less than 4 feet.

• Before opening the TPAR, place TPAR signing and other TCM as shown, or as directed. Maintain the “SIDEWALK CLOSED, Daily” (CW11-5) signs while the TPAR is open to pedestrian traffic.

• Install "ROAD WORK AHEAD" (W20-1-48) signs with a 36 by 24-inch "FINES DOUBLE" (R2-6aP) rider on the Tualatin Valley (OR8) Highway, according to the "TCD Spacing Table" shown on the Standard Drawings or as modified by the Plans except do not install the "FINES DOUBLE" rider on concrete barrier mounted signs.

• Install beyond each end of the Project, facing outgoing traffic, an "END ROAD WORK"

(CG20-2A-24) sign a distance of (A ÷ 2) according to the "TCD Spacing Table" shown on the Standard Drawings or as modified by the Plans.

• For paving operations on non-freeways, place “ABRUPT EDGE” (CW21-9) and “ROAD

WORK XX MPH” (CW20-1a) signs as shown. Use an “XX” value equal to 10 mph below the current posted regulatory speed. If a speed is posted for a temporary regulatory speed reduction, that speed is the current posted regulatory speed.

• For all other moving operations that do not create an abrupt edge adjacent to traffic, omit the “ABRUPT EDGE” signs.

• When construction requires bicycles to use the Traffic Lanes, install a "Bicycle ON

ROADWAY" (CW11-1) symbol sign on 1/2 mile spacing through the affected area.

Keep the signs in place until completion of the Shoulder or bikeway final surface.

• When construction requires bicycles to use the Traffic Lanes on Structures, install a

"Bicycle ON ROADWAY" (CW11-1) symbol sign according to "Sign Spacing A", from the "TRAFFIC CONTROL DEVICES SPACING TABLE" shown on the Standard Drawings, in advance of the Structure or the initial point where the bicycle facility is impacted by construction. Keep the signs in place until completion of the bikeway final surface.

• Install a 72 by 24-inch "CONSTRUCTION VEHICLE DO NOT FOLLOW" (CW23-14) sign on rigid substrate on the back of all Material or Equipment delivery vehicles.

00222.80(a) Area Basis -

Add the following sentence to the end of the paragraph that begins "Temporary signs will…":

No measurement of quantities will be made for “CONSTRUCTION VEHICLE DO NOT FOLLOW” (CW23-14) signs.

SECTION 00223 - WORK ZONE TRAFFIC CONTROL LABOR AND VEHICLES

Comply with Section 00223 of the Standard Specifications modified as follows:

00223.40 Flaggers - Add the following paragraph to the end of this subsection:

During bridge resurfacing work (grinding, membrane installation, paving, striping), provide a dedicated flagger station and flagger to escort bicycle and pedestrian traffic through the affected Work Area.

SECTION 00224 - TEMPORARY TRAFFIC CHANNELIZING DEVICES

Comply with Section 00224 of the Standard Specifications.

SECTION 00225 - TEMPORARY PAVEMENT MARKINGS

Comply with Section 00225 of the Standard Specifications modified as follows:

00225.90 Payment – Replace the paragraph that begins “Item (a)…” with the following paragraph:

Item (a) includes installation and removal of temporary pavement markers having either one or two reflective faces.

Replace the paragraph that begins “Item (b)…” with the following paragraph:

Item (b) includes installation of flexible temporary pavement markers and removal of flexible temporary pavement markers and temporary flexible pavement marker covers.

Add the following paragraph after the paragraph that begins “Item (b)…”:

Items (c) and (e) include removal of the temporary tape.

SECTION 00226 - TEMPORARY ROADSIDE BARRIERS AND IMPACT ATTENUATORS

Comply with Section 00226 of the Standard Specifications modified as follows:

00226.43 Truck Mounted Attenuator – Replace the title of this subsection with “Temporary Impact Attenuator, Truck Mounted –

Replace the paragraph that begins “When workers or construction Equipment…” with the following paragraphs:

Use a temporary truck mounted impact attenuator (TMA), when workers or construction Equipment are exposed to Public Traffic on a Freeway or Multi-Lane Highway and are not located behind a rigid barrier system, as follows unless otherwise shown or directed:

• Each Shoulder or each lane closure where the preconstruction posted speed is 45 mph or more.

Place the TMA in advance of the exposed workers or Equipment, located as shown in the TMA Support Vehicle Placement tables, or as directed. If the TMA is not available when the Work requires its use, postpone the Work until the TMA is available.

00226.63 Truck Mounted Attenuators – Replace the title of this subsection with “Temporary Impact Attenuator, Truck Mounted”

00226.90 Payment -

Add the following paragraphs after the paragraph that begins "In items (g) and (h)…":

Payment for items (g) performed beyond the quantity shown in the Contract Schedule of Items will be made at the Contract unit price if the Engineer determines that the Contract unit price does not exceed the value of the Work as determined according to Section 00197. If the Engineer determines that the Contract unit price exceeds the value of the Work, payment for the Additional Work will be made according to 00195.20.

Add the following paragraph:

No separate or additional payment will be made for TMA’s when the Contractor elects to use them where they otherwise are not required.

SECTION 00228 - TEMPORARY PEDESTRIAN AND BICYCLIST ROUTING

Comply with Section 00228 of the Standard Specifications.

SECTION 00280 - EROSION AND SEDIMENT CONTROL

Comply with Section 00280 of the Standard Specifications modified as follows:

00280.00 Scope - Replace the paragraph that begins "This Work also consists of providing temporary …" with the following paragraph:

This Work also consists of providing temporary erosion and sediment control (ESC) measures and furnishing, installing, moving, operating, maintaining, inspecting, and removing ESC throughout the Project area according to the Standard Drawings, the erosion and sediment control plan (ESCP), the Specifications, or as directed, until the site is permanently stabilized. Included also is the monitoring of weather, of stormwater and receiving waters, the reporting of monitoring observations, the reporting of corrective actions (when necessary) and the updates and revisions of the ESCP, including ESCP cover sheet, necessary to keep it representative of current site conditions and compliant with the NPDES 1200-CA, 1200-CN, OR 1200-C permit if applicable.

Delete the paragraph that begins “When contaminants, pollutants or hazardous materials…”.

Add the following paragraph to the end of this subsection:

The Agency’s NPDES 1200-CA permit is not applicable to this Project. Comply with all applicable conditions of this Section.

00280.02 Definitions - Delete the definition Wet Season Work

00280.04 Erosion and Sediment Control Plan on Agency Controlled Lands - Replace the bullet that begins “Information required under 1200-CA…” with the following bullet:

• Information required under 1200-CA permit, if applicable.

00280.06 Erosion and Sediment Control Manager - Delete this subsection.

00280.16(k) Active Treatment System – Add the following sentence to the end of this subsection:

Obtain approval of the active treatment system from DEQ prior to use.

00280.41(c) Wet Season Work and Temporary Work Suspension - Replace this subsection with the following subsection:

00280.41(c) Temporary Work Interruption - Update the ESCP and schedule for Work proposed between October 1 and May 31 to ensure that all appropriate controls, including ESC during Work interruption, are implemented and maintained. Submit the updated ESCP and schedule to the Agency and receive approval before beginning any Work between October 1 and May 31.

Between October 1 and May 31, limit excavation and bare ground activities to only those required for immediate operations. Stabilize stockpiles at the end of each workday by diverting flows, placing covers, or installing Sediment barriers.

00280.41(f) Hauling Material – Replace this subsection, except for the subsection number and title, with the following:

Cover loads carrying soil or sediment which may generate dust. Haul saturated loads in water tight beds or drain saturated loads prior to leaving the Project Site.

00280.41(g) Underground Injection Controls (UIC) – Replace this subsection, except for the subsection number and title, with the following:

Do not allow storm water from work area to enter Underground Injection Control (UIC) inlets, UIC catch basins or UIC wells.

00280.62 Inspecting and Monitoring – Delete the paragraph that begins “Inspect the Project Site…”.

00280.62(a) Inspection - Replace the paragraph that begins "Perform site inspection, complete…" with the following paragraph:

Inspect the Project Site and all ESC devices for Effective Function and potential erosion or sediment movement and complete all applicable parts of the ODOT Erosion Control Monitoring Form, and submit the form to the Agency as follows:

00280.64(a) Corrective Action Timelines – Delete the bullet that begins “If completion of corrective action is not feasible…”

Delete the bullet that begins “Provide a schedule for clean-up and corrective actions…”

Delete the bullet that begins “Provide all corrective action documentation and photographs…”

00280.91 Payment – Replace the paragraph that begins “Emergency Materials that are incorporated…” with the following paragraph:

Materials listed in 00280.48 that are incorporated into the Project will be paid for under the appropriate items listed in the Contract Schedule of Items.

SECTION 00290 - ENVIRONMENTAL PROTECTION

Comply with Section 00290 of the Standard Specifications modified as follows:

Add the following subsection:

00290.30(a)(7) Water Quality:

• Do not discharge water contaminated by pollutants including sediment, drilling fluids and waste, concrete, grout, or water contained within a work area isolation, into any waters of the State or U.S. or conveyances draining thereto until it has been treated using Materials such as those listed in 00280.15 or 00280.16 or by pumping to a vegetated upland location. Do not allow Project discharges to increase the concentration of any pollutant in the receiving water to a level that exceeds the limits prescribed by OAR 340-041.

• Do not use permanent stormwater quality treatment facilities to treat construction runoff unless prescribed by an ESCP approved under Section 00280.

• If construction discharge water is released using an outfall or diffuser port, do not exceed velocities more than 4 feet per second, and do not exceed an aperture size of 1 inch.

• Implement containment measures adequate to prevent pollutants from entering waters of the State or U.S. Such pollutants include but are not limited to construction and demolition materials, waste spoils, fuel or petroleum products, detergents, silt, welding slag and grindings, concrete sawcutting by-products and sandblasting abrasives.

SECTION 00305 - CONSTRUCTION SURVEY WORK

Comply with Section 00305 of the Standard Specifications.

SECTION 00503 - BRIDGE DECK COLD PLANE PAVEMENT REMOVAL

Comply with Section 00503 of the Standard Specifications.

SECTION 00504 - CONCRETE DECK SURFACE PREPARATION

Comply with Section 00504 of the Standard Specifications modified as follows:

00504.01 Definitions: Replace this subsection with the following subsection:

00504.01 Definitions and Acronym:

(a) Definitions:

Bonded Membrane - A polymer or spray-on waterproofing membrane system that is fully or partially bonded to the concrete deck.

Class 1 Preparation - Deck surface preparation for a membrane or overlay system on an existing bridge deck, where the existing concrete is sound, and minimal concrete removal is required to reach sound concrete.

Class 2 Preparation - Deck surface preparation in areas that are determined by the Engineer to have Unsound Concrete that requires concrete removal beyond the limits of Class 1 Preparation.

Class 3 Preparation - Deck surface preparation in areas where concrete removal extends through the full thickness of the deck.

Fabric Membrane - A rolled or sheet waterproofing membrane system that is installed below or between layers of asphalt Pavement.

Unsound Concrete - Delaminated or otherwise deteriorated concrete identified by a deck delamination survey or during surface preparation operations.

(b) Acronym:

ICRI - International Concrete Repair Institute

00504.21(b) Scarifying Equipment – Replace the paragraph that begins “Furnish power-operated diamond grinding…” with the following paragraph:

Furnish power-operated diamond grinding, micro-milling, or shot blasting scarifying Equipment capable of uniformly removing the existing surface to depths required.

00504.21(b)(3) Shot-blasting - Replace this subsection, except for the subsection number and title, with the following:

Furnish mono-directional or bi-directional shot blast machines with single or multiple blast wheels that conform to EPA air pollution requirements by containing dust and steel abrasive media and that can prepare concrete surfaces according to ICRI Technical Guideline No. 310.2R, to the project specific Concrete Surface Profiles (CSP) profile. Furnish shot type S-330 or larger diameter. If the Equipment is not equipped for simultaneous bi-directional blasting, make separate passes in opposite directions to ensure equal cleaning on all sides of the exposed aggregate.

00504.21(b)(4) Hydroblasting – Delete this subsection.

00504.40(f) Structural Overlay Removal - Replace the paragraph that begins “Remove the existing Structural Overlay to the parent …” with the following paragraph:

Remove the existing Structural Overlay to the parent deck surface. Use Equipment that can sufficiently remove the overlay without exceeding 1/2 inch of parent deck removal.

00504.41(b) Class 1 Preparation – Replace this subsection, except for the subsection number and title, with the following:

• Roughen the existing concrete surface to an exposed aggregate surface texture meeting the following volumetric profiles and ICRI CSP:

• Polymer overlays (MPCO’s and PPC’s) and membranes require minimum profile depth of 1/16 inch and CSP 5.

• Structural cementitious overlays (SCO’s and HESC’s) require a minimum profile depth of 1/8 inch and CSP 7.

• Determine profile depth according to ASTM E965 (standard volumetric test). Perform four tests per 500 square yards of concrete surface prepared, with a minimum of four tests per Day. Visually verify CSP profile with ICRI CSP chips.

• Protect visible reinforcing steel and reinforcing steel where the Plans show it to be within 1/2 inch of the surface.

• When not in conflict with this Specification, follow surface preparation requirements in ICRI Technical Guideline No. 310.2R.

00504.42(a) PPC, MPCO, and Membrane Installations – Replace this subsection with the following:

00504.42(a) PPC, MPCO, Deck Seal, and Membrane Installations - Prepare all surfaces that are to be in contact with the membrane, deck seal or overlay, including vertical contact areas, as follows:

• Clean the entire surface by shot-blasting within 24 hours of placing the membrane or overlay.

• Sweep the area magnetically to remove metal residue.

• Blow clean the surfaces with compressed air.

• Immediately after surface preparation is complete cover the prepared deck with clear plastic, overlapping it to prevent contaminants from construction vehicles or other sources from contacting the deck. Maintain the covering until PPC, MPCO, deck seal or membrane installation.

• If the prepared surface becomes contaminated by spills, rain, or other contaminant before placing the membrane or overlay, prepare the surface again according to this Subsection.

00504.42(b) SCO Overlays – Replace the bullet that begins “Clean the entire surface by shot-blasting…” with the following bullet:

• Clean the entire surface by shot-blasting. Shot-blasting is not required on final surfaces that were prepared by chipping or jack hammering.

SECTION 00585 - EXPANSION JOINTS

Comply with Section 00585 of the Standard Specifications modified as follows:

00585.01 Definitions – Replace the paragraph that begins “Filled Joint…” with the following paragraph:

Filled Joint - A joint using a preformed joint filler placed prior to concrete pour. Hot applied joint sealant or poured joint seal may be placed on top of the joint filler.

Add the following paragraph after the paragraph that begins “Filled Joint…”

Hot Applied Joint Seal - A joint filled with hot applied, single component sealant.

00585.02(b) Personnel Qualifications - Replace this subsection, except for the subsection number and title, with the following:

At the pre-construction conference, submit the following:

• Joint installer personnel certifications(s) from the manufacturer affirming that the installers have been trained in application methods of Materials and health and safety to install Closed Joints as detailed.

• A letter from the manufacturer affirming that the technical representative is qualified to provide technical assistance regarding expansion joint installation.

00585.10 Materials – Add the following Material to the Material list:

Portland Cement Concrete Repair Material

00585.11 Concrete for Blockout Opening – Replace this subsection with the following subsection:

00585.11 Material for Blockout Opening - Fill blockout openings with the same class and type of concrete used in the deck, unless otherwise shown.

For joint surface reconstruction, fill openings with Material as shown or specified. If not shown, fill openings with one of the following Materials:

• Structural polymer concrete with a minimum compressive strength of 10 ksi, a minimum tensile strength of 1 ksi, and a minimum modulus of elasticity of 2,500 ksi.

• High early strength concrete (HESC), Class HESC4000 – 3/4 inch, designed according to Section 02001. Incorporate the following:

• Rapid hardening hydraulic cement meeting the requirements of Section 02011.

• Aggregate meeting the requirements of Section 02690.

• Macro fibers meeting the requirements of 02045.20.

• Portland cement concrete repair materials meeting the requirements of Section 02015.

00585.30(b) Expansion Joint Seal Manufacturer’s Representative - Replace this subsection with the following subsection:

00585.30(b) Expansion Joint Seal Manufacturer’s Technical Representative - Provide a manufacturer’s technical representative during the Work. Prior to beginning the Work, discuss with the representative regarding the Work to be done, methods of installation, installation procedures, and required Equipment to assure correct expansion joint installation.

Ensure the manufacturer’s technical representative remains available for consultation until the completion and acceptance of the Work. For strip seals, the manufacturer’s technical representative is required to be on-site during the Work.

00585.42(c) Joint Preparation - Replace the paragraph that begins "For joint replacement, remove… " with the following paragraph:

For joint replacement, remove joint material from existing joints and clean the existing joints full depth and full width as directed by the Engineer. If existing joint surfaces have spalled, cracked, or deteriorated concrete, repair as shown or directed to provide a uniform and smooth surface. Unless otherwise shown or directed, epoxy inject cracks according to Section 00538 and repair surfaces using an approved PCC repair material.

00585.43 Armored Corners – Replace the title of this subsection with “Armored Corners and Edgebeam”

Replace the paragraph that begins "Provide joint corner armoring …" with the following paragraph:

Provide joint corner armoring or edgebeam with anchors as shown or specified, and according to the following:

00585.43(a) Tolerance - Replace the paragraph that begins "Install armored corners that are straight…" with the following paragraph:

Install armored corners or edgebeams that are straight and do not deviate from a true line by more than 1/4 inch horizontal and 1/8 inch vertical over the length of the joint, nor more than 1/16 inch in either direction from a 12-foot straightedge.

00585.43(b) Installation - Replace the paragraph that begins "Furnish armored corners in the longest …" with the following paragraph:

Furnish armored corners or edgebeams in the longest practical length as controlled by transportation and installation.

Replace the paragraph that begins "For new construction, install armored …" with the following paragraph:

For new construction, install armored corners or edgebeams with anchors in preformed blockouts at least 14 Days after the deck is cast with the joint opening as shown. Support the armored corners or edgebeams securely in position before placing concrete in the joint blockout. Install the preformed seal at least 7 Days after the concrete blockouts have been cast and after the deck concrete reaches 3,000 psi.

00585.47 Strip Seal - Replace the bullet that begins "Use steel retainers acting …” with the following bullet:

• Use steel retainers acting as the edgebeams according to 00585.43.

00585.50 Control Joint - Replace this subsection, except for the subsection number and title, with the following:

Construct Control Joints as shown. If details of the Control Joint are not shown, sawcut the surface 1 1/2 inches deep and 1/2 inch wide. Flush the sawcut thoroughly with a high-pressure water stream after the cut has been made. Before the cut dries out, blow it free of water and debris with compressed air. Fill the sawcut joint with a hot applied joint sealant from the QPL.

Add the following subsection:

00585.51 Hot Applied Joint Seal Replacement - Remove existing hot applied joint sealant from joint. Clean and repair joint surfaces and edges. Install hot applied joint sealant from the QPL and according to the manufacturer’s recommendations.

Add the following subsection:

00585.52 Joint for Sidewalk, Multi-Use Path, or Other Facility Intended for Pedestrian Travel - Provide an expansion joint seal having a firm, stable, and slip resistant top surface, not more than 3/8 inch below finished surface.

For joint seals installed greater than 1/4 inch below finished surface, bevel the joint surface corners with a Slope not steeper than 1V:2H.

For Precompressed Foam Silicone Joint Seals, provide a joint seal having at least double width of the seal designed for the joint size. Install the joint seal according to the manufacturer’s recommendations.

For joint openings 3 inches or wider, design and detail a steel cover plate for facilities with a pedestrian access route (as defined in 00759.02), Temporary Pedestrian Accessible Route, Multi -Use Path, or other structures intended for pedestrian travel. Hot-dip galvanize the steel plate and provide a slip-resistant surface or coating. Limit the elevation change between the steel plate and deck surface with a vertical face to 1/4 inch not to exceed 1/2 inch. When the elevation change is greater than 1/4 inch, bevel the steel plate corners to a Slope not steeper than 1V:2H.

00585.80 Measurement - Replace the paragraph that begins “No measurement of … with the following paragraph:

No measurement of quantities will be made for joints, gland replacement for strip seals, or joint surface reconstruction. Estimated quantities of joints, gland replacement, and joint surface reconstruction are listed below. The listed quantities are based on the theoretical horizontal length from gutter line to gutter line.

Add the following to the end of the subsection:

The estimated quantities of joints are:

Quantity Structure Joint Type (Foot)

Bridge No 16185 Precompressed Foam Silicone Joint Seal 189.0

00585.90 Payment - Add the following paragraph after the paragraph that begins “In item (d), the….”:

Item (g) includes sawcutting and hot applied joint sealant.

SECTION 00590 - POLYMER MEMBRANE

Comply with Section 00590 of the Standard Specifications.

SECTION 00620 - COLD PLANE PAVEMENT REMOVAL

Comply with Section 00620 of the Standard Specifications modified as follows:

00620.43 Maintenance Under Traffic - Replace this subsection, except for the subsection number and title, with the following:

Traffic will be allowed on the cold planed surface up to 7 Calendar Days after removing the existing surface. Sweep and clean the cold planed surface before opening to traffic.

Before beginning paving operations, make repairs to the existing cold planed surface as directed. Payment for the repairs will be made according to 00195.20.

SECTION 00730 - EMULSIFIED ASPHALT TACK COAT

Comply with Section 00730 of the Standard Specifications modified as follows:

00730.11 Emulsified Asphalt – Replace the sentence that begins “Furnish CSS-1, CSS- 1h…” with the following sentence:

Furnish CSS-1, CSS-1h, CMS-2, CMS-2S, CMS-2h, CRS-1, CRS-2, HFRS-2, HFMS-2 or HPTC as selected by the Contractor.

00730.90 Payment - Replace this subsection, except for the subsection number and title, with the following:

No separate or additional payment will be made for Emulsified Asphalt tack coat.

Approximately 3.11 Tons of Emulsified Asphalt in tack coat will be required on this Project.

SECTION 00745 - ASPHALT CONCRETE PAVEMENT - STATISTICAL ACCEPTANCE

Comply with Section 00745 of the Standard Specifications modified as follows:

00745.11(b) Asphalt Cement Additives – Delete the bullet that begins “Anti-stripping asphalt cement…”

00745.47(a)(2) Wearing Course - Replace this subsection, except for the subsection number and title, with the following:

Construct longitudinal joints six inches from permanent lane markings, or as shown or directed.

00745.48(c) Bridge Deck Overlays - Replace the paragraph that begins "Saw cut the wearing Course of Pavement …" with the following paragraph:

Sawcut the wearing or base Course of Pavement directly over the joints in bridge decks, bridge end joints and end Panel end joints as soon as practical but within 48 hours of paving each stage of the wearing or base Course, unless otherwise directed. Saw the cut 3/8 inch wide, ± 1/8 inch, by 1/2 inch less than the thickness of the Panel of Pavement depth or 1 1/2 inches deep, whichever is less.

00745.80 Measurement - Add the following paragraph to the beginning of this subsection:

The quantities of ACP shown in the Contract Schedule of Items were computed on the basis of Aggregates…