Attachment A - Itemized Schedule of Values Cost Breakdown.xlsx

XLSX spreadsheet 73 KB Posted

Attached to
Z1QA--565-20-201 Replace Fire Alarm System (VA-23-00008530)
Solicitation number
36C24623B0002
Issued by

About this file

This document contains a cost proposal template and itemized schedule of values for a federal contract opportunity to replace the fire alarm system at the Veterans Affairs Medical Center located at 2300 Ramsey Street in Fayetteville, North Carolina. The template includes divisions for general requirements, existing conditions, concrete, masonry, metals, wood and plastics, thermal and moisture protection, doors and windows, finishes, specialties, equipment, furnishings, special construction, conveying equipment, fire suppression, plumbing, HVAC, electrical, communications, electronic safety and security, earthwork, exterior improvements, utilities, and transportation. Bidders are to provide labor and material costs by division, overhead and profit percentages, and bonding percentage to calculate total proposed costs for the base offer and up to eight alternatives. The related federal contract opportunity from the Department of Veterans Affairs Veterans Health Administration VISN6 has a solicitation number of 36C24623B0002 and involves replacing the existing fire alarm systems across the campus with a Siemens Desigo system to provide code compliance and integration capabilities.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Base Offer

Base Offer Cost Breakdown

Project Number: 565-20-201 Edward L Roy: VA assigned project #

Date:
Project TitleReplace Fire Alarm System

Edward L Roy: VA assigned Project Title

Project Location2300 Ramsey Street, Fayetteville, NC 28301
Offeror Name
Offeror Street
Offeror CityStateZip

Item Description Labor Cost Edward L Roy: Enter all Labor Costs by Division

Material Cost
Edward L Roy: Enter all Material Costs by DivisionTotal Cost

Edward L Roy: This Column is the sum of the Division's Labor and Material Costs

Division 1General Requirements$ - 0$ - 0$ - 0
Division 2Existing Conditions- 0- 0- 0
Division 3Concrete- 0- 0- 0
Division 4Masonry- 0- 0- 0
Division 5Metals- 0- 0- 0
Division 6Wood and Plastic- 0- 0- 0
Division 7Thermal & Moisture Protect- 0- 0- 0
Division 8Doors and Windows- 0- 0- 0
Division 9Finishes- 0- 0- 0
Division 10Specialties- 0- 0- 0
Division 11Equipment- 0- 0- 0
Division 12Furnishings- 0- 0- 0
Division 13Special Construction- 0- 0- 0
Division 14Conveying Equipment- 0- 0- 0
Division 21Fire Suppression- 0- 0- 0
Division 22Plumbing- 0- 0- 0
Division 23HVAC- 0- 0- 0
Division 26Electrical- 0- 0- 0
Division 27Communications- 0- 0- 0
Division 28Electronic Safety & Security- 0- 0- 0
Division 31Earthwork- 0- 0- 0
Division 32Exterior Improvements- 0- 0- 0
Division 33Utilities- 0- 0- 0
Division 34Transportation Subtotal- 0- 0- 0
Division Subtotals :$ - 0$ - 0$ - 0

Overhead % 0.00% Edward L Roy: Enter Overhead % here. This % will be multiplied by the Division Total Cost Subtotal (cell F36).

Edward L Roy: Date Offer Prepared/Submitted

- 0
Profit %0.00%
Edward L Roy: Enter Profit % here.This % will be multiplied by the sum of the Division Total Cost subtotal (cell F36) plus the calculated Overhead (cell F38).- 0
Bond %0.00%

Edward L Roy: Enter Bond % here. This % will be multiplied by the sum of the Division Total Cost Subtotal (cell F36), the amount of calculated Overhead (cell F38) and the amount of calculated Profit (cell F39).

Edward L Roy: Enter all Labor Costs by Division

- 0
Overhead/Profit Subtotals :$ - 0

Edward L Roy: Sum of Overhead, Profit and Bond %.

Edward L Roy: Enter all Material Costs by Division Edward L Roy: This Column is the sum of the Division's Labor and Material Costs Total Base Offer Cost $ - 0 $ - 0 $ - 0

Alternative 1

Alternative 1 Offer Cost Breakdown

Project Number: 565-20-201 Edward L Roy: VA assigned project #

Date:
Project TitleReplace Fire Alarm System

Edward L Roy: VA assigned Project Title

Project Location2300 Ramsey Street, Fayetteville, NC 28301
Offeror Name
Offeror Street
Offeror CityStateZip

Item Description Labor Cost Edward L Roy: Enter all Labor Costs by Division

Material Cost
Edward L Roy: Enter all Material Costs by DivisionTotal Cost

Edward L Roy: This Column is the sum of the Division's Labor and Material Costs

Division 1General Requirements$ - 0$ - 0$ - 0
Division 2Existing Conditions- 0- 0- 0
Division 3Concrete- 0- 0- 0
Division 4Masonry- 0- 0- 0
Division 5Metals- 0- 0- 0
Division 6Wood and Plastic- 0- 0- 0
Division 7Thermal & Moisture Protect- 0- 0- 0
Division 8Doors and Windows- 0- 0- 0
Division 9Finishes- 0- 0- 0
Division 10Specialties- 0- 0- 0
Division 11Equipment- 0- 0- 0
Division 12Furnishings- 0- 0- 0
Division 13Special Construction- 0- 0- 0
Division 14Conveying Equipment- 0- 0- 0
Division 21Fire Suppression- 0- 0- 0
Division 22Plumbing- 0- 0- 0
Division 23HVAC- 0- 0- 0
Division 26Electrical- 0- 0- 0
Division 27Communications- 0- 0- 0
Division 28Electronic Safety & Security- 0- 0- 0
Division 31Earthwork- 0- 0- 0
Division 32Exterior Improvements- 0- 0- 0
Division 33Utilities- 0- 0- 0
Division 34Transportation Subtotal- 0- 0- 0
Division Subtotals :$ - 0$ - 0$ - 0

Overhead % 0.00% Edward L Roy: Enter Overhead % here. This % will be multiplied by the Division Total Cost Subtotal (cell F36).

Edward L Roy: Date Offer Prepared/Submitted

- 0
Profit %0.00%
Edward L Roy: Enter Profit % here.This % will be multiplied by the sum of the Division Total Cost subtotal (cell F36) plus the calculated Overhead (cell F38).- 0
Bond %0.00%

Edward L Roy: Enter Bond % here. This % will be multiplied by the sum of the Division Total Cost Subtotal (cell F36), the amount of calculated Overhead (cell F38) and the amount of calculated Profit (cell F39).

Edward L Roy: Enter all Labor Costs by Division

- 0
Overhead/Profit Subtotals :$ - 0

Edward L Roy: Enter all Material Costs by Division Edward L Roy: This Column is the sum of the Division's Labor and Material Costs Total Alt. 1 Offer Cost $ - 0 $ - 0 $ - 0

Alternative 2

Alternative 2 Offer Cost Breakdown

Project Number: 565-20-201 Edward L Roy: VA assigned project #

Date:
Project TitleReplace Fire Alarm System

Edward L Roy: VA assigned Project Title

Project Location2300 Ramsey Street, Fayetteville, NC 28301
Offeror Name
Offeror Street
Offeror CityStateZip

Item Description Labor Cost Edward L Roy: Enter all Labor Costs by Division

Material Cost
Edward L Roy: Enter all Material Costs by DivisionTotal Cost

Edward L Roy: This Column is the sum of the Division's Labor and Material Costs

Division 1General Requirements$ - 0$ - 0$ - 0
Division 2Existing Conditions- 0- 0- 0
Division 3Concrete- 0- 0- 0
Division 4Masonry- 0- 0- 0
Division 5Metals- 0- 0- 0
Division 6Wood and Plastic- 0- 0- 0
Division 7Thermal & Moisture Protect- 0- 0- 0
Division 8Doors and Windows- 0- 0- 0
Division 9Finishes- 0- 0- 0
Division 10Specialties- 0- 0- 0
Division 11Equipment- 0- 0- 0
Division 12Furnishings- 0- 0- 0
Division 13Special Construction- 0- 0- 0
Division 14Conveying Equipment- 0- 0- 0
Division 21Fire Suppression- 0- 0- 0
Division 22Plumbing- 0- 0- 0
Division 23HVAC- 0- 0- 0
Division 26Electrical- 0- 0- 0
Division 27Communications- 0- 0- 0
Division 28Electronic Safety & Security- 0- 0- 0
Division 31Earthwork- 0- 0- 0
Division 32Exterior Improvements- 0- 0- 0
Division 33Utilities- 0- 0- 0
Division 34Transportation Subtotal- 0- 0- 0
Division Subtotals :$ - 0$ - 0$ - 0

Overhead % 0.00% Edward L Roy: Enter Overhead % here. This % will be multiplied by the Division Total Cost Subtotal (cell F36).

Edward L Roy: Date Offer Prepared/Submitted

- 0
Profit %0.00%
Edward L Roy: Enter Profit % here.This % will be multiplied by the sum of the Division Total Cost subtotal (cell F36) plus the calculated Overhead (cell F38).- 0
Bond %0.00%

Edward L Roy: Enter Bond % here. This % will be multiplied by the sum of the Division Total Cost Subtotal (cell F36), the amount of calculated Overhead (cell F38) and the amount of calculated Profit (cell F39).

Edward L Roy: Enter all Labor Costs by Division

- 0
Overhead/Profit Subtotals :$ - 0

Edward L Roy: Enter all Material Costs by Division Edward L Roy: This Column is the sum of the Division's Labor and Material Costs Total Alt. 2 Offer Cost $ - 0 $ - 0 $ - 0

Alternative 3

Alternative 2 Offer Cost Breakdown

Project Number: 565-20-201 Edward L Roy: VA assigned project #

Date:
Project TitleReplace Fire Alarm System

Edward L Roy: VA assigned Project Title

Project Location2300 Ramsey Street, Fayetteville, NC 28301
Offeror Name
Offeror Street
Offeror CityStateZip

Item Description Labor Cost Edward L Roy: Enter all Labor Costs by Division

Material Cost
Edward L Roy: Enter all Material Costs by DivisionTotal Cost

Edward L Roy: This Column is the sum of the Division's Labor and Material Costs

Division 1General Requirements$ - 0$ - 0$ - 0
Division 2Existing Conditions- 0- 0- 0
Division 3Concrete- 0- 0- 0
Division 4Masonry- 0- 0- 0
Division 5Metals- 0- 0- 0
Division 6Wood and Plastic- 0- 0- 0
Division 7Thermal & Moisture Protect- 0- 0- 0
Division 8Doors and Windows- 0- 0- 0
Division 9Finishes- 0- 0- 0
Division 10Specialties- 0- 0- 0
Division 11Equipment- 0- 0- 0
Division 12Furnishings- 0- 0- 0
Division 13Special Construction- 0- 0- 0
Division 14Conveying Equipment- 0- 0- 0
Division 21Fire Suppression- 0- 0- 0
Division 22Plumbing- 0- 0- 0
Division 23HVAC- 0- 0- 0
Division 26Electrical- 0- 0- 0
Division 27Communications- 0- 0- 0
Division 28Electronic Safety & Security- 0- 0- 0
Division 31Earthwork- 0- 0- 0
Division 32Exterior Improvements- 0- 0- 0
Division 33Utilities- 0- 0- 0
Division 34Transportation Subtotal- 0- 0- 0
Division Subtotals :$ - 0$ - 0$ - 0

Overhead % 0.00% Edward L Roy: Enter Overhead % here. This % will be multiplied by the Division Total Cost Subtotal (cell F36).

Edward L Roy: Date Offer Prepared/Submitted

- 0
Profit %0.00%
Edward L Roy: Enter Profit % here.This % will be multiplied by the sum of the Division Total Cost subtotal (cell F36) plus the calculated Overhead (cell F38).- 0
Bond %0.00%

Edward L Roy: Enter Bond % here. This % will be multiplied by the sum of the Division Total Cost Subtotal (cell F36), the amount of calculated Overhead (cell F38) and the amount of calculated Profit (cell F39).

Edward L Roy: Enter all Labor Costs by Division

- 0
Overhead/Profit Subtotals :$ - 0

Edward L Roy: Enter all Material Costs by Division Edward L Roy: This Column is the sum of the Division's Labor and Material Costs Total Alt. 2 Offer Cost $ - 0 $ - 0 $ - 0

Alternative 4

Alternative 2 Offer Cost Breakdown

Project Number: 565-20-201 Edward L Roy: VA assigned project #

Date:
Project TitleReplace Fire Alarm System

Edward L Roy: VA assigned Project Title

Project Location2300 Ramsey Street, Fayetteville, NC 28301
Offeror Name
Offeror Street
Offeror CityStateZip

Item Description Labor Cost Edward L Roy: Enter all Labor Costs by Division

Material Cost
Edward L Roy: Enter all Material Costs by DivisionTotal Cost

Edward L Roy: This Column is the sum of the Division's Labor and Material Costs

Division 1General Requirements$ - 0$ - 0$ - 0
Division 2Existing Conditions- 0- 0- 0
Division 3Concrete- 0- 0- 0
Division 4Masonry- 0- 0- 0
Division 5Metals- 0- 0- 0
Division 6Wood and Plastic- 0- 0- 0
Division 7Thermal & Moisture Protect- 0- 0- 0
Division 8Doors and Windows- 0- 0- 0
Division 9Finishes- 0- 0- 0
Division 10Specialties- 0- 0- 0
Division 11Equipment- 0- 0- 0
Division 12Furnishings- 0- 0- 0
Division 13Special Construction- 0- 0- 0
Division 14Conveying Equipment- 0- 0- 0
Division 21Fire Suppression- 0- 0- 0
Division 22Plumbing- 0- 0- 0
Division 23HVAC- 0- 0- 0
Division 26Electrical- 0- 0- 0
Division 27Communications- 0- 0- 0
Division 28Electronic Safety & Security- 0- 0- 0
Division 31Earthwork- 0- 0- 0
Division 32Exterior Improvements- 0- 0- 0
Division 33Utilities- 0- 0- 0
Division 34Transportation Subtotal- 0- 0- 0
Division Subtotals :$ - 0$ - 0$ - 0

Overhead % 0.00% Edward L Roy: Enter Overhead % here. This % will be multiplied by the Division Total Cost Subtotal (cell F36).

Edward L Roy: Date Offer Prepared/Submitted

- 0
Profit %0.00%
Edward L Roy: Enter Profit % here.This % will be multiplied by the sum of the Division Total Cost subtotal (cell F36) plus the calculated Overhead (cell F38).- 0
Bond %0.00%

Edward L Roy: Enter Bond % here. This % will be multiplied by the sum of the Division Total Cost Subtotal (cell F36), the amount of calculated Overhead (cell F38) and the amount of calculated Profit (cell F39).

Edward L Roy: Enter all Labor Costs by Division

- 0
Overhead/Profit Subtotals :$ - 0

Edward L Roy: Enter all Material Costs by Division Edward L Roy: This Column is the sum of the Division's Labor and Material Costs Total Alt. 2 Offer Cost $ - 0 $ - 0 $ - 0

Alternative 5

Alternative 2 Offer Cost Breakdown

Project Number: 565-20-201 Edward L Roy: VA assigned project #

Date:
Project TitleReplace Fire Alarm System

Edward L Roy: VA assigned Project Title

Project Location2300 Ramsey Street, Fayetteville, NC 28301
Offeror Name
Offeror Street
Offeror CityStateZip

Item Description Labor Cost Edward L Roy: Enter all Labor Costs by Division

Material Cost
Edward L Roy: Enter all Material Costs by DivisionTotal Cost

Edward L Roy: This Column is the sum of the Division's Labor and Material Costs

Division 1General Requirements$ - 0$ - 0$ - 0
Division 2Existing Conditions- 0- 0- 0
Division 3Concrete- 0- 0- 0
Division 4Masonry- 0- 0- 0
Division 5Metals- 0- 0- 0
Division 6Wood and Plastic- 0- 0- 0
Division 7Thermal & Moisture Protect- 0- 0- 0
Division 8Doors and Windows- 0- 0- 0
Division 9Finishes- 0- 0- 0
Division 10Specialties- 0- 0- 0
Division 11Equipment- 0- 0- 0
Division 12Furnishings- 0- 0- 0
Division 13Special Construction- 0- 0- 0
Division 14Conveying Equipment- 0- 0- 0
Division 21Fire Suppression- 0- 0- 0
Division 22Plumbing- 0- 0- 0
Division 23HVAC- 0- 0- 0
Division 26Electrical- 0- 0- 0
Division 27Communications- 0- 0- 0
Division 28Electronic Safety & Security- 0- 0- 0
Division 31Earthwork- 0- 0- 0
Division 32Exterior Improvements- 0- 0- 0
Division 33Utilities- 0- 0- 0
Division 34Transportation Subtotal- 0- 0- 0
Division Subtotals :$ - 0$ - 0$ - 0

Overhead % 0.00% Edward L Roy: Enter Overhead % here. This % will be multiplied by the Division Total Cost Subtotal (cell F36).

Edward L Roy: Date Offer Prepared/Submitted

- 0
Profit %0.00%
Edward L Roy: Enter Profit % here.This % will be multiplied by the sum of the Division Total Cost subtotal (cell F36) plus the calculated Overhead (cell F38).- 0
Bond %0.00%

Edward L Roy: Enter Bond % here. This % will be multiplied by the sum of the Division Total Cost Subtotal (cell F36), the amount of calculated Overhead (cell F38) and the amount of calculated Profit (cell F39).

Edward L Roy: Enter all Labor Costs by Division

- 0
Overhead/Profit Subtotals :$ - 0

Edward L Roy: Enter all Material Costs by Division Edward L Roy: This Column is the sum of the Division's Labor and Material Costs Total Alt. 2 Offer Cost $ - 0 $ - 0 $ - 0

Alternative 6

Alternative 2 Offer Cost Breakdown

Project Number: 565-20-201 Edward L Roy: VA assigned project #

Date:
Project TitleReplace Fire Alarm System

Edward L Roy: VA assigned Project Title

Project Location2300 Ramsey Street, Fayetteville, NC 28301
Offeror Name
Offeror Street
Offeror CityStateZip

Item Description Labor Cost Edward L Roy: Enter all Labor Costs by Division

Material Cost
Edward L Roy: Enter all Material Costs by DivisionTotal Cost

Edward L Roy: This Column is the sum of the Division's Labor and Material Costs

Division 1General Requirements$ - 0$ - 0$ - 0
Division 2Existing Conditions- 0- 0- 0
Division 3Concrete- 0- 0- 0
Division 4Masonry- 0- 0- 0
Division 5Metals- 0- 0- 0
Division 6Wood and Plastic- 0- 0- 0
Division 7Thermal & Moisture Protect- 0- 0- 0
Division 8Doors and Windows- 0- 0- 0
Division 9Finishes- 0- 0- 0
Division 10Specialties- 0- 0- 0
Division 11Equipment- 0- 0- 0
Division 12Furnishings- 0- 0- 0
Division 13Special Construction- 0- 0- 0
Division 14Conveying Equipment- 0- 0- 0
Division 21Fire Suppression- 0- 0- 0
Division 22Plumbing- 0- 0- 0
Division 23HVAC- 0- 0- 0
Division 26Electrical- 0- 0- 0
Division 27Communications- 0- 0- 0
Division 28Electronic Safety & Security- 0- 0- 0
Division 31Earthwork- 0- 0- 0
Division 32Exterior Improvements- 0- 0- 0
Division 33Utilities- 0- 0- 0
Division 34Transportation Subtotal- 0- 0- 0
Division Subtotals :$ - 0$ - 0$ - 0

Overhead % 0.00% Edward L Roy: Enter Overhead % here. This % will be multiplied by the Division Total Cost Subtotal (cell F36).

Edward L Roy: Date Offer Prepared/Submitted

- 0
Profit %0.00%
Edward L Roy: Enter Profit % here.This % will be multiplied by the sum of the Division Total Cost subtotal (cell F36) plus the calculated Overhead (cell F38).- 0
Bond %0.00%

Edward L Roy: Enter Bond % here. This % will be multiplied by the sum of the Division Total Cost Subtotal (cell F36), the amount of calculated Overhead (cell F38) and the amount of calculated Profit (cell F39).

Edward L Roy: Enter all Labor Costs by Division

- 0
Overhead/Profit Subtotals :$ - 0

Edward L Roy: Enter all Material Costs by Division Edward L Roy: This Column is the sum of the Division's Labor and Material Costs Total Alt. 2 Offer Cost $ - 0 $ - 0 $ - 0

Alternative 7

Alternative 2 Offer Cost Breakdown

Project Number: 565-20-201 Edward L Roy: VA assigned project #

Date:
Project TitleReplace Fire Alarm System

Edward L Roy: VA assigned Project Title

Project Location2300 Ramsey Street, Fayetteville, NC 28301
Offeror Name
Offeror Street
Offeror CityStateZip

Item Description Labor Cost Edward L Roy: Enter all Labor Costs by Division

Material Cost
Edward L Roy: Enter all Material Costs by DivisionTotal Cost

Edward L Roy: This Column is the sum of the Division's Labor and Material Costs

Division 1General Requirements$ - 0$ - 0$ - 0
Division 2Existing Conditions- 0- 0- 0
Division 3Concrete- 0- 0- 0
Division 4Masonry- 0- 0- 0
Division 5Metals- 0- 0- 0
Division 6Wood and Plastic- 0- 0- 0
Division 7Thermal & Moisture Protect- 0- 0- 0
Division 8Doors and Windows- 0- 0- 0
Division 9Finishes- 0- 0- 0
Division 10Specialties- 0- 0- 0
Division 11Equipment- 0- 0- 0
Division 12Furnishings- 0- 0- 0
Division 13Special Construction- 0- 0- 0
Division 14Conveying Equipment- 0- 0- 0
Division 21Fire Suppression- 0- 0- 0
Division 22Plumbing- 0- 0- 0
Division 23HVAC- 0- 0- 0
Division 26Electrical- 0- 0- 0
Division 27Communications- 0- 0- 0
Division 28Electronic Safety & Security- 0- 0- 0
Division 31Earthwork- 0- 0- 0
Division 32Exterior Improvements- 0- 0- 0
Division 33Utilities- 0- 0- 0
Division 34Transportation Subtotal- 0- 0- 0
Division Subtotals :$ - 0$ - 0$ - 0

Overhead % 0.00% Edward L Roy: Enter Overhead % here. This % will be multiplied by the Division Total Cost Subtotal (cell F36).

Edward L Roy: Date Offer Prepared/Submitted

- 0
Profit %0.00%
Edward L Roy: Enter Profit % here.This % will be multiplied by the sum of the Division Total Cost subtotal (cell F36) plus the calculated Overhead (cell F38).- 0
Bond %0.00%

Edward L Roy: Enter Bond % here. This % will be multiplied by the sum of the Division Total Cost Subtotal (cell F36), the amount of calculated Overhead (cell F38) and the amount of calculated Profit (cell F39).

Edward L Roy: Enter all Labor Costs by Division

- 0
Overhead/Profit Subtotals :$ - 0

Edward L Roy: Enter all Material Costs by Division Edward L Roy: This Column is the sum of the Division's Labor and Material Costs Total Alt. 2 Offer Cost $ - 0 $ - 0 $ - 0

Alternative 8

Alternative 2 Offer Cost Breakdown

Project Number: 565-20-201 Edward L Roy: VA assigned project #

Date:
Project TitleReplace Fire Alarm System

Edward L Roy: VA assigned Project Title

Project Location2300 Ramsey Street, Fayetteville, NC 28301
Offeror Name
Offeror Street
Offeror CityStateZip

Item Description Labor Cost Edward L Roy: Enter all Labor Costs by Division

Material Cost
Edward L Roy: Enter all Material Costs by DivisionTotal Cost

Edward L Roy: This Column is the sum of the Division's Labor and Material Costs

Division 1General Requirements$ - 0$ - 0$ - 0
Division 2Existing Conditions- 0- 0- 0
Division 3Concrete- 0- 0- 0
Division 4Masonry- 0- 0- 0
Division 5Metals- 0- 0- 0
Division 6Wood and Plastic- 0- 0- 0
Division 7Thermal & Moisture Protect- 0- 0- 0
Division 8Doors and Windows- 0- 0- 0
Division 9Finishes- 0- 0- 0
Division 10Specialties- 0- 0- 0
Division 11Equipment- 0- 0- 0
Division 12Furnishings- 0- 0- 0
Division 13Special Construction- 0- 0- 0
Division 14Conveying Equipment- 0- 0- 0
Division 21Fire Suppression- 0- 0- 0
Division 22Plumbing- 0- 0- 0
Division 23HVAC- 0- 0- 0
Division 26Electrical- 0- 0- 0
Division 27Communications- 0- 0- 0
Division 28Electronic Safety & Security- 0- 0- 0
Division 31Earthwork- 0- 0- 0
Division 32Exterior Improvements- 0- 0- 0
Division 33Utilities- 0- 0- 0
Division 34Transportation Subtotal- 0- 0- 0
Division Subtotals :$ - 0$ - 0$ - 0

Overhead % 0.00% Edward L Roy: Enter Overhead % here. This % will be multiplied by the Division Total Cost Subtotal (cell F36).

Edward L Roy: Date Offer Prepared/Submitted

- 0
Profit %0.00%
Edward L Roy: Enter Profit % here.This % will be multiplied by the sum of the Division Total Cost subtotal (cell F36) plus the calculated Overhead (cell F38).- 0
Bond %0.00%

Edward L Roy: Enter Bond % here. This % will be multiplied by the sum of the Division Total Cost Subtotal (cell F36), the amount of calculated Overhead (cell F38) and the amount of calculated Profit (cell F39).

Edward L Roy: Enter all Labor Costs by Division

- 0
Overhead/Profit Subtotals :$ - 0

Edward L Roy: Enter all Material Costs by Division Edward L Roy: This Column is the sum of the Division's Labor and Material Costs Total Alt. 2 Offer Cost $ - 0 $ - 0 $ - 0

File details come from the government source that posted it. Updated .