Attachment A.pdf

PDF 6 MB Posted

Attached to
ASHLEY AVE SIGN
Solicitation number
5400026266
Issued by
Charleston County, South Carolina

About this file

This is a Project Manual and specification document for the Medical University of South Carolina (MUSC) Horseshoe Gateway Sign project located in Charleston, South Carolina, prepared by landscape and structural engineers ADC Engineering. The project, identified as MUSC Project #WO23-103676, encompasses the design and construction of a gateway sign structure with associated concrete work, including cast-in-place concrete footings and slabs-on-grade, as well as precast architectural concrete cladding units. The manual contains detailed specifications across multiple divisions, including general requirements for execution, cutting and patching, selective demolition, closeout procedures, and project record documentation. The specifications establish comprehensive requirements for concrete materials, reinforcement, formwork, placement procedures, finishing standards, and quality assurance protocols, with particular emphasis on structural performance, durability, and architectural finishes.

The specifications detail extensive performance and material requirements for both cast-in-place and precast concrete work, including minimum compressive strength of 3,000 psi for footings and slabs-on-grade, specific admixture requirements, and vapor barrier specifications with permeance limits. The precast architectural concrete units are to be manufactured by The Cast Stone Company/Tanner Stone in standard white color, with fabrication tolerances specified in accordance with PCI MNL 117 standards and design compressive strength of 5,000 psi minimum. The document mandates pre-installation conferences, independent testing agency engagement, qualified installer and fabricator credentials, welding certifications, and detailed quality control testing including core sampling procedures. Fabrication and erection tolerances are tightly controlled, with exposed panel dimensions specified to plus or minus 1/8 inch for units under 10 feet, and comprehensive field quality control and inspection requirements are outlined throughout to ensure compliance with all structural and architectural specifications.

View the file

Other files

File Type Posted
Solicitation.pdf PDF
Award.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Manual for:

Medical University of South Carolina

MUSC Horseshoe Gateway Sign Charleston, SC

MUSC Project #: WO23-103676

FOR BIDDING

November 17, 2023

Landscape and Structural Engineers:

ADC Engineering 1226 Yeamans Hall Road Hanahan, South Carolina 29410 843 566-0161 o

Table of Contents MUSC Horseshoe Gateway Sign 11/17/23 Page 1 of 1

TABLE OF CONTENTS

PROJECT NUMBER: WO23 - 103676

PROJECT NAME: MUSC Horseshoe Gateway Sign

Division 1 General Requirements Date Pages

017000 Execution Requirements 11/17/23 7 pages 017310 Cutting and Patching 11/17/23 5 pages 017320 Selective Demolition 11/17/23 10 pages

Division 2 Not Used

Division 3 Concrete

033000 Cast in Place Concrete 11/17/23 25 pages 034500 Precast Architectural Concrete 11/17/23 17 pages

DRAWING LIST

L100 Cover Sheet and Index L101 Code Information and General Notes L300 General Notes

017000

Execution Requirements MUSC Horseshoe Gateway Sign 11/17/23

SECTION 017000 -EXECUTION REQUIREMENTS

PART 1-GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General Conditions and other Division 1 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This section includes general procedural requirements governing execution of the Work Including, but not limited to, the following:

1. Construction layout.

2. General installation of products.

3. Coordination of Owner-installed products.

4. Progress cleaning.

5. Starting and adjusting.

6. Protection of installed construction.

7. Correction of the Work.

PART 2 -PRODUCTS (Not Used)

PART 3-EXECUTION

3.1 EXAMINATION

A. Existing Conditions: The existence and location of utilities and other construction indicated as existing are not guaranteed. Before beginning work investigate and verify the existence and location of mechanical and electrical systems and other construction affecting the Work.

1. Before construction, verify the location and points of connection of utility services.

B. Existing Utilities: The existence and location of utilities and construction indicated as existing are not guaranteed.

C. Acceptance of Conditions: Examine substrates areas, and conditions, with

Installer or Applicator present where indicated, for compliance with requirements for installation tolerances and other conditions affecting performance. Record observations.

1. Verify compatibility with and suitability of substrates, including compatibility with existing finishes or primers.

2. Proceed with installation only after unsatisfactory conditions have been corrected. Proceeding with the Work indicates acceptance of surfaces and conditions.

3.2 PREPARATION

A. Field Measurements: Take field measurements as required to fit the Work properly. Recheck measurements before installing each product. Where portions of the Work are indicated to fit to other construction verify dimensions of other construction by field measurements before fabrication.

Coordinate fabrication schedule with construction progress to avoid delaying the Work.

B. Space Requirements: Verify space requirements and dimensions of items shown diagrammatically on Drawings.

C. Review of Contract Documents and Field Conditions: Immediately on discovery of the need for clarification of the Contract Documents, submit:

a request for information to Landscape Architect. Include a detailed description of problem encountered, together with recommendations for changing the Contract Documents. Submit requests on Request for Information form provided in the Project Manual.

3.3 CONSTRUCTION LAYOUT

A. Verification: Before proceeding to layout the Work, verify layout information shown on Drawings, in relation to the property survey and existing benchmarks. If discrepancies are discovered, notify Landscape Architect promptly.

B. Record Log: Maintain a log of layout control work. Record deviations from required lines and levels. Make the log available for reference by Landscape Architect.

C. General: Layout the Work using accepted surveying practices.

1. Establish benchmarks and control points to set lines and levels as needed to locate each element of Project.

2. Establish dimensions within tolerances indicated. Do not scale Drawings to obtain required dimensions.

3. Inform installers of lines and levels to which they must comply.

4. Check the location, level and plumb, of every major element as the Work progresses.

5. Notify Landscape Architect when deviations from required lines and levels exceed allowable tolerances.

3.4 INSTALLATION

A. General: Locate the Work and components of the Work accurately, in correct alignment and elevation, as indicated.

1. Make vertical work plumb and make horizontal work level.

2. Where space is limited, install components to maximize space available for maintenance and ease of removal for replacement.

3. Conceal pipes, ducts, and Wiring in finished areas, unless otherwise indicated.

4. Maintain minimum headroom clearance of 8 feet in spaces without a suspended ceiling.

B. Comply with manufacturer1s written instructions and recommendations for installing products in applications indicated.

C. Install products at the time and under conditions that will ensure the best possible results. Maintain conditions required for product performance until Substantial Completion.

D. Conduct construction operations so no part of the Work is subjected to damaging operations or loading in excess of that expected during normal conditions of occupancy.

E. Tools and Equipment: Do not use tools or equipment that produce harmful noise levels.

F. Templates: Obtain and distribute to the parties involved templates for work specified to be factory prepared and field installed. Check Shop Drawings of other work to confirm that adequate provisions are made for locating and installing products to comply with indicated requirements.

G. Anchors and Fasteners: Provide anchors and fasteners as required to anchor each component securely in place, accurately located and aligned with other portions of the Work.

1. Mounting Heights: Where mounting heights are not: indicated, mount components at heights directed by Landscape Architect.

2. Allow for building movement, including thermal expansion and contraction.

3. Coordinate installation of anchorages. Furnish setting drawings, templates, and directions for installing anchorages, including sleeves, concrete inserts, anchor bolts, and items with integral anchors, that are to be embedded in concrete or masonry. Deliver such items to Project site in time for installation.

H. Joints: Make joints of uniform width. Where joint locations in exposed work are not indicated, arrange joints for the best visual effect. Fit exposed connections together to form hairline joints.

I. Hazardous Materials: Use products, cleaners, and installation materials that are not considered hazardous.

3.5 OWNER-INSTALLED PRODUCTS

A. Site Access: Provide access to Project site for Owner's construction forces.

B. Coordination: Coordinate construction and operations of the Work with work performed by Owner's construction forces.

1. Construction Schedule: Inform Owner of Contractor's preferred construction schedule for Owner's portion of the Work. Adjust construction schedule based on a mutually agreeable timetable.

Notify Owner if changes to schedule are required due to differences in actual construction progress.

2. Pre-installation Conferences: Include Owner's construction forces at pre-installation conferences covering portions of the Work that are to receive Owner's work. Attend pre-installation conferences conducted by Owner's construction forces if portions of the Work depend on Owner's construction.

3.6 PROGRESS CLEANING

A. General: Clean Project site and work areas daily, including common areas.

Coordinate progress cleaning for joint-use areas where more than one installer has worked. Enforce requirements strictly. Dispose of materials lawfully.

1. Comply with requirements in NFPA 241 for removal of combustible waste materials and debris.

2. Do not hold materials more than 7 days during normal weather or 3 days if the temperature is expected to rise above 80 deg F.

3. Containerize hazardous and unsanitary waste materials separately from other waste. Mark containers appropriately and dispose of legally, according to regulations.

B. Site: Maintain sign site free of waste materials and debris.

C. Work Areas: Clean areas where work is in progress to the level of cleanliness necessary for proper execution of the Work.

1. Remove liquid spills promptly.

2. Where dust would impair proper execution of the Work, broom-clean or vacuum the entire work area, as appropriate.

D. Installed Work: Keep installed work clean. Clean installed surfaces according to written instructions of manufacturer or fabricator of product installed, using only cleaning materials specifically recommended. If specific cleaning materials are not recommended, use cleaning materials that are not hazardous to health or property and that will not damage exposed surfaces.

E. Concealed Spaces: Remove debris from concealed spaces before enclosing the space.

F. Exposed Surfaces in Finished Areas: Clean exposed surfaces and protect as necessary to ensure freedom from damage and deterioration at time of Substantial Completion.

G. Waste Disposal: Burying or burning waste materials on-site will not be permitted. Washing waste materials down sewers or into waterways will not be permitted.

H. During handling and installation, dean and protect construction in progress and adjoining materials already in place. Apply protective covering where required to ensure protection from damage or deterioration at Substantial Completion.

I. Clean and provide maintenance on completed construction as frequently as necessary through the remainder of the construction period. Adjust and lubricate operable components to ensure operability without damaging effects.

J. Limiting Exposures: Supervise construction operations to assure that no part of the construction, completed or in progress, is subject: to harmful, dangerous, damaging, or otherwise deleterious exposure during the construction period.

3.7 STARTING AND ADJUSTING

A. Start equipment and operating components to confirm proper operation.

Remove malfunctioning units, replace with new units, and retest.

B. Adjust operating components for proper operation without binding. Adjust equipment for proper operation.

C. Test each piece of equipment to verify proper operation. Test and adjust controls and safeties. Replace damaged and malfunctioning controls and equipment.

3.8 PROTECTION OF INSTALLED CONSTRUCTION

A. Provide final protection and maintain conditions that ensure installed Work is without damage or deterioration at time of Substantial Completion.

B. Comply with manufacturer's written instructions for temperature and relative humidity.

3.9 CORRECTION OF THE WORK

A. Repair or remove and replace defective construction. Restore damaged substrates and finishes. Comply with requirements in Division 1 Section "Cutting and Patching.”

1. Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, and properly adjusting operating equipment.

B. Restore permanent facilities used during construction to their specified condition.

C. Remove and replace damaged surfaces that are exposed to view if surfaces cannot be repaired without visible evidence of repair.

D. Repair components that do not operate properly. Remove and replace operating components that cannot be repaired.

E. Remove and replace chipped, scratched, and broken glass or reflective surfaces.

END OF SECTION 017000

017310

Cutting and Patching

SECTION 017310 -CUTTING AND PATCHING

PART 1 -GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General Conditions and other Division 1 Specifications Sections, apply to this Section.

A. This Section includes procedural requirements for cutting and patching.

B. Related Sections include the following:

1. Division 1 Section "Selective Demolition' for demolition of selected portions of the building.

1.3 DEFINITIONS

A. Cutting: Removal of in-place construction necessary to permit installation or performance of other Work.

B. Patching: Fitting and repair work required to restore surfaces to original conditions after installation of other Work.

1.4 QUALITY ASSURANCE

A. Structural Elements: Do not cut: and patch structural elements in a manner that could change their load-carrying capacity or load-deflection ratio.

B. Miscellaneous Elements: Do not cut and patch miscellaneous elements or related components in a manner that could change their load-carrying capacity, that results in reducing their capacity to perform as intended, or that results in increased maintenance or decreased operational life or safety.

Miscellaneous elements include the following:

a. Water, moisture, or vapor barriers.

b. Membranes and flashings.

c. Exterior curtain-wall construction.

d. Equipment supports.

e. Piping, ductwork, vessels, and equipment

f. Noise-and vibration-control elements and systems.

BI. Protect fire-resistive material, according to advice of product manufacturer from damage resulting from cutting and patching or other causes so fire protection will be without damage or deterioration at the time of Substantial Completion.

1. As installation of other construction proceeds, inspect fire-resistive material and patch any damaged or removed areas.

2. Repair or replace work that has not been successfully protected.

Visual Requirements: Do not cut and patch construction in a manner that results in visual evidence of cutting and patching.

Remove and replace construction that has been cut and patched in a visually unsatisfactory manner.

1.5 WARRANTY

A. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during cutting and patching operations, by methods and with materials so as not to void existing warranties.

PART 2 -PRODUCTS

1.1 MATERIALS

A. General: Comply with requirements specified in other Sections.

B. In-Place Materials: Use materials identical to in-place materials. For exposed surfaces, use materials that visually match in-place adjacent surfaces to the fullest extent possible.

1. If identical materials are unavailable or cannot be used, use materials that, when installed, will match the visual and functional performance of in-place materials.

PART 3-EXECUTION

A. Examine surfaces to be cut and patched and conditions under which cutting and patching are to be performed.

1. Compatibility: Before patching, verify compatibility with and Suitability of substrates, including compatibility with in-place finishes or primers.

2. Proceed with installation only after unsafe or unsatisfactory conditions have been corrected.

3.2 PREPARATION

A. Temporary Support: Provide temporary support of Work to be cut.

B. Protection: Protect in-place construction during cutting and patching to prevent damage. Provide protection from adverse weather conditions for portions of Project that might be exposed during cutting and patching operations.

C. Adjoining Areas: Avoid interference with use of adjoining areas or interruption of free passage to adjoining areas.

D. Existing Utility Services and Mechanical and Electrical Systems: Where existing services/systems are required to be removed, relocated, or abandoned, bypass such services/systems before cutting to prevent interruption to occupied areas.

3.3 PERFORMANCE

A. General: Employ skilled workers to perform cutting and patching. Proceed with cutting and patching at the earliest feasible time, and complete without delay.

1. Cut in-place construction to provide for installation of other components or performance of other construction, and subsequently patch as required to restore surfaces to their original condition.

B. Cutting: Cut in-place construction by sawing, drilling, breaking, chipping, grinding, and similar operations, including excavation, using methods least likely to damage elements retained or adjoining construction. If possible, review proposed procedures with original Installer; comply with original Installer's written recommendations.

1. In general, use hand or small power tools designed for sawing and grinding, not hammering and chopping. Cut holes and slots as small as possible, neatly to size required, and with minimum disturbance of adjacent surfaces. Temporarily cover openings when not in use.

2. Finished Surfaces: Cut or drill from the exposed or finished side into concealed surfaces.

3. Concrete and Masonry: Cut using a cutting machine, such as an abrasive saw or a diamond-core drill.

4. Mechanical and Electrical Services: Cut off pipe or conduit in walls or partitions to be removed. Cap, valve, or plug and seal remaining portion of pipe or conduit to prevent entrance of moisture or other

Page 10 of foreign matter after cutting.

5. Proceed with patching after construction operations requiring cutting are complete.

C. Patching: Patch construction by filling, repairing, refinishing, dosing up, and similar operations following performance of other Work. Patch with durable seams that are as invisible as possible. Provide materials and comply with installation requirements specified in other Sections.

1. Inspection: Where feasible, test and inspect patched areas after completion to demonstrate integrity of installation.

2. Exposed Finishes: Restore exposed finishes of patched areas and extend finish restoration into retained adjoining construction in a manner that will eliminate evidence of patching and refinishing.

D. Cleaning: Clean areas and spaces where cutting and patching are performed. Completely remove paint, mortar, oils, putty, and similar materials.

END OF SECTION 017310

017320

Selective Demolition

SECTION 017320 - SELECTIVE DEMOLITION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General Conditions and other Division 1 Specification sections, apply to this Section.

1.2 SUMMARY

A. This Section includes the following:

1. Demolition and removal of selected portions of building or structure.

2. Salvage of existing items to be reused or recycled.

B. Related sections include the following:

1. Division 1 Section "Cutting and Patching" for cutting and patching procedures.

1.3 DEFINITIONS

A. Remove: Detach items from existing construction and legally dispose of them off-site, unless indicated to be removed and salvaged or removed and reinstalled.

B. Remove and Salvage: Detach items from existing construction and deliver them to Owner ready for reuse.

C. Remove and Reinstall: Detach items from existing construction prepare them for reuse, and reinstall them where indicated.

D. Existing to Remain: Existing items of construction that are not to be removed and that are not otherwise indicated to be removed, removed and salvaged, or removed and reinstalled.

1.4 MATERIALS OWNERSHIP

A. Except for items or materials indicated to be reused, salvaged, reinstalled, or otherwise indicated to remain Owner's property, demolished materials shall become Contractor's property and shall be removed from Project site.

1.5 SUBMITTALS

A. Inventory: After selective demolition is complete, submit a list of items that have been removed and salvaged.

B. Pre-demolition Photographs or Videotapes: Show existing conditions of adjoining construction and site improvements, including finish surfaces that might be misconstrued as damage caused by selective demolition operations. Comply with Division 1 section "Photographic Documentation." Submit before Work begins.

1.6 QUALITY ASSURANCE

A. Demolition Firm Qualifications:

1. An experienced firm that has specialized in demolition work similar in material and extent to that indicated for this Project.

B. Regulatory Requirements: Comply with governing DHEC 61-70 notification, hauling and disposal regulations before beginning selective demolition.

C. Standards: Comply with ANSI A10.6 and NFPA 241.

D. Pre-demolition Conference: Conduct conference at Project site

1. Inspect and discuss condition of construction to be selectively demolished. Remove ceiling tiles for Inspection of above-ceiling conditions. Identify any items not shown on drawings.

2. Review structural load limitations of existing structure.

3. Review and finalize selective demolition schedule and verify availability of materials, demolition personnel, equipment, and facilities needed to make progress and avoid delays.

4. Review requirements of work performed by other trades that rely on substrates exposed by selective demolition operations.

5. Waste management and recycling opportunities.

F. Post-Demolition Inspection and Conference: Make arrangements with Owner’s representative and Architect for a post-demolition Inspection and conference at Project site. Identify any items not shown on drawings and non-code-compliant conditions which have been uncovered by demolition.

Discuss methods and procedures recommended for making such conditions rode compliant.

1.7 PROJECT CONDITIONS

A. Owner will occupy portions of building immediately adjacent to selective demolition area. Conduct selective demolition so Owners operations will not be disrupted.

B. Notify Architect of discrepancies between existing conditions and

Drawings before proceeding with selective demolition.

C. Hazardous Materials: It is not expected that hazardous materials will be encountered in the Work.

1. If materials suspected of containing hazardous materials are encountered, do not disturb; immediately notify Landscape Architect and Owner. Owner will remove hazardous materials under a separate contract.

D. Storage or sale of removed items or materials on-site is not permitted.

E. Utility service: Maintain existing utilities indicated to remain in service and protect them against damage during selective demolition operations.

1.8 WARRANTY

A. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during selective demolition, by methods and with materials so as not to void existing warranties.

PART 2 -PRODUCTS (Not Used)

PART 3 -EXECUTION

A. Verify that utilities have been disconnected and capped.

B. Survey existing conditions and correlate with requirements indicated to determine extent of selective demolition required.

C. Inventory and record the condition of items to be removed and reinstalled and items to be removed and salvaged.

D. When unanticipated mechanical, electrical, or structural elements that conflict with intended function or design are encountered, investigate and measure the nature and extent of conflict. Promptly submit a written report to Landscape Architect.

E. Survey condition of building to determine whether removing any element might result in structural deficiency or unplanned collapse of any portion of structure or adjacent structures during selective demolition operations.

F. Survey of Existing Conditions: Record existing conditions by use of measured drawings and preconstruction photographs.

1. Before selective demolition or removal of existing building elements that will be reproduced or duplicated in final Work. Make permanent record of measurements, materials, and construction details required to make exact reproduction.

G. Perform surveys as the Work progresses to detect hazards resulting from selective demolition activities.

UTILITY SERVICES AND MECHANICAL / ELECTRICAL SYSTEMS

3.2 A. Existing services/Systems: Maintain services/systems indicated to remain and protect them against damage during selective demolition operations.

B. Do not interrupt existing utilities serving occupied or operating facilities unless authorized in writing by Owner and authorities having jurisdiction.

Provide temporary services during interruptions to existing utilities, as acceptable to Owner and to authorities having jurisdiction.

C. Service/System Requirements: Locate, identify, disconnect, and seal or cap off indicated utility services and mechanical/electrical systems serving areas to be selectively demolished.

1. If services/systems are required to be removed, relocated, or abandoned, before proceeding with selective demolition provide temporary services/systems that bypass area of selective demolition and that maintain continuity of services/systems to other parts of building.

2. Cut off pipe or conduit in walls or partitions to be removed. Cap, valve, or plug and seal remaining portion of pipe or conduit after bypassing.

3.3 PREPARATION

A. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.

B. Temporary Facilities: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.

a. Provide protection to ensure safe passage of people around selective demolition area and to and from occupied portions of building.

b. Provide temporary weather protection, during interval between selective demolition of existing construction on exterior surfaces and new construction, to prevent water leakage and damage to structure and interior areas.

c. Protect walls, ceilings, floors, and other existing finish work that are to remain or that are exposed during selective demolition operations.

BI. Temporary Shoring: Provide and maintain shoring, bracing, and structural supports as required to preserve stability and prevent movement, settlement, or collapse of construction and finishes to remain, and to prevent unexpected or uncontrolled movement or collapse of construction being demolished.

1. Strengthen or add new supports when required during progress of selective demolition.

3.4 SELECTIVE DEMOLITION, GENERAL

A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations and as follows:

1. Proceed with selective demolition systematically, from higher to lower level. Complete selective demolition operations above each floor or tier before disturbing supporting members on the next lower level.

2. Neatly art openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction. Use hand tools or small power tools designed for sawing or grinding, not hammering and chopping, to minimize disturbance of adjacent surfaces.

Temporarily cover openings to remain.

3. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces.

4. Do not use cutting torches until work area is cleared of flammable materials. At concealed spaces, such as duet and pipe interiors, verify condition and contents of hidden space before starting flame-cutting operations. Maintain fire watch and portable fire-suppression devices during flame-cutting operations.

5. Maintain adequate ventilation when using cutting torches.

6. Remove decayed, vermin-infested, or otherwise dangerous or unsuitable materials and promptly dispose of off-site.

7. Remove structural framing members and lower to ground by method suitable to avoid free fall and to prevent ground impact or dust generation.

8. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing.

9. Dispose of demolished items and materials promptly.

B. Removed and Reinstalled Items: As indicated on Drawings.

1. Clean and repair items to functional condition adequate for intended reuse.

2. Where existing equipment and components are to be modified for relocation and reinstallation comply with requirements for new work as indicated in appropriate specification sections.

3. Paint equipment to match new equipment.

4. Reinstall items in locations indicated. Comply with installation requirements for new materials and equipment Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated.

C. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by Landscape Architect, items may be removed to a suitable, protected storage location during selective demolition and cleaned and reinstalled in their original locations after selective demolition operations are complete.

SELECTIVE DEMOLITION PROCEDURES FOR SPECIFIC

MATERIALS

3.5 PATCHING AND REPAIRS

A. General: Promptly repair damage to adjacent construction caused by selective demolition operations.

B. Patching: Comply with Division 1 Section "Cutting and Patching.”

C. Repairs: Where repairs to existing surfaces are required, patch to produce surfaces suitable for new materials.

1. Completely fill holes and depressions in existing masonry walls that are to remain with an approved masonry patching material applied according to manufacturer's written recommendations.

CI. Finishes: Restore exposed finishes of patched areas and extend restoration into adjoining construction in a manner that eliminates evidence of patching and refinishing.

DISPOSAL OF DEMOLISHED MATERIALS

3.7 A. General: except for items or materials indicated to be recycled, reused, salvaged, reinstalled, or otherwise indicated to remain Owner's property, remove demolished materials from site and legally dispose of them.

1. Do not allow demolished materials to accumulate on-site.

2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.

B. Burning: Do not burn demolished materials.

C. Disposal: Transport demolished materials off Owner's property and legally disposes of them.

3.8 CLEANING

A. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.

END OF SECTION 017320

017700

Closeout Procedures

SECTION 017700 - CLOSEOUT PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative and procedural requirements for contract closeout, including, but not limited to, the following:

1. Inspection procedures.

2. Warranties.

1.2 SUBSTANTIAL COMPLETION

A. Preliminary Procedures: Before requesting inspection for determining date of Substantial Completion, complete the following. List items below that are incomplete in request.

1. Prepare a list of items to be completed and corrected (punch list), the value of items on the list, and reasons why the Work is not complete.

2. Advise Owner of pending insurance changeover requirements.

3. Submit specific warranties, workmanship bonds, maintenance service agreements, final certifications, and similar documents.

4. Obtain and submit releases permitting Owner unrestricted use of the Work and access to services and utilities. Include occupancy permits, operating certificates, and similar releases.

5. Prepare and submit Project Record Documents, operation and maintenance manuals, Final Completion construction photographs, damage or settlement surveys, paint color schedules, and similar final record information.

6. Deliver tools, spare parts, extra materials, and similar items to location designated by Owner. Label with manufacturer's name and model number where applicable.

7. Terminate and remove temporary facilities from site, along with mockups, construction tools, and similar elements.

9. Submit changeover information related to Owner's occupancy, use, operation, and maintenance.

10. Complete final cleaning requirements, including touchup painting.

11. Touch up and otherwise repair and restore marred exposed finishes to eliminate visual defects.

12. Submit record indicating completion of all Owner training requirements.

B. Inspection: Submit a written request for inspection for Substantial

Completion. On receipt of request, Landscape Architect will either proceed with inspection or notify Contractor of unfulfilled requirements. Landscape Architect will prepare the Certificate of Substantial Completion after inspection or will notify Contractor of items, either on Contractor's list or additional items; identified by Landscape Architect that must be completed or corrected before certificate will be issued.

1. Reinspection: Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.

2. Results of completed inspection will form the basis of requirements for Final Completion.

1.3 FINAL COMPLETION

A. Preliminary Procedures: Before requesting final inspection for determining date of Final Completion, complete the following:

1. Submit a final Application for Payment

2. Submit certified copy of Landscape Architect's Substantial Completion inspection list of items to be completed or corrected (punch list), endorsed and dated by Landscape Architect. The certified copy of the list shall state that each Item has been completed or otherwise resolved for acceptance.

3. Submit evidence of final, continuing insurance coverage complying with insurance requirements.

4. Instruct Owners personnel in operation, adjustment, and maintenance of products, equipment, and systems. Submit demonstration and training videotapes.

B. Inspection: Submit a written request for final inspection for acceptance. On receipt of request, Landscape Architect will either proceed with inspection or notify Contractor of unfulfilled requirements. Landscape Architect will prepare a final Certificate for Payment after inspection or will notify Contractor of construction that must be completed or corrected before certificate will be issued.

1. Reinsertion: Request reinsertion when the Work identified in previous inspections as incomplete is completed or corrected.

1.4 LIST OF INCOMPLETE ITEMS (PUNCH LIST)

A. Preparation: Submit three copies of list. Include name and identification of each space and area affected by construction operations for incomplete items and items needing correction including, if necessary, areas disturbed by Contractor that are outside the limits of construction. Use CSI Form 14.1A.

1. Organize list of spaces in sequential order, starting with exterior areas first and proceeding from lowest floor to highest floor.

2. Organize items applying to each space by major element, including categories for ceiling, individual walls, floors, equipment, and building systems.

3. Include the following information at the top of each page:

Project name.

Date.

Name of Landscape Architect.

Name of Contractor.

Page number.

2. Maintenance Data:

a. Point of contact, name of individual and phone number.

b. Manufacturer's information, including list of spare parts.

c. Name, address, and telephone number of Installer or supplier.

d. Maintenance procedures.

e. Maintenance and service schedules for preventive and routine maintenance.

f. Maintenance record forms.

g. Sources of spare parts and maintenance materials.

h. Copies of maintenance service agreements.

i. Copies of warranties and bonds.

B. Organize maintenance manuals into suitable sets of manageable size. Bind and index data in heavy-duty, 3-ring, vinyl- covered, loose-leaf binders, in thickness necessary to accommodate contents, with pocket inside the covers to receive folded oversized sheets. Identify each binder on front and spine with the printed title "OPERATION AND MAINTENANCE MANUAL,” Project name, and subject matter of contents.

1.6 WARRANTIES

A. Submittal lime: Submit written warranties on request of Landscape

Architect for designated portions of the Work where commencement of warranties other than date of Substantial Completion is indicated.

B. Partial Occupancy: Submit properly executed warranties within 15 days of completion of designated portions of the Work that are completed and occupied or used by Owner during construction period by separate agreement with Contractor.

C. Organize warranty documents into an orderly sequence based on the table of contents of the Project Manual.

PART 2 - PRODUCTS

1.1 MATERIALS

A. Cleaning Agents: Use cleaning materials and agents recommended by manufacturer or fabricator of the surface to be cleaned. Do not use cleaning agents that are potentially hazardous to health or property or that might damage finished surfaces.

1. Submit list of proposed cleaning agents with related product data to Owner prior to use.

3.1 FINAL CLEANING

A. General: Provide final cleaning. Conduct cleaning and waste-removal operations to comply with local taws and ordinances and Federal and local environmental and antipollution regulations.

B. Comply with safety standards for cleaning. Do not burn waste materials.

Do not bury debris or excess materials on Owner's property. Do not discharge volatile, harmful, or dangerous materials into drainage systems.

Remove waste materials from Project site and dispose of lawfully.

END OF SECTION 017700

017810

Project Record Documents

SECTION 017810 PROJECT RECORD DOCUMENTS

PART 1 – GENERAL

1.2 SUMMARY

A. This Section includes administrative and procedural requirements for Project Record Documents, including the following:

1. Record Drawings.

2. Record Specifications.

3. Record Product Data.

1.3 SUBMITTALS

A. Record Drawings: Comply with the following:

1. Number of Copies: Submit one set(s) of marked-up Record Prints.

B. Record Specifications: Submit one copy of Project's Specifications, including addenda and contract modifications.

C. Record Product Data: Submit one copy of each Product Data submittal.

1. Where Record Product Data is required as part of operation and maintenance manuals, submit marked-up Product Data as an insert in manual instead of submittal as Record Product Data.

PART 2 – PRODUCTS

2.1 RECORD DRAWINGS

A. Record Prints: Maintain one set of blue-or black-line white prints of the

Contract Drawings and Shop Drawings.

1. Preparation: Mark Record Prints to show the actual installation where installation varies from that shown originally. Require individual or entity who obtained record data, whether individual or entity is Installer, subcontractor, or similar entity, to prepare the marked-up Record Prints.

a. Give particular attention to information on concealed elements that would be difficult to identify or measure and record later.

b. Accurately record information in an understandable drawing technique.

c. Record data as soon as possible after obtaining it. Record and check the markup before enclosing Concealed installations.

2. Content: Types of items requiring marking include, but are not limited to, the following:

a. Dimensional changes to Drawings.

b. Revisions to details shown on Drawings.

c. Depths of foundations below first floor.

d. Locations and depths of underground utilities.

e. Revisions to routing of piping and conduits.

f. Revisions to electrical circuitry.

g. Actual equipment locations.

h. Duct size and routing.

i. Locations of concealed internal utilities.

j. Changes made by Change Order or Construction Change

Directive.

k. Changes made following Architect's written orders.

l. Details not on the original Contract Drawings.

m. Field records for variable and concealed conditions.

n. Record information on the Work that is shown only schematically.

3. Mark the Contract Drawings or Shop Drawings, whichever is most capable of showing actual physical conditions, completely and accurately. If Shop Drawings are marked, show cross reference on the Contract Drawings.

4. Mark record sets with erasable, red-colored pencil. Use other colors to distinguish between changes for different categories of the Work at same location.

5. Mark important additional information that was either shown schematically or omitted from original Drawings.

6. Note Construction Change Directive numbers, alternate numbers, Change Order numbers, and similar identification, where applicable.

B. Newly Prepared Record Drawings: Prepare new Drawings instead of preparing Record Drawings where Landscape Architect determines that neither the original Contract Drawings nor Shop Drawings are suitable to show actual installation.

1. New Drawings may be required when a Change Order is issued as a result of accepting an alternate, substitution, or other modification.

2. Consult Landscape Architect for proper scale and scope of detailing and notations required to record the actual physical installation and its relation to other construction. Integrate newly prepared Record Drawings into Record Drawing sets; comply with procedures for formatting, organizing, copying, binding, and submitting.

C. Format: Identify and date each Record Drawing; include the designation

"PROJECT RECORD DRAWING” in a prominent location.

1. Record Prints: Organize Record Prints and newly prepared Record Drawings into manageable sets. Bind each set with durable paper cover sheets. Include identification on cover sheets.

2. Identification: As follows:

a. Project name.

b. Date.

c. Designation "PROJECT RECORD DRAWINGS."

d. Name of Architect.

e. Name of Contractor.

2.2 RECORD SPECIFICATIONS

A. Preparation: Mark Specifications to indicate the actual product installation where installation varies from that indicated in Specifications, addenda, and contract modifications.

1. Give particular attention to information on concealed products and installations that cannot be readily identified and recorded later.

2. Mark copy with the proprietary name and model number of products, materials, and equipment furnished, including substitutions and product options selected.

3. Record the name of manufacturer, supplier, Installer, and other information necessary to provide a record of selections made.

4. For each principal product indicate whether Record Product Data has been submitted in operation and maintenance manuals Instead of submitted as Record Product Data.

5. Note related Change Orders, Record Product Data, and Record Drawings where applicable.

2.3 RECORD PRODUCT DATA

A. Preparation: Mark Product Data to indicate the actual product installation where installation varies substantially from that indicated in Product Data submittal.

1. Give particular attention to information on concealed products and installations that cannot be readily identified and recorded later.

2. Include significant changes in the product delivered to Project site and changes in manufacturer's written instructions for installation.

2.4 ELECTRONIC RECORD DRAWINGS, SPECIFICATIONS AND

PRODUCT DATA.

A. All drawings must be received by MUSC in AutoCad 2018 format and include all files required to view, modify, and print the complete drawing set. All other electronic drawings must be in “pdf” format, Microsoft Word (compatible with 2010 version), or Microsoft Excel (compatible with 2010 version) unless otherwise agreed upon with Project Manager. Each document should be included as a separate document file, not combined into one PDF file. Each document file shall be named with text such that it is easily understood what information is contained within the file.

B. The General Contractor shall provide the following “record documents” to the Lead Architect prior to Substantial Completion:

1. One electronic list of all Record Documents submitted

2. Original “As-Built Master Mark-up Documents” from the construction site

3. One electronic version of all required maintenance manuals.

4. One electronic version of all warranties, manufacturer start-up, and guarantees.

5. One electronic version of all commissioning documentation.

6. One electronic version of all T&B documentation.

C. The General Contractor shall provide the following “record documents” to the Landscape Architect within 15 days of Final Completion:

1. One electronic version of final Submittal Log

2. One electronic version of final Change Order Log

3. One electronic version of all other documentation required by specifications and not already provided.

2.5 MISCELLANEOUS RECORD SUBMITTALS

A. Assemble miscellaneous records required by other Specification Sections for miscellaneous record keeping and submittal in connection with actual performance of the Work. Bind or file miscellaneous records and identify each, ready for continued use and reference.

3.1 RECORDING AND MAINTENANCE

A. Recording: Maintain one copy of each submittal during the construction period for Project Record Document purposes. Post changes and modifications to Project Record Documents as they occur; do not wait until the end of Project.

B. Maintenance of Record Documents and Samples: Store Record Documents and samples in the field office apart from the Contract Documents used for construction. Do not use Project Record Documents for construction purposes. Maintain Record Documents in good order and in a clean, dry, legible condition, protected from deterioration and loss. Provide access to Project Record Documents for Landscape Architect's reference during normal working hours.

END OF SECTION 017810

11/17/23 Page 1 of 25 MUSC Horseshoe Gateway Sign

SECTION 033000 - CAST-IN-PLACE CONCRETE

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

A. Section includes cast-in-place concrete, including formwork, reinforcement, concrete materials, mixture design, placement procedures, and finishes, for the following:

1. Footings.

2. Slabs-on-grade.

1.3 PERFORMANCE REQUIREMENTS

A. Moisture level in finished concrete shall be within limits acceptable to types of finish flooring indicated. Test methods and acceptable limits shall be as specified in Division 09 finish flooring Sections, or as required by finish flooring manufacturer's written product data or certified written statement. General Contractor is responsible for choosing and implementing methods of limiting excessive moisture during construction and curing, or remedial treatment, process, or other means to bring moisture level within acceptable limits, and for assigning and contracting for these responsibilities to installers

033000 Cast In Place Concrete

Compass 5 Partners, LLC

033000

Cast In Place Concrete

1.4 DEFINITIONS

A. Cementitious Materials: Portland cement alone or in combination with one or more of the following: blended hydraulic cement, fly ash and other pozzolans, ground granulated blast-furnace slag, and silica fume; subject to compliance with requirements.

1.5 SUBMITTALS

A. Contractor’s Statement of Responsibility Per Division 01 Section "Collective Inspections and Structural Testing"

B. Product Data:

1. Bar supports

2. Vapor barriers

3. Epoxy Bonding Adhesive

4. Cartridge Injection Adhesive

5. Form materials

6. Form-release agents

7. Evaporation retarder

8. Curing compound

9. Curing and sealing compound

10. Semirigid joint filler

11. Joint-filler strips

12. Controlled low-strength material, including design mixture.

C. Design Mixtures: For each concrete mixture.

1. Mix design submittals shall include test results and/or trial batch data that meet or exceed the required average compressive strength as required by ACI 301.

2. Trial batches shall consist of identical cementitious materials, fine and course aggregates, and admixtures to be used for mix design.

3. Submit alternate design mixtures when characteristics of materials, Project conditions, weather, test results, or other circumstances warrant adjustments.

D. Steel Reinforcement Shop Drawings:

1. Drawings that detail fabrication, bending, and placement.

2. Include bar sizes, lengths, material, grade, bar schedules, stirrup spacing, bent bar diagrams, bar arrangement, splices and laps, mechanical connections, tie spacing, hoop spacing, and bar supports for concrete reinforcement.

3. Identify all step footing locations and associated reinforcing

4. Identify and dimension all grade beam and tie beam construction joints

5. Include slab on grade construction joint reinforcement

6. Construction Joint Layout: Indicate proposed construction joints required to construct the structure.

a. Location of construction joints is subject to approval of the Architect.

E. Mill Test Reports (to be provided to the special inspector with each delivery to the site):

1. Submit mill test reports for ASTM A615 reinforcing steel indicating compliance with the ASTM and additional restrictions

2. Submit mill test reports for ASTM A706 reinforcing steel indicating compliance with the ASTM.

F. Formwork Shop Drawings:

1. Prepared by or under the supervision of a qualified professional engineer detailing fabrication, assembly, and support of formwork.

2. Shoring and Reshoring: Indicate proposed schedule and sequence of stripping formwork, shoring removal, and reshoring installation and removal.

3. All documentation shall be signed and sealed by a registered professional engineer

G. Qualification Data:

1. For ready-mix concrete manufacturer.

2. For Cartridge injection adhesive installer. Include manufacturer's training certificates or letter from manufacturer certifying training was complete with a list of individuals that were trained

H. Material Certificates: For each of the following indicating compliance with the required standards and signed by manufacturers:

1. Vapor barriers

I. Research/Evaluation Reports:

1. Submit ICC reports for the following:

a. Cartridge Injection Adhesive

J. Hot Weather Program (As required, see below):

1. Describe in detail procedure for working in Hot Weather when concrete temperatures exceed the specified limits. Included detailed description of methods, materials, and equipment to be used to comply with requirements.

K. Substitutions for Cartridge Injection Adhesive:

1. Substitution requests may only be made using products with ICC-ESR reports for the product in the specific substrate.

2. Substitution request shall include signed and sealed calculations demonstrating that the product is capable of providing equivalent performance of the specified product for each specific location and condition when calculated using the data in the referenced ESR report and in accordance with the appropriate design procedure and standards required by the building code.

3. Substitution request shall specify the diameter and embedment depth of the substituted product

4. Any increase in material cost resulting from the substitution shall be the responsibility of the contractor.

L. Minutes of preinstallation conference.

1.6 QUALITY ASSURANCE

A. Engineering Responsibility: Preparation of Shop Drawings, design…

This is the start of the file's text. The full file is on GovTribe.