Attachment A.pdf
PDF 2 MB Posted
- Attached to
- Nederman Exhaust System State and local contract opportunity
- Solicitation number
- 6065AB
- Issued by
- Colorado
About this file
This document is a comprehensive project specification for the City of Aurora's Public Safety Training Center (CAPSTC) Vehicle Exhaust System Replacement project, prepared by RTM Engineering Consultants. The project involves completely removing the existing Plymovent diesel exhaust removal system from three truck bays and installing a new Nederman diesel exhaust removal system. The work scope includes removing all existing system appurtenances, installing new vehicle exhaust rails, exhaust collection ductwork, a new exhaust fan, electrical circuiting, system controls, and auxiliary support elements like metal panels, CMU, and painting. The project will also involve repairing and patching existing wall openings, creating new wall openings, installing equipment supports, and integrating CO/NO2 sensors with the Nederman control panel. Long Building Technologies (LONG) will handle the primary system installation, with a separate licensed electrical contractor managing electrical work.
The project specifications detail extensive technical requirements for the installation, including specific division and section guidelines for everything from general requirements to electrical and HVAC components. The documents outline quality assurance standards, submission procedures, execution requirements, and commissioning protocols. Third-party commissioning will be coordinated with NORESCO to ensure the system meets design document performance specifications. While specific budget details are not explicitly stated, the comprehensive nature of the specifications suggests a complex infrastructure improvement project focused on upgrading the vehicle exhaust system's safety, efficiency, and technological capabilities at the Aurora Public Safety Training Center.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| Project Manual Nederman Exhaust System.pdf | ||
| Attachment B.pdf | ||
| Bid Sheet.xlsx | XLSX spreadsheet | |
| Attachment C.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT SPECIFICATIONS
CITY OF AURORA
CAPSTC � VEHICLE EXHAUST SYSTEM
AURORA, CO
PREPARED FOR:
CITY OF AURORA
FACILITIES PROJECT DIVISION
GABRIELLE TOBIN | PROJECT MANAGER
PREPARED BY:
RTM ENGINEERING CONSULTANTS
1626 COLE BLVD., STE.300
LAKEWOOD, CO 80401
(303)278-3820
RTM PROJECT NO: 24.100000.5843
March 21, 2025
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 011000 � SUMMARY
SECTION 012600 � CONTRACT MODIFICATION PROCEDURES
SECTION 012900 � PAYMENT PROCEDURES
SECTION 013100 � PROJECT MANAGEMENT AND COORDINATION
SECTION 013200 � CONSTRUCTION PROGRESS DOCUMENTATION
SECTION 013300 � SUBMITTAL PROCEDURES
SECTION 014000 � QUALITY REQUIREMENTS
SECTION 015000 � TEMPORARY FACILITIES AND CONTROLS
SECTION 016000 � PRODUCT REQUIREMENTS
SECTION 017300 � EXECUTION
SECTION 017419 � CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
SECTION 017700 � CLOSEOUT PROCEDURES
SECTION 017823 � OPERATION AND MAINTENANCE DATA
SECTION 017839 � PROJECT RECORD DOCUMENTS
SECTION 017900 � DEMONSTRATION AND TRAINING
DIVISION 02 - EXISTING CONDITIONS
SECTION 010450 � CUTTING AND PATCHING
DIVISION 04 - MASONRY
SECTION 041000 � MORTAR AND GROUT
SECTION 042000 � UNIT MASONRY
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
SECTION 072100 � BUILDING INSULATION
SECTION 076000 � FLASHING AND SHEET METAL
SECTION 079000 � JOINT SEALERS
DIVISION 09 - FINISHES
SECTION 099000 - PAINTING
DIVISION 23 - HEATING, VENTILATING, AND AIR-CONDITIONING(HVAC)
SECTION 230010 � HVAC GENERAL PROVISIONS
SECTION 230553 - IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT
SECTION 233113 - METAL DUCTS
SECTION 233300 - AIR DUCT ACCESSORIES
DIVISION 26 - ELECTRICAL
SECTION 260000 - ELECTRICAL GENERAL PROVISIONS
SECTION 260010 � SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND
CABLING
SECTION 260519 - LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
SECTION 260533 - RACEWAYS AND BOXES
SECTION 260553 � ELECTRICAL IDENTIFICATION
SECTION 262816 � ENCLOSED SWITCHES AND CIRCUIT BREAKERS
City of Aurora CAPSTC � Vehicle Exhaust System Replacement
March 21, 2025
SUMMARY 011000 - 1
SECTION 011000 - SUMMARY
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.02 SUMMARY
A. Section Includes:
Project information.
1. Work covered by Contract Documents.
2. Access to site.
3. Coordination with occupants.
4. Work restrictions.
5. Specification and drawing conventions.
B. Related Requirements:
Section 015000 "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.
1.03 PROJECT INFORMATION
A. Project Identification: City of Aurora � CAPSTC � Vehicle Exhaust System Replacement
B. Project Location: 25950 East Quincy Ave. Aurora, CO 80016
Owner: City of Aurora
Engineer: RTM Engineering Consultants 1626 Cole Blvd. Suite 300 Lakewood, CO.
1.04 WORK COVERED BY CONTRACT DOCUMENTS
A. The Work of Project is defined by the Contract Documents and consists of the following:
1. Complete removal of the existing vehicle exhaust system including all appurtenances.
2. Installation of a new vehicular exhaust system.
3. Repair and patch of existing wall openings and installation/cutting of new wall openings.
4. Installation of equipment supports
5. Installation of Vehicle exhaust rails and exhaust collection ductwork, and vehicle exhaust fan.
6. Installation of electrical circuiting
7. Installation of system controls.
8. Auxiliary support (i.e. metal panel, CMU, paint, etc).
B. Type of Contract:
Project will be constructed under a single prime contract.
1.05 ACCESS TO SITE
A. General: Contractor shall have limited use of Project site for construction operations as indicated on Drawings by the Contract limits and as indicated by requirements of this Section.
B. Use of Site: Limit use of Project site to work in areas indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
C. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weathertight condition throughout construction period. Repair damage caused by construction operations.
March 21, 2025
SUMMARY 011000 - 2
1.06 COORDINATION WITH OCCUPANTS
A. Full Owner Occupancy: Owner will occupy site and building(s) during entire construction period.
Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's day-to-day operations. Maintain existing exits unless otherwise indicated.
Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities.
Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and approval of authorities having jurisdiction.
1. Notify Owner not less than one week in advance of activities that will affect Owner's operations.
1.07 WORK RESTRICTIONS
A. Work Restrictions, General: Comply with restrictions on construction operations.
1. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.
B. On-Site Work Hours: Limit work in the existing building to normal business working hours of Monday through Friday, unless otherwise indicated.
1. Bid Alternate: Perform work nights and weekends (Monday night excluded).
C. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to Owner occupancy with Owner.
1. Notify Owner not less than five days in advance of proposed disruptive operations.
2. Obtain Owner's written permission before proceeding with disruptive operations.
D. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor-air intakes.
E. Controlled Substances: Use of tobacco products and other controlled substances is not permitted.
1.08 SPECIFICATION AND DRAWING CONVENTIONS
A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.
These conventions are as follows:
1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.
B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 011000
March 21, 2025
CONTRACT MODIFICATION PROCEDURES 012600 - 1
SECTION 012600 - CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.02 SUMMARY
Section includes administrative and procedural requirements for handling and processing Contract modifications.
A. Related Requirements:
Section 016000 "Product Requirements" for administrative procedures for handling requests for substitutions made after the Contract award.
1.03 MINOR CHANGES IN THE WORK
Engineer will issue supplemental instructions authorizing minor changes in the Work, not involving adjustment to the Contract Sum or the Contract Time on letterhead with any accompanying supplemental Contract Document modifications.
1.04 PROPOSAL REQUESTS
Owner/Engineer-Initiated Proposal Requests: Engineer will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.
Work Change Proposal Requests issued are not instructions either to stop work in progress or to execute the proposed change.
1. Within ten days after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change.
Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
a. Include costs of labor and supervision directly attributable to the change.
b. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
Contractor-Initiated Proposals: If latent or changed conditions require modifications to the Contract, Contractor may initiate a claim by submitting a request for a change to the Owner and Engineer.
March 21, 2025
CONTRACT MODIFICATION PROCEDURES 012600 - 2
Include a statement outlining reasons for the change and the effect of the change on the Work.
Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.
2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
4. Include costs of labor and supervision directly attributable to the change.
5. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
6. Comply with requirements in Section 016000 "Product Requirements" if the proposed change requires substitution of one product or system for product or system specified.
7. Proposal Request Form: containing all information above.
1.05 CHANGE ORDER PROCEDURES
On Owner's approval of a Proposal Request, a Change Order will be issued per the terms of the General Conditions.
1.06 CONSTRUCTION CHANGE DIRECTIVE
Construction Change Directive: Engineer may issue a Construction Change Directive. A Change Directive instructs Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.
Work Change Directive contains a complete description of change in the Work. It also designates method to be followed to determine change in the Contract Sum or the Contract Time.
Documentation: Maintain detailed records on a time and material basis of work required by the Work Change Directive.
After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.
PART 2 - PRODUCTS (Not Used)
END OF SECTION 012600
March 21, 2025
PAYMENT PROCEDURES 012900 - 1
SECTION 012900 - PAYMENT PROCEDURES
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.02 SUMMARY
Section includes administrative and procedural requirements necessary to prepare and process Applications for Payment.
A. Related Requirements:
Section 012600 "Contract Modification Procedures" for administrative procedures for handling changes to the Contract.
1. Section 013200 "Construction Progress Documentation" for administrative requirements governing the preparation and submittal of the Contractor's construction schedule.
1.03 DEFINITIONS
A. Schedule of Values: A statement furnished by Contractor allocating portions of the Contract Sum to various portions of the Work and used as the basis for reviewing Contractor's Applications for Payment.
1.04 SCHEDULE OF VALUES
Coordination: Coordinate preparation of the schedule of values with preparation of Contractor's construction schedule.
Coordinate line items in the schedule of values with other required administrative forms and schedules, including the following:
Application for Payment forms with continuation sheets.
a. Submittal schedule.
b. Contractor's construction schedule.
Submit the schedule of values to Engineer at earliest possible date, but no later than seven days before the date scheduled for submittal of initial Applications for Payment.
Format and Content: Use Project Manual table of contents as a guide to establish line items for the schedule of values. Provide at least one line item for each Specification Section.
Identification: Include the following Project identification on the schedule of values:
Project name and location.
c. Name of Engineer.
d. Engineer's project number.
e. Contractor's name and address.
f. Date of submittal.
Arrange the schedule of values in tabular form with separate columns to indicate the following for each item listed:
Related Specification Section or Division.
g. Name of subcontractor.
h. Name of manufacturer or fabricator.
March 21, 2025
PAYMENT PROCEDURES 012900 - 2
i. Name of supplier.
j. Change Orders (numbers) that affect value.
k. Dollar value of the following, as a percentage of the Contract Sum to nearest one-hundredth percent, adjusted to total 100 percent.
Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of
Applications for Payment and progress reports. Coordinate with Project Manual table of contents. Provide multiple line items for principal subcontract amounts in excess of percent of the Contract Sum.
2. Round amounts to nearest whole dollar; total shall equal the Contract Sum.
3. Provide separate line items in the schedule of values for initial cost of materials, for each subsequent stage of completion, and for total installed value of that part of the Work.
4. Each item in the schedule of values and Applications for Payment shall be complete.
Include total cost and proportionate share of general overhead and profit for each item.
Temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in the schedule of values or distributed as general overhead expense, at Contractor's option.
Schedule Updating: Update and resubmit the schedule of values before the next Applications for Payment when Change Orders or Construction Change Directives result in a change in the Contract Sum.
1.05 APPLICATIONS FOR PAYMENT
Each Application for Payment following the initial Application for Payment shall be consistent with previous applications and payments as certified by Engineer and paid for by Owner.
Initial Application for Payment, Application for Payment at time of Substantial Completion, and final Application for Payment involve additional requirements.
Payment Application Times: The date for each progress payment is indicated in the Agreement between Owner and Contractor. The period of construction work covered by each Application for Payment is the period indicated in the Agreement.
Application for Payment Forms: Use form provided by Owner for Applications for Payment.
A. Application Preparation: Complete every entry on form. Notarize and execute by a person authorized to sign legal documents on behalf of Contractor. Engineer will return incomplete applications without action.
Entries shall match data on the schedule of values and Contractor's construction schedule. Use updated schedules if revisions were made.
1. Include amounts of Change Orders and Construction Change Directives issued before last day of construction period covered by application.
Transmittal: Submit signed and notarized original copies of each Application for Payment to Engineer by a method ensuring receipt within 24 hours. One copy shall include waivers of lien and similar attachments if required.
Transmit each copy with a transmittal form listing attachments and recording appropriate information about application.
Waivers of Mechanic's Lien: With each Application for Payment, submit waivers of mechanic's lien from entities lawfully entitled to file a mechanic's lien arising out of the Contract and related to the Work covered by the payment.
March 21, 2025
PAYMENT PROCEDURES 012900 - 3
Submit partial waivers on each item for amount requested in previous application, after deduction for retainage, on each item.
2. When an application shows completion of an item, submit conditional final or full waivers.
3. Owner reserves the right to designate which entities involved in the Work must submit waivers.
4. Waiver Forms: Submit executed waivers of lien on forms acceptable to Owner.
Waivers of Mechanic's Lien: With each Application for Payment, submit waivers of mechanic's liens from subcontractors, sub-subcontractors, and suppliers for construction period covered by the previous application.
Submit partial waivers on each item for amount requested in previous application, after deduction for retainage, on each item.
5. When an application shows completion of an item, submit conditional final or full waivers.
6. Owner reserves the right to designate which entities involved in the Work must submit waivers.
7. Submit final Application for Payment with or preceded by conditional final waivers from every entity involved with performance of the Work covered by the application who is lawfully entitled to a lien.
8. Waiver Forms: Submit executed waivers of lien on forms, acceptable to Owner.
Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following:
List of subcontractors.
9. Schedule of values.
10. Contractor's construction schedule (preliminary if not final).
11. Products list (preliminary if not final).
12. Submittal schedule (preliminary if not final).
13. List of Contractor's staff assignments.
14. List of Contractor's principal consultants.
15. Copies of building permits.
16. Copies of authorizations and licenses from authorities having jurisdiction for performance of the Work.
17. Initial progress report.
18. Report of preconstruction conference.
19. Data needed to acquire Owner's insurance.
Application for Payment at Substantial Completion: After Engineer issues the Certificate of Substantial Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete.
Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum.
20. This application shall reflect Certificate(s) of Substantial Completion issued previously for
Owner occupancy of designated portions of the Work.
Final Payment Application: After completing Project closeout requirements, submit final Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following:
Evidence of completion of Project closeout requirements.
21. Insurance certificates for products and completed operations where required and proof that taxes, fees, and similar obligations were paid.
22. Updated final statement, accounting for final changes to the Contract Sum.
March 21, 2025
PAYMENT PROCEDURES 012900 - 4
23. AIA Document G706, "Contractor's Affidavit of Payment of Debts and Claims."
24. AIA Document G706A, "Contractor's Affidavit of Release of Liens."
25. AIA Document G707, "Consent of Surety to Final Payment."
26. Evidence that claims have been settled.
27. Final liquidated damages settlement statement.
PART 2 - PRODUCTS (Not Used)
END OF SECTION 012900
March 21, 2025
PROJECT MANAGEMENT AND COORDINATION 013100 - 1
SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
General coordination procedures.
1. Requests for Information (RFIs).
2. Project meetings.
B. Related Requirements:
Section 013200 "Construction Progress Documentation" for preparing and submitting
Contractor's construction schedule.
1. Section 017300 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
2. Section 017700 "Closeout Procedures" for coordinating closeout of the Contract.
1.02 DEFINITIONS
A. RFI: Request from Owner, Engineer, or Contractor seeking information required by or clarifications of the Contract Documents.
1.03 GENERAL COORDINATION PROCEDURES
Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, that depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
4. Prepare similar memoranda for Owner and separate contractors if coordination of their Work is required.
Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities to avoid conflicts and to ensure orderly progress of the Work.
Such administrative activities include, but are not limited to, the following:
5. Preparation of Contractor's construction schedule.
6. Preparation of the schedule of values.
7. Installation and removal of temporary facilities and controls.
March 21, 2025
PROJECT MANAGEMENT AND COORDINATION 013100 - 2
8. Delivery and processing of submittals.
9. Progress meetings.
10. Preinstallation conferences.
11. Project closeout activities.
12. Startup and adjustment of systems.
Conservation: Coordinate construction activities to ensure that operations are carried out with consideration given to conservation of energy, water, and materials. Coordinate the use of temporary utilities to minimize waste.
13. Salvage materials and equipment involved in performance of, but not actually incorporated into, the Work. See other Sections for disposition of salvaged materials that are designated as Owner's property.
1.04 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.
1. Engineer will return RFIs submitted to Engineer by other entities controlled by Contractor with no response.
2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. Project name.
2. Project number.
3. Date.
4. Name of Contractor.
5. RFI number, numbered sequentially.
6. RFI subject.
7. Specification Section number and title and related paragraphs, as appropriate.
8. Drawing number and detail references, as appropriate.
9. Field dimensions and conditions, as appropriate.
10. Contractor's suggested resolution. If Contractor's suggested resolution impacts the
Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
11. Contractor's signature.
12. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. RFI Forms: Software-generated form with substantially the same content as indicated above.
1. Attachments shall be electronic files in PDF format.
D. Engineer's Action: Engineer will review each RFI, determine action required, and respond. Allow seven working days for Engineer's response for each RFI. RFIs received by Engineer after 1:00 p.m. will be considered as received the following working day.
1. The following Contractor-generated RFIs will be returned without action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in the Contract Documents.
e. Requests for adjustments in the Contract Time or the Contract Sum.
March 21, 2025
PROJECT MANAGEMENT AND COORDINATION 013100 - 3
f. Requests for interpretation of Engineer's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. Engineer's action may include a request for additional information, in which case Engineer's time for response will date from time of receipt of additional information.
3. Engineer's action on RFIs that may result in a change to the Contract Time or the Contract Sum may be eligible for Contractor to submit Change Proposal according to Section 012600 "Contract Modification Procedures."
a. If Contractor believes the RFI response warrants change in the Contract Time or the
Contract Sum, notify Engineer in writing within 10 days of receipt of the RFI response.
E. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number.
Submit log weekly. Include the following:
1. Project name.
2. Name and address of Contractor.
3. Name and address of Engineer.
4. RFI number including RFIs that were returned without action or withdrawn.
5. RFI description.
6. Date the RFI was submitted.
7. Date Engineer's response was received.
F. On receipt of Engineer's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify Engineer within seven days if Contractor disagrees with response.
1.05 PROJECT MEETINGS
A. General: Schedule and conduct meetings and conferences at Project site unless otherwise indicated.
1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify Owner and Engineer of scheduled meeting dates and times.
2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.
3. Minutes: Entity responsible for conducting meeting will record significant discussions and agreements achieved. Distribute the meeting minutes to everyone concerned, including Owner, Construction Manager, and Engineer, within three days of the meeting.
B. Preconstruction Conference: Schedule and conduct a preconstruction conference before starting construction, at a time convenient to Owner, but no later than 15 days after execution of the Agreement.
1. Conduct the conference to review responsibilities and personnel assignments.
2. Attendees: Authorized representatives of Owner; Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the conference.
Participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.
3. Agenda: Discuss items of significance that could affect progress, including the following:
Tentative construction schedule.
a. Staging/Site Access
b. Critical work sequencing and long-lead items.
c. Designation of key personnel and their duties.
d. Lines of communications.
e. Procedures for processing field decisions and Change Orders.
f. Procedures for testing and inspecting.
g. Procedures for processing Applications for Payment.
h. Distribution of the Contract Documents.
March 21, 2025
PROJECT MANAGEMENT AND COORDINATION 013100 - 4
i. Submittal procedures.
j. Preparation of record documents.
k. Use of the premises and existing building.
l. Work restrictions.
m. Working hours.
n. Owner's occupancy requirements.
o. Responsibility for temporary facilities and controls.
p. Procedures for moisture and mold control.
q. Procedures for disruptions and shutdowns.
r. Construction waste management and recycling.
s. Parking availability.
t. Office, work, and storage areas.
u. Equipment deliveries and priorities.
v. First aid.
w. Security.
x. Progress cleaning.
4. Minutes: Entity responsible for conducting meeting will record and distribute meeting minutes.
C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity that requires coordination with other construction.
1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise Engineer of scheduled meeting dates.
2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:
Contract Documents.
a. Options.
b. Related RFIs.
c. Related Change Orders.
d. Purchases.
e. Deliveries.
f. Submittals.
g. Possible conflicts.
h. Compatibility requirements.
i. Time schedules.
j. Weather limitations.
k. Manufacturer's written instructions.
l. Warranty requirements.
m. Compatibility of materials.
n. Acceptability of substrates.
o. Temporary facilities and controls.
p. Space and access limitations.
q. Regulations of authorities having jurisdiction.
r. Testing and inspecting requirements.
s. Installation procedures.
t. Coordination with other work.
u. Required performance results.
v. Protection of adjacent work.
w. Protection of construction and personnel.
March 21, 2025
PROJECT MANAGEMENT AND COORDINATION 013100 - 5
3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.
4. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information.
5. Do not proceed with installation if the conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.
D. Progress Meetings: Conduct progress meetings at regular intervals.
Attendees: In addition to representatives of Owner, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.
1. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.
a. Contractor's Construction Schedule: Review progress since the last meeting.
Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's construction schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so.
Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.
1) Review schedule for next period.
b. Review present and future needs of each entity present, including the following:
Interface requirements.
1) Sequence of operations.
2) Status of submittals.
3) Deliveries.
4) Off-site fabrication.
5) Access.
6) Site utilization.
7) Temporary facilities and controls.
8) Progress cleaning.
9) Quality and work standards.
10) Status of correction of deficient items.
11) Field observations.
12) Status of RFIs.
13) Status of proposal requests.
14) Pending changes.
15) Status of Change Orders.
16) Pending claims and disputes.
17) Documentation of information for payment requests.
2. Minutes: Entity responsible for conducting the meeting will record and distribute the meeting minutes to each party present and to parties requiring information.
March 21, 2025
PROJECT MANAGEMENT AND COORDINATION 013100 - 6
PART 2 - PRODUCTS (Not Used)
END OF SECTION 013100
March 21, 2025
CONSTRUCTION PROGRESS
DOCUMENTATION
013200 - 1
SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.02 SUMMARY
A. Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:
Startup construction schedule.
1. Contractor's construction schedule.
2. Daily construction reports.
3. Site condition reports.
4. Special reports.
B. Related Requirements:
Section 013300 "Submittal Procedures" for submitting schedules and reports.
1. Section 014000 "Quality Requirements" for submitting a schedule of tests and inspections.
1.03 DEFINITIONS
Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.
1. Critical Activity: An activity on the critical path that must start and finish on the planned early start and finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
3. Successor Activity: An activity that follows another activity in the network.
Cost Loading: The allocation of the schedule of values for the completion of an activity as scheduled.
The sum of costs for all activities must equal the total Contract Sum unless otherwise approved by Engineer.
B. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.
C. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.
D. Event: The starting or ending point of an activity.
E. Float: The measure of leeway in starting and completing an activity.
1. Float time is not for the exclusive use or benefit of either Owner or Contractor, but is a jointly owned, expiring Project resource available to both parties as needed to meet schedule milestones and Contract completion dat].
2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the successor activity.
March 21, 2025
CONSTRUCTION PROGRESS
DOCUMENTATION
013200 - 2
3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.
Resource Loading: The allocation of manpower and equipment necessary for the completion of an activity as scheduled.
1.04 SUBMITTALS
Format for Submittals: Submit required submittals in the following format:
1. Working electronic copy of schedule file, where indicated.
2. PDF electronic file.
B. Contractor's Construction Schedule: Initial schedule, of size required to display entire schedule for entire construction period.
Submit a working electronic copy of schedule, using software indicated, and labeled to comply with requirements for submittals. Include type of schedule (initial or updated) and date on label.
CPM Reports: Concurrent with CPM schedule, submit each of the following reports. Format for each activity in reports shall contain activity number, activity description, cost and resource loading, original duration, remaining duration, early start date, early finish date, late start date, late finish date, and total float in calendar days.
Activity Report: List of all activities sorted by activity number and then early start date, or actual start date if known.
1. Logic Report: List of preceding and succeeding activities for all activities, sorted in ascending order by activity number and then early start date, or actual start date if known.
2. Total Float Report: List of all activities sorted in ascending order of total float.
C. Daily Construction Reports: Submit at weekly intervals.
D. Site Condition Reports: Submit at time of discovery of differing conditions.
E. Special Reports: Submit at time of unusual event.
1.05 QUALITY ASSURANCE
A. Prescheduling Conference: Conduct conference at Project site to comply with requirements in Section 013100 "Project Management and Coordination." Review methods and procedures related to the preliminary construction schedule and Contractor's construction schedule, including, but not limited to, the following:
1. Review software limitations and content and format for reports.
2. Verify availability of qualified personnel needed to develop and update schedule.
3. Discuss constraints, including phasing work stages.
4. Review submittal requirements and procedures.
5. Review time required for review of submittals and resubmittals.
6. Review requirements for tests and inspections by independent testing and inspecting agencies.
7. Review time required for Project closeout and Owner startup procedures, including commissioning activities.
8. Review and finalize list of construction activities to be included in schedule.
9. Review procedures for updating schedule.
March 21, 2025
CONSTRUCTION PROGRESS
DOCUMENTATION
013200 - 3
1.06 COORDINATION
A. Coordinate Contractor's construction schedule with the schedule of values, list of subcontracts, submittal schedule, progress reports, payment requests, and other required schedules and reports.
1. Secure time commitments for performing critical elements of the Work from entities involved.
2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.
PART 2 - PRODUCTS
2.01 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL
A. Time Frame: Extend schedule from date established for commencement of the Work to date of final completion.
1. Contract completion date shall not be changed by submission of a schedule that shows an early completion date, unless specifically authorized by Change Order.
B. Activities: Treat each story or separate area as a separate numbered activity for each main element of the Work. Comply with the following:
1. Activity Duration: Define activities so no activity is longer than 20 days, unless specifically allowed by Engineer.
2. Procurement Activities: Include procurement process activities for the following long lead items and major items, requiring a cycle of more than 60 days, as separate activities in schedule. Procurement cycle activities include, but are not limited to, submittals, approvals, purchasing, fabrication, and delivery.
3. Submittal Review Time: Include review and resubmittal times indicated in Section 013300 "Submittal Procedures" in schedule. Coordinate submittal review times in Contractor's construction schedule with submittal schedule.
4. Startup and Testing Time: Include no fewer than 15 days for startup and testing.
5. Substantial Completion: Indicate completion in advance of date established for Substantial
Completion, and allow time for Engineer's administrative procedures necessary for certification of Substantial Completion.
6. Punch List and Final Completion: Include not more than 30 days for completion of punch list items and final completion.
C. Constraints: Include constraints and work restrictions indicated in the Contract Documents and as follows in schedule and show how the sequence of the Work is affected.
1. Products Ordered in Advance: Include a separate activity for each product. Include delivery date indicated in Section 011000 "Summary." Delivery dates indicated stipulate the earliest possible delivery date.
2. Work Restrictions: Show the effect of the following items on the schedule:
a. Coordination with existing construction.
b. Limitations of continued occupancies.
c. Use of premises restrictions.
d. Environmental control.
3. Work Stages: Indicate important stages of construction for each major portion of the Work, including, but not limited to, the following:
Submittals.
a. Purchases.
b. Mockups.
c. Fabrication.
March 21, 2025
CONSTRUCTION PROGRESS
DOCUMENTATION
013200 - 4
d. Sample testing.
e. Deliveries.
f. Installation.
g. Tests and inspections.
h. Adjusting.
i. Startup and placement into final use and operation.
D. Milestones: Include milestones indicated in the Contract Documents in schedule, including, but not limited to, the Notice to Proceed, Substantial Completion, and final completion.
E. Cost Correlation: Superimpose a cost correlation timeline, indicating planned and actual costs.
On the line, show planned and actual dollar volume of the Work performed as of planned and actual dates used for preparation of payment requests.
1. See Section 012900 "Payment Procedures" for cost reporting and payment procedures.
F. Computer Scheduling Software: Prepare schedules using current version of a program that has been developed specifically to manage construction schedules.
2.02 CONTRACTOR'S CONSTRUCTION SCHEDULE (GANTT CHART)
A. Gantt-Chart Schedule: Submit a comprehensive, fully developed, horizontal, Gantt-chart-type, Contractor's construction schedule within 30 days of date established for commencement of the Work. Base schedule on the startup construction schedule and additional information received since the start of Project.
B. Preparation: Indicate each significant construction activity separately. Identify first workday of each week with a continuous vertical line.
1. For construction activities that require three months or longer to complete, indicate an estimated completion percentage in 10 percent increments within time bar.
2.03 REPORTS
Daily Construction Reports: Prepare a daily construction report recording the following information concerning events at Project site:
List of subcontractors at Project site.
1. List of separate contractors at Project site.
2. Approximate count of personnel at Project site.
3. Equipment at Project site.
4. Material deliveries.
5. High and low temperatures and general weather conditions, including presence of rain or snow.
6. Accidents.
7. Meetings and significant decisions.
8. Unusual events (see special reports).
9. Stoppages, delays, shortages, and losses.
10. Emergency procedures.
11. Orders and requests of authorities having jurisdiction.
12. Change Orders received and implemented.
13. Construction or Work Change Directives received and implemented.
14. Services connected and disconnected.
15. Equipment or system tests and startups.
16. Partial completions and occupancies.
17. Substantial Completions authorized.
March 21, 2025
CONSTRUCTION PROGRESS
DOCUMENTATION
013200 - 5
Site Condition Reports: Immediately on discovery of a difference between site conditions and the Contract Documents, prepare and submit a detailed report. Submit with a Request for Information. Include a detailed description of the differing conditions, together with recommendations for changing the Contract Documents.
2.04 SPECIAL REPORTS
A. General: Submit special reports directly to Owner within one day(s) of an occurrence. Distribute copies of report to parties affected by the occurrence.
B. Reporting Unusual Events: When an event of an unusual and significant nature occurs at Project site, whether or not related directly to the Work, prepare and submit a special report. List chain of events, persons participating, response by Contractor's personnel, evaluation of results or effects, and similar pertinent information. Advise Owner in advance when these events are known or predictable.
PART 3 - EXECUTION
3.01 CONTRACTOR'S CONSTRUCTION SCHEDULE
Contractor's Construction Schedule Updating: At monthly intervals, update schedule to reflect actual construction progress and activities. Issue schedule one week before each regularly scheduled progress meeting.
Revise the schedule immediately after each meeting or other activity where revisions have been recognized or made. Issue updated schedule concurrently with the report of each such meeting.
1. Include a report with an updated schedule that indicates every change, including, but not limited to, changes in logic, durations, actual starts and finishes, and activity durations.
2. As the Work progresses, indicate final completion percentage for each activity.
Distribution: Distribute copies of approved schedule to Engineer Owner, separate contractors, testing and inspecting agencies, and other parties identified by Contractor with a need-to-know schedule responsibility.
3. Post copies in Project meeting rooms and temporary field offices.
4. When revisions are made, distribute updated schedules to the same parties and post in the same locations. Delete parties from distribution when they have completed their assigned portion of the Work and are no longer involved in performance of construction activities.
END OF SECTION 013200
March 21, 2025
SUBMITTAL PROCEDURES 013300 - 1
SECTION 013300 - SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.02 SUMMARY
A. Section includes requirements for the submittal schedule and administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other submittals.
B. Related Requirements:
1. Section 012900 "Payment Procedures" for submitting Applications for Payment and the schedule of values.
2. Section 013200 "Construction Progress Documentation" for submitting schedules and reports, including Contractor's construction schedule.
3. Section 017823 "Operation and Maintenance Data" for submitting operation and maintenance manuals.
4. Section 017839 "Project Record Documents" for submitting record Drawings, record
Specifications, and record Product Data.
5. Section 017900 "Demonstration and Training" for submitting video recordings of demonstration of equipment and training of Owner's personnel.
1.03 DEFINITIONS
A. Action Submittals: Written and graphic information and physical samples that require Engineer's responsive action. Action submittals are those submittals indicated in individual Specification Sections as "action submittals."
B. Informational Submittals: Written and graphic information and physical samples that do not require Engineer's responsive action. Submittals may be rejected for not complying with requirements. Informational submittals are those submittals indicated in individual Specification Sections as "informational submittals."
PART 2 - PRODUCTS
2.01 SUBMITTAL PROCEDURES
A. General Submittal Procedure Requirements: Prepare and submit submittals required by individual Specification Sections. Types of submittals are indicated in individual Specification Sections.
Submit electronic submittals via email as PDF electronic files.
B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard published data are not suitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each copy of each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
a. Manufacturer's catalog cuts.
b. Manufacturer's product specifications.
c. Standard color charts.
d. Statement of compliance with specified referenced standards.
e. Testing by recognized testing agency.
f. Application of testing agency labels and seals.
March 21, 2025
SUBMITTAL PROCEDURES 013300 - 2
g. Notation of coordination requirements.
For equipment, include the following in addition to the above, as applicable:
Wiring diagrams showing factory-installed wiring.
h. Printed performance curves.
Submit Product Data before or concurrent with Samples.
4. Submit Product Data in the following format:
a. PDF electronic file.
C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.
1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:
a. Identification of products.
b. Schedules.
c. Compliance with specified standards.
d. Notation of coordination requirements.
e. Notation of dimensions established by field measurement.
f. Relationship and attachment to adjoining construction clearly indicated.
g. Seal and signature of professional engineer if specified.
Submit Shop Drawings in the following format:
h. PDF electronic file.
D. Coordination Drawing Submittals: Comply with requirements specified in Section 013100 "Project Management and Coordination."
E. Contractor's Construction Schedule: Comply with requirements specified in Section 013200 "Construction Progress Documentation."
F. Application for Payment and Schedule of Values: Comply with requirements specified in Section 012900 "Payment Procedures."
G. Test and Inspection Reports and Schedule of Tests and Inspections Submittals: Comply with requirements specified in Section 014000 "Quality Requirements."
H. Closeout Submittals and Maintenance Material Submittals: Comply with requirements specified in Section 017700 "Closeout Procedures."
I. Maintenance Data: Comply with requirements specified in Section 017823 "Operation and Maintenance Data."
J. Qualification Data: Prepare written…