Attachment A - Bid Specifications.pdf
PDF 3 MB Posted
- Attached to
- Fox Theater HVAC Replacement and Upgrades
- Solicitation number
- 6066AB
- Issued by
- Colorado
About this file
This document is a comprehensive bid specification for the City of Aurora Fox Theater HVAC Alterations project, involving mechanical systems replacement and upgrades. The project encompasses the renovation of HVAC systems for studio theater and workshop areas, with a base bid and optional alternates that include removing and replacing the lobby mechanical system. The base scope includes demolishing existing roof top units, installing new replacement units, connecting to existing systems, providing electrical connections, installing new duct detectors, creating new mechanical unit curbs, implementing new condensate piping, and performing associated architectural repairs and modifications. The specification details comprehensive requirements for mechanical, electrical, and architectural work, with specific technical standards for ductwork, insulation, dampers, and system integration.
The bid specifications are structured to provide detailed technical guidance for contractors, with extensive requirements for materials, installation methods, testing, and quality control. The project appears to be funded by the City of Aurora and is designed to preserve the historic character of the Fox Theater while modernizing its HVAC infrastructure. The specifications include multiple sections covering everything from general mechanical provisions to specific installation requirements, with particular attention to technical standards, performance specifications, and compliance with local building codes and HVAC industry standards. Bidders are required to submit detailed documentation, including shop drawings, product data, and comprehensive installation plans, with a focus on ensuring high-quality, code-compliant HVAC system upgrades.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Sheet.xlsx | XLSX spreadsheet | |
| Attachment B - Drawings.pdf | ||
| Attachment C - Special Conditions.pdf | ||
| Project Manual_Fox Theater - HVAC Replacement and Upgrades (6066AB).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
City of Aurora
Fox Theater HVAC Alterations
September 26, 2025
For Bid Revision 1 Specifications
Architect: Architectural Workshop, LLC.
2 Kalamath Street
Denver, CO 80223
303.788.1717
City of Aurora Fox Theater HVAC Alterations
TABLE OF CONTENTS 00 01 00 - 1
SECTION 00 01 00
TABLE OF CONTENTS
Division Section Title
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 GENERAL
01 30 00 ADMINISTRATION AND SUPERVISION
01 31 00 PROJECT COORDINATION
01 31 13 MECHANICAL AND ELECTRICAL COORDINATION
01 31 19 PROJECT MEETINGS
01 33 00 SUBMITTAL, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES
01 35 00 CUTTING AND PATCHING
01 35 13 SPECIAL PROJECT PROCEDURES
01 41 00 REGULATORY REQUIREMENTS
01 42 00 SPECIFICATION SYSTEM
01 45 00 QUALITY CONTROL
01 50 00 TEMPORARY FACILITIES
01 60 00 MATERIAL AND EQUIPMENT
01 74 00 CLEANING
01 77 00 CONTRACT CLOSEOUT
01 78 20 OPERATING AND MAINTENANCE
01 78 39 PROJECT RECORD DOCUMENTS
DIVISION 02 - EXISTING CONDITIONS – N/A
DIVISION 03 – CONCRETE – N/A
DIVISION 04 – MASONRY
04 20 00 UNIT MASONRY
DIVISION 05 - METALS
05 12 00 STRUCTURAL STEEL FRAMING
05 40 00 COLD-FORMED METAL FRAMING
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 53 MISCELLANEOUS ROUGH CARPENTRY
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 21 00 BUILDING INSULATION
07 53 23 EPDM ROOFING
07 92 00 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 30 50 ACCESS DOORS
TABLE OF CONTENTS 00 01 00 - 2
DIVISION 09 - FINISHES
09 00 00 FINISHES
09 20 00 LATH AND PLASTER
09 22 16 NON-STRUCTURAL METAL FRAMING
09 29 00 GYPSUM BOARD
09 65 00 RESILIENT FLOORING
09 91 23 INTERIOR PAINTING
DIVISION 10 – SPECIALTIES –N/A
DIVISION 11 – EQUIPMENT –N/A
DIVISION 12 – FURNISHINGS –N/A
DIVISION 13 - SPECIAL CONSTRUCTION – N/A
DIVISION 14 - CONVEYING EQUIPMENT –N/A
DIVISION 21 – FIRE SUPPRESSION –N/A
DIVISION 22 – PLUMBING –N/A
DIVISION 23 - HEATING VENTILATING AND AIR CONDITIONING
23 00 10 HVAC GENERAL PROVISIONS
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 13 DUCT INSULATION
23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC
23 11 23 FACILITY NATURAL-GAS PIPING
23 31 13 METAL DUCTS
23 33 00 AIR DUCT ACCESSORIES
DIVISION 26 - ELECTRICAL
26 00 10 ELECTRICAL GENERAL PROVISIONS
26 00 10 SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND CABLING
26 05 19 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
26 05 26 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
26 05 33 RACEWAY AND BOXES
26 05 53 ELECTRICAL IDENTIFICATION
26 24 16 PANELBOARDS
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 11 DIGITAL, ADDRESSABLE FIRE ALARM SYSTEMS
END OF SECTION 00 01 00
GENERAL 01 10 00 - 1
SECTION 01 10 00
GENERAL
PART 1 - GENERAL
1.1 CONDITIONS AND REQUIREMENTS
Division 1 - General Requirements shall govern work under all Divisions of the Specifications.
1.2 SPECIFICATION LANGUAGE EXPLANATION
Specifications are of abbreviated, simplified or streamlined type and include incomplete sentences.
Omissions of words or phrases such as "the Contractor shall," "in conformity therewith," "shall be," "as noted on the Drawings," "a," "the" are intentional. Supply omitted words or phrases by inference in same manner as they are when "NOTE" occurs on Drawings. Supply words "shall be" or "shall" by inference when colon is used within sentences or phrases. Supply words "on the Drawings" by inference when "as indicated" is used with sentences or phrases.
Where reference is made to specifications, societies, institutes, or associations or manufacturer's directions, they are, except as may be inconsistent herewith, made part of specifications, to same extent as if written out in full herein. Use latest edition, at time of bidding, if a date is not given.
1.3 ABBREVIATIONS
References in Contract Documents to trade associations, technical societies, recognized authorities and other institutions include following organizations, which are sometimes referred to only by corresponding abbreviations:
AA Aluminum Association AAMA Architectural Aluminum Manufacturer's Association ACI American Concrete Institute AIMA Acoustical and Insulating Materials Association (successor to AMA and IBI) AISC American Institute of Steel Construction AISI American Iron and Steel Institute AMA Acoustical Materials Association ANSI American National Standards Institute (successor to USASI and ASA) APA American Plywood Association ASHRAE American Society of Heating, Refrigerating and Air Conditioning Engineers ASTM American Society for Testing Materials AWI Architectural Woodwork Institute AWPA American Wood Preservers Association AWS American Welding Society CDA Copper Development Associations, Inc.
CM/GC Construction Manager/General Contractor CRA California Redwood Association CRSI Concrete Reinforcing Steel Institute CS Commercial Standard (U.S. Department of Commerce) DFPA Douglas Fir Plywood Association EPA Environmental Protection Agency FIA Factory Insurance Association FM Factory Mutual Engineering Division
GENERAL 01 10 00 - 2
FS Federal Specification MIL Military Specification
MILMA Metal Lath Manufacturer's Association NAAMM The National Association of Architectural Metal Manufacturers NBFU National Board of Fire Underwriters NBS National Bureau of Standards NCMA National Concrete Masonry Association NEC National Electric Code (of NBFU) NEMA National Electrical Manufacturers' Association NFPA National Fire Protection Association NIOSH National Institute of Occupational Safety and Health NMWIA National Mineral Wool Insulation Association NPVLMA National Paint, Varnish and Lacquer Manufacturers' Association OSHA Occupational Safety and Health Administration PCA Portland Cement Association PEI Porcelain Enamel Institute PS Product Standard (U.S. Department of Commerce) SDI Steel Deck Institute SJI Steel Joist Institute SMACNA Sheet Metal and Air Conditioning Contractor's National Association SPA Southern Pine Association SPR Simplified Practice Recommendation (U.S. Department of Commerce) SSPC Steel Structures Painting Council SWI Steel Window Institute UL Underwriters' Laboratories, Inc.
WCLA West Coat Lumbermen's Association WRI Wire Reinforcement Institute WWPA Western Wood Products Association
1.4 LAYING OUT WORK
The Contractor will furnish reference bench mark and maintain bench mark and all other grades, lines, and levels and dimensions as indicated in the Contract Documents. Report any errors or inconsistencies in above to the City before commencing work.
Except as delegated by subcontract or normal trade practice, the Contractor will be responsible for all lines, elevations, and measurements of work indicated.
1.5 EXAMINATION OF SITE
Failure to visit the site will in no way relieve any Contractor from the necessity of furnishing materials or performing work that may be required to complete work in accordance with the Contract Documents without additional cost to the City.
END OF SECTION 01 10 00
ADMINISTRATION AND SUPERVISION 01 30 00- 1
SECTION 01 30 00
ADMINISTRATION AND SUPERVISION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the contract, including General and Supplementary Conditions and other Division 1 Specification sections, apply to work of this section.
1.2 SURVEYS, LAYOUTS, AND LEVELS
A. General: Working from lines and levels established by the existing bench marks, and as shown in relation to the work, establish and maintain bench marks and other dependable markers to set the lines and levels for the work of construction as needed to properly locate every element of the work of the entire project. Calculate and measure required dimensions as shown (within recognized tolerances if not otherwise indicated); do not scale the drawings to determine dimensions. Continuously advise tradesmen performing the work of the marked lines and levels provided for use in the layout of work.
1.3 PROJECT RECORD DOCUMENTS
A. Maintain at job site, one copy of:
1. Contract Drawings
2. Specifications
3. Addenda
4. Reviewed Shop Drawings
5. Change Orders
6. Other Modifications to Contract
7. Field Test Records
8. As-Built Drawings
B. Maintain documents in clean, dry, legible condition and do not use record documents for construction purposes. Make documents available at all times for inspection by the Consultant and the City.
C. Label each document "Project Record" in 1" or larger printed letters.
D. Record drawing information in colored pencil with different colors for the various systems and defined by color legend.
E. Record drawings and specifications shall include the following:
1. Location of internal utilities and appurtenances concealed in construction referenced to visible and accessible features of structure. Location of concealed valves, dampers, controls, balancing devices, junction boxes, clean-outs, and other items requiring access or maintenance.
2. Field changes of dimension and detail, changes made by Change Order or Field Order and details not on original contract drawings.
3. Fire protection and alarm systems shop drawings.
F. Submit all record drawings to the Architect at the completion of the project.
ADMINISTRATION AND SUPERVISION 01 30 00- 2
1.4 CLEANING
A. Cleaning and Protection Work: At the time each unit of work or element of the construction is completed (substantially) in each area of the Project, clean the unit or element to a condition suitable for occupancy and use (as intended), and restore minor or superficial damage. Replace units and elements which are damaged beyond successful restoration. Clean and restore adjoining surfaces and other work which was soiled or damaged (superficially) during the installation;
replace other work damaged beyond successful restoration. Where the performance of subsequent work could possibly result in damage to the complete unit or element, provide protective covering or other provisions to minimize possible damage. Repeat cleaning and protection operations during remainder of construction period, wherever work might otherwise be damaged by sustained soiling or exposure.
B. During Construction: Oversee cleaning and ensure that building, grounds, and public properties are maintained free from accumulation of waste materials and rubbish. At reasonable intervals during daily progress of work, clean up site and access and dispose of waste materials, rubbish, and debris. Vacuum clean interior building areas when ready and continue vacuum cleaning on an as-needed basis until building is ready for acceptance or occupancy.
1.5 PROJECT SIGN
Erect no project sign or job-site sign of any kind, except warning signs as specified in Section 01500, without written authorization of the City.
1.6 COORDINATION
A. The Contractor shall be responsible for coordinating all the work of the project. The Contractor shall coordinate the efforts of all subcontractor(s) and the deliveries of suppliers so that the work progresses in an orderly fashion without delay towards timely completion of a complete project in accordance with the drawings and specifications.
B. The Contractor shall note that concurrent with his work, other contractors, suppliers, and the City's facilities and maintenance personnel may be working in relatively close proximity. The Contractor will be solely responsible for coordinating his work with that of other contractors and will make no claims for failure to do so.
1.8 METHODS OF CONSTRUCTION
A. The procedure and method of construction is the prerogative and the responsibility of the
Contractor. If professional assistance is required to safely implement method of construction, the Contractor shall, on his own, employ professional help.
END OF SECTION 01 30 00
PROJECT COORDINATION 01 31 00 - 1
SECTION 01 31 00
PROJECT COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. General Contractor is responsible for all of the work of this contract.
1. Assign and subcontract portions of the work as required to assure that all work is constructed in compliance with these documents.
2. Coordinate the work of the several subcontractors for the project.
3. Coordinate work of this contract with work by separate contractors / vendors.
B. Each subcontractor shall:
1. Coordinate work of his own employees and subcontractors.
2. Expedite his work to assure compliance with schedules.
3. Coordinate his work with that of other subcontractors and work by separate contractor.
4. Comply with orders and instructions of City thru the general contractor.
C. Related Requirements
1. All Division 1 Sections.
1.2 CONSTRUCTION ORGANIZATION AND START-UP
A. Establish on-site lines of authority and communications.
1. Attend pre-construction meeting with subcontractors upon commencement of the project.
2. Establish procedures for intra-project communications.
a. Submittals.
b. Reports and records.
c. Recommendations.
d. Coordination Drawings.
e. Schedules.
f. Resolution of conflicts.
3. Interpret Contract Documents.
a. Consult with Architect to obtain interpretation.
b. Assist in resolution of questions or conflicts which may arise.
c. Transmit written interpretations to subcontractors, and to other concerned parties.
4. Assist in obtaining permits and approvals.
a. Obtain building permits and special permits required for work or for temporary facilities.
b. Verify that subcontractors have obtained inspections for work and for temporary facilities.
c. Coordinate with City Project Manager.
5. Control the use of site.
a. Supervise field engineering and site layout, coordinate with City Project
Manager.
b. Allocate space for each subcontractor's use for field offices, sheds, work and storage areas.
c. Establish access, traffic and parking allocations and regulations.
d. Monitor use of site during construction.
PROJECT COORDINATION 01 31 00 - 2
1.3 CONTRACTOR DUTIES
A. Construction Schedules.
1. Coordinate schedules with several subcontractors.
2. Monitor schedules as work progresses.
a. Identify potential variances between schedules and probable completion dates for each phase.
b. Recommend adjustments in schedule to meet required completion dates.
c. Adjust schedules of subcontractors as required.
d. Document changes in schedule.
3. Observe work of each subcontractor to monitor compliance with schedule.
a. Verify that labor and equipment are adequate for the work and the schedule.
b. Verify that product procurement schedules are adequate.
c. Verify that product deliveries are adequate to maintain schedule.
d. Coordinate deliveries with City Project Manager.
B. Process Shop Drawings, Product Data and Samples.
1. Review for compliance with Contract Documents.
a. Field dimensions and clearance dimensions.
b. Relation to available space.
c. Relation to other trades, equipment and systems.
d. Submit to Architect.
C. Monitor the use of temporary utilities.
1. Verify that adequate services are provided and maintained.
D. Inspection and Testing.
1. Inspection work to assure performance in accord with requirements of Contract
Documents.
2. Administer special testing and inspections of suspected work.
3. Reject work which does not comply with requirements of Contract Documents.
4. Coordinate testing laboratory services.
a. Verify that required laboratory personnel are present.
b. Verify that tests are made in accordance with specified standards.
c. Review test reports for compliance with specified criteria.
d. Recommend and administer required retesting.
E. Monitor contractor's periodic cleaning.
1. Enforce compliance with specifications.
2. Resolve any conflicts.
F. Coordinate changes.
1. Recommend necessary or desirable changes.
2. Assist the City in negotiating change orders.
3. Promptly notify all subcontractors of pending changes.
G. Maintain Reports and Records at Job Site available to Architect and Subcontractors.
1. Log progress of work of each subcontractor.
2. Records
a. Contracts.
b. Purchase orders.
c. Materials and equipment records.
d. Applicable handbooks, codes and standards.
3. Obtain information from subcontractors and maintain file of Project Record Documents.
PROJECT COORDINATION 01 31 00 - 3
4. Assemble documentation for handling of claims and disputes.
H. Coordinate work of this Contract and requirements of this section with work by Separate Contract including but not limited to:
1. Equipment Vendors.
1.4 CONTRACT CLOSEOUT
A. Coordinate equipment start-up.
1. Provide seven days notification prior to start-up of each item.
2. Ensure that each piece of equipment or system is ready for operation.
3. Execute start-up under supervision of responsible persons in accordance with manufacturer's instructions.
4. Perform required testing and balancing.
5. Record dates of start of operation of systems and equipment. Submit written report that equipment or system has been properly installed and is functioning correctly.
6. Provide written notice of beginning of warranty period for equipment put into service.
B. Demonstration and Instructions
1. Demonstrate operation and maintenance of products to the City Facilities Operations personnel two weeks prior to Substantial Completion.
2. Demonstrate start-up, operation, control, adjustment, trouble-shooting, servicing, maintenance, seasonal operation, and shutdown of each item of equipment.
C. At completion of work of each Section, conduct an inspection to assure that
1. Specified cleaning has been accomplished.
2. Temporary facilities have been removed from site.
D. At completion
1. Conduct an inspection to list work to be completed or corrected.
2. Supervise correction and completion of work as established in Certificate of Completion.
E. When a portion of the Project is occupied prior to final completion, coordinate established responsibilities of each subcontractor.
F. Final completion.
1. When each Subcontractor determines that work is finally complete, conduct an inspection to verify completion of work.
2. Assist the City and architect in inspection.
G. Administer contract closeout.
1. Receive and review Subcontractor's final submittals.
2. Transmit to architect with recommendation for action.
END OF SECTION 01 31 00
MECHANICAL AND ELECTRICAL COORDINATION 01 31 13 - 1
SECTION 01 31 13
MECHANICAL AND ELECTRICAL COORDINATION
1.1 SUMMARY:
A. Carefully coordinate the interface between Division 23 (Mechanical) and Division 26 (Electrical) before submitting any equipment for review or commencing installation.
B. Responsibility: Unless otherwise indicated, all motor and controls for Division 23 equipment shall be furnished, set in place and wired in accordance with the following schedule:
ITEM
FURNISHED
BY
SET IN
PLACE OR
MOUNTED
BY
POWER
WIRED AND
CONNECTED
BY
CONTROL
WIRED AND
CONNECTED BY
Equipment Motor 23 23 26 -
Automatically Controlled Starter/contractors:
Separate 23 26 26 23
Factory Mounted & Wired 23 23 26 23
In Motor Control Centers 26 26 26 16
Manually Controlled Starter/Contractors:
Separate 23 26 26 26
Factory Mounted & Wired 23 26 26 26
Motor Speed Controllers 23 26 26 26
Disconnect (Note 1) Switches 26 26 26 -
Contactors 26 26 26 -
Thermal Overload (Note 1) Switches 26 26 26 -
Manual Operation (Note 2) 26 26 26 -
Switches 26 26 26 -
Control Relays (Note 2) 23 23 - 23
Control Transformers 23 23 26 23
Control Circuit Outlets 26 26 26 -
Thermostats (Note 2) 23 23 - 23
MECHANICAL AND ELECTRICAL COORDINATION 01 31 13 - 2
Time Switches (Note 2) Not in Control Panel
23 23 26 23
Push Button Stations, Pilot Lights 26 26 26 26
Thermostatic (Note 2) Controls: Integral with Equipment or Directly Applied to Ducts, Pipes, etc.
Equipment in Temperature Control Panels
23 23 26 23
Valve Motors, Damper Motors, Solenoid Valves, etc.
23 23 - 23
EP Valves or Switches, P.E. Switches, etc.
23 23 - 23
Fire Alarm Systems 28 28 28 28
Fire Sprinkler Alarm 21 21 - 28
Firestats 21 21 - 21
Smoke Detectors Including Relays for Fan Control
28 23 26 23
Control Air Compressor 28 21 28 21
Equipment Interlocks 23 23 - 23
C. NOTES:
1. If furnished as part of factory wired equipment furnished and set in place under Division 23, wiring and connections under Division 26.
2. If float switches, line thermostats, P.E. switches, time switches, or other controls carry the
FULL LOAD CURRENT to any motor, they shall be furnished under Division 23, but they shall be set in place and connected under Division 26 except that where such items are an integral part of the mechanical equipment, or directly attached to ducts, piping, or other mechanical equipment, they shall be set in place under Division 23 and connected under Division 26. If they do not carry the FULL LOAD CURRENT to any motor, they shall be furnished, set in place and wired under Division 23.
D. Control Wiring: Consists of wiring in pilot circuits of contactor, starters, sensors, controllers, and relays, and wiring for valve and damper operators.
E. Connections: Connections to all controls directly attached to ducts, piping and mechanical equipment shall be made with flexible connections.
F. Starters: Provide magnetic starters for all three phase motors and equipment complete with:
1. Control transformers.
2. 120V holding coils.
3. Integral hand-off-auto switch.
4. Auxiliary contacts required for system operation plus one (1) spare.
5. Starters shall be in full compliance with Division 26 requirements.
G. Remote Switches and Push Button Stations: Provide all remote switches and/or push button stations required for manually operated equipment (if no automatic controls have been provided) complete with pilot lights of an approved type lighted by current from load side of starter.
MECHANICAL AND ELECTRICAL COORDINATION 01 31 13 - 3
H. Special Requirements: Motors, starters and other electrical equipment installed in moist areas or areas of special conditions, such as explosion proof, shall be designed and approved for installation in such areas with appropriate enclosure.
I. Identification: Provide identification of purpose for each switch and/or push button station furnished. Identification may be either engraved plastic sign or permanent mounting to wall below switch, or stamping on switch cover proper. All such identification signs and/or switch covers in finished areas shall match other hardware in the immediate areas.
J. Control Voltage:
1. Maximum allowable control voltage 120V. Fully protect control circuit conductors in accordance with National Electrical Code.
2. Provide 20A breakers in emergency panels under Division 26 as required for BMS/ATC controls. Provide all control transformers, control wiring and connections to circuits under Division 23.
K. Related Requirements:
1. Division 26: Electric Motors
a. Coordinate with efficiency requirements.
PART 2 - PRODUCTS
2.1 MOTOR HORSEPOWER:
A. In general, all motors 1/2 HP and above shall be three phase, all motors less than 1/2 HP shall be single phase.
B. Voltage and phase of motors as scheduled on the electrical drawings shall take precedence in the case of a conflict between the mechanical and electrical drawings or 2.1.A, above.
C. Work under Division 23 includes coordinating the electrical requirements of all mechanical equipment with the requirements of the work under Division 26, before ordering the equipment.
1. If motor horsepowers are changed under the work of Division 23, without a change in duty of the motor's driven device, coordination of additional electrical work (if any) and additional payment for the work (if any) shall be provided under the section of Division 23 initiating the change. Increases or decreases in motor horsepower from that specified shall not be made without written approval from the Architect.
PART 3 - EXECUTION
Not Used.
END OF SECTION 01 31 13
PROJECT MEETINGS 01 31 19 - 1
SECTION 01 31 19
PROJECT MEETINGS
1.1 REQUIREMENTS
A. The types and minimum requirements for project meetings are included but are not necessarily limited to the following categories:
Pre-construction meeting Progress and Coordination meetings Specially called meetings
B. The pre-construction meeting will be scheduled within fifteen days after date of Notice to Proceed, and held at the Fox Theater.
1. Attendance:
a. City's Representative
b. Consultant and sub-consultants, as applicable
c. Contractor's Superintendent
d. Major Subcontractor(s)
e. Others as appropriate
2. Suggested Agenda:
a. Distribution and discussion of:
List of major subcontractors and suppliers Projected construction schedules Critical work sequencing Major equipment deliveries and priorities, including equipment with long lead times Project Coordination Designation of responsible personnel
b. Procedures and processing of:
Field decisions Proposal requests Submittals Change Orders Applications for Payment
c. Adequacy of Distribution of Contract Documents
d. Procedure for Maintaining Record Documents
e. Inspections
C. The Contractor will: Record the minutes; including significant proceedings and decisions.
D. The Contractor shall schedule and administer subcontractor and vendor pre-construction meetings throughout progress of the work. They will:
1. Prepare agenda for meetings.
2. Distribute written notice of each meeting four days in advance of meeting date.
3. Make physical arrangements for meetings.
4. Preside at meeting.
5. Record the minutes; including significant proceedings and decisions.
6. Representatives of Contractors, Subcontractors, and Suppliers attending meetings shall be qualified and authorized to act on behalf of the entity each represents.
7. Use of Premises:
PROJECT MEETINGS 01 31 19 - 2
Office, work, staging and storage areas City's requirements
8. Temporary construction Facilities, Utilities, Controls and Construction Aids
9. Safety, First-aid, Security and Housekeeping Procedures
10. Administrative Procedures and Documents as Required by City
1.2 PROGRESS AND COORDINATION MEETING
The Contractor will schedule and administer job progress and coordination meeting at the site.
A. Attendance:
1. City Project Manager as needed
2. Consultant and his sub-consultants as needed
3. Subcontractor as appropriate to the agenda
4. Suppliers as appropriate to the agenda
5. Others
B. Suggested Agenda:
1. Review of work progress since previous meeting.
2. Field observations, problems and conflicts.
3. Problems which impede Construction Schedule.
4. Review of off-site fabrication and delivery schedules.
5. Corrective measures and procedures to regain projected schedule.
6. Revisions to Construction Schedule.
7. Coordination of schedules.
8. Progress and schedule during succeeding work period.
9. Review submittal schedules and expedite as required.
10. Maintenance of quality standards.
11. Pending changes and substitutions.
12. Review proposed changes for:
a. Effect on Construction Schedule and on completion date.
b. Effect on other contracts of the Project.
C. The general contractor shall record and distribute the minutes of all progress meetings throughout the construction period and shall visit the site a minimum of once every two weeks.
END OF SECTION 01 31 19
SUBMITTALS, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES 01 33 00 - 1
SECTION 01 33 00
SUBMITTALS, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES
1.1 DESCRIPTION OF WORK
A. Submit shop drawings, product data and samples as required by various sections of the specifications. All submittals are to be uploaded to the city construction management software, projectmates and sent to the city project manager and architect.
1.2 QUALITY ASSURANCE
A. Shop Drawings:
1. Drawings shall be presented in a clear and thorough manner.
2. Details shall be identified by reference to sheet, detail, schedule, or room numbers shown on drawings.
B. Product Data:
1. Preparation:
a. Clearly mark each copy to identify pertinent products or models.
b. Show performance characteristics and capabilities.
c. Show dimensions and clearances required.
d. Show wiring or piping diagrams and controls.
2. Manufacturer's standard schematic drawings and diagrams.
a. Modify drawings and diagrams to delete information that is not applicable to the work.
b. Supplement Standard information to provide information specifically applicable to the work.
C. Responsibilities of the Contractor:
1. Review shop drawings, product data, samples and project record drawings for specification performance prior to submission.
2. Determine and Verify:
a. Field measurements
b. Field construction criteria
c. Catalog numbers and similar data
d. Conformance with specifications
3. Coordinate each submittal with requirements of the work and of the Contract Documents.
4. Notify the Architect in writing, at the time of submission, of any deviations in the submittals for requirements of the Contract Documents.
5. Begin no fabrication or work that requires submittals until return of submittals with
Architect's acceptance.
6. Contractor’s responsibility for deviations in submittals from requirements of Contract
Documents is not relieved by Architect’s review of submittals.
7. Contractor shall stamp, sign or initial, and date each submittal to show compliance with the Contract Documents prior to submittal to the Architect.
1.3 SUBMITTALS
A. Make submittals promptly in accordance with approved schedule and in such sequence as to cause no delay in the work.
SUBMITTALS, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES 01 33 00 - 2
B. Number of Submittals Required:
1. Shop Drawings: one electronic copy.
2. Product Data: one electronic copy.
3. Samples: Submit the number stated in each specification section.
C. Submittals shall contain:
1. Date of the submission and dates of any previous submissions.
2. Project title and number.
3. Contract identifications.
4. Names of:
a. Contractor and Subcontractor(s), if applicable.
b. Supplier
c. Manufacturer
5. Identification of product with the specification section number.
6. Field dimensions, clearly identified as such.
7. Relation to adjacent or critical features of the work or materials.
8. Applicable standards, such as ASTM or Federal specification numbers.
9. Identification of deviations from Contract Documents.
10. Identification of revisions on resubmittals.
11. An 8"x3" blank space in lower right-hand corner for review stamps.
D. Resubmission Requirements:
1. Make any corrections or changes in the submittals required by the Architect and resubmit until accepted.
2. Shop drawings and product data:
a. Revise initial drawings or data and resubmit as specified for initial submittal.
b. Indicate any changes that have been made, other than those requested by the
Architect.
3. Samples: Submit new samples as required for initial submittal.
E. Distribution: Shop drawings and product data will be distributed via Projectmates software.
1. Distribute reproductions of approved shop drawings and copies of product data to affected subcontractors and retain one copy for use at the job-site.
2. Distribute approved samples as directed.
F. Architect's Duties:
1. Review submittals with reasonable promptness and in accordance with schedule.
2. Review of separate item does not constitute review of an assembly in which item functions.
3. Affix stamp and initials or signature, and indicate requirements for resubmittal or acceptance of submittal.
4. Return submittals to the Contractor for distribution or for resubmission.
G. Schedule of Values and pay applications:
1. Submit typed schedule of values on spread sheet.
2. Format: Table of Contents of this Project Manual.
3. Include in each line item a directly proportional amount of Contractor's overhead and profit.
H. Schedule of Submittals: The Contractor shall submit the submittals required by the specifications.
The Contractor shall develop a submittal schedule that confirms the submittals and the time frame for review by the City Project Manager and Architects.
SUBMITTALS, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES 01 33 00 - 3
I. Construction Schedule:
1. The Contractor shall submit a critical-path method (CPM) construction schedule prior to start of construction activities. The CPM schedule shall include notice to proceed, submittal activities, construction activities, change order work (when applicable), close-out, testing, demonstration, and acceptance. The CPM shall correlate specifically to the schedule of values line items and be cost loaded.
Float, slack time, or contingency within the schedule (i.e., the difference in time between the project's early completion date and the required contract completion date), and total float within the overall schedule, is not for the exclusive use of either the principal City representative or the Contractor, but is jointly owned by both and is a resource available to and shared by both parties as needed to meet contract milestones and the contract completion date.
The Contractor will be required to submit an as-built progress CPM schedule with each progress billing. This CPM schedule will be the basis for making progress payments.
The level of detail and quantity of work activities in the CPM schedule should be negotiated with the principal representative prior to starting construction.
J. Daily Reports
1. The contractor shall keep daily reports. The report should include weather, equipment, workforce count, subcontractors on site, short description of work for that day, inspections, visitors, items that may affect progress or quality of project.
K. Request for Information (RFI):
1. The Contractor will be responsible for submitting RFIs on a agreed upon format. The
RFI should identify in writing any unclear, inconsistent, or conflicting item in the documents that could not be answered by thorough review by the Contractor or subcontractors. The RFI should include a description of the item and a proposed solution. The RFI should indicate schedule or cost impact, if any. Contractor shall be required to submit cost or schedule impact within seven days of receipt of the RFI response. Each RFI shall be numbered in sequence.
PART 2 - MATERIALS
Not used.
Not used.
END OF SECTION 01 33 00
CUTTING AND PATCHING 01 35 00 - 1
SECTION 01 35 00
CUTTING AND PATCHING
PART 1 - GENERAL
1.1 DESCRIPTION
A. Work Included: This section establishes general requirements in addition to those indicated in the
General Conditions of the Contract for Construction pertaining to cutting, fitting, and patching of the work required to:
1. Make the several parts fit properly.
2. Uncover work to provide for installation, inspection, or both, of ill-timed work.
3. Remove and replace work not conforming to requirements of Contract Documents.
4. Patch new construction into existing construction and paint to match.
B. Related Work:
1. In addition to requirements specified, upon the Architect's request, uncover work to provide for inspection of covered work, and remove samples of installed materials for testing.
2. Do not cut or alter work performed under separate contract without the Architect's written permission.
1.2 QUALITY ASSURANCE
A. Perform all cutting and patching in strict accordance with pertinent requirements of the
Specifications and, in the event no such requirements are determined, in conformance with the Architect's written direction and with approval from City Project Manager.
1. Use skilled workforce to perform all cutting and patching work.
2. Use methods least likely to damage existing surfaces and materials to remain, while providing proper surfaces to receive installation of repair, patching, and/or new work.
B. Visual Quality:
1. Do not cut and patch work exposed to public view, and the exterior and/or interior of the building in a manner that will result in an unacceptable appearance as determined by the Architect.
2. Do not cut and patch work in a manner that will result in obvious appearance that cutting and patching work was done.
3. When cutting existing structural concrete, do not extend saw cuts beyond the corners of the required opening on either side of the opening. Should require concrete scanning prior to cutting existing structural concrete.
1.3 EXISTING CONSTRUCTION
A. Where cutting and patching of existing construction is required; prior to start of work, inform City of existing construction to be disturbed. City will determine if elements of existing construction contain asbestos. Do not proceed with work until after City has examined areas to be disturbed.
Refer to Exhibit A, Project Pre-Inspection for Possible Presence of Asbestos for additional information concerning the possible presence of materials containing asbestos.
1.4 SUBMITTALS
CUTTING AND PATCHING 01 35 00 - 2
A. Submit proposed cutting and patching procedures in writing for the following categories of work prior to proceeding with this work:
1. Cutting new openings in existing concrete floors.
B. Submittals shall comply with Section 01300.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Except as otherwise indicated in pertinent sections of these specifications, or as directed by the Architect, use materials which are identical to existing materials in workmanship, appearance, and performance.
B. If identical materials are not available, match existing as closely as possible, especially existing visual characteristics.
PART 3 - EXECUTION
3.1 INSPECTION
A. Before proceeding, inspect existing conditions, including elements subject to movement or damage during cutting, and patching.
B. After uncovering the work, inspect conditions affecting installation of new work.
C. If uncovered conditions are not as anticipated or if existing construction is not as indicated on the Drawings, immediately notify the City Project Manager and Architect for further instructions.
3.2 PREPARATION
A. Provide shoring, bracing, and support as required to maintain structured integrity of the project.
B. Take all necessary action required to protect adjacent existing surfaces from damage due to the work of this section.
C. Take all precautions necessary to protect existing surfaces and materials, new work, and the work of this section from damage due to adverse weather conditions.
D. Provide temporary support of work to cut and adjacent work to prevent failure or damage due to the work of this section.
E. Properly prepare substrate surfaces exposed during cutting as required to receive the work of this or other sections of these specifications in strict compliance with manufacturer's recommendations and these specifications.
3.3 EXECUTION
A. Perform all required cutting and patching as required or reasonably implied under pertinent sections of these specifications.
CUTTING AND PATCHING 01 35 00 - 3
B. Perform cutting and demolition by methods which will prevent damage to other portions of the work and will provide proper finished installation complying with the specified tolerances and finishes.
3.4 PERFORMANCE
A. Execute cutting and demolition by methods which will prevent damage to other work, and will provide proper surfaces to receive installation of repairs and new work. Saw-cut and otherwise isolate areas to be demolished.
B. Repair or otherwise rebuild and/or construct all surfaces affected by cutting and demolition.
Execute fitting and adjustment of products to provide totally finished installation to comply with tolerances, finishes, and profiles of adjacent surfaces, whether new or existing.
C. Restore work which has been cut or exposed by demolition; install new construction in compliance with specifications for type of new work to be done or as required to match existing adjacent surfaces. In no case shall any exposed existing surface be left in a raw, marred, or unfinished surface.
D. Refinish entire surfaces as necessary to provide an even finish.
1. Continuous Surfaces: To nearest intersections.
2. Assembly: Entire refinishing.
3. Paint to match.
END OF SECTION 01 35 00
SPECIAL PROJECT PROCEDURES 01 35 13 - 1
SECTION 01 35 13
SPECIAL PROJECT PROCEDURES
A. Section Includes:
1. Remodel Work scheduling.
2. Construction sequence scheduling.
B. Related Sections:
1. Section 01500 - Temporary Facilities and Controls.
1.2 SYSTEM DESCRIPTION
A. An essential condition of this Contract shall be the scheduling and conduct of all phases of construction operations in such a manner that the City's operations and use of the existing buildings shall be uninterrupted at all times, except for such limited interruption as is required and approved by the City.
B. Contractor shall repair at his own expense all damage done to City's property, unknown utilities and adjoining public property as a result of Contractor's construction activities.
1. 3 PROJECT/SITE CONDITIONS
A. Access and use of site:
1. Contractor shall use the designated site access for construction offices and material storage in such a manner that access to existing buildings remain accessible at all times for use.
2. Confine operations to as limited a use of the existing building as possible. A route of access to and from the work for employees shall be agreed upon and it shall be the Contractor's responsibility to see that the agreed route is maintained in order to prevent unwarranted or unnecessary traffic through the existing buildings or site.
B. City notice and approval:
1. All arrangements and scheduling in connection with the work of this Contract shall be made with and subject to the approval of the Architect and the City.
2. All work under this Contract which will require interruption of service of the existing building shall be scheduled to suit the need and convenience of the City's operation, and arrangements shall be made with the City and the Architect at least eight (8) working days in advance of the start of such work.
Not Used
SPECIAL PROJECT PROCEDURES 01 35 13 - 2
3.1 CLEAN-UP
A. All areas within existing facilities, which are not within enclosed areas to be constructed used for access to work areas shall be completely cleaned of all debris and made "broom-clean" at the end of each day's work.
B. Dust, which permeates areas of existing facilities because of improperly constructed dust-proof barriers, shall be the responsibility of the Contractor. The Contractor shall employ the services of a professional cleaning company to clean any area outside of the designated construction dust barriers that are contaminated by Contractor’s operations. Completely clean all such areas to the satisfaction of the City at no additional cost.
END OF SECTION 01 35 13
REGULATORY REQUIRMENTS 01 41 00 - 1
SECTION 01 41 00
REGULATORY REQUIREMENTS
1.1 RELATED DOCUMENTS:
A. Drawings and general provisions of the Contract, including General Conditions and other Division
1 - Specification sections, apply to work of this section.
1.2 SUMMARY:
A. Section Includes:
1. General administrative requirements and procedures and related applicable codes.
1.3 APPROVAL AND RECOMMENDATION AGENCIES:
A. Per the jurisdiction that the project is located within.
1.4 CODES:
A. All Contractors shall comply with all applicable codes, ordinances and regulations in effect at the time of bid openings.
B. In case of a conflict between references applicable codes, the one having the more stringent requirements shall govern. Where governing codes indicate that the drawings or specifications do not comply with the minimum requirements of the codes, the Contractor shall be responsible for providing an installation, which will comply with code requirements. Drawings and specifications shall be followed where they are superior to code requirements.
1.5 OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION (OSHA):
A. The Contractor shall have sole responsibility for compliance on the job site to all applicable portions of the Occupational Safety and Health Act. The Contractor is responsible for other regulatory requirements as they relate to occupational Health and Safety requirements. For example, NIOSH, ANSI, and MSA.
B. Protection of life, health and public welfare as it relates to the execution of the construction contract is the responsibility of the Contractor. The City’s Representative may, at their discretion, observe, inspect, or comment on plans, procedures, or actions employed at the project as they relate to safety of life, health or public welfare. If conditions are imposed by the City which interfere with, or imply actions detrimental to safety, written notice shall be returned to the City for action prior to affecting any unsafe conditions.
C. Contractors shall use OSHA Lock Out / Tag Out procedures when working with energized equipment.
END OF SECTION 01 41 00
SPECIFICATION SYSTEM 01 42 00 - 1
SECTION 01 42 00
SPECIFICATION SYSTEM
A. Work Included:
1. Specification system format.
2. Grammar (syntax) description.
1.2 DESCRIPTION
A. These specifications have been derived from automated specification systems, and include minor deviations from format and traditional writing forms. Such deviations must be recognized as a normal result of this production technique, and no other meaning will be implied or permitted.
B. Imperative language of the technical sections is directed to the Contractor. The term "provide" used repeatedly in the text is defined to mean..."furnish and install, complete, in place and ready for operation and use unless specifically indicated otherwise."
C. Specifications are of abbreviated, simplified or streamlined type and include incomplete sentences.
Omissions of work or phrases such as "the Contractor shall" "in conformity therewith," "shall be," "as noted on the Drawings", "A", "The", are intentional. Supply omitted words or phrases by inference in same manner as they are when "Note" occurs on Drawings. Supply words "on the Drawings" by inference when "as indicated" is used with sentences or phrases.
Not used
Not used
END OF SECTION 01 42 00
QUALITY CONTROL 01 45 00 - 1
SECTION 01 45 00
QUALITY CONTROL
PART 1 - GENERAL
1.1 SUPPLEMENTAL TESTING
If required, the following testing shall be performed at the expense of the contractor installing the material being tested:
A. Material Substitution: Any tests of basic material or fabrication equipment offered as a substitute for specified item on which a test may be required in order to prove its compliance with the specifications.
B. Mechanical/Electrical: Tests on mechanical and electrical systems required to insure their proper installation and operation.
C. Any test that fails shall be paid for by the installing contractor subject to the following conditions:
1. Quantity and nature of tests will be determined by the City.
2. All test shall be done in the presence of the City Project Manager or City representative.
3. Proof of noncompliance will make the installing contractor liable for any corrective action which the City feels is prudent including complete removal and replacement of defective material.
1.2
1.3
Nothing contained herein is intended to imply that the installing contractor does not have the right to have tests performed on any material at any time for his own information and job control so long as the City does not assume responsibility for costs or for giving them consideration when appraising quality of materials.
D. The City shall determine the type and number of tests to be performed on the project.
TEST REPORTS
Reports of all tests made by testing laboratories shall be distributed by the testing laboratory as follows:
1 copy - Contractor 1 copy - Applicable supplier or subcontractor 1 copy - City 1 copy - Architect Other copies - as directed
QUALITY CONTROL SYSTEM
A. General: The contractor shall establish a quality control system to perform sufficient inspection and tests of all items of work, including that of all subcontractors, to ensure conformance to the Contract Documents for materials, workmanship, construction, finish, functional performance and identification. This control shall be established for all construction except where the Contract Documents provide for specific compliance tests by testing laboratories or Consultants employed by the City.
The quality control system is the means by which the Contractor assures that construction complies with the requirements of the Contract Documents. Controls shall be adequate to cover all construction operations and should be keyed to the proposed construction schedule.
QUALITY CONTROL 01 45 00 - 2
B. The Contractor shall designate a quality control representative on staff to review the work to insure compliance with the contract documents by weekly jobsite visits for observation. The quality control representative shall review the work and make necessary corrections to bring the work into compliance prior to scheduling the Architect for the final punchlist review.
C. Records: The Contractor shall maintain correct records on an appropriate form for all inspections and tests performed, instruction received from the City and actions taken as a result of those instructions. These records shall include evidence that the required inspections or tests have been performed (including type and number of inspections or tests, nature of defects, causes for rejection, etc.) proposed or directed remedial action, and corrective action taken. The Contractor shall document inspections and tests as required by each Section of the Specifications.
1.4 INDEPENDENT TESTING AGENCY SERVICES
A. The City will employ and pay for the services of an independent Testing Agency to perform the
Inspections, special inspections, tests and other services when required by sections of the specification. Services shall be performed in accordance with requirements of governing authorities and with specified standards.
1. Contractor shall cooperate with Testing Agency personnel and shall furnish tools, sample of materials, design mixes, equipment and assistance as requested.
2. Contractor shall provide and maintain, for the sole use of the Testing Agency, adequate facilities for the safe storage and proper curing of concrete testing cylinders on the project site for the first 24 hours after casting as required by ASTM C 31, Method of Making and Curing Concrete Test Specimens in the field.
3. Contractor shall notify Testing Agency sufficiently in advance of operations to allow for completion of initial tests and proper assignment of inspection personnel.
4. Contractor shall notify the testing agency sufficiently in advance of cancellation of required testing operations. The Contractor shall assume responsibility for costs incurred due to the failure to provide such notice.
END OF SECTION 01 45 00
TEMPORARY FACILITIES 01 50 00 - 1
SECTION 01 50 00
TEMPORARY FACILITIES
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other
Division 1 Specification sections, apply to work of this section.
1.2 DESCRIPTION OF REQUIREMENTS
A. This section of the General Requirements outlines the basic requirements for temporary services, utilities, and facilities which will indirectly enable adequate construction progress and processes, and will…