BLANK SHEET

Price Schedule

Project: SAHNC Gates and Fence Repair and Repaint

Solicitation No.: 140P2123Q0098

Work Item: Repair and Repaint Vehicle Gates and Fence Sections.

Cost Breakdown
QuantityDescriptionUnit PriceAmount
Removal and transport of Gates and Curved fence Sections.
2Removal of vehicle gates at the Lodge
2Removal of curved fence sections flanking the Lodge Gate
1Transport of gates and fence panels
Lodge Entry Gates
1Remove derelict gate closure components & repair hardware
2Strip paint and prepare surfaces
2Prime and paint ornamental iron of vehicle gates offsite
1Repair, Prepare and paint gate posts and components onsite
Lodge Entry Fence
1Repair ironwork of the fence panels flanking the Lodge Gate
2Strip paint and prepare iron surfaces for coating
2Prime an paint the fence panels offsite
Reinstallation and transport of the gates and fence components:
1Transport of vehicle gates and curved fence panels
2Install vehicle gates to fully operable condition
2Install of curved fence panel sections000000000000000000000000000000000000000000000000

TOTAL AMOUNT $0.00

EXAMPLE

ESTIMATE of COST - NATIONAL PARK SERVICE, HPTC

Park: Nasvhille National Cemetery By: Korpan/Grabinski

Project: Rehabilitate Masonry Boundary Walls Pkg. No.:

Contract No.: RFP No.:

Work Item:Detail #10Change Item No.:
LABOR
QuantityDescriptionDaysPrice/DayAmount
2demo full wall1.00$ 300.00$600.00
2form concrete footer1.00$ 300.00$600.00
2pour concrete footer0.40$ 300.00$240.00
2form concrete wall0.50$ 300.00$300.00
2pour concrete wall0.30$ 300.00$180.00
2form removal0.13$ 300.00$75.00
3construct face2.00$ 300.00$1,800.00
1miscellaneous0.50$ 300.00$150.00

Subtotal $3,945.00

Total $3,945.00

EQUIPMENT
QuantityDescriptionUnitPriceAmount
1Equipment and OperatorsLump$1,000.00$1,000.00
Subtotal$1,000.00
Sales Tax,5%$50.00
Total$1,050.00
MATERIALS
QuantityDescriptionUNITPriceAmount
10concretecu yd$150.00$1,500.00
$0.00
Subtotal$1,500.00
Sales Tax,5%$75.00
Total$1,575.00
ESTIMATE TOTALS & MARKUPS
Labor, Equipment and MaterialSub-Total$6,570.00

Estimate Sub-Total $6,570.00

TEI Overhead & Profit 20% $1,314.00

TOTAL AMOUNT (Lump Sum) $7,884.00