This is a pricing table attachment for a Financial Management/Payroll Services contract opportunity with the State of South Carolina. The document presents the cost structure for Acme FMS Company across three distinct phases: Implementation, Operations, and Turnover. The Implementation Phase consists of ten payment milestones occurring over three contract months, with fixed prices ranging from $500 to $2,000 per milestone, totaling $10,000. The Operations Phase spans five contract years with variable pricing per beneficiary receiving waiver services, ranging from $20.00 to $30.00 monthly, with estimated beneficiary counts increasing from 2,200 to 2,500 individuals, generating total operations costs of $3,273,000. The Turnover Phase includes two service components—Turnover Services and Post-Turnover Services—each valued at $1,000, for a combined total of $2,000.
The Total Cost of Ownership for the contract is $3,285,000, comprising $1,635,000 for the three base years and $1,650,000 across two option years ($750,000 for the first option year and $900,000 for the second option year). The Implementation Phase pricing remains constant with no charges for option years, while Operations Phase pricing increases to $750,000 and $900,000 in the respective option years, reflecting anticipated growth in beneficiary populations and adjusted per-beneficiary rates. The Turnover Phase costs are applied only to the base contract period with no associated option year expenses.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment #3.docx | DOCX document | |
| Amendment #1.docx | DOCX document | |
| Notice of Cancellation.doc | DOC document | |
| Solicitation Document.docx | DOCX document | |
| Amendment #2.docx | DOCX document | |
| Attachment 2.pdf | ||
| Award Extension #1.docx | DOCX document | |
| Attachment 5.xls | XLS spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
List of Tables
| List Of Pricing Tables | |
| Table | Title |
| Pricing Table A | Implementation Phase Price |
| Pricing Table B | Operations Phase Price |
| Pricing Table C | Turnover Phase Price |
| Pricing Table D | Total Cost of Ownership |
| Enter Contractor Name Here ---> | Acme FMS Company |
Implementation Phase Price Operations Phase Price Turnover Phase Price Total Cost of Ownership
A- Implementation
| Pricing Table A - Implementation Phase Price | |||
| Contractor: | Acme FMS Company | ||
| Payment Milestone No. | Milestone Name | Contract Month of Milestone | Fixed Price |
| 1 | A | 1 | $ 500 |
| 2 | B | 1 | $ 500 |
| 3 | C | 2 | $ 1,000 |
| 4 | D | 2 | $ 1,000 |
| 5 | E | 2 | $ 1,500 |
| 6 | F | 2 | $ 1,500 |
| 7 | G | 3 | $ 2,000 |
| 8 | H | 3 | $ 500 |
| 9 | I | 3 | $ 500 |
| 10 | J | 3 | $ 1,000 |
| Remove lines as necessary | |||
| Total Fixed Price for Implementation Phase | $ 10,000 |
B - Operations
| Pricing Table B - Operations Phase Price | ||||
| Contractor: | Acme FMS Company | |||
| Contract Year | Price Per Beneficiary Receiving Wavier Services per Month | Estimated Monthly Beneficiaries receiving Wavier Services | Estimated Price per Month | Estimated Price per Year |
| 1 | $ 25.00 | 2,200 | $ 55,000.00 | $ 495,000.00 |
| 2 | $ 20.00 | 2,300 | $ 46,000.00 | $ 552,000.00 |
| 3 | $ 20.00 | 2,400 | $ 48,000.00 | $ 576,000.00 |
| 4 | $ 25.00 | 2,500 | $ 62,500.00 | $ 750,000.00 |
| 5 | $ 30.00 | 2,500 | $ 75,000.00 | $ 900,000.00 |
| Total Operations Price used in Evaluation | $ 3,273,000.00 |
C - Turnover
| Pricing Table C - Turnover Phase Price | M | ||
| Contractor: | Acme FMS Company | D | |
| $ Amount | |||
| Turnover Services | $ 1,000.00 | ||
| Post Turnover Services | $ 1,000.00 | ||
| Total Turnover Phase Price | $ 2,000.00 |
D - TCO
| Pricing Table D - Total Cost of Ownership | |||
| Contractor: | Acme FMS Company | ||
| Pricing Table | Total Price for 3 Base Years | Price for 1st Option Year | Price for 2nd Option Year |
| A - Implementation Phase | $ 10,000.00 | $ - 0 | $ - 0 |
| B - Operations Phase | $ 1,623,000.00 | $ 750,000.00 | $ 900,000.00 |
| C - Turnover Phase | $ 2,000.00 | $ - 0 | $ - 0 |
| Total Price of the Contract | $ 1,635,000.00 | $ 750,000.00 | $ 900,000.00 |
| Total Cost of Ownership | $ 3,285,000.00 |