This document provides installation quality assurance procedures for the rehabilitation of sewage lagoons under solicitation number 12639522R0030 from the Department of Agriculture Animal and Plant Health Inspection Service Marketing and Regulatory Programs Business Services. The project involves installing geomembrane lining systems, with procedures covering material delivery, earthwork preparation, panel placement, trial welds, field seaming, destructive and non-destructive testing, defect repair, and as-built drawings. The geomembrane products must be installed according to industry standards and the customer's specifications, with quality assurance checks performed on the seaming process, seam strengths, and completed liner installation through vacuum, air pressure, and spark testing to verify no leaks are present.

View the file

Other files for this federal contract opportunity

Other files attached to Sewage Lagoon Rehabilitation, newest first.
File Type Posted
Geotechnical Soil Boring Logs 8-1-18.pdf PDF
Questions and answers.pdf PDF
Geotech survey 2015.pdf PDF
Partial plot plan.pdf PDF
05092022 Site Visit Sign In Sheet.pdf PDF
Amendment 0001.pdf PDF
Contractor questions_responses 04292022.pdf PDF
Evaporation ponds general permit.pdf PDF
Attachment 2 Final SOW.doc DOC document
12639522R0030.pdf PDF
Attachment 4 Sewer Lagoon Edge Anchor Detail.jpg JPG image
Attachment 6 NEPA Category Exclusion Determination.doc DOC document
Attachment 5 NEPA Checklist.doc DOC document
Attachment 7 Drawings_final.pdf PDF
Attachment 1 Federal construction wage determination.pdf PDF
Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GEOMEMBRANE PRODUCTS

INSTALLATION QUALITY ASSURANCE MANUAL

Attachment 3, 12639522R0030

Contents

1.0 INTRODUCTION

2.0 STANDARD TEST METHODS

3.0 ADDITIONAL REFERENCES

4.0 MATERIAL DELIVERY

5.0 EARTHWORK

6.0 PANEL PLACEMENT

7.0 TRIAL WELDS

8.0 GEOMEMBRANE FIELD SEAMING

9.0 FIELD DESTRUCTIVE TESTING

10.0 NON-DESTRUCTIVE TESTING

11.0 DEFECTS & REPAIRS

12.0 REPAIR PROCEDURES

13.0 AS-BUILT DRAWINGS

APPENDIX A

APPENDIX B

APPENDIX C

APPENDIX D

APPENDIX E

APPENDIX F

APPENDIX G

APPENDIX H

APPENDIX I

APPENDIX J

APPENDIX K

Geomembrane Products

Geomembrane Products

1.0 INTRODUCTION

This manual provides an overview of the GSE Installation Quality Assurance procedures consistent with industry accepted practices to ensure that the geomembrane products installed will perform for its intended purpose. In addition, all installation work will be performed in strict accordance per the customer’s specifications. Please read the procedures below completely before you begin. If you need further clarification, contact GSE Engineering

Support Staff for assistance. Remember safety first and use safe practices always on every project.

2.0 STANDARD TEST METHODS

ASTM D 6392: Standard Test Methods For Determining The Integrity Of Non-Reinforced Geomembrane

Seams Produced Using Thermo Fusion Methods

ASTM D 5820: Standard Practice For Pressurized Air Channel Evaluation of Dual Seamed Geomembranes

ASTM D 5641: Standard Practice For Geomembrane Seam Evaluation By Vacuum Chamber

ASTM D 6497: Standard Guide For Mechanical Attachment of Geomembrane to Penetrations or Structures

ASTM D 7007 - 09 “Standard Practices for Electrical Methods for Locating Leaks in Geomembranes Covered with

Water or Earth Materials”

ASTM D 7240: Standard Practice for Leak Location using Geomembranes with an Insulating Layer in

Intimate Contact with a Conductive Layer via Electrical Capacitance Technique (Conductive

Geomembrane Spark Test)

GRI Standard GM13: Test Methods, Test Properties, and Testing Frequency for High Density Polyethylene (HDPE)

Smooth and Textured Geomembranes

GRI Standard GM14: Selecting Variable Intervals for Taking Geomembrane Destructive Seam Samples Using the

Method of Attributes

GRI Standard GM 17: Test Properties, Testing Frequency, and Recommended Warranty for Linear Low Density

Polyethylene (LLDPE) Smooth and Textured Geomembranes

GRI Standard GM19: Standard Specification for Seam Strength and Related Properties of Thermally Bonded

Polyolefin Geomembranes

3.0 ADDITIONAL REFERENCES

GSI White Paper 26: Need for Justification of Quality Management Systems for Successful Geosynthetic

Performance

GRI GM14: Standard Guide for Selecting Variable Intervals for Taking Geomembrane Destructive Seam Samples Using the Method of Attributes

GRI GM20: Standard Guide for Selecting Variable Intervals for Taking Geomembrane Destructive Seam Samples Using Control Charts

Liner Integrity Survey: General Guide published by TRI Environmental

4.0 MATERIAL DELIVERY

A. Upon arrival on site, the QA personnel will inventory all materials on the job site.

B. Roll numbers of geomembrane will be logged on the Inventory Check List (Appendix A) and crossreferenced with the Bill of Lading for materials supplied by GSE.

GSEworld.com Installation Quality Assurance Manual

C. Copies of the Inventory Check List and signed Bill of Lading should be sent to the appropriate parties (CQA

Management and Engineer of Record) while the QA personnel retains the original copies.

D. Any visible damage to roll materials should be noted on the roll and Inventory Check List.

5.0 EARTHWORK

A. The general contractor is responsible for preparing and maintaining the subgrade. The subgrade should be prepared and maintained per the job specifications.

B. The site manager shall be responsible for assuring that the subgrade surface has been properly prepared for deployment of geosynthetics. After each day’s deployment the Subgrade Surface Acceptance form

(Appendix B) will be signed by all parties.

6.0 PANEL PLACEMENT

A. Each panel will be assigned a number as described below.

1. When there is one layer, panels may be designated with only a number, i.e...1, 2, 3, 4 etc.

2. When two or more layers are required, use a letter and number, i.e

Primary Liner P1, P2, P3, P4 etc...

Secondary Liner S1, S2, S3, S4 etc...

Tertiary Liner T1, T2, T3, T4 etc...

B. This numbering system should be used whenever possible. Agreement to a panel numbering system should be made at the pre-construction meeting. However, it is essential that the installer, the owner representative and third party QA inspector agree.

C. Panel numbers shall be written in large block letters in the center of each deployed panel. The roll number, date of deployment and length (gross) should be noted below the panel number. All notes should be made, so that they are easily visible from a distance. On long panels it is beneficial to write information on both ends.

Spray painting is appropriate for roll labeling.

D. Panel numbers shall be logged on the Panel Placement Log (Appendix C) along with the roll number and other information neccessary to complete the form.

E. If there is a partial roll left after deployment, it is important to write the last four digits of the roll number in several locations on the roll along with the estimated length for future identification.

F. Deployment of geomembrane panels shall be performed in a manner that will comply with the following guidelines:

1. Unroll geomembrane using methods that will not damage geomembrane and will protect underlying surface from damage. GSE Leak Location should be installed with Conductive layer facing down.

2. Place temporary ballast, such as sangbags, on geomembrane that will not damage the geomembrane and to prevent wind uplift.

3. Personnel walking on geomembrane shall not engage in activities or wear shoes that could damage it.

Smoking is not permitted on the geomembrane.

4. Do not allow heavy vehicular traffic directly on geomembrane. Rubber tired and tracked ATV’s and equipment are acceptable if contact pressure is less than 8 psi.

a. Protect geomembrane in areas of heavy traffic by placing protective cover over the geomembrane.

b. Prior to driving on any geomembrane layer, please check for sharp edges, embedded rocks, or other foreign objects that may protrude in the tires and tracks.

c. Path driven on geomembranes shall be as straight as possible with no sharp turns, sudden stops or quick starts.

d. Areas where driving occurs shall be continuously and thoroughly inspected throughout the deployment process by the contractor and the third party CQA.

G. In the past, it has been a common practice to turn to leak surveys once the project has been constructed and the barrier system performance has been found unsatisfactory. A current state-of-the-practice geosynthetic installation would plan ahead for both post-installation/exposed, pre-cover soil placement survey (commonly done utilizing ASTM D 7240 or ASTM D 7002) AND a post soil cover survey (commonly done utilizing ASTM D

7007). Proper execution of these surveys and protocols are best applied before installation. State-of-the-art welding techniques, proper isolation of sections for testing, and other details can be simply and inexpensively addressed during installation, but may be expensive and complicated to recreate if a leak is discovered after the facility has been placed into service. See the reference LINER INTEGRITY SURVEY: GENERAL GUIDE published by TRI Environmental.

7.0 TRIAL WELDS

A. Seaming apparatus shall be allowed to warm up a minimum of 10 minutes before performing trial welds.

B. Each seaming apparatus along with a welding technician will pass a trial weld prior to use. Trial welds to be performed in the morning and afternoon, as a minimum, as well as whenever there is a power shutdown.

C. Fusion or wedge welds will always be performed or conducted on samples at least 6.0 ft long. Extrusion welds will be done on samples at least 3.0 ft long.

Note: Always perform trial welds in the same conditions that exist on the job. Run the trial welds on the ground, not the installed liner. Do not use a wind break unless you are using one on the job.

D. Operating temperatures should be monitored while welding. The welding technician should verify that the equipment is capable of maintaining temperature while welding.

E. Sampling Procedure

1. Cut five 1.0 in wide specimens from the trial weld sample. Specimens will always be cut using a 1.0 in die cutter, so the peel values may be used for qualitative analysis.

2. When cutting coupons from the trial weld samples, the inside and outside tracks on the coupon should be identified to assist in troubleshooting problems in case the weld fails. The outside track will be defined as the track, which would be peeled if pulling the overlap exposed in a typical installation, or the seam that is closest to the edge of the top sheet. The inside track is the seam closest to the edge of the bottom sheet.

F. Cutter

1. Only cut one sample at a time to avoid damaging the die cutter.

2. Samples should be free of sand and grit prior to cutting sample.

3. Inspect the die edge weekly for nicks, dents or signs of dullness. Dullness of the cutting edge may damage the units.

4. Remove die when edge has been dulled and lightly reshape it with a medium hand file. When wear is excessive return it for a replacement die.

5. When the cutting board becomes deeply scored and/or interferes with coupon cutting it should be replaced.

6. To adjust the depth of the die cut into the cutting board, after replacing the cutting board or sharpening the die, 0.015 in washer shims can be added or removed between the cutting ram and the ram extension.

Only add shims when cutting is difficult due to lack of depth of cut.

G. Trial Weld Testing

1. Allow coupons to cool prior to testing. Avoid separating the coupons while hot as failure of the sheet may be initiated and false readings indicated.

2. In extreme heat the coupons may need to be cooled, using water or an insulated cooler prior to peel testing. Lab conditions specify 70 degrees (plus or minus 4 degrees) Fahrenheit. Coupon temperatures greater than 70 degrees may result in lowered strengths.

3. Visually inspect the coupons for squeeze-out, footprint, pressure and general appearance.

4. Each of the five coupons will be tested in peel on the field tensiometer at a separation rate of 2 in per minute (for HDPE). Shear tests, in addition to the peel tests, will be performed.

H. Pass/Fail Criteria

1. Criteria for passing trial welds will be as follows:

a. Seam must exhibit film tear bond (FTB). Trial welds should have no incursion into the weld.

b. Peel and shear values shall meet or exceed the values as listed in Appendix D, Table 1 for HDPE smooth or textured sheet (@ 2 in/min).

c. Peel and shear values shall meet or exceed the values as listed in Appendix D, Table 2 for LLDPE smooth or textured sheet (@ 20 in/min).

d. Both tracks of fusion welded samples must pass for the trial weld to be considered acceptable. If any of the five coupons fail due to seam incursion (no FTB) or low strength values, the trial weld must be performed again.

e. The QA personnel will give approval to proceed with welding after observing and recording all trial welds.

2. All trial weld data will be logged on the Trial Weld Log (Appendix E).

3. When logging fusion welded peel values on the Trial Weld Log indicate the values. for the outside track first, followed by the inside track.

4. Speed and temperature settings will be recorded for each machine trial weld as appropriate.

8.0 GEOMEMBRANE FIELD SEAMING

A. The seam number takes the identity of the panels on each side. The seam between panels 1 & 2 becomes seam 1/2.

B. Welding technicians will record their initials, machine number, date and time at the start of every seam and on the Seam Log (Appendix F). The technician should also periodically mark temperatures along the seam and at the end of the seam.

C. Approved processes for field seaming and repairing are fusion welding and extrusion welding. All welding equipment shall have accurate temperature monitoring devices installed and working to ensure proper measurement.

D. Fusion welding shall be used for seaming panels together and is not used for patching or detail work.

The site manager shall verify that:

1. The equipment used is functioning properly.

2. All work is performed on clean surfaces and done in a professional manner. No seaming will be performed in adverse weather conditions. (GRI Test Method GM9: Standard Practice for Cold Weather Seaming of

Geomembranes

E. Extrusion welding shall be used primarily for repairs, patching and special detail fabricating and may be used for seaming. The site manager shall verify that:

1. Equipment used is functioning properly.

2. Welding personnel are purging the extrusion welders of heat degraded extrudate prior to actual use.

3. All work is performed on clean surfaces and done in a professional manner. No seaming will be performed in adverse weather conditions.

F. For seam preparation, the welding technician shall verify that:

1. Prior to seaming, the seaming area is free of moisture, dust, dirt, sand or debris of any nature.

2. The seam is overlapped properly for fusion welding.

3. The seam is overlapped or extended beyond damaged areas at least 4.0 in when extrusion welding.

4. The seam is properly heat tacked and abraded prior to extrusion welding.

5. Seams are welded with fewest number of unmatched wrinkles or ”fishmouths”.

G. No seaming will be performed in ambient air temperatures or adverse weather conditions that would jeopardize the integrity of the liner installation.

9.0 FIELD DESTRUCTIVE TESTING

The process and protocol of obtaining destructive samples is damaging to the geosynthetic systems, and even when done properly, it may result in a geosynthetic system that is weaker and less effective. Clearly destructive samples are necessary; they are a key step in verifying the effectiveness of the welding process. However the frequency of sampling should reward “good welding” and penalize “poor welding.” Of more importance is the location of the destructive samples. Everything that can be done to remove destructive sample locations from within the geosynthetic system should be done: taking samples from runouts, anchor trenches, and practice pads.

Within the body of the installation, sample locations should be removed from critical areas: the toe of sloped areas, near panel connections, adjacent to penetrations, etc. Ideally the destructive samples will be taken at as low a frequency as possible, within flat areas of the installation where the impact of a hole in the liner can be minimized.

A. Destructive seam tests shall be performed to evaluate bonded seam strength. The frequency of sample removal shall be one sample per 500 ft of seam, unless site specifications differ. Location of the destructive samples will be selected and marked by the QA technician or third party QA inspector. Field testing should take place as soon as possible after seam is completed.

B. Samples should be labeled in numerical order, i.e. DS-1, DS-2 etc....This should carry through any layer and/or multiple ponds; do not start numbering from 1 again. The size of samples and distribution should be approximately 12 in x 39 in (Size may vary depending on job requirements) and distributed as follows:

1. 12 in x 12 in piece given to QA technician for field testing.

2. 12 in x 12 in piece sent to the GSE’s corporate headquarters for testing, if required.

3. 12 in x 12 in piece given to third party for independent testing or to archive.

NOTE: All samples will be labeled showing test number, seam number, machine number, job number, date welded and welding tech number.

C. The sample given to the QA technician in the field shall have ten coupons cut and be tested with a tensiometer adjusted to a pull rate as shown below. The strength of four out of five specimens should meet or exceed the values below, and the fifth specimen must meet or exceed 80% of the value below.

1. Seam must exhibit film tear bond (FTB). Welds should have < 25% incursion into the weld.

2. Peel and shear values shall meet or exceed the values as listed in Appendix D, Table 1 for HDPE smooth or textured sheet (@ 2 in/min).

3. Peel and shear values shall meet or exceed the values as listed in Appendix D, Table 2 for LLDPE smooth or textured sheet (@ 20 in/min).

D. All weld destructive test data will be logged on the Destructive Test Log (Appendix G).

E. When logging fusion welded peel values on the Destructive Test Log, indicate the values for the outside track first, followed by the inside track.

F. Test results will be noted in the Destructive Test Log as Pass (P) or Fail (F).

G. If a test fails, additional samples will be cut, approximately 10 ft on each side of the failed test, and retested.

These will be labeled A (After) & B (Before). This procedure will repeat itself until a sample passes. Then the area of failed seam between the two tests that pass will be capped or reconstructed.

10.0 NON-DESTRUCTIVE TESTING

A. All seams shall be non-destructively tested over their full length using an air pressure or vacuum test. The purpose of this test is to check the continuity of the seam.

B. For air pressure testing, the following procedures are applicable to those seams welded with a double seam fusion welder.

1. The equipment used shall consist of an air tank or pump capable of producing a minimum 35 psi and a sharp needle with a pressure gauge attached to insert into the air chamber.

2. Seal both ends of the seam by heating and squeezing them together. Insert the needle with the gauge into the air channel. Pressurize the air channel to 30 psi. Note time test starts and wait a minimum of 5 minutes to check. If pressure after five minutes has dropped less than 2 psi then the test is successful (Thickness of material may cause variance).

3. Cut opposite seam end and listen for pressure release to verify full seam has been tested.

4. If the test fails, follow these procedures.

a. While channel is under pressure, walk the length of the seam listening for a leak.

b. While channel is under pressure, apply a soapy solution to the seam edge and look for bubbles formed by air escaping.

c. Re-test the seam in smaller increments until the leak is found.

5. Once the leak is found using one of the procedures above, cut out the area and retest the portions of the seams between the leak areas per 4a to 4b above. Continue this procedure until all sections of the seam pass the pressure test.

6. Repair the leak with a patch and vacuum test.

C. For vacuum testing, the following procedures are applicable to those seams welded with an extrusion welder.

1. The equipment used shall consist of a vacuum pumping device, a vacuum box and a foaming agent in solution.

2. Wet a section with the foaming agent, place vacuum box over wetted area. Evacuate air from the vacuum box to a pressure suitable to affect a seal between the box and geomembrane. Observe the seam through the viewing window for the presence of soap bubbles emitting from the seam.

3. If no bubbles are observed, move box to the next area for testing. If bubbles are observed, mark the area of the leak for repair per section 11.0 and re-test per section 9.0.

NOTE: If vacuum testing fusion welded seams, the overlap flap must be cut off to perform the tests

4. All non-destructive tests will be noted in the Non-Destructive Logs (Appendixes H-I).

D. For spark testing GSE Leak Location geomembranes, ASTM D 7240 will be the procedure, unless otherwise instructed by the engineer client.

11.0 DEFECTS & REPAIRS

A. All seams and non-seam areas of the geomembrane lining system shall be examined for defects.

B. Identification of the defect should be made using the following procedures:

1. For any defect in the seam or sheet that is an actual breach (hole) in the liner, installation personnel shall circle the defect and mark with the letter P along side the circle. The letter P indicates a patch is required.

2. For any defect that is not an actual hole, installation personnel shall circle the defect indicating that the repair method may be only an extruded bead and that a patch is not required.

3. Each suspect area that has been identified as repair shall be repaired in accordance with section 11.0 and in the non-destructively testing per section 9.0. After all work is completed, the site manager will conduct a final walk-through to confirm all repairs have been completed and debris removed. Only after this final evaluation by the site manager, the owner, and the agent shall any material be placed over the installed liner.

12.0 REPAIR PROCEDURES

A. Any portion of the geomembrane lining system exhibiting a defect that has been marked for repair may be repaired with any one or combination of the following procedures:

1. Patching - used to repair holes, tears, undispersed raw materials in the sheet.

2. Grind and Reweld - used to repair small sections of extrusion welded seams.

3. Spot Welding - Used to repair small minor, localized flaws.

4. Flap Welding - Used to extrusion weld the flap of a fusion weld in lieu of a full cap.

5. Capping - Used to repair failed seams.

B. The following conditions shall apply to the above methods:

1. Surfaces of the geomembrane which are to be repaired shall be prepared according to this section.

2. All surfaces must be clean and dry at the time of the repair.

3. All seaming equipment used in repairing procedures shall be qualified.

4. All patches and caps shall extend at least 4 in beyond the edge of the defect, and all patches must have rounded corners.

5. All cut out holes in liner must have rounded corners of 3.0 in minimum radius.

C. Patches should be labeled in numerical order, i.e. RP-1, RP-2, etc... This should carry through any layer and/or multiple ponds, and do not start with the number 1 again.

13.0 AS-BUILT DRAWINGS

The installer shall provide the following:

A. As-built drawings will be provided at the completion of the project.

B. As-built drawings will include geomembrane panels and panel numbers with the last four digits of the roll number.

C. Panel numbers and the full roll numbers will correspond with the Panel Placement Log(Appendix C).

D. All destructive testing and repair locations will be placed on the as-built drawings.

In ve nt o ry C he ck

L is t

P ro je c t:

S it e M a n a g e r:

D a te ro je c t

Q A

T e c h n ic ia n

P a g e o f

M a te ri a l

R o ll

U se d M a te ri a l

R o ll

U se d M a te ri a l

R o ll

U se d M a te ri a l

R o ll

U se d

APPENDIX A

S ub g ra d e

S ur fa ce

A cc ep ta nc e

D a te

P ro je c t:

S it e M a n a g e r:

P ro je c t

L o c a ti o n a rt ia l:

F in a l:

T h is d o c u m e n t o n ly a p p li e s to t h e a c c e p ta b il it y o f su rf a c e c o n d it io n s fo r in st a ll a ti o n o f g e o sy n th e ti c p ro d u c ts

G

S E d o e s n o t a c c e p t re sp o n si b il it y fo r c o m p a c ti o n e le v a ti o n o r m o is tu re c o n te n t, n o r fo r th e s u rf a c e m a in te n a n c e d u ri n g d e p lo y m e n t.

S tr u c tu ra l in te g ri ty o f th e su b g ra d e a n d m a in te n a n c e o f th e se c o n d it io n s a re t h e r e sp o n si b il it y o f th e o w n e r o r e a rt h w o rk c o n tr a c to r.

G o sy n th e ti c I n st a ll e r o r

O w n e r

C o n tr a c to r:

A c c e p ta n c e N u m b e r:

A re a A c c e p te d s.

f

T o ta l A re a A c c e p te d t o d a te s.

f.

APPENDIX B

APPENDIX C

Panel Placement Log

Project Name: _____________________________________________________________________________________________ Location: ____________________________________ Site Supervisor: _______________________________________________ Job Number: _________________________________ Type of Materials: _____________________________________________ Q.A. Tech.: ___________________________________ Sheet Thickness: ______________________________________________

Panel Number

Roll Number

Deployment Date

Width (Feet)

Length (Feet)

Squar Feet Squar Feet (Cumulative)

A/T

A/T

APPENDIX D

TABLE 1. HDPE Seam Strength Properties

80 60

120 91

160 121

200 151

TABLE 1. LLDPE Seam Strength Properties

APPENDIX E

P ss il

S h e a r p p i S h e a r p p i S h e a r p p i S h e a r p p i S h e a r p p i P e e l p p i P e e l p p i P e e l p p i P e e l p p i P e e l p p i S p e d h e a t

W e d g

M ss

W e ld e r

T y p e A m b ie n t Te m p

Te c h n ic ia n s

ID

N u m b e r

T im e o f T ri a l

D a te o f

T ri a l

T ri a l

N o

Tr ia l W el d L o g

P ro je c t

N a m e e S u p e rv is o r:

u si o n p p i)

E x tr u si o n p p i)

L o c a ti o n

T y p e o f M a te ri a l:

P e e l

M in P e e l_

J o b N u m b e r:

h e e t

T h ic k n e ss

S h e e r

M in S h e e r_

Q .A

APPENDIX F

Seam Log

Project Name: _____________________________________________________________________________________________ Location: ____________________________________ Site Supervisor: _______________________________________________ Job Number: _________________________________ Type of Materials: _____________________________________________

Q.A. Tech.: ___________________________________ Sheet Thickness: ______________________________________________

Seam Number

Time of Weld Date of Weld Type of Weld Length of Seam

Machine Num-ber

Technician ID Number

APPENDIX G

P ss il

S h e a r p p i S h e a r p p i S h e a r p p i S h e a r p p i S h e a r p p i P e e l p p i P e e l p p i P e e l p p i P e e l p p i P e e l p p i Te st g q u e n c y

L o c a ti o n

M a c h p e

N o

Te c h n ic ia n s

ID

N u m b e r

S e m

N m b e r

D te

W ld e d

S a m le

N m b e r

D es tr uc ti ve

T es t Lo g

P ro je c t

N a m e e S u p e rv is o r:

si o n p i)

E x tr u si o n p p i)

L o c a ti o n p e o f M a te ri a l:

P e e l

M in P e e l_

J o b N u m b e r:

h e e t

T h ic k n e ss

S h e e r

M in S h e e r_

Q .A

APPENDIX H

Repair Log - Vacuum Test

Project Name: _____________________________________________________________________________________________ Location: ____________________________________ Site Supervisor: _______________________________________________ Job Number: _________________________________ Type of Materials: _____________________________________________ Q.A. Tech.: ___________________________________ Sheet Thickness: ______________________________________________

Repair Number

Weld Date

Machine Number

Tech

ID

Location Test Date

Tech

ID

Pass/Fail

APPENDIX I

Non-Destructive Log - Air Test

Project Name: _____________________________________________________________________________________________ Location: ____________________________________ Site Supervisor: _______________________________________________ Job Number: _________________________________ Type of Materials: _____________________________________________ Q.A. Tech.: ___________________________________ Sheet Thickness: ______________________________________________

Seam Number

Test Date

Technician ID Number

Air Pressure Test psi start psi finish

Test Result (P or F)

Location

APPENDIX J

Non-Destructive Log - Air Test/Leak Location Liner Seam Isolation Test

Project Name: _____________________________________________________________________________________________ Location: ____________________________________ Site Supervisor: _______________________________________________ Job Number: _________________________________ Type of Materials: _____________________________________________ Q.A. Tech.: ___________________________________ Sheet Thickness: ______________________________________________

Seam

Number

Test

Date

Technician ID Number

Air Pressure Test psi start psi finish Test Result

(P or F)

Seam Isolation Test (M ohms)

S1 S2

Test Result

(P or F)

APPENDIX K

Liner Integrity Survey Log

Project Name: _____________________________________________________________________________________________ Location: ____________________________________ Site Supervisor: _______________________________________________ Job Number: _________________________________ Type of Materials: _____________________________________________ Q.A. Tech.: ___________________________________ Sheet Thickness: ______________________________________________ ASTM Liner Integrity Protocol Used: ___________________________________________________________________________

Panel Number

Date of Test

Time of Test

Technician ID Number

Spark Tester

ID

Pass/Fail Location of Repairs

GSE is a leading manufacturer and marketer of geosynthetic lining products and services. We’ve built a reputation of reliability through our dedication to providing consistency of product, price and protection to our global customers.

Our commitment to innovation, our focus on quality and our industry expertise allow us the flexibility to collaborate with our clients to develop a custom, purpose-fit solution.

For more information on this product and others, please visit us at GSEworld.com, call 800.435.2008 or contact your local sales office.

REV14MAY2015