Attachment 3 E1A Target schedule.pdf
PDF 195 KB Posted
- Attached to
- ARCF LAR E1A Mitigation Federal contract opportunity
- Solicitation number
- W9123822Q0032
About this file
This target project schedule outlines the establishment period and tasks required for the ARCF LAR E1A Mitigation federal contract opportunity issued by the Department of the Army Corps of Engineers Engineering District Sacramento. The schedule includes six establishment periods over five years, breaking down 25 contract line items (CLINs) into 165 sub-CLIN tasks with start and end dates. Key requirements include mitigation site preparation and installation, elderberry shrub transplanting, sign installation, vegetation clearing, container plant installation, irrigation system installation and maintenance, weed and browse control, cultural resources monitoring, stormwater monitoring and BMP upkeep, records and reports, surveys, replanting, seeding, infrastructure maintenance, and optional tree trimming and thinning. Quotes are due by September 9th, with an assumed start date of September 30th, 2022 for the base contract and five establishment periods running through January 31st, 2027.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Exhibit A Drawings.pdf | ||
| Questions and Answers.Posted.pdf | ||
| Attachment 1.Deliverable Schedule.pdf | ||
| Attachment 2 E1A Price schedule.pdf | ||
| Solicitation W9123822Q0032.pdf | ||
| Attachment 4 Drawings .pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 3, Target Project Schedule ARCF 2016 LAR Contract E1A
Assumed Contract Start Date: 9/30/2022
CLIN Title
Start, Days from Contract Award
Finish, Days from
Contract Award
Duration, Days Start Date Finish Date
CLIN 0001 Base Contract 1 273 272 10/1/2022 6/30/2023
0001.1 Project Schedule 1 31 30 10/1/2022 10/31/2022
0001.2 Quality Control Plan 1 31 30 10/1/2022 10/31/2022
0001.3 Accident Prevention Plan 1 16 15 10/1/2022 10/16/2022
0001.4 Environmental Protection Plan 1 31 30 10/1/2022 10/31/2022
0001.5 Performance Work Plan 1 31 30 10/1/2022 10/31/2022
0001.6 Irrigation System Plan 1 31 30 10/1/2022 10/31/2022
0001.7 Stormwater Permit 1 31 30 10/1/2022 10/31/2022
0001.8 Installing Best Management Practices (BMPs) 32 42 10 11/1/2022 11/11/2022
0001.9 Stomwater Monitoring and BMP upkeep 32 232 200 11/1/2022 5/20/2023
0001.10 Facility Set Up and Upkeep 32 42 10 11/1/2022 11/11/2022
0001.11 Traffic Control 32 138 106 11/1/2022 2/15/2023
0001.12 Monitoring for Culturall Resources 45 138 93 11/14/2022 2/15/2023
0001.13 Clearing Site Layout 16 21 5 10/16/2022 10/21/2022
0001.14 Mitigation site layout 16 21 5 10/16/2022 10/21/2022
0001.15 Mitigation Site Preparation 21 35 14 10/21/2022 11/4/2022
0001.16 Irrigation system installation 35 45 10 11/4/2022 11/14/2022
0001.17 Elderberry Shrub Transplanting 45 138 93 11/14/2022 2/15/2023
0001.18 Sign installation 21 211 190 10/21/2022 4/29/2023
0001.19 Establishment Maintenance during installation 45 243 198 11/14/2022 5/31/2023
0001.20 Vegetation Clearing 42 72 30 11/11/2022 12/11/2022
0001.21 Container Plant installation 213 243 30 5/1/2023 5/31/2023
0001.22 Bank area seeding 72 77 5 12/11/2022 12/16/2022
0001.23 Monthly Records and Reports 32 243 211 11/1/2022 5/31/2023
0001.24 As-Builts 243 273 30 5/31/2023 6/30/2023
0001.25 Post Clearing/Installation Cleanup 243 258 15 5/31/2023 6/15/2023
CLIN 1001 Establishment Period Year One 124 488 364 2/1/2023 1/31/2024
1001.1 Irrigation 243 397 154 5/31/2023 11/1/2023
1001.2 Weed Control 124 488 364 2/1/2023 1/31/2024
1001.3 Browse Control 243 488 364 5/31/2023 1/31/2024
1001.4 Monthly Records and Reports 243 488 364 5/31/2023 1/31/2024
1001.5 As Built Update 350 380 30 9/15/2023 10/15/2023
1001.6 Plant Survival Survey 336 351 15 9/1/2023 9/16/2023
1001.7 Replanting 365 380 15 9/30/2023 10/15/2023
1001.8 Yearly Report 380 410 30 10/15/2023 11/14/2023
1001.9 Stormwater Monitoring and BMP Upkeep 232 488 256 5/20/2023 1/31/2024
1001.10 Mitigation Site Infrastructure Maintenance 243 488 245 5/31/2023 1/31/2024 CLIN 2001 Establishment Period Year Two 489 854 365 2/1/2024 1/31/2025
2001.1 Irrigation 549 763 214 4/1/2024 11/1/2024
2001.2 Weed Control 489 854 365 2/1/2024 1/31/2025
2001.3 Browse Control 489 854 365 2/1/2024 1/31/2025
2001.4 Monthly Records and Reports 489 854 365 2/1/2024 1/31/2025
2001.5 As Built Update 716 746 30 9/15/2024 10/15/2024
Days from contract award
6/2/2022 1 of 2
Attachment 5, Target Project Schedule ARCF 2016 LAR Contract E1A
Assumed Contract Start Date: 9/30/2022
CLIN Title
Start, Days from Contract Award
Finish, Days from
Contract Award
Duration, Days Start Date Finish Date
Days from contract award
2001.6 Plant Survival Survey 702 717 15 9/1/2024 9/16/2024
2001.7 Replanting 731 746 15 9/30/2024 10/15/2024
2001.8 Yearly Report 746 776 30 10/15/2024 11/14/2024
2001.9 Stormwater Monitoring and BMP Upkeep 489 854 365 2/1/2024 1/31/2025
2001.10 Mitigation Site Infrastructure Maintenance 489 854 365 2/1/2024 1/31/2025
2001.11 Seeding 763 793 30 11/1/2024 12/1/2024
CLIN 3001 Establishment Period Year Three 855 1219 364 2/1/2025 1/31/2026
3001.1 Irrigation 914 1128 214 4/1/2025 11/1/2025
3001.2 Weed Control 855 1219 364 2/1/2025 1/31/2026
3001.3 Browse Control 855 1219 364 2/1/2025 1/31/2026
3001.4 Monthly Records and Reports 855 1219 364 2/1/2025 1/31/2026
3001.5 As Built Update 855 1219 364 2/1/2025 1/31/2026
3001.6 Plant Survival Survey 1067 1082 15 9/1/2025 9/16/2025
3001.7 Replanting 1096 1111 15 9/30/2025 10/15/2025
3001.8 Yearly Report 1111 1141 30 10/15/2025 11/14/2025
3001.9 Stormwater Monitoring and BMP Upkeep 855 1219 364 2/1/2025 1/31/2026
3001.10 Mitigation Site Infrastructure Maintenance 855 1219 364 2/1/2025 1/31/2026
3001.11 Seeding 855 1219 364 2/1/2025 1/31/2026
CLIN 4001 Establishment Period Year Four 1220 1584 364 2/1/2026 1/31/2027
4001.1 Irrigation 1279 1462 183 4/1/2026 10/1/2026
4001.2 Weed Control 1220 1584 364 2/1/2026 1/31/2027
4001.3 Browse Control 1220 1584 364 2/1/2026 1/31/2027
4001.4 Monthly Records and Reports 1220 1584 364 2/1/2026 1/31/2027
4001.5 As Built Update 1220 1584 364 2/1/2026 1/31/2027
4001.6 Plant Survival Survey 1432 1447 15 9/1/2026 9/16/2026
4001.7 Yearly Report 1448 1478 30 9/17/2026 10/17/2026
4001.8 Stormwater Closeout 1293 1353 60 4/15/2026 6/14/2026
4001.9 Mitigation Site Infrastructure Maintenance 1220 1584 364 2/1/2026 1/31/2027
CLIN 5001 Establishment Period Year Five 1585 1825 240 2/1/2027 9/29/2027
5001.1 Irrigation 1644 1797 153 4/1/2027 9/1/2027
5001.2 Weed Control 1585 1825 240 2/1/2027 9/29/2027
5001.3 Browse Control 1585 1825 240 2/1/2027 9/29/2027
5001.4 Monthly Records and Reports 1585 1825 240 2/1/2027 9/29/2027
5001.5 As Built Update 1585 1825 240 2/1/2027 9/29/2027
5001.6 Plant Survival Survey 1735 1750 15 7/1/2027 7/16/2027
5001.7 Yearly Report 1751 1781 30 7/17/2027 8/16/2027
5001.8 Mitigation Site Infrastructure Maintenance 1585 1825 240 2/1/2027 9/29/2027
5001.9 Final Browse Guard Removal 1780 1810 30 8/15/2027 9/14/2027
5001.10 Irrigation System Removal 1780 1810 30 8/15/2027 9/14/2027
5001.11 Final Mitigatio Site Clean-up 1797 1812 15 9/1/2027 9/16/2027
CLIN 6001 Optional Tree Trimming 6001 Optional Tree Thinning 1705 1825 120 6/1/2027 9/29/2027
6/2/2022 2 of 2
Target Project Schedule