This site specification document outlines requirements for a single-user vault toilet replacement project at Clara Lake Campground within Superior National Forest. The project involves removing an existing vault toilet and installing a prefabricated concrete vault toilet building that meets ADA accessibility standards. The new building should have a left-facing layout with one deadbolt lock and one non-keyed privacy locking handle on the door. Minimal site preparation work is needed as there are few trees in the area. This project is part of a larger solicitation by the US Department of Agriculture Forest Service to replace vault toilets at multiple locations within Superior National Forest. The solicitation involves tasks such as demolition of existing toilets, installation of precast concrete buildings, excavation, backfilling, and other site work as specified.
View the file
Other files for this federal contract opportunity
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Site Specific Specifications for Eastern Region Vault Toilet Building Contracts
Superior National Forest
Bid Item #1: Clara Lake Campground
Tofte Ranger District, Lutsen, MN (Lat/ Long N 47.77445 – W 90.752190)
Project Area Map
Existing Toilet
Overview of Installation Site This work is to include removing a single-user vault toilet and installing a CXT “Cascadian” (or equivalent) single vault toilet. The toilet door shall have one deadbolt lock and one non-keyed “privacy” locking handle, and a left-facing layout. There are no large trees, and few trees (<6) of small diameter (6” or less) that need to be removed. The toilet shall be placed so as to include the void left by the complete removal of the former vault toilet. Installation must include an ABAAS accessible poured concrete side walk that incorporates an angled accessible transition. The concrete transition shall be angled to “dive under” the gravel path or have a radiused end where it meets with the gravel path in order to prevent height difference between the two materials of 1” or greater from occurring. Place approximately 20 cubic yards (CY) crushed aggregate (compacted in place) from the edge of the campground road to the new vault toilet entrance. Path shall be 48 inches wide by approximately 25 feet long.
Contractor is responsible for removal of all portions of the existing vault toilet.
Work shall commence no sooner than April 1, 2022 and be completed by August 31, 2022.
Work shall not take place on weekends or on any federal holidays.
Existing vault should be entirely removed, and the new toilet placed in the same location as the former.
Contractor is responsible for clearing the site location staked by the engineer.
All cut timber shall be left in lengths of at least 12 feet and remain on site for firewood for campers.
All stumps shall be excavated from the site and disposed of on site as per CO/COR.
Supply 5 yards of topsoil around new building that is loped to drain water away from the vault.
All disturbed ground shall be seeded with a seed mix furnished by the contractor that meets the specifications in the chart below:
Native Seed Mix Common Name Botanical Name % of Mix Canada Wild Rye Elymus canadensis 20.0 Slender Wheatgrass Agropyron trachycaulum 30.0 Oats Avena sativa 50.0 Total 100% Recommended rate = 20 lbs/acre
Bid Item #2 Cascade River Rustic Campground
Gunflint Ranger District, Grand Marais, MN (Lat/ Long N 47.8323094, W 90.529867)
This work is to include removing a single-user vault toilet and installing a CXT “Cascadian” (or equivalent) single vault toilet. The toilet door shall have one deadbolt lock and one non-keyed “privacy” locking handle, and a right-facing layout. There are no large trees, and few trees (<6) of small diameter (6” or less) that need to be removed. The toilet shall be placed so as to include the void left by the complete removal of the former vault toilet. Installation must include an ABAAS accessible poured concrete side walk that incorporates an angled accessible transition. The concrete transition shall be angled to “dive under” the gravel path or have a radiused end where it meets with the gravel path in order to prevent height difference between the two materials of 1” or greater from occurring. Place approximately 30 cubic yards (CY) crushed aggregate (compacted in place) from the edge of the campground road to the new vault toilet entrance. Path shall be 48 inches wide by approximately 60 feet long.
Contractor is responsible for removal of all portions of the existing vault toilet.
Work shall commence no sooner than April 1, 2022 and be completed by August 31, 2022.
Work shall not take place on weekends or on any federal holidays.
Existing vault should be entirely removed, and the new toilet placed in the same location as the former.
Contractor is responsible for clearing the site location staked by the engineer.
All cut timber shall be left in lengths of at least 12 feet and remain on site for firewood for campers.
All stumps shall be excavated from the site and disposed of on site as per CO/COR.
Supply 5 yards of topsoil around new building that is loped to drain water away from the vault.
All disturbed ground shall be seeded with a seed mix furnished by the contractor that meets the specifications in the chart below:
Native Seed Mix Common Name Botanical Name % of Mix Canada Wild Rye Elymus canadensis 20.0 Slender Wheatgrass Agropyron trachycaulum 30.0 Oats Avena sativa 50.0 Total 100%
Bid Item #3 Jackpot ATV Trailhead, Isabella, MN Lat/Long: 47°38'51.8"N 91°37'41.9"W
Existing Toilet and Overview of Installation Site
This work is to include removing a single-user vault toilet and installing a CXT “Cascadian (or equivalent) single vault toilet. The toilet door shall have one deadbolt lock and one non-keyed “privacy” locking handle, and a right-facing layout. There is one large tree and several small trees/ bushes (<6) of small diameter (6” or less) that need to be removed. The toilet shall be placed so as to include the void left by the complete removal of the former vault toilet. Installation must include an ABAAS accessible poured concrete side walk that incorporates an angled accessible transition. The concrete transition shall be angled to “dive under” the gravel path or have a radiused end where it meets with the gravel path in order to prevent height difference between the two materials of 1” or greater from occurring. Place approximately 5 cubic yards (CY) crushed aggregate (compacted in place) from the edge of the parking lot to the new vault toilet entrance. Path shall be 48 inches wide by approximately 20 feet long.
Contractor is responsible for removal of all portions of the existing vault toilet.
Work shall commence no sooner than April 1, 2022 and be completed by August 31, 2022.
Work shall not take place on weekends or on any federal holidays.
Existing vault should be entirely removed, and the new toilet placed in the same location as the former.
Contractor is responsible for clearing the site location staked by the engineer.
All cut timber shall be disposed of on site as per COR.
All stumps shall be excavated from the site and disposed of on site as per CO/COR.
Supply 5 yards of topsoil around new building that is loped to drain water away from the vault.
All disturbed ground shall be seeded with a seed mix furnished by the contractor that meets the specifications in the chart below:
Native Seed Mix Common Name Botanical Name % of Mix Canada Wild Rye Elymus canadensis 20.0 Slender Wheatgrass Agropyron trachycaulum 30.0 Oats Avena sativa 50.0 Total 100%
Bid Item #4 Vermilion Falls Day Use Site (Lat: N 48.263018°, Long: W 92.570099°)
This work is to include removing a single-user vault toilet and installing a CXT “Gunnison” Right Hand layout Rich Earth color and Barnwood texture (or equivalent) single vault toilet. The toilet door shall have one deadbolt lock and one non-keyed “privacy” locking handle. There are several large boulders at the site that might need to be moved during construction and should be moved back in place after the new toilet is installed. The toilet shall be placed so as to include the void left by the complete removal of the former CXT Toilet. Installation must include an ABAAS accessible poured concrete side walk that incorporates an angled accessible transition. The concrete transition shall be angled to “dive under” the gravel path or have a radiused end where it meets with the gravel path in order to prevent height difference between the two materials of 1” or greater from occurring. Place approximately 20 cubic yards (CY) crushed aggregate (compacted in place) from the edge of the road to the new vault toilet entrance. Path shall be 48 inches wide by approximately 80 feet long.
Work shall not take place on weekends or on any federal holidays.
Existing vault should be entirely removed, and the new toilet placed in the same location as the former.
Contractor is responsible for clearing the site location staked by the engineer.
All cut timber shall be left in lengths of at least 12 feet and remain on site for firewood for campers.
All stumps shall be excavated from the site and disposed of on site as per CO/COR.
Supply 5 yards of topsoil around new building that is loped to drain water away from the vault.
All disturbed ground shall be seeded with a seed mix furnished by the contractor that meets the specifications in the chart below:
Native Seed Mix Common Name Botanical Name % of Mix Canada Wild Rye Elymus canadensis 20.0 Slender Wheatgrass Agropyron trachycaulum 30.0 Oats Avena sativa 50.0 Total 100%
Bid Item #5 – One Pine Boat landing, Ely, MN (Lat: N 47°48’24.99, Long: W 91°53’11.72)
This work is to include removing a single-user vault toilet and installing a CXT “Cascadian” right-hand layout (or equivalent) single vault toilet. The toilet door shall have one deadbolt lock and one non-keyed “privacy” locking handle. There are 2 medium trees that (8” or less) and multiple trees (<6) of small diameter (6” or less) that need to be removed. The toilet shall be placed so as to include the void left by the complete removal of the former vault toilet. Installation must include an ABAAS accessible poured concrete side walk that incorporates an angled accessible transition. The concrete transition shall be angled to “dive under” the gravel path or have a radiused end where it meets with the gravel path in order to prevent height difference between the two materials of 1” or greater from occurring.
Place approximately 10 cubic yards (CY) crushed aggregate (compacted in place) from the edge of the parking lot to the new vault toilet entrance. Path shall be 48 inches wide by approximately 40 feet long.
Work shall not take place on weekends or on any federal holidays.
Existing vault should be entirely removed, and the new toilet placed in the same location as the former.
Contractor is responsible for clearing the site location staked by the engineer.
All cut timber shall be disposed of on site as per COR.
All stumps shall be excavated from the site and disposed of on site as per CO/COR.
Supply 5 yards of topsoil around new building that is loped to drain water away from the vault.
All disturbed ground shall be seeded with a seed mix furnished by the contractor that meets the specifications in the chart below:
Native Seed Mix Common Name Botanical Name % of Mix Canada Wild Rye Elymus canadensis 20.0 Slender Wheatgrass Agropyron trachycaulum 30.0 Oats Avena sativa 50.0 Total 100%
Bid Item #6– Sand Lake Campground, Isabella, MN (Lat: N 47.58221°, Long: W 91.66190°)
This work is to include removing a single-user vault toilet and installing a CXT “Cascadian” left-hand layout (or equivalent) single vault toilet. The toilet door shall have one deadbolt lock and one non-keyed “privacy” locking handle. There is 1 large tree, and a few trees (<6) of small diameter (6” or less) that need to be removed. The toilet shall be placed so as to include the void left by the complete removal of the former vault toilet. Installation must include an ABAAS accessible poured concrete side walk that incorporates an angled accessible transition. The concrete transition shall be angled to “dive under” the gravel path or have a radiused end where it meets with the gravel path in order to prevent height difference between the two materials of 1” or greater from occurring. Place approximately 20 cubic yards (CY) crushed aggregate (compacted in place) from the edge of the campground road to the new vault toilet entrance. Path shall be 48 inches wide by approximately 80 feet long.
Work shall not take place on weekends or on any federal holidays.
Existing vault should be entirely removed, and the new toilet placed in the same location as the former.
Contractor is responsible for clearing the site location staked by the engineer.
All cut timber shall be left in lengths of at least 12 feet and remain on site for firewood for campers.
All stumps shall be excavated from the site and disposed of on site as per CO/COR.
Supply 5 yards of topsoil around new building that is loped to drain water away from the vault.
All disturbed ground shall be seeded with a seed mix furnished by the contractor that meets the specifications in the chart below:
Native Seed Mix Common Name Botanical Name % of Mix Canada Wild Rye Elymus canadensis 20.0 Slender Wheatgrass Agropyron trachycaulum 30.0 Oats Avena sativa 50.0 Total 100%
Bid Item 7- SNF Alternate
Mink Lake Toilet, Gunflint Ranger District, Grand Marais, MN (Lat/ Long N 47.86717627663272, – W 90.21759968167747)
Example of Existing Toilet and Project Site Type
This work is to include removing a single-user vault toilet and installing a CXT “Cascadian” left-hand layout (or equivalent) single vault toilet. The toilet door shall have one deadbolt lock and one non-keyed “privacy” locking handle. The toilet entrance shall be on the left. The toilet shall be placed so as to include the void left by the complete removal of the former CXT Toilet. Installation must include an ABAAS accessible poured concrete side walk that incorporates an angled accessible transition. The concrete transition shall be angled to “dive under” the gravel path or have a radiused end where it meets with the gravel path in order to prevent height difference between the two materials of 1” or greater from occurring. Place approximately 2 cubic yards (CY) crushed aggregate (compacted in place) from the edge of the parking Area to the new vault toilet entrance.
Work shall not take place on weekends or on any federal holidays.
Existing vault should be entirely removed, and the new toilet placed in the same location as the former.
Contractor is responsible for clearing the site location staked by the engineer.
All cut timber shall be left in lengths of at least 12 feet and remain on site for firewood for campers.
All stumps shall be excavated from the site and disposed of on site as per CO/COR.
Supply 5 yards of topsoil around new building that is loped to drain water away from the vault.
All disturbed ground shall be seeded with a seed mix furnished by the contractor that meets the specifications in the chart below:
Native Seed Mix Common Name Botanical Name % of Mix Canada Wild Rye Elymus canadensis 20.0 Slender Wheatgrass Agropyron trachycaulum 30.0 Oats Avena sativa 50.0 Total 100%