Attachment 2 _Statement of Work _Specification.pdf
PDF 658 KB Posted
- Attached to
- CGC VALIANT FY22 AA
- Solicitation number
- 70Z080-22-Q-P4502800
About this file
This is a solicitation for a dockside availability period for the Coast Guard Cutter VALIANT. The period of performance is from November 15, 2021 through December 13, 2021. The solicitation is being issued by the Department of Homeland Security United States Coast Guard.
The availability period involves conducting various repairs and inspections on the cutter as outlined in the specification. Work items include load testing power supplies, inspecting and renewing components of the helicopter landing system, preserving helicopter operating areas on the flight deck, renewing sections of deck drain piping, inspecting flight deck plating and stiffeners, and renewing visual landing aid structures and sections of deck plating. The specification provides requirements, references, notes, and government furnished property or equipment for each work item.
The response date is not included, though the award date would fall prior to the start of the period of performance on November 15, 2021. Pricing terms and potential set asides are not specified. The Coast Guard and Naval Air Warfare Center are the primary federal agencies involved according to references in the specification. No incumbent is mentioned.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 1 Page 2 of 2.pdf | ||
| Amendment 1 Page 1 of 2.pdf | ||
| 70Z080-22-Q-P4502800.pdf | ||
| Attachment 1_ Schedule of Services_Blank Price Schedule.xls | XLS spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC VALIANT (WMEC 621)
SPECIFICATION FOR DOCKSIDE REPAIRS
FY2022
Developed By: Brett M Gardner
(Rev-0, 30 June 2021)
USCGC VALIANT (WMEC-210B) DOCKSIDE AVAILABILITY FY2022
ii (Rev-0)
TABLE OF CONTENTS
Revisions Record ......................................................................................................................................... iii Consolidated List of References ................................................................................................................... iv Consolidated List of Government-furnished Property ................................................................................. vi Consolidated List of Critical Inspection Items ........................................................................................... vii Principal Characteristics ............................................................................................................................ viii General Requirements WORK ITEM 1: 28 Volt DC Helo Power Supply, Load Test WORK ITEM 2: 400 Hz Power Supply (FCX Systems Inc.), Load Test WORK ITEM 3: Windspeed Transmitter (Anemometer), Renew WORK ITEM 4: Flow Meter (Aviation Fuel), Calibrate WORK ITEM 5: Helo Talon Grids, Inspect and Test WORK ITEM 6: Decks, Helicopter Operating Areas, Preserve WORK ITEM 7: Deck Drain Piping, Renewal WORK ITEM 8: Flight Deck, Inspect WORK ITEM 9: Helo Visual Landing Aids, Structure, Renew WORK ITEM 10: Deck Plating, Renew iii (Rev-0)
REVISIONS RECORD
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK
ITEM#
CHANGES MADE
NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
iv (Rev-0)
CONSOLIDATED LIST OF REFERENCES
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.
All Coast Guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.
COAST GUARD DRAWINGS
Coast Guard Bill of Materials 627 WMEC 008, Arr. Firemain, Sprinkling & Washdown, Mn Dk & Above Coast Guard Bill of Materials 627 WMEC 011, Rev C, 3rd Dk, 2nd Dk, Main Dk, 01 Dk, 02 Dk &
Bridge Dk Plt’g & Supports Coast Guard Bill of Materials 627 WMEC 079, Rev F, Arr of Weather Deck & A/C Drains Coast Guard Bill of Materials 627 WMEC 097, Rev G, Arrangement Aviation Fuel System Coast Guard Drawing 618 WMEC 314-001, Rev J, Helo 400 Hz & 28.5 VDC Replacement Diagram Coast Guard Drawing 618 WMEC 430-050, Rev -, I.C. Distribution Panel Coast Guard Drawing 627 WMEC 085-231, Rev D, Booklet of General Plans Coast Guard Drawing 627 WMEC 136-001, Rev G, 01, 02 & Bridge Deck Plating & Supports Coast Guard Drawing 627 WMEC 186-002, Rev C, Talon Grid Fdn & Structural Mod 01 Level Coast Guard Drawing 627 WMEC 437-002, Rev B, Wind speed & Direction Ind Sys Elem Wrg Diag IC
Ckt “HD & HE” Coast Guard Drawing 627 WMEC 437-003, Rev A, Wind Spd & Dir Ind Sys Ckt “HD & HE” Block and
Elem Wrg Diag Coast Guard Drawing 627 WMEC 492-001, Rev D, Helicopter Visual Landing Aids Lighting
Arrangement & Dets Block Wiring Diag CKT “1K-FL” Coast Guard Drawing 627 WMEC 521-002, Rev G, Arr. Of Firemain, Sprinkling & Washdown System
Main Deck & Above Coast Guard Drawing 627 WMEC 526-001, Rev G, Arr Weather Deck & A/C Drains Coast Guard Drawing 627 WMEC 542-001, Rev E, Diagram Aviation Fuel System Coast Guard Drawing 627 WMEC 542-002, Rev E, Arrangement of Aviation Fuel System Coast Guard Drawing 627 WMEC 601-004, Rev D, General Arrangement Main & 01 Deck Coast Guard Drawing 627 WMEC 601-005, Rev F, General Arrangement - 02 Dk, Bridge Dk, & House
Top Coast Guard Drawing 627 WMEC 613-001, Rev B, Main Mast Rigging, Arrg’t & Dets.
Coast Guard Drawing FL-588-003, Rev -, Talon Grid, Supporting Skirt & Cover Fabrication & Instl
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors
Manual Coast Guard Technical Publication (TP) 3234A, Dec 2012, Distribution Switchboard v (Rev-0)
Coast Guard Technical Publication (TP) 3239A, SWBS 542, Section E, Feb 2020, JP-5 Flow Meter Coast Guard Technical Publication (TP) 3368, Jun 2020, Talon Helicopter Landing Grid - Type 18-22-01
Multiple Class Cutters Coast Guard Technical Publication (TP) 4931, Aug 2009, Section 321A, Precision Frequency Converters Coast Guard Technical Publication (TP) 5461, SWBS 421, Nov 2012, Anemometer – Model 120 & 122 Coast Guard Technical Publication (TP) 7099, SWBS 314, Oct 2009, Rectifier Power Supply - 28 VDC, 300 A Coast Guard Technical Publication (TP) 9142, Nov 2016, Meter – Model M-5-2 Direct Drive Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General
Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2020, Welding and
Allied Processes Surface Forces Logistics Center Standard Specification 3041 (SFLC Std Spec 3041), 2020, Shipboard
Electrical Cable Test Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2020, Requirements for Preservation of Ship Structures
OTHER REFERENCES
ASTM International (ASTM) D5363, 2016, Standard Specification for Anaerobic Single-Component
Adhesives (AN) MIL-PRF-16173, 2017, Corrosion Preventive Compound, Solvent Cutback, Cold-Application MIL-PRF-24667, March 2018, Coating system, Non-Skid, for Roll, Spray, or Self-Adhering Application MIL-STD-1399 Section 300, Part 1, 25 September 2018, Low Voltage Electric Power, Alternating
Current NAVAIR SI-ACS-AFB-1P, 01 July 2020, Air Capable Ship Aviation Facilities Bulletin No. 1P Naval Air Warfare Center (NAVAIR) Drawing 626348, Rev C, Visual Landing Aids Installation WMEC-
210 Class Ships QPL-24667, Aug 2019, Qualified Product List of Products Qualified under Performance The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2012, Power Tool Cleaning to Bare Metal vi (Rev-0)
CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
WORK
ITEM
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
3 Y Anemometer NSN: 6600-00-709-9947 1 ea. 5,316.00 4 N **JP-5 Flow meter, Meter NSN: 6680-01-658-6663 1 ea. 3,800.00
4 N ** Counter Rotating, Register
NSN: 6680-01-439-2365 1 ea. 388.00
5 N Screw, Cap, 5/8-11 UNC 2A x 3in.
NSN: 5305-01-393-1827 24 ea. 25.65
5 N Screw, Cap, M12-1.75 x 42 mm
NSN: 5305-01-584-6095 12 ea. 33.75
5 N **Talon Grid Stanchion Bolt
Assembly, Including Locking Nut
NSN: 5340-01-481-3786 60 ea. 31.50
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
vii (Rev-0)
CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.1.4 (Inspection report particulars)):
Work Item Title
5 Helo Talon Grids, Inspect and Test
8 Flight Deck, Inspect viii (Rev-0)
PRINCIPAL CHARACTERISTICS
210' WMEC (B-CLASS)
PHYSICAL
Length overall 210' 6" Length between perpendiculars 200' 0" Beam molded 34' 0" Depth molded, main deck amidships 19' 6" Full load displacement 1,170 long tons Draft, full load to baseline amidships *Baseline is 9” below keel amidships
12' 0"
Design drag between perpendiculars 1' 6" Highest projection above baseline *VHF-FM ADF antenna
90' 0"
Shore tie voltage requirements 400A / 440V Frame spacing 1' 0"
MACHINERY
Main propulsion 2 ALCO Model 16-251-B Diesel Engines, 5,000 BHP total Ship's service generators 2 Caterpillar Model 3406B Diesel-driven SR4, 250 KW each @ 0.8 power factor, 440VAC, 3 phase, 60 cycle
Emergency generator Caterpillar Model 3306B Diesel-driven SR4, 180 KW @ 0.8 power factor, 440VAC, 3 phase 60 cycle
Number of propellers 2 Propeller diameter 7' 6" Number of blades, each 4 Pitch Controllable Shaft RPM 300 Shaft diameter 8.25" at exit of hull Anchor & chain Two 2,800 lb Navy Stockless Anchors, 7 shots of chain each
TANK CAPACITIES
Diesel fuel total (95%) 48,427 gal.
Fresh water total (100%) 11,693 gal.
JP-5 fuel total (95%) 4,683 gal.
Lube oil total (95%) 2,390 gal.
1 (Rev-0)
00000_0521_FLT
REC_00000_FLT_Commercial Project @ CG Facility (0121)
General Requirements
1. SCOPE
1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed by commercial contractors at a Coast Guard facility for Coast Guard vessels.
1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General
Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2020, Welding and
Allied Processes Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2020, Requirements for Preservation of Ship Structures
OTHER REFERENCES
None
3. REQUIREMENTS
3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirements of this WI applies to all work under the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
2 (Rev-0)
3.1.1 NAVSEA drawings listed will be available FOR INSPECTION ONLY from the Coast Guard Port Engineer post-award. SFLC will not redistribute NAVSEA documents. Contractors can apply to NAVSEA headquarters directly for copies.
3.2 Fire watch requirements. The Contractor must refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec 0000, in accomplishing the following task:
• Provide portable fire extinguishers for Coast Guard fire watch personnel. Coast Guard fire watch is in lieu of contractor personnel during the hours of 0800-1600, Monday through Friday, and limited to two Coast Guard fire watch personnel.
• Provide fire watch personnel and fire extinguishers for the duration of the availability period, during and beyond noted Coast Guard fire watch support.
3.3 Preservation requirements. The Contractor must accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.
3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).
3.3.2 Coating colors and system color schemes. The Contractor must obtain a written KO authorization to deviate from any coatings required in SFLC Std Spec 6310 Appendix C before work.
3.4 Welding and brazing requirements. The Contractor must perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.
3.5 Environmental protection requirements. The Contractor must adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:
3.5.1 USCG facilities. The Contractor must provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix B, Requirements for Environmental Protection at USCG Facilities, during the performance of this availability. Contractor must plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor must comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item must not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.
3.5.1.1 USCG Generator status. The activity Generator Status for the Coast Guard Facility is Large Quantity Generator (LQG).
3.5.1.2 Plans and permits. The CG Facility has unit specific permits including the following:
• Spill Prevention Control and Countermeasures (SPCC) Plan: Unit has a SPCC Plan which requires certain unit-specific procedures be followed for the storage, inspection, and transfer of petroleum products in containers 55 gallons or greater.
• National Pollutant Discharge Elimination System (NPDES) Storm Water (SW) Permit: Unit has an NPDES SW permit which requires unit-specific procedures be followed for the storage and inspection of equipment and materials which may contribute contaminants to storm water discharges.
• Air Emission Permit: Unit has an Air Emission Permit which requires unit-specific procedures be followed for the emissions of VOCs and hazardous air pollutants.
3 (Rev-0)
3.5.2 Test and procedures. The Contractor must be required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work must be done by qualified laboratories; and where required by law, the laboratories must be certified.
3.5.3 Regulatory notifications. The Contractor must be responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The Contractor must submit copies of all regulatory notifications to the Contracting Officer and the local Facility Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications must be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System (NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.
3.5.4 Environmental manager. The Contractor must appoint in writing an Environmental Manager for the project, and must be responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager must ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out; ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas;
ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close-out.
3.5.5 HW disposal. Contractor must comply with SFLC Std Spec 0000 Appendix B, Requirements For Environmental Protection At USCG Facilities for HW disposal, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).
3.5.6 Additional Requirements. The Contractor must be aware of the following:
3.5.6.1 No Contractor or Subcontractor must have the authority to sign a Hazardous Waste Manifest using the Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast Guard facility without COR or KO-approval.
3.5.6.2 Local environmental regulations at the Government facilities may be more stringent. As with all environmental regulations, the Contractor must prepare for and comply with local and state regulations.
3.5.6.3 Coast Guard facilities do not maintain Facilities Response Plans (FRPs) per 33 CFR 154. Contractor must furnish the FRP when required for over-the-water liquids transfers to and from vessels, and is required for oil/fuel transfers to/from vessels for 250 barrels (10,500 gallons) or more.
3.6 Local Policy. None.
3.6.1 This availability is to be conducted at an US Navy facility. The Contractor must comply with all US Naval facility instructions (e.g. NAVFAC P-307 for Weight Handling Program Management, etc.)
4 (Rev-0)
3.7 SFLC Standard Specification approved changes. The Contractor must be aware that the following are approved changes to published SFLC 2020 Edition Standard Specifications and supersede published content:
3.7.1 SFLC Standard Specification 8636. Add missing paragraphs between 3.2 and 3.5 of Std Spec 8636 as follows:
“3.3 Access cut boundaries. The Contractor must ensure that access cuts comply with the requirements and restrictions detailed in the following and in SFLC Std Spec 0740, and referenced codes.
3.3.1 Location of boundaries. Boundaries of access cuts and closure plates must, in general, be located between principal ship framing, bulkheads, and other structural members and must be at least three inches from any of these members or from the toes of other welds. A reduction in this three inch minimum may be approved by the KO on a case by case basis provided sufficient clearance is maintained for welding and inspection requirements.
The boundaries of access cuts and closure plates should land on existing butts or seams, wherever practicable. The boundaries of prior access cuts should be utilized wherever possible. Boundaries may extend across one or more frames as required for the size of the opening.
3.3.2 Access hole dimensions and arrangements. Holes or access cuts must be the minimum size necessary and must be in accordance with the following:
• Rectangular access cuts and closure plates welded into primary hull structure must be at least 12 inches wide in the lesser dimension.
• For circular access cuts, the minimum diameter must be 4T, where T = thickness of the involved structural member, but not less than three inches.
• Circular closure plates for access cuts less than two feet in diameter must be dished 1/16 to 1/8 inch to allow for shrinkage when welded.
• Corners of rectangular access cuts and closure plates must have a minimum radius of 6 inches except when a boundary lands on an existing hull longitudinal seam or transverse butt weld.
• Corners at an existing seam or butt must intersect at a 90 degree angle.
• Cuts that are to cross existing butts or seams must do so at an angle of 90 degrees plus or minus 15 degrees.
• In primary hull structure, existing welds forming the boundary of a cut must be cut back 3 inches beyond the toe of the access cut, except that the cut back must not intersect or cross an existing weld, frame, or structural member. In which case, the cut back may be reduced to a minimum of two inches in length.
• Existing welds crossed by the cut must not be cut back.
3.3.3 Primary hull structure. Primary Hull Structure includes the shell, main strength decks, principal longitudinal bulkheads, vertical keel, deep web girders and stiffeners designed to withstand the ship bending stress.
3.3.4 Mechanically fastened joints. Welding closer than six inches to a mechanically fastened joint should be avoided. When access cuts cross or come within six inches of a mechanically fastened joint, the fasteners must be checked for tightness and if necessary, loose fasteners must be seal welded or removed, and replaced for a distance of 6 inches beyond the edge of the cut. When a cut crosses a mechanically fastened seam the cut plates must be repaired using single V welds backed with glass tape (MIL-C-20079) to prevent fusion between the mechanically fastened plates.
3.4 Ship integrity maintenance. The Contractor must maintain safety and ship integrity by installing temporary guarding and coaming, in addition to weathertight and watertight closures. Remove these temporary fabrications after closing the hull access, and grind surfaces flush in way of removals. For shell plating cuts made at or below
5 (Rev-0) the waterline where temporary closures are impractical, the Contractor must secure each vulnerable compartment and subdivision to minimize potential damage to the extent permitted by the scope and urgency of the work.
3.4.1 Guarding. Install temporary guards in accordance with 29 CFR 1915.73.
3.4.2 Coaming. Ensure that in areas where flammable liquids may be stored, a 4 inch high metal coaming must be installed on the surface of the deck with tack welds and fully sealed with caulking compound. The coaming must encircle the access cut in the deck.
3.4.3 Weathertight and contamination closures. Fabricate temporary closures, using fire retardant material, before cutting access openings and install closures whenever access is not in use. Closures must be:
• Constructed to protect the access from inclement weather and entry of contaminants (must include a coaming or dam on the deck to redirect rain runoff away from the opening).
• Fitted with fasteners that permit rapid installation and removal.
• Able to support a minimum of 150 pounds per square foot for horizontal deck closures.
• Where the access opening is in way of a removed hatch, scuttle or door, the closure must be configured to allow normal passage of ship’s personnel and equipment.
3.4.4 Watertight closures. Ensure that access openings created four feet or less above the maximum anticipated waterline must include temporary watertight closures when the vessel is waterborne.
NOTE
NAVSEA S0600-AA-PRO-160/CH16 provides requirements for design, fabrication, and installation of temporary watertight closures.”
4. NOTES
4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.
6 (Rev-0)
QA-1 - QUALITY ASSURANCE INSPECTION FORM
(PRESERVATION CHECKLIST)
VESSEL NAME HULL # WORK ITEM
WORK ITEM TITLE
LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfg.
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfg.
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
Verify equipment setup, blast media, and surface preparation methods match designated test coupon.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).
Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.
Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).
Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.
Ensure that system cure is in accordance with manufacturer's recommendation for intended service.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
For immersion coatings (including tank U/W body), record date and time of the following events:
Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME
7 (Rev-0)
QA-2 - QUALITY ASSURANCE INSPECTION FORM
(ENVIRONMENTAL READINGS)
VESSEL NAME HULL # WORK ITEM
# WORK ITEM TITLE
Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.
DATE
TIME
ACTIVITY (SURFACE
PREPARATION, PRIMER COAT,
BARRIER COAT, TOP COAT,
ETC…)
LOCATION (FRAME &
DECK, RELATION TO
EQUIPMENT, ETC.)
TEMPERATURE % REL.
HUMID-
ITY
DEW
PT.
SURFACE AMBIENT ΔT
| DP -
SURFACE |
NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME
8 (Rev-0)
QA-3A - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)
VESSEL NAME HULL # WORK ITEM
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-1/NACE WJ-1
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP WJ-3/NACE WJ-3
SSPC-SP WJ-4/NACE WJ-4
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS
PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS
DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:
NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE /
TIME
9 (Rev-0)
QA-3B - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)
VESSEL NAME HULL # WORK ITEM
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-1/NACE WJ-1
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP WJ-3/NACE WJ-3
SSPC-SP WJ-4/NACE WJ-4
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT QA
RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO
SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Mean Reading (mils)
Mean Reading (mils) IAW ASTM DD4417).
10 (Rev-0)
QA-4 - QUALITY ASSURANCE INSPECTION FORM
(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)
VESSEL NAME HULL # WORK ITEM
SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.
DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)
11 (Rev-0)
QA-5 - QUALITY ASSURANCE DATA FORM
(COATING THICKNESS)
(Use one sheet for each sequence)
VESSEL NAME HULL # WORK ITEM
# WORK ITEM TITLE
COATING MFG PRODUCT NAME BATC
H #
INDUCTI
ON TIME
COATING SYSTEM
SEQUENCE
(PRIMER/TOUCHUP/3RD
COAT, ETC.)
DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.
SPOT 1 2 3 4 5 AVERAGE
VALUE
*BASE METAL READING
(BMR) Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
1 AVG. BMR DEVIATION
1 AVG. BMR DEVIATION
APPLICATION METHOD (AIRLESS,
CONVENTIONAL SPRAY, ROLLED)
AVERAGE DFT
12 (Rev-0)
31410_CNJ_0221_210_270
REC_31410_210_270_210 WMEC ‘B’ Class (ALL) (0221)
WORK ITEM 1: 28 Volt DC Helo Power Supply, Load Test
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to load test the 28 Volt DC Helo Power Supply.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 618 WMEC 314-001, Rev J, Helo 400 Hz & 28.5 VDC Replacement
Diagram
COAST GUARD PUBLICATIONS
Coast Guard Technical Publication (TP) 7099, SWBS 314, Oct 2009, Rectifier Power Supply - 28
VDC, 300 A
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General Requirements
OTHER REFERENCES
NAVAIR SI-ACS-AFB-1P, 01 July 2020, Air Capable Ship Aviation Facilities Bulletin No. 1P
3. REQUIREMENTS
3.1 General. The Contractor must refer to the Coast Guard drawing(s) listed under Section 2 (References) for guidance in accomplishing this work item.
3.1.1 CIR.
None.
3.1.2 Tech Rep.
Not applicable.
13 (Rev-0)
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, (Vessel component, space, and equipment protection).
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, (Interferences).
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.2 Operational test, initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR.
3.3 Load test 28 VDC helo start rectifier. The Contractor must load test the 28 VDC Helo Start Rectifier in accordance with NAVAIR Air Capable Ship Aviation Facilities Bulletin (latest revision as cited in Section 2 References) and using Coast Guard Drawing 618 WMEC 314-001 and TP 7099, as guidance.
Submit completed Data Sheet via CFR.
3.3.1 In the event the load test for the 28 VDC helo start rectifier fails, the Contractor must troubleshoot and identify faulty component and submit CFR for repairs.
3.3.2 Once repairs are complete, the Contractor must re-conduct load test in accordance with paragraph
3.3 (Load test 28 VDC helo start rectifier).
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.4 Operational test, post repairs. After completion of work, the Contractor must thoroughly test, in the presence of the Coast Guard Inspector and demonstrate all items or shipboard devices that have been disturbed, used, repaired, altered, or installed to be in satisfactory operating condition. Submit a CFR.
3.5 Report. The Contractor must submit a CFR for the completed Data Sheet in Section 4.1.
4. NOTES
4.1 Data sheet.
14 (Rev-0)
28 VOLT DC HELO START POWER SUPPLY TEST DATA SHEET (SHEET 1 OF 2)
HULL NUMBER_________________
TABLE 1: PERFORMANCE TEST DATA1,2
AMPS OUTPUT
VOLTS3 NOMINAL ACTUAL
1. The test must be conducted with the ship on ship’s power (not shore tie) with Power Supply connected to a suitably sized resistive load bank.
2. The calibrated load bank must be connected to the Power Supply using the helo start cable supplied with the cutter used for starting the aircraft. The cable must be adjusted prior to conducting the test so that its length is sufficient to service the aircraft in its normal landing position on the flight deck. If required to make connections to the load bank, it is permissible to conduct the test before installing the helicopter end plug.
3. The voltage at the aircraft end of all installed system servicing cables must be between 24.0 to 29.0 volts for steady state load currents from 0 to 300 amperes.
4. Perform full load test at 300A for 60 minutes. Record values at the conclusion of the full load test.
Increase no-load voltage to 28.5V prior to start of this burn-in test to ensure output voltage will not drop below 24.0 during the burn-in period.
15 (Rev-0)
28 VOLT DC HELO START POWER SUPPLY TEST DATA SHEET (SHEET 2 OF 2)
Name Plate Data of the Power Supply
Make________________________________ Model_______________________________
Serial No.____________________________
Calibrated Load Bank Information
Make________________________________ Model_______________________________
Serial No.___________________________________ Calibration Due Date_________________
Calibrated Hand Held Voltage Meter
Make________________________________ Model_______________________________
Serial No.___________________________________ Calibration Due Date_________________
Certification of Test Results
The voltage at the aircraft end of all installed system servicing cables must be between 24.0 to 29.0 volts for steady state load currents from 0 to 300 amperes.
Name of Testing Facility or Company_____________________________________
Test Conductor_____________________________________ Date_________________
Test Supervisor/QC_________________________________ Date__________________
16 (Rev-0)
31420_CNJ_0221_210_270
REC_31420_210_270_210 WMEC ‘B’ Class (ALL) (0221)
WORK ITEM 2: 400 Hz Power Supply (FCX Systems Inc.), Load Test
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to load test the 400 HZ FCX power supply.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 618 WMEC 314-001, Rev J, Helo 400 Hz & 28.5 VDC Replacement
Diagram
COAST GUARD PUBLICATIONS
Coast Guard Technical Publication (TP) 4931, Aug 2009, Section 321A, Precision Frequency
Converters Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General Requirements
OTHER REFERENCES
NAVAIR SI-ACS-AFB-1P, 01 July 2020, Air Capable Ship Aviation Facilities Bulletin No. 1P MIL-STD-1399 Section 300, Part 1, 25 September 2018, Low Voltage Electric Power, Alternating Current
3. REQUIREMENTS
3.1 General. The Contractor must refer to the Coast Guard drawing(s) listed under Section 2 (References) as guidance in accomplishing this work item.
3.1.1 CIR.
None.
3.1.2 Tech Rep. The Contractor must provide the services of a Qualified Technical Representative who is
17 (Rev-0) familiar with the FCX Systems Inc. PFC 400 Hz Power Supply equipment/system, to accomplish the following on site:
• Advise on manufacturer's proprietary system information.
• Ensure compliance with manufacturer's procedures and standards during system disassembly, inspection, and reassembly as applicable.
3.1.2.1 Ensure the Tech Rep has experience with the system/equipment stated above and demonstrated on their résumé.
3.1.2.2 Submit the name and résumé of the Tech Rep to the COR at the Arrival Conference.
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, (Vessel component, space, and equipment protection).
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, (Interferences).
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.2 Operational test, initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR
3.3 Load test. The Contractor must perform load test of the 400 HZ FCX Solid State Frequency Converter in accordance with MIL-STD-1399 Section 300, Part 1 and NAVAIR Air Capable Ship Aviation Facilities Bulletin (latest revision as cited in Section 2 References), using Coast Guard Drawing 618 WMEC 314-001 and TP 4931 as guidance. Submit a CFR.
3.3.1 In the event the load test for the 400 HZ (FCX) Power Supply fails, troubleshoot and identify faulty component and submit CFR for repairs.
3.3.2 Once repairs are complete, re-conduct load test in accordance with paragraph 3.3 (400 HZ (FCX) Power Supply, load test). Submit CFR.
3.4 Operational test, post repairs. After completion of work, the Contractor must thoroughly test, in the presence of the Coast Guard Inspector and demonstrate all items or shipboard devices that have been disturbed, used, repaired, altered, or installed to be in satisfactory operating condition. Submit a CFR.
3.5 Report. The Contractor must submit a CFR for the completed Data Sheet in Section 4.1.
4.1 Data sheet.
18 (Rev-0)
400 HZ HELICOPTER POWER SUPPLY TEST DATA SHEET (SHEET 1 OF 2)
HULL NUMBER___________________
TABLE 1: PERFORMANCE TEST DATA1,2
AMPS3
(NOMINAL)
VOLTS4,5 AMPS6 FREQUENCY6,7
AN BN CN A B C
Continuity between pins “E” and “F” Satisfactory □
Plug pin “N” grounded to the ship’s hull and not interrupted by the disconnect switch. Satisfactory □
1. The 400Hz Helicopter Service System must be tested by connection to a suitably sized load bank and operated at loads from 2 amps up to the load specified for the Coast Guard H-65 Helicopter (10 KVA).
2. The power supply must be connected to the load bank using the cable supplied to the cutter for aircraft servicing.
If necessary to make the connection to the load bank, the test may be conducted prior to attachment of the helicopter end plug. The cable must be adjusted to the length necessary to service the aircraft in its normal landing position on the flight deck.
3. The required amperage for this test is calculated as:
I = P/[(E)(3)1/2] At P = 10 kVA (for H-65 Helicopter), and E = 200V (line to line), the maximum current required is 28.9 amps.
4. Verify the voltage output is between the limits of 113.0 to 118.0 Volts RMS, line-to-neutral, for steady state loads from no load to full rated load , at 0.7 lagging power factor. To allow for flexibility in loading techniques, the acceptable power factor range is from 0.7 lagging to 0.8 leading power factor.
5. The maximum allowable voltage unbalance is 3.0 volts RMS throughout the load range. Voltage unbalance = maximum difference between RMS phase voltage amplitudes at the utilization equipment terminals (Vmax – Vmin).
6. Verify the phase rotation and frequency is in accordance with Type III power requirements of MIL-STD-1399 Section 300, Part 1.
7. Frequency range must be between 398 to 402 Hz (400 Hz +/- 0.5%).
8. Perform burn-in test at 29A for 60 minutes. Record values at the conclusion of the full load test.
19 (Rev-0)
400 HZ HELICOPTER POWER SUPPLY TEST DATA SHEET (SHEET 2 OF 2)
4.1.1 Name Plate Data of the Power Supply
Make________________________________ Model_______________________________
Serial No.____________________________
4.1.2 Calibrated Load Bank Information
Make________________________________ Model_______________________________
Serial No.___________________________________ Calibration Due Date_________________
4.1.3 Calibrated Hand Held Voltage Meter
Make________________________________ Model_______________________________
Serial No.___________________________________ Calibration Due Date_________________
4.1.4 Calibrated Hand Held Ammeter
Make________________________________ Model_______________________________
Serial No.___________________________________ Calibration Due Date_________________
4.1.5 Certification of Test Results
• The phase rotation and frequency is IAW the Type III power requirements of MIL-STD-1399
Section 300 Part 1.
• Voltage does not fall outside of the range of 118 Volts to 113 Volts, line-to-neutral, for the entire load range at 0.7 lagging power factor. To allow for flexibility in loading techniques, the acceptable power factor range is from 0.7 lagging to 0.8 leading power factor.
• Frequency must not fall outside of the range of 398 Hz to 402 Hz.
• Continuity must exist between pins “E” and “F”. Plug pin “N” must be grounded to the ship’s hull and not be interrupted by the disconnect switch.
Name of Testing Facility or Company_____________________________________
Test Conductor_____________________________________ Date_________________
Test Supervisor/QC_________________________________ Date__________________
20 (Rev-0)
43700_0221_210_270
REC_43700_210’ B WMEC (0620)
WORK ITEM 3: Windspeed Transmitter (Anemometer), Renew
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to renew the port side wind speed transmitter and test both the port and starboard wind speed transmitters.
1.2 Government-furnished property.
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
Y Anemometer NSN: 6600-00-709-9947 1 ea. 5,316.00
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 618 WMEC 430-050, Rev -, I.C. Distribution Panel Coast Guard Drawing 627 WMEC 437-002, Rev B, Wind speed & Direction Ind Sys Elem Wrg
Diag IC Ckt “HD & HE” Coast Guard Drawing 627 WMEC 437-003, Rev A, Wind Spd & Dir Ind Sys Ckt “HD & HE”
Block and Elem Wrg Diag Coast Guard Drawing 627 WMEC 613-001, Rev B, Main Mast Rigging, Arrg’t & Dets.
COAST GUARD PUBLICATIONS
Coast Guard Technical Publication (TP) 3234A, Dec 2012, Distribution Switchboard Coast Guard Technical Publication (TP) 5461, SWBS 421, Nov 2012, Anemometer – Model 120
& 122 Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General Requirements Surface Forces Logistics Center Standard Specification 3041 (SFLC Std Spec 3041), 2020, Shipboard Electrical Cable Test
OTHER REFERENCES
21 (Rev-0)
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
None.
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, (Vessel component, space, and equipment protection).
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, (Interferences). Known interferences include, but are not limited to the following:
• Height above the main deck.
• Electrical wiring.
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.2 Operational test, initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, and the equipment listed below to demonstrate existing operational condition. .
Submit a CFR.
• Starboard Anemometer
3.3 Wind speed transmitter renewal. The Contractor must renew the port wind speed transmitter using the Government-furnished anemometer listed above; turn over the removed anemometer to the Coast Guard Property Administrator as MTI. Make all electrical and mechanical connections using Coast Guard Drawings 618 WMEC 430-050, 627 WMEC 437-002, 627 WMEC 437-003, 627 WMEC 613-001; and TPs 3234A and 5461 as guidance.
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.4 Operational test, post repairs. After completion of work and in the presence of the Coast Guard Inspector, the Contractor must thoroughly test and demonstrate the equipment listed below to be in satisfactory operating condition.
• Port Anemometer
3.4.1 Perform continuity checks and insulation resistance measurements for the newly installed anemometer in accordance with SFLC Std Spec 3041. Submit a CFR.
22 (Rev-0)
This section is not applicable to this work item.
23 (Rev-0)
50400_0221_210_270 REC_50400_210_270_210’ WMEC ‘B’ Class (ALL) (0620)
WORK ITEM 4: Flow Meter (Aviation Fuel), Calibrate
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to inspect and calibrate the instrumentation identified in Table 1.
TABLE 1 - INSTRUMENTATION
DESCRIPTION SYSTEM USE RATING
1 ½ inch Flow meter JP-5 Helicopter refueling 50 GPM
1.2 Government-furnished property.
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
N **JP-5 Flow meter, Meter NSN: 6680-01-658-6663 1 ea. 3,800.00 N ** Counter Rotating, Register NSN: 6680-01-439-2365 1 ea. 388.00
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Bill of Materials 627 WMEC 097, Rev G, Arrangement Aviation Fuel System Coast Guard Drawing 627 WMEC 542-001, Rev E, Diagram Aviation Fuel System Coast Guard Drawing 627 WMEC 542-002, Rev E, Arrangement of Aviation Fuel System
COAST GUARD PUBLICATIONS
Coast Guard Technical Publication (TP) 3239A, SWBS 542, Section E, Feb 2020, JP-5 Flow
Meter Coast Guard Technical Publication (TP) 9142, Nov 2016, Meter – Model M-5-2 Direct Drive Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General Requirements
None
24 (Rev-0)
3.1.1 CIR.
None.
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, (Vessel component, space, and equipment protection).
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, (Interferences). Known interferences include, but are not limited to the following:
• Aviation fuel piping and contents
• Fluid pressure.
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment
3.2 Operational test, initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR
3.3 Instrument inspection and calibration. The Contractor must remove, clean, inspect, calibrate and reinstall the instrumentation identified in Table 1 in accordance with the referenced Coast Guard TP in Section 2 (References). The Contractor must refer to the Coast Guard drawings listed in Section 2 (References) for guidance while accomplishing this work item.
3.3.1 Cleaning and inspection. The Contractor must disassemble the flow meter sufficiently to expose the gears, rotors and metering chamber. Inspect and clean gear teeth, rotors and internal housing surfaces.
Submit a CFR. A soft wire brush may be used to clean surfaces, taking care not to alter the contour of the part surfaces. Remove nicks or burrs with a stone. Ensure all parts are clean and free of foreign matter prior to reassembly. Renew all disturbed seals, packing and gaskets.
3.3.2 Calibration. The Contractor must test for meter accuracy prior to disassembly and cleaning; and again after reassembly. Submit a CFR for each accuracy test. The Contractor must calibrate the meter using a certified calibration facility. The Contractor must provide a certificate of calibration to the COR.
3.3.3 Renewal. If a Change Request has been authorized and released, the Contractor must replace the…