USDA Administration Office Remodel– Statement of Work

6/17/2020

Scope:

Remodel administration area roughly 1,200 SF. See attached plan files “Demo Supply and Exhaust2 Model DWGs (1) 20200617.pdf” and “New Supply and Return2 Model Dwgs (1) 20200617.pdf”.

Supervision required onsite through the duration of the project.

Dumpsters will be provided by the GC.

Architectural Demo all existing: flooring, acoustical ceilings, blinds, and casework. Remove and discard existing modular furniture to include desks and walls. Existing door into the administration area and door to the loading dock will remain as is. Remove wall at Room E.

New work to included: (All labor and materials)

• steel stud framing, 5/8” gypsum board, level 4 finish, prime with 2 coats of interior paint.

Painting/finishing of doors and frames are required.

o Extend wall at room E for new door

• New solid core red oak wood doors for each of the new offices along with associated frame and hardware. 24x60 ¼” glass is need for each new door. 5 EACH

• Flooring – Carpet Tile J&J Smolder, Wall base – Johnsonite 4” cove base, color: TBD

• Acoustical Ceilings: USG Eclipse #76775-143, Color: Straw 24”x24”, Grid: USG DXL 15/16” color:

002 Silver Satin

• Casework – Lower casework will be P-Lam with solid surface countertop.

• Blinds – for all exterior and interior windows. (Included blinds at door glass insert) Blinds will be : Fabric – Color Empire, 5% Silver Pearl #207.

• New 3’x4 overhead counter shutter

Electrical

• Demo all existing: All existing unused electrical devices and wire back to the source. Remove all existing light fixtures and dispose of properly. Existing fluorescent lamps shall be recycled.

New work to include: (All labor and materials)

• New lighting throughout construction area (QTY 20 lights) o Shall be Metalux Encounter type fixtures (24EN LED)

• All Devices shall be 20A spec grade (Grey in color)

• All receptacle and switch plates shall be stainless steel

• All Data shall be Panduit or equal (Grey in color)

• Baseboard Heaters shall be 4’ Qmark 2500 Series Northern white in color.

• All wire to be 12 AWG THHN minimum in size

• All wire lengths over 100’ shall be 10 AWG THHN

• Flexible conduit shall be limited to 6’

Mechanical

• Demo Registers and Duct

• Demo sink and cap piping

• Revise duct to isolate office from other zone

• Modify supply air and return air duct as required

• Replace all supply air and return air registers

• Remove and replace existing booster fan with new direct drive fan

• Add new sink and revise plumbing

• Add new water cooler and revise plumbing

• Insulate revised duct at offices and exhaust fan and insulate revised water piping

• Rebalance airflow to space