This is a solicitation for dry-dock repairs to the USCGC DAUNTLESS for fiscal year 2023. The Coast Guard requires ship repair services during a period of performance from November 2nd, 2022 to January 11th, 2023. The solicitation includes a schedule of services, statement of work with specifications, and instructions for submitting price quotes. Offerors must follow all instructions and include all required documents for their quotes to be considered. The Coast Guard will evaluate quotes and make an award determination. The statement of work outlines preservation and repair requirements for various areas of the vessel in accordance with standard specifications.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFQ SHIP REPAIR COMBINED SYNOPSIS DAUNTLESS DD rev.docx.pdf | ||
| SF30 Amendment 0001 10 AUG 2022.pdf | ||
| Attachment 1SOSS BLANK.xls | XLS spreadsheet | |
| RFQ SHIP REPAIR COMBINED SYNOPSIS DAUNTLESS DD .pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC DAUNTLESS (WMEC 624)
SPECIFICATION FOR DRYDOCK REPAIRS
FY2022
Developed By: Celestin Jules
(Rev-0, 26 April 2022)
USCGC DAUNTLESS (WMEC-210B) DRYDOCK AVAILABILITY FY2022
ii (Rev-0)
TABLE OF CONTENTS
Revisions Record .......................................................................................................................................... iv Consolidated List of References .................................................................................................................... v Consolidated List of Government-furnished Property .................................................................................. x Consolidated List of Critical Inspection Items ........................................................................................... xii Principal Characteristics ............................................................................................................................ xiii General Requirements WORK ITEM 1: Hull Plating, Side Scan, Ultrasonic Testing WORK ITEM 2: Hull Plating, U/W Body, Ultrasonic Testing WORK ITEM 3: U/W Body, Preserve, 100 percent WORK ITEM 4: Hull Plating Freeboard, Preserve, 100 Percent WORK ITEM 5: Appendages (U/W), Preserve (Internal) and Leak Test WORK ITEM 6: Propulsion Shaft Fairwaters And Rope Guards, Inspect WORK ITEM 7: Voids (Non-Accessible), Preserve (Internal) and Leak Test WORK ITEM 8: Main Mast, Preserve, 100 Percent WORK ITEM 9: Propulsion Shafting, Strain Gage Alignment, Inspect WORK ITEM 10: Propulsion Propeller Shaft Coating, Inspect and Test WORK ITEM 11: Propulsion Shaft Seal (Mechanical And Inflatable) Assemblies, Inspect And Repair Or
Renew WORK ITEM 12: Controllable Pitch Propellers, Clean and Inspect WORK ITEM 13: Controllable Pitch Propeller (CPP) System, Inspect and Service WORK ITEM 14: Controllable Pitch Propeller (CPP) Hubs, Remove, Inspect and Reinstall WORK ITEM 15: Fathometer Transducer, Renew WORK ITEM 16: Sea Valves and Waster Pieces, Overhaul Or Renew WORK ITEM 17: Sea Strainers, Duplex, All Sizes, Overhaul WORK ITEM 18: Rudder Assemblies, Inspect and Repair WORK ITEM 19: Superstructure, Preserve, 100 Percent WORK ITEM 20: Cathodic Protection, Zinc Anodes, Renew, WORK ITEM 21: Drydock WORK ITEM 22: Temporary Services, Provide - Cutter WORK ITEM 23: Armory Bilge Hull Plating, Renew WORK ITEM 24: MSD Bilge Hull Plating and Stringers, Renew WORK ITEM 25: JP-5 Fuel Storage Tank Top, Renew WORK ITEM 26: Galley Deck Plating and Piping, Renew WORK ITEM 27: Raw Water Piping, Clean and Flush WORK ITEM 28: JP-5 Hull Plating, Renew WORK ITEM 29: Main Passageway Deck Plating, Renew WORK ITEM 30: Reefer Flats Deck Plating, Renew WORK ITEM 31: Deep Water Sounder, Remove WORK ITEM 32: Doppler Speed Log, Replace WORK ITEM 33: Propulsion Shafting; Remove, Inspect, and Reinstall WORK ITEM 34: Propulsion Intermediate Shafts; Remove, Inspect, and Reinstall WORK ITEM 35: Propulsion Shaft Coating, Renew WORK ITEM 36: Propulsion Shafting, Straighten WORK ITEM 37: Propeller Shaft Sleeves, Renew WORK ITEM 38: Propulsion Shaft Bearings, External, Renew WORK ITEM 39: Propulsion Stern Tube Bearings, Renew WORK ITEM 40: 32 Stores Hull Plating, Renew WORK ITEM 41: Paint Locker Deck Plating, Renew iii (Rev-0)
WORK ITEM 42: Stern Tube Interior Surfaces, Preserve, 100 Percent iv (Rev-0)
REVISIONS RECORD
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK
ITEM#
CHANGES MADE
NOTEo;o: All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
v (Rev-0)
CONSOLIDATED LIST OF REFERENCES
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.
All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.
COAST GUARD DRAWINGS
Coast Guard Bill of Materials 627 WMEC 11-001, Rev C, 3rd Dk, 2nd Dk, Main Dk., 02 Dk, 02 Dk &
Bridge Dk Plt’g & Support
Coast Guard Drawing 601-003, Rev E, General Arrangement – Second and Third Decks
Coast Guard Drawing 618 WMEC 410-001, Rev P, Seawatch Block Diagram & Installation Details
Coast Guard Drawing 618 WMEC 424-005, Rev -, Doppler Speed Log System Replacement Ripout, Installation, Arrangement, Wiring, and Details
Coast Guard Drawing 618 WMEC 424-007, Rev -, ODOM ECHOTRAC II Deep Water Depth Sounder
System Removal
Coast Guard Drawing 618 WMEC 426-003, Rev D, MK27F Gyro Compass Installation Design Plan
Coast Guard Drawing 618 WMEC 612-008, Rev C, NAVSEA Certified Flight Deck Net Installation
Coast Guard Drawing 618 WMEC 801-008, Rev -, Curves of Form
Coast Guard Drawing 627 WMEC 085-241, Rev D, Booklet of General Plans
Coast Guard Drawing 627 WMEC 085-242, Rev D, Docking Plan
Coast Guard Drawing 627 WMEC 101-001, Rev -, Structural Details
Coast Guard Drawing 627 WMEC 111-001, Rev A, Shell Expansion Framing & C.V.K.
Coast Guard Drawing 627 WMEC 116-001, Rev -, Forepeak Framing, Chain Locker & Transv. Bhds #12
& #15 ½
Coast Guard Drawing 627 WMEC 117-001, Rev B, Transverse Wen Frames Fwd and Aft of Midship
Coast Guard Drawing 627 WMEC 122-001, Rev D, Transverse Bulkhead Fwd & Aft of Midship
Coast Guard Drawing 627 WMEC 131-001, Rev D, Second & Main Deck Plating & Supports
Coast Guard Drawing 627 WMEC 133-001, Rev B, Third Deck Plating & Supports
Coast Guard Drawing 627 WMEC 152-001, Rev G, Superstructure -Aircastle, 01 & 02 Deckhouse &
Stack
Coast Guard Drawing 627 WMEC 161-001, Rev B, Arrg’t & Details Stern Tube & Strut
Coast Guard Drawing 627 WMEC 163-001, Rev C, Transducer Sea Chest Struct. Arrg’ts & Details
Coast Guard Drawing 627 WMEC 163-003, Rev C, Transducer Sea Chests Struct Arrgts & Details
Coast Guard Drawing 627 WMEC 184-004, Rev E, Doppler Sea Valve Foundations
Coast Guard Drawing 627 WMEC 184-007, Rev -, DS60 Doppler Sea Valve Foundation
Coast Guard Drawing 627 WMEC 201-003, Rev B, Arrangement of Auxiliary Machinery Space
Coast Guard Drawing 627 WMEC 243-001, Rev D, Arrangement & Detail Stern Tube Seal vi (Rev-0)
Coast Guard Drawing 627 WMEC 243-002, Rev C, Arrg’t Dets of Piping and Hydraulics
Coast Guard Drawing 627 WMEC 243-005, Rev-, Coupling (Muff) Thrust Ring & Key
Coast Guard Drawing 627 WMEC 243-006, Rev D, Line Shaft
Coast Guard Drawing 627 WMEC 243-007, Rev D, Tail Shaft
Coast Guard Drawing 627 WMEC 243-008, Rev K, Shaft Installation
Coast Guard Drawing 627 WMEC 243-009, Rev A, Arr. and Details Installation of New John Crane Seal
(Type MX9)
Coast Guard Drawing 627 WMEC 243-010, Rev-, CPP Hydraulic Storage Tank & Piping Arrangement
Coast Guard Drawing 627 WMEC 244-001, Rev B, Propulsion Shaft Alignment
Coast Guard Drawing 627 WMEC 245-001, Rev-, Hub Assy (LH)
Coast Guard Drawing 627 WMEC 245-002, Rev-, Hub Assy (RH)
Coast Guard Drawing 627 WMEC 245-003, Rev-, Control Plate Assy (LH)
Coast Guard Drawing 627 WMEC 245-004, Rev-, Control Plate Assy (RH)
Coast Guard Drawing 627 WMEC 245-008, Rev-, CPP Hydraulic System Schematic
Coast Guard Drawing 627 WMEC 245-009, Rev A, Pitch Limit Bracket
Coast Guard Drawing 627 WMEC 245-010, Rev-, Pitch Stop Installation
Coast Guard Drawing 627 WMEC 245-017, Rev E, 210 Foot B Class WMEC Major Maint Availability
Propeller Blade for 66X/4 Hub
Coast Guard Drawing 627 WMEC 245-021, Rev A, CPP Hub Modification Details
Coast Guard Drawing 627 WMEC 245-022, Rev-, Pitch Limit Bracket
Coast Guard Drawing 627 WMEC 261-001, Rev C, Diagram Fuel Oil System
Coast Guard Drawing 627 WMEC 261-002, Rev F, Arrangement of Fuel Oil System
Coast Guard Drawing 627 WMEC 320-001, Rev AZ, 440 & 115 Power One Line Wiring Diagram and
Details
Coast Guard Drawing 627 WMEC 320-002, Rev AW, Power Supplies to Electronic Equipment
Coast Guard Drawing 627 WMEC 401-001, Rev AL, I.C. & Gyro Room General Arrangement
Coast Guard Drawing 627 WMEC 401-002, Rev BK, Arrangement of Elex Eqpt Radio Room & CIC
Coast Guard Drawing 627 WMEC 401-004, Rev AR, Pilothouse Arrangement
Coast Guard Drawing 627 WMEC 424-001, Rev U, Underwater Navigation Sys Block Wiring Diagram
Coast Guard Drawing 627 WMEC 424-002, Rev V, Underwater Navigation Sys Wiring Data
Coast Guard Drawing 627 WMEC 426-001, Rev P, MK 27 Mod 1 Gyrocompass Blk Wiring Diagram
CKT “LC”
Coast Guard Drawing 627 WMEC 451-009, Rev B, 1SG38-SINS2(V)43 Installation BWD & Details
Coast Guard Drawing 627 WMEC 516-005, Rev A, Diag of SS Refrigeration Sys. & S.W. Cooling
Piping
Coast Guard Drawing 627 WMEC 521-003, Rev H, Arr. of Firemain, Sprinkling and Washdown System
2nd Dk. & Below
Coast Guard Drawing 627 WMEC 533-001, Rev K, Diagram Hot & Cold Potable Water System, Coast Guard Drawing 627 WMEC 535-001, Rev G, Diagram Steam, Feed and Condensate System Piping
Coast Guard Drawing 627 WMEC 535-002, Rev H, Arr. Stm., Feed & Condensate System Piping
Coast Guard Drawing 627 WMEC 536-002, Rev G, Arr. Of S.W. Cooling for Main and Aux Engines and
A/C Condensers vii (Rev-0)
Coast Guard Drawing 627 WMEC 562-001, Rev H, Arrg't & Details Rudder Stocks, Bearings, & Stuffing
Box
Coast Guard Drawing 627 WMEC 601-001, Rev F, Outboard Profile
Coast Guard Drawing 627 WMEC 601-003, Rev K, General Arrangement - Second and Third Decks
Coast Guard Drawing 627 WMEC 601-004, Rev D, General Arrangement Main & 01 Deck
Coast Guard Drawing 627 WMEC 602-001, Rev B, Vessel’s Name, Number, & Draft Marks
Coast Guard Drawing 627 WMEC 633-001, Rev C, Hull Protectors
Coast Guard Drawing 627 WMEC 672-002, Rev D, Storeroom 3rd Deck
Coast Guard Drawing 627 WMEC-111-001, Rev A, Shell Expansion Framing & C.V.K.
Coast Guard Drawing 627-WMEC 171-001, Rev R, MMA Main Mast Radar Platform
Coast Guard Drawing 627-WMEC 613-001, Rev B, Mainmast Rigging Arrg’t & Dets.
Coast Guard Drawing FL 184-002, Rev A, SS60 Transducer Install Adapter Assy
Coast Guard Drawing FL 6701-221, Rev R, SIRVSS & CVRS BWDs & Installation Details
Coast Guard Fleet Drawing FL 2804-12, Rev -, U.S.C.G. Emblem
Coast Guard Fleet Drawing FL 2804-22, Rev A, Consolidated Visual ID for Cutters
NAVSEA Drawing 803-1385866, Rev E, Penetration, Bulkhead and Deck
NAVSEA Drawing 803-2145807, Rev C, Propulsion Shafting and Components
NAVSEA Drawing 803-921865, Rev R, Cathodic Protection Hull Zinc Anodes
NAVSEA Drawing 804-5773931, Rev A, Acoustic & Thermal Insulation for Compartments Installation
Details oast Guard Drawing 627 WMEC 601-001, Rev F, Outboard Profile
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors
Manual
Coast Guard Technical Publication (TP) 0701, SWBS 245, Section A, Feb 2019, Controllable Pitch
Propeller
Coast Guard Technical Publication (TP) 3231A, Oct 2019, Manufacturer’s Instruction Book-SWBS
Group(s) 242-245, Chapter 243, Section A, Stern Tube Seal, MX9, US-71996
Coast Guard Technical Publication (TP) 3446, May 2013, Doppler Speed Log, Model SRD-500 Dual
Axis
Coast Guard Technical Publication (TP) 3965, Jan 2020, Air Conditioning System
Coast Guard Technical Publication (TP) 4034, Aug 2018, Electro-Hydraulic Steering System & Alarm
System Upgrade, 210’ WMEC “A” and “B” Class Cutters
Coast Guard Technical Publication E-424-027, 2012, SOUNDER, DEEP WATER - MODEL DF3200
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General
Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2020, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 0850 (SFLC Std Spec 0850), 2020, General
Requirements for Drawing Preparation
Surface Forces Logistics Center Standard Specification 3041 (SFLC Std Spec 3041), 2020, Shipboard
Electrical Cable Test viii (Rev-0)
Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2020, Shipboard
Electrical Cable Removal, Relocation, Splice, Repair and Installation
Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2020, Auxiliary
Machine Systems
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2020, Requirements for Preservation of Ship Structures
Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2020, Drydocking
Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2020, Temporary
Services
Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), 2020, Temporary
Hull Accesses
OTHER REFERENCES
Actisense Data Multiplexer NDC-4 Full User Manual
American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2019, Disinfection of Water-Storage Facilities
American Society for Nondestructive Testing (ASNT) SNT-TC-1A, 2020, Recommended Practice for
Personal Qualification and Certification in Nondestructive Testing
American Society of Mechanical Engineers (ASME) B16.34, 2017, Valves-Flanged, Threaded, and
Welding End
ASTM International (ASTM) D1330, 2015, Standard Specification for Rubber Sheet Gaskets
ASTM International (ASTM) D5363, 2016, Standard Specification for Anaerobic Single-Component
Adhesives (AN)
ASTM International (ASTM) F683, 2014, Standard Practice for Selection and Application of Thermal
Insulation for Piping and Machinery
ASTM International (ASTM) F992, 2017, Standard Specification for Valve Label Plates
Commercial Item Description (CID) A-A-59313, Nov 2003, Thread Compound; Anti-seize, Zinc Dust-
Petrolatum
DOD-STD-2187, Aug 1987, Chemical Cleaning of Salt Water Piping Systems
DS60 Doppler Speed Log Operator’s Manual
Federal Specification (Fed Spec) HH-P-151, Mar 1991, Packing; Rubber-Sheet, Cloth-Insert
IME/72640-G1, FURUNO DS60 Doppler Speed Log Installation Manual
International Standard Organization (ISO) 4406, 2017, Hydraulic Fluid Power – Fluids – Method for
Coding the Level of Contamination by Solid Particles – Third Edition
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2013 Edition, Pressure Testing Of Steel Valves
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2017 Edition, Butterfly Valves
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 2018 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service
Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2013 Edition, Bronze Gate, Globe, Angle and Check Valves
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS), SP-58, 2018, Pipe
Hangers and Supports – Materials, Design, Manufacture, Selection, Application and Installation
MIL PRF-16173, Oct 2017, Corrosion Preventive Compound, Solvent Cutback, Cold-Application ix (Rev-0)
MIL-A-18001, Dec 2015, Anodes, Sacrificial Zinc Alloy
MIL-A-22262, Mar 1996, Abrasive Blasting Media Ship Hull Blast Cleaning
MIL-L-46152E, May 1990, Lubricating Oil, Internal Combustion Engine, Administrative Service
MIL-PRF-16173, Oct 2017, Corrosion Preventive Compound, Solvent Cutback, Cold-Application
MIL-PRF-24647, Jan 2018, Paint System, Anticorrosive and Antifouling, Ship Hull
MIL-S-45180, 1998, Sealing Compound, Gasket, Hydrocarbon Fluid and Water Resistant
MIL-STD-2191, Nov 1992, Repair Welding, Weld Cladding, Straightening, and Cold Rolling of Main
Propulsion Shafting
MIL-STD-2199B (SH), Jan 2020, Covering for Waterborne Main Propulsion Shafting on U.S. Naval
Surface Ships and Submarines
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) G-6032, 2020 Grease, Plug Valve, Gasoline and Oil Resistant, NATO Code Number G-363, Metric
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2016, Solvent Cleaning
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2012, Power-Tool Cleaning to Bare Metal
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation
Standard SSPC-SP 10/NACE No.2, 2007, Near-White Blast Cleaning
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation
Standard SSPC-SP 12/NACE No.5, 2002, Surface Preparation and Cleaning of Metals by
Waterjetting Prior to Recoating
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation
Standard SSPC-SP WJ-2, 2012, Waterjet Cleaning of Metals – Very Thorough Cleaning
The Society for Protective Coatings (SSPC)/NACE International (NACE), 2007, Joint Surface
Preparation Standard SSPC-SP 10/NACE No.2, Near-White Blast Cleaning
The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation
Standard SSPC-SP 10/NACE No. 2, 2007, Near-White Metal Blast Cleaning x (Rev-0)
CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
WORK
ITEM
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
11 N Overhaul kit NSN: 2040-01-537-0557 PN:
WLP001319-001
2 kt. 30,575.00
11 N **Seal Assy NSN: 2040-01-433-6781 PN:
US71996
2 ea. 56,688.00
13 N Servo Box seal kit
(NOTE: Parts may require machining for proper fit.)
NSN: 5330-01-517-4281 2 kt. 6,561.00
14 Y **Hub Assembly (R/H) NSN: 2010-01-091-5056 1 ea. 90,220.00
14 Y **Hub Assembly (L/H) NSN: 2010-01-092-0440 1 ea. 87,439.00
14 N Hub Installation Kit NSN: 2010-01-466-4844 2 ea. 9,500.00
14 Y **Port Propeller Blades
(R/H)
NSN: 2010-01-134-7238 1 se. 33,091.00
14 Y **Starboard Propeller
Blades (L/H)
NSN: 2010-01-134-0378 1 se. 33,091.00
14 N **Propeller Blade Bolts NSN: 5306-01-225-2920 48 ea. 1,900.00
15 Y ***Fathometer
Transducer, Shallow
Water
NSN: 5845-01-518-7245 PN: FL-
6713-203
1 ea. 1,885.00
17 N 2 inch SSDG Duplex
Strainers
NSN: 4730-01-363-3085 PN: 72-
40F
2 ea. 5,840.00
17 N 6 inch MDE Duplex
Strainers
NSN: 4730-01-354-0482 PN: 72-
52F
2 ea. 23,349.00
17 N 3 inch A/C Plant Duplex
Strainers
NSN: 4730-01-614-9064 PN: 72-
44F
2 ea. 6,191.00
17 N 4 inch #1 Fire Pump
Duplex Strainer
NSN:4730- 01-173-1413 PN: 72-
48F
1 ea. 9,384.00
17 N 1½ inch EDG Duplex
Strainer
NSN: 4730-01-600-9049 PN: 72-
38F
1 ea. 3,240.00
18 N **Upper Roller Bearing
Assembly
NSN: 3110-01-080-0814 2 ea. 2,300.00
18 N **Lower Micarta Split
Bearing Assembly (9-
3/8"ID x 10-1/8"OD x
14" Lg)
NSN: 3120-01-148-3763 2 ea. 2,429.00
21 Y *Transducer Cover Plate N/A 3 ea. 50.00
32 N Display Unit, DS60 PN: DS600 2 ea. 2,400.00
32 N Distribution Unit, DS60 PN: DS610 1 ea. 1,200.00
32 N Transceiver Unit, DS60 PN: DS620 1.ea. 800.00
32 N Transducer w/30M Cable PN: DS630-30 1 ea. 200.00
32 N Gate Valve, DS60 PN: DS661 1 ea. 300.00
32 N Hull ring PN: N/A 1 ea. 350.00
32 N Bracket, DS600 Display
Unit
PN: OP26-8-1 2 ea. 100.00 xi (Rev-0)
33 Y **Propeller shaft NSN: 2010-01-092-5810 2 ea. 54,080.00
34 Y **Intermediate Line Shaft NSN: 2010-01-141-3512 2 ea. 49,651.00
37 N Inboard stern tube seal sleeve
NSN: 2010-01-187-1763 1 ea. 1,485.00
37 N Outboard stern tube bearing sleeve
NSN: 2010-01-094-8938 1 ea. 1,792.00
37 N Forward Strut Sleeve NSN: 2010-01-222-9353 1 ea. 1,917.00
37 N Aft Strut Sleeve NSN: 2010-01-222-9322 1 ea. 2,067.00
38 N Intermediate strut bearing NSN: 3120-01-027-0025 2 ea. 5516.00
38 N Aft strut bearing NSN: 3120-01-024-6328 PN:
620WPC-4301-55-BA2
2 ea. 3101.00
39 N Stern tube bearing NSN: 3120-01-027-0025 2 ea. 5,516.00
*Government-loaned property, which shall be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter xii (Rev-0)
CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.1.4
(Inspection report particulars)):
Work
Item Title
1 Hull Plating, Side Scan, Ultrasonic Testing
2 Hull Plating, U/W Body, Ultrasonic Testing
3 U/W Body, Preserve, 100 percent
5 Appendages (U/W), Preserve (Internal) and Leak Test
7 Voids (Non-Accessible), Preserve (Internal) and Leak Test
10 Propulsion Propeller Shaft Coating, Inspect and Test
Propulsion Shaft Seal (Mechanical And Inflatable) Assemblies, Inspect And Repair Or
Renew
12 Controllable Pitch Propellers, Clean and Inspect
13 Controllable Pitch Propeller (CPP) System, Inspect and Service
14 Controllable Pitch Propeller (CPP) Hubs, Remove, Inspect and Reinstall
17 Sea Strainers, Duplex, All Sizes, Overhaul
18 Rudder Assemblies, Inspect and Repair
33 Propulsion Shafting; Remove, Inspect, and Reinstall
34 Propulsion Intermediate Shafts; Remove, Inspect, and Reinstall
38 Propulsion Shaft Bearings, External, Renew xiii (Rev-0)
PRINCIPAL CHARACTERISTICS
210' WMEC (B-CLASS)
PHYSICAL
Length overall 210' 6"
Length between perpendiculars 200' 0"
Beam molded 34' 0"
Depth molded, main deck amidships 19' 6"
Full load displacement 1,170 long tons
Draft, full load to baseline amidships
*Baseline is 9” below keel amidships
12' 0"
Design drag between perpendiculars 1' 6"
Highest projection above baseline
*VHF-FM ADF antenna
90' 0"
Shore tie voltage requirements 400A / 440V
Frame spacing 1' 0"
MACHINERY
Main propulsion 2 ALCO Model 16-251-B Diesel Engines, 5,000 BHP total
Ship's service generators 2 Caterpillar Model 3406B Diesel-driven SR4, 250 KW each @ 0.8 power factor, 440VAC, 3 phase, 60 cycle
Emergency generator Caterpillar Model 3306B Diesel-driven SR4, 180 KW @ 0.8 power factor, 440VAC, 3 phase 60 cycle
Number of propellers 2
Propeller diameter 7' 6"
Number of blades, each 4
Pitch Controllable
Shaft RPM 300
Shaft diameter 8.25" at exit of hull
Anchor & chain Two 2,800 lb Navy Stockless Anchors, 7 shots of chain each
TANK CAPACITIES
Diesel fuel total (95%) 48,427 gal.
Fresh water total (100%) 11,693 gal.
JP-5 fuel total (95%) 4,683 gal.
Lube oil total (95%) 2,390 gal.
1 (Rev-0)
00000_0821_FLT
REC_00000_FLT_Commercial Project @ Contractor’ Facility (0121)
General Requirements
1. SCOPE
1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed at a commercial contractor’s facility for Coast Guard vessels.
1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and
'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is
Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General
Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2020, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2020, Requirements for Preservation of Ship Structures
OTHER REFERENCES
None
3. REQUIREMENTS
3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirements of this WI applies to all work under the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
2 (Rev-0)
3.1.1 NAVSEA drawings listed will be available FOR INSPECTION ONLY from the Coast Guard Port Engineer post-award. SFLC will not redistribute NAVSEA documents. Contractors can apply to NAVSEA headquarters directly for copies.
3.2 Fire watch requirements. The Contractor must refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec
0000, in accomplishing the following task:
Provide portable fire extinguishers for Coast Guard fire watch personnel. Coast Guard fire watch is in lieu of contractor personnel during the hours of 0800-1600, Monday through Friday, and limited to two Coast Guard fire watch personnel.
Provide fire watch personnel and fire extinguishers for the duration of the availability period, during and beyond noted Coast Guard fire watch support.
3.3 Preservation requirements. The Contractor must accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.
3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec
6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).
3.3.2 Coating colors and system color schemes. The Contractor must obtain a written KO authorization to deviate from any coatings required in SFLC Std Spec 6310 Appendix C before work.
3.3.3 In-process quality control measures. The Contractor must abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).
3.3.3.1 Quality control requirements. The Contractor must abide by the following when performing preservation related inspections. The following measurements must be randomly spaced throughout for the purposes of providing a representation of the entire prepared or coated surface.
3.3.3.1.1 Surface profile measurements. One surface profile measurement must be taken for every 200 square feet for the first 1000 square feet; for each additional 500 square feet or less, one profile measurement must be taken.
Profile measurements must be taken in accordance with SFLC Std Spec 6310, paragraph 3.1.8.3 (Surface profile measurements). A “measurement” for surface profile is defined as follows:
ASTM D4417, Method B: One profile measurement is the average (mean) of 10 individual readings.
ASTM D4417, Method C: One profile measurement is the average (mean) of 2 individual readings.
3.3.3.1.2 Soluble salt conductivity measurements. 5 conductivity measurements must be taken every 1000 square feet. For submerged (immersed) applications conductivity measurements must not exceed 30 microsiemens/cm.
For non-submerged (non-immersed) applications conductivity measurements must not exceed 70 microsiemens/cm. If a conductivity check fails, clean the surface in accordance with SFLC Std Spec 6310, paragraph 3.1.8.5 (Soluble salt removal).
3.3.3.1.3 Coating thickness measurements. Three area measurements must be taken for the first 1000 square feet;
for each additional 1000 square feet, perform an additional area measurement. A “measurements” for coating thickness is defined as follows:
SSPC-PA 2 defines an area measurement as 5 separate spot measurements randomly spaced throughout a 100 square foot area.
SSPC-PA 2 defines a spot measurement as 3 gage readings and each new gage reading the probe must be moved to a new location within a 1.5 inch diameter circle defining the spot.
3 (Rev-0)
3.4 Welding and brazing requirements. The Contractor must perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.
3.5 Environmental protection requirements. The Contractor must adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:
3.5.1 Contractor operated (non USCG) facilities. The Contractor must provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix A, Requirements for Environmental Protection at
Contractor Operated (Non USCG) Facilities, as applicable, during the performance of this availability. Contractor must plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor must comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item must not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.
3.5.2 Test and procedures. The Contractor must be required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work must be done by qualified laboratories; and where required by law, the laboratories must be certified.
3.5.3 Regulatory notifications. The Contractor must be responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The
Contractor must submit copies of all regulatory notifications to the Contracting Officer and the local Facility
Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications must be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System
(NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.
3.5.4 Environmental manager. The Contractor must appoint in writing an Environmental Manager for the project, and must be responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager must ensure compliance with Hazardous Waste
Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the
Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out; ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas;
ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the
Environmental Records binder and required documentation, including environmental permits compliance and close-out.
3.5.5 HW disposal. Contractor must comply with SFLC Std Spec 0000 Appendix A, Requirements For
Environmental Protection At Contractor Operated (Non USCG) Facilities for HW disposal.
4 (Rev-0)
3.6 Local Policy. The Contractor must refer to site (e.g. Base) Regulations and Instructions for details regarding local policies (e.g. crane services, parking, or facility usage).
3.7 SFLC Standard Specification approved changes. The Contractor must be aware that the following are approved changes to published SFLC 2020 Edition Standard Specifications and supersede published content:
3.7.1 SFLC Standard Specification 8636. Add missing paragraphs between 3.2 and 3.5 of Std Spec 8636 as follows:
“3.3 Access cut boundaries. The Contractor shall ensure that access cuts comply with the requirements and restrictions detailed in the following and in SFLC Std Spec 0740, and referenced codes.
3.3.1 Location of boundaries. Boundaries of access cuts and closure plates shall, in general, be located between principal ship framing, bulkheads, and other structural members and shall be at least three inches from any of these members or from the toes of other welds. A reduction in this three inch minimum may be approved by the
KO on a case by case basis provided sufficient clearance is maintained for welding and inspection requirements.
The boundaries of access cuts and closure plates should land on existing butts or seams, wherever practicable. The boundaries of prior access cuts should be utilized wherever possible. Boundaries may extend across one or more frames as required for the size of the opening.
3.3.2 Access hole dimensions and arrangements. Holes or access cuts shall be the minimum size necessary and shall be in accordance with the following:
Rectangular access cuts and closure plates welded into primary hull structure shall be at least 12 inches wide in the lesser dimension.
For circular access cuts, the minimum diameter shall be 4T, where T = thickness of the involved structural member, but not less than three inches.
Circular closure plates for access cuts less than two feet in diameter shall be dished 1/16 to 1/8 inch to allow for shrinkage when welded.
Corners of rectangular access cuts and closure plates shall have a minimum radius of 6 inches except when a boundary lands on an existing hull longitudinal seam or transverse butt weld.
Corners at an existing seam or butt shall intersect at a 90 degree angle.
Cuts that are to cross existing butts or seams shall do so at an angle of 90 degrees plus or minus 15 degrees.
In primary hull structure, existing welds forming the boundary of a cut shall be cut back 3 inches beyond the toe of the access cut, except that the cut back shall not intersect or cross an existing weld, frame, or structural member. In which case, the cut back may be reduced to a minimum of two inches in length.
Existing welds crossed by the cut shall not be cut back.
3.3.3 Primary hull structure. Primary Hull Structure includes the shell, main strength decks, principal longitudinal bulkheads, vertical keel, deep web girders and stiffeners designed to withstand the ship bending stress.
3.3.4 Mechanically fastened joints. Welding closer than six inches to a mechanically fastened joint should be avoided. When access cuts cross or come within six inches of a mechanically fastened joint, the fasteners shall be checked for tightness and if necessary, loose fasteners shall be seal welded or removed, and replaced for a
5 (Rev-0) distance of 6 inches beyond the edge of the cut. When a cut crosses a mechanically fastened seam the cut plates shall be repaired using single V welds backed with glass tape (MIL-C-20079) to prevent fusion between the mechanically fastened plates.
3.4 Ship integrity maintenance. The Contractor shall maintain safety and ship integrity by installing temporary guarding and coaming, in addition to weathertight and watertight closures. Remove these temporary fabrications after closing the hull access, and grind surfaces flush in way of removals. For shell plating cuts made at or below the waterline where temporary closures are impractical, the Contractor shall secure each vulnerable compartment and subdivision to minimize potential damage to the extent permitted by the scope and urgency of the work.
3.4.1 Guarding. Install temporary guards in accordance with 29 CFR 1915.73.
3.4.2 Coaming. Ensure that in areas where flammable liquids may be stored, a 4 inch high metal coaming shall be installed on the surface of the deck with tack welds and fully sealed with caulking compound. The coaming shall encircle the access cut in the deck.
3.4.3 Weathertight and contamination closures. Fabricate temporary closures, using fire retardant material, before cutting access openings and install closures whenever access is not in use. Closures shall be:
Constructed to protect the access from inclement weather and entry of contaminants (shall include a coaming or dam on the deck to redirect rain runoff away from the opening).
Fitted with fasteners that permit rapid installation and removal.
Able to support a minimum of 150 pounds per square foot for horizontal deck closures.
Where the access opening is in way of a removed hatch, scuttle or door, the closure shall be configured to allow normal passage of ship’s personnel and equipment.
3.4.4 Watertight closures. Ensure that access openings created four feet or less above the maximum anticipated waterline shall include temporary watertight closures when the vessel is waterborne.
NOTE
NAVSEA S0600-AA-PRO-160/CH16 provides requirements for design, fabrication, and installation of temporary watertight closures.”
4. NOTES
4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.
6 (Rev-0)
QA-1 - QUALITY ASSURANCE INSPECTION FORM
(PRESERVATION CHECKLIST)
VESSEL NAME HULL # WORK ITEM
WORK ITEM TITLE
LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfg.
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfg.
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
Verify equipment setup, blast media, and surface preparation methods match designated test coupon.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).
Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.
Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).
Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.
Ensure that system cure is in accordance with manufacturer's recommendation for intended service.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
For immersion coatings (including tank U/W body), record date and time of the following events:
Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME
NAME OF CG REPRESENTATIVE SIGNATURE UNIT DATE/TIME
7 (Rev-0)
QA-2 - QUALITY ASSURANCE INSPECTION FORM
(ENVIRONMENTAL READINGS)
VESSEL NAME HULL #
WORK ITEM
Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.
DATE
TIME
ACTIVITY (SURFACE
PREPARATION, PRIMER COAT,
BARRIER COAT, TOP COAT,
ETC…)
LOCATION (FRAME &
DECK, RELATION TO
EQUIPMENT, ETC.)
TEMPERATURE % REL.
HUMID-
ITY
DEW
PT.
SURFACE AMBIENT ΔT
| DP -
SURFACE |
8 (Rev-0)
QA-3a - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)
VESSEL NAME HULL # WORK ITEM
LOCATION OF WORK (FRAME REFERENCES) AREA (SQFT)
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area)
Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS
PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS
DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:
9 (Rev-0)
QA-3b - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)
VESSEL NAME HULL # WORK ITEM
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area)
Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT
QA RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO
SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Mean Mils Reading (IAW ASTM D4417-Method B for above 10 readings (by column):
Mean Reading
(mils)
10 (Rev-0)
QA-4 - QUALITY ASSURANCE INSPECTION FORM
(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)
VESSEL NAME HULL # WORK ITEM
SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.
DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)
11 (Rev-0)
QA-5 - QUALITY ASSURANCE DATA FORM
(COATING THICKNESS)
(Use one sheet for each sequence)
VESSEL NAME HULL #
WORK ITEM
COATING MFG PRODUCT NAME
BATC
H #
INDUCTI
ON TIME
COATING SYSTEM
SEQUENCE
(PRIMER/TOUCHUP/3RD
COAT, ETC.)
DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.
SPOT 1 2 3 4 5
AVERAGE
VALUE
*BASE METAL READING
(BMR)
*Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
APPLICATION METHOD (AIRLESS,
CONVENTIONAL SPRAY, ROLLED)
AVERAGE DFT
12 (Rev-0)
11000_SideScan_ESD_1021_FLT
REC_11000_Side_Scan_FLT_210 WMEC ‘B’ Class (ALL) (0821)
WORK ITEM 1: Hull Plating, Side Scan, Ultrasonic Testing
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to perform thickness measurements of underwater (u/w) hull plating by ultrasonic side scan method.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 627 WMEC 085-242, Rev D, Docking Plan
Coast Guard Drawing 627 WMEC 111-001, Rev A, Shell Expansion Framing & C.V.K.
Coast Guard Drawing 627 WMEC 562-001, Rev H, Arrg't & Details Rudder Stocks, Bearings, &
Stuffing Box
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General Requirements
OTHER REFERENCES
American Society for Nondestructive Testing (ASNT) SNT-TC-1A, 2020, Recommended
Practice for Personal Qualification and Certification in Nondestructive Testing
3. REQUIREMENTS
3.1 General. The Contractor must refer to the Coast Guard Drawings listed in Section 2 (References) as guidance in accomplishing this work item.
3.1.1 CIR. The Contractor must submit a CIR for the inspections listed in the following paragraph(s):
3.3 Side scan requirements and procedures.
3.1.2 Tech Rep.
Not applicable.
13 (Rev-0)
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, (Vessel component, space, and equipment protection).
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, (Interferences). Known interferences include, but are not limited to the following:
Hull zinc anode system
Docking blocks
3.2 Work coordination and preparation. The Contractor must plan all specified vessel work detailed in this specification package to ensure the side scan survey does not necessitate a work stoppage. The
Contractor must abide by the following guidance, to facilitate the ultrasonic survey:
Ensure that all u/w body surface preparation and primer coat application tasks are completed within ten days of lifting the vessel.
Provide a continuous supply of fresh water at .50 gpm within 50 feet of the vessel with standard hose bib fitting.
Provide 110 VAC electrical power, and scaffolding or other suitable means of access to bring inspection personnel within one foot of all the body surface inspection areas that are five feet above ground level.
After completion of the hull survey, and authorized hull repairs, resume/complete u/w body preservation process by applying the second coat of the anti-corrosive coating system, and all anti-fouling paint coats.
Pay close attention to manufacturer’s recommended practices in regards to paint system overcoat time limitations and required degree of surface cleanliness prior to resuming u/w body coating application.
3.3 Side scan requirements and procedures. The Contractor must ensure the following referring to the
Coast Guard drawings listed in Section 2 (References) herein as guidance during the performance of the tasks specified below and submit a CIR.
3.3.1 Testing company and personnel. Provide the services of a qualified ultrasonic testing company, with suitable side scan equipment, to conduct a “Scanning Crawler Automated Test” of the vessel’s u/w hull plating for the presence of metal corrosion and deterioration. Ensure the following:
All scanning operations are completed by personnel meeting the personnel qualification and certification, as required by contractor process. This contractor-developed personnel qualification and certification process must meet, at a minimum, ASNT Recommended
Practice No. SNT-TC-1A.
An SNT Level III Analyst is on site, to oversee the project and evaluate the collected data.
An SNT Level III or II Analyst is on site, to verify with a hand held gauge all areas on the hull identified as thinner than the specified criteria, in order to expedite all repair procedures.
Qualified personnel are provided to complete all on-site corrosion inspections.
3.3.2 Coast Guard notification. Accomplish all required tasks within 10 calendar days of the start of the availability.
3.3.2.1 Provide a daily update to the COR on all areas inspected and potential issues or schedule changes.
14 (Rev-0)
3.3.2.2 Notify the COR at least 3 days prior to completion for an onsite review of readings and repair areas.
3.3.3 Scanning parameters. Use the following parameters during the course of this inspection:
Automated scanning resolution must be set to 0.5” x 0.5”
Plates where scan data indicating wastage greater than or equal to 25% nominal plate thickness must be highlighted in “RED” and designated “repair areas”.
Plates where scan data indicating wastage greater than or equal to 15% to 24%…