Attachment_1_-_Statement_of_Work.pdf

PDF 4 MB Posted

Attached to
DEVA EMERGENCY HVAC & EVAP COOLER RPLCMT Federal contract opportunity
Solicitation number
140P8124Q0083
Issued by
Department of the Interior National Park Service Pacific West Region

About this file

This document is a Statement of Work (SOW) for a federal contract opportunity to replace heating, ventilation, and air conditioning (HVAC) systems, including evaporative coolers, at various facilities within Death Valley National Park.

The SOW provides background on the project goal to replace failed or failing HVAC equipment to improve heating and cooling for employees, residents, and visitors. The work is to be performed at multiple locations within the park, including Furnace Creek, Cow Creek, and Stovepipe Wells Village. The contractor shall remove existing HVAC units, install new Energy Star-rated equipment, and perform associated electrical, plumbing, and finish work. Hazardous materials surveys are provided, and the contractor must use industry best practices to minimize exposure. The contractor shall provide one-year parts and labor warranty and respond within specified timeframes to service requests. The work must be completed within 90 calendar days after the notice to proceed is issued. The contractor shall comply with all applicable laws, regulations, and policies, including obtaining required licenses and certifications.

View the file

Other files for this federal contract opportunity

Other files attached to DEVA EMERGENCY HVAC & EVAP COOLER RPLCMT, newest first.
File Type Posted
Sol_140P8124Q0083_Amd_0002.pdf PDF
Drawings_Quarters_0002.pdf PDF
Sol_140P8124Q0083_Amd_0001.pdf PDF
Sol_140P8124Q0083.pdf PDF
Attachment_4_-_Coyote_Loop_Asbestos_Survey_2024.pdf PDF
Attachment_2_-_Price_Schedule.xlsx XLSX spreadsheet
Attachment_3_-_Wage_Determination_-_CA20240029_01_12_2024.pdf PDF
Attachment_6_-_Construction_Contract_Administration_Notice.pdf PDF
Attachment_5_-_Asbestos_Containing_Materials_Survey_2011.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work: HVAC Replacement in Death Valley National Park

PMIS 342948

National Park Service

Death Valley National Park

Inyo County, California

1. Background

a. Project Goal: The goal of this project is to replace failed or failing heating, ventilation, and air conditioning (HVAC), which, herein, includes evaporative coolers, at Death Valley National Park with consistent equipment that will provide heating and cooling for the comfort and safety of employees, residential tenants, and visitors.

b. Location: Death Valley National Park is approximately 3.4 million acres in Eastern California and Southern Nevada. Furnace Creek, where the Park headquarters is, is on California Highway 190 (CA-190), about 120 miles west of Las Vegas, Nevada and 300 Miles northeast of Los Angeles, California. The project includes work at Furnace Creek, Cow Creek, 3 miles west of Furnace Creek on CA-190, and Stovepipe Wells Village, 25 miles west of Furnace Creek on CA-190. The project area includes all the Park’s developed areas, including, but not limited, to Furnace Creek, Cow Creek, Stovepipe Wells, Emigrant, Grapevine, and Scotty’s Castle.

c. Issues: Death Valley National Park is the hottest place on Earth. In July, the hottest month ever recorded, Death Valley had 9 consecutive days over 125°F, multiple thunderstorms, and a more-than-three-day power outage. Extreme weather events and unstable power have caused numerous mechanical system failures in June and July of 2024. This project will replace units that are beyond their useful life and/or damaged beyond repair.

d. Objective: Damaged HVAC systems in 15 facilities shall be replaced in Death Valley National Park. This will require ancillary electrical and plumbing work to connect HVAC units. Old equipment shall be removed and disposed or recycled at appropriately licensed facilities.

e. Hazardous Materials: Work is not expected to impact asbestos containing materials.

However, asbestos containing materials are present in some of the facilities. A good faith survey of asbestos containing materials is provided to ensure that asbestos is not disturbed by the work. Facilities may also have lead-based or lead-containing paint or other hazardous materials that are not expected to be impacted. The Contractor shall use industry best practices to minimize employee and tenant exposure to hazardous materials.

f. Energy Efficiency: All units shall be Energy Star rated with a SEER2 rating not less than

16. Gas furnaces, if installed, shall be 96% efficient and compatible with the fuel supply at the facility.

2. Project Tasks

a. The Contractor shall perform the following tasks.

i. Remove existing equipment to be replaced, including any existing mounting hardware, appurtenances, and associated components.

ii. Cap junction boxes, duct vents, piping, conduit, or similar when abandoned in place according to appropriate laws, codes, best practices, or similar.

iii. Restore exterior siding/roofing and interior walls/ceilings of facilities where equipment is removed, installed, or replaced with equipment of different size, which shall include filling holes in walls and finishes, repairing damaged finishes to include texturing, painting, or similar, to create a uniform finish in, around, and adjacent to the work.

iv. Ensure all penetrations are adequately sealed to prevent loss of conditioned air and infiltration of outside pests, air, and debris.

v. Recycle or dispose of removed equipment, material, and construction debris at an appropriately permitted facility outside the Park according to applicable laws.

Provide the approximate tonnage of waste disposed and material recycled.

vi. Perform vent-testing procedures in accordance to American National Standard ANSI Z21.47 to assure proper venting.

vii. Install vent/flue pipe at proper vent size and connectors.

viii. Install air conditioning coils on top of furnaces. Ensure that units are mounted so that proper draining of condensation can occur.

ix. Install drain pan, trap, and lines per the manufacturer’s recommended configuration.

x. Where concrete footings are inadequate, install concrete pads in place per manufacturer’s recommended dimensions. Adjustable stands may be substituted for concrete footings where acceptable by code and manufacturer’s recommendations. Stands shall have sun and rain protection where it will not interfere with the operation of the equipment. Location of pads, stands, and equipment when not replaced in-kind shall be defined by the contractor and approved by the COR prior to installation.

xi. Install new electrical service where required. Electrical service lines shall be installed to conceal them as much as possible in attic, crawls spaces, and walls.

Electrical service lines may be installed on the exterior north wall of the Cow Creek Ranger Station.

xii. Install copper, or approved equal, refrigerant lines from air condensers (or similar) to air conditioning coils (or similar). Line sets shall be insulated and installed to conceal them as much as possible in attic, crawl spaces, and walls.

Where line sets are not concealed, they shall be covered with line set covers suitable for the location, including color and sunlight resistance.

xiii. Install duct transitions from new HVAC units to existing building ducting.

xiv. Install new thermostat at existing thermostat location. If existing thermostat wires are incompatible with the new equipment, required wiring shall be installed and traced through walls for the new thermostat to function as intended by manufacturer.

xv. Paint and repair any unfinished wall/ceiling/floor interior/exterior surfaces created by replacing HVAC units this may require caulk, flashing, transitions, or painted wood trim.

xvi. All installation shall be in accordance with manufacturer specifications.

xvii. Test newly installed HVAC system by performing manufacture gas pressure test, temperature rise test, AC leak test, heating and cooling test, and any other tests recommended by the manufacturer or industry standards.

xviii. Provide training on each type of unit to include user interface controls and common troubleshooting.

3. Project Product List

a. All replacement units shall be of the same make and similar series or model across tonnages. Commercial products may be installed in residential applications. Residential products shall not be installed in commercial applications.

b. Central HVAC units shall be Daikin, Trane, or approved equal.

c. Mini-split heat pumps shall be Daikin, Trane, Pioneer, or approved equal.

d. Cabinet HVAC units shall be Rittal 3302.100, or approved equal.

e. Evaporative Coolers shall be Master Cool ASA7112 side-ducted single-inlet, or have fully interchangeable parts with the Master Cool ASA7112. Evaporative coolers shall be complete and functional units; including, but not limited to, housing, motors, pumps, evaporative media, diffusers, hoses, pulleys, belts, controls, etc.

f. The Contractor may submit HVAC units of different size and capabilities based on professional opinion of the most efficient and effective HVAC units for the building/unit size. Replacement of central units with mini-split heat pumps may be considered, provided there is not less than one head unit or cassette in each occupied room (e.g., kitchens, living rooms, bedrooms, offices, etc.). There shall be no additional cost to the Government for hazardous materials testing, abatement, or work.

g. Equipment by location:

Facility Unit Qty Page # CC321 - Cow Creek Ranger Station 5-ton Central heat pump 1 5 CC321 - Cow Creek Ranger Station Two-zone mini-split 1 5 SPW351 - Stovepipe Wells Ranger Station 5-ton Central heat pump 1 6 CCQ129 Skyline Drive 5-ton Central heat pump 1 7 CCQ336A Coyote Loop 5-ton Central heat pump 1 8 CCQ1 Canyonview Court 4-ton Central heat pump 1 9 CC51 - Warehouse 4-ton Central heat pump 1 10 CC348 - Auto Shop 3-ton Central heat pump 1 11 CCQ343A-D Nevares Springs Road 3-ton Central heat pump 4 12 FC270&271 - Furnace Creek Visitor Center and Headquarters Evapco VSD fan 1 14 Furnace Creek Water Plant Bulk Chlorine Storage Room Single-zone mini-split 1 15 CCQ343A Nevares Springs Road MasterCool ASA7112 1 16 CCQ222A-F Skyline Drive MasterCool ASA7112 6 17 CCQ120 Skyline Drive MasterCool ASA7112 1 18 Furnace Creek Water Plant Wellhead 1 Rittal 3302.100 1 19 Furnace Creek Water Plant Wellhead 2 Rittal 3302.100 1 20

i. Cow Creek Ranger Station CC321

1. The facility was constructed in 1988 and is 2,440 gross square feet.

Approximately 958 GSF are served by the 5-ton unit.

2. No asbestos in the facility, see Attachment 5 - Asbestos Containing

Materials Survey 2011.

3. Remove one 5-ton central heat pump system and replace it with one 5-ton central heat pump system.

4. Install one two-zone mini-split system in two storage rooms with sensitive material.

5. Photograph of existing equipment.

ii. Stovepipe Wells Ranger Station SPW351

1. The facility was constructed in 2007 and is 1,000 gross square feet.

2. No asbestos in the facility, see Attachment 5 - Asbestos Containing

Materials Survey 2011.

3. Remove and replace one 5-ton central heat pump system with a 5-ton central heat pump system.

4. Photograph of existing equipment.

iii. 129 Skyline Drive

1. The facility was constructed in 1958, a historic structure, and is

1,253 gross square feet.

2. Asbestos found in facility, see Attachment 5 - Asbestos Containing

Materials Survey 2011.

a. 9”x9” floor tiles and underlying mastic

b. Wallboard joint compound

c. Spray applied acoustical finish, white (popcorn ceiling)

d. Wall panel adhesive, behind existing finishes (shower insert, assumed)

3. Remove and replace one 5-ton central heat pump system with a 5-

iv. 336A Coyote Loop

1. The facility was constructed in 1999 and is 3,106 gross square feet.

The facility is a duplex with two 5-ton units each cooling approximately 1,200 GSF.

2. No asbestos in facility.

a. 2011 survey assumed asbestos in joint compound.

b. 2024 found joint compound non-detect, clearing facility see Attachment 4 - Coyote Loop Asbestos Survey 2024.

3. Remove and replace one 5-ton central heat pump system with a 5-

v. 1 Canyon View Court

1. The facility was constructed in 1933, a historic unit, and is 1,051 gross square feet.

2. Asbestos in facility, see Attachment 5 - Asbestos Containing Materials Survey 2011.

a. Black sheet flooring adhesive

b. Covebase mastic, beige

c. Joint compound

d. 9”x9” floor tile and mastic

e. Spray applied acoustical finish, white (popcorn ceiling)

f. Grey exterior stucco (assumed)

3. Remove one 4-ton heat pump system and replace it with one 4-ton heat pump system.

vi. Cow Creek 51 - Warehouse

1. The facility was constructed in 1935, a historic unit, and is 1,448 gross square feet. The unit cools a Bally Box walk-in cooler.

2. No asbestos in this facility, see Attachment 5 - Asbestos Containing

Materials Survey 2011.

3. Remove one 4-ton heat pump system that cools a walk-in cold storage facility and replace it with one 4-ton heat pump system that cools a walk-in cold storage facility.

vii. Cow Creek 348 - Auto Shop

1. The facility was constructed in 2003 and is 8,999 gross square feet.

The unit cools only office space, approximately 1,700 GSF.

2. No asbestos in this facility, see Attachment 5 - Asbestos Containing

Materials Survey 2011.

3. Remove one 3-ton central heat pump system and replace it with one 3-ton central heat pump system.

viii. 343A-D Nevares Springs Road

1. The facility was constructed in 1997 and is 2,940 gross square feet.

The facility is a 4-plex apartment complex with four similar units each with one 3-ton unit cooling approximately 735 GSF.

2. Asbestos assumed in this facility, see Attachment 5 - Asbestos Containing Materials Survey 2011.

a. Joint compound was assumed to be asbestos-containing materials.

3. Remove and replace four 3-ton central heat pump systems with four 3-ton central heat pump systems.

4. Photographs of existing equipment in order A-D.

ix. Furnace Creek Visitor Center & Headquarters Cooling Tower

1. The facility was constructed in 2011 and provides cooling to FC270 and FC 271, approximately 19,808 gross square feet.

2. Presence of asbestos unknown, asbestos in served facilities, see

Attachment 5 - Asbestos Containing Materials Survey 2011.

3. Remove one Evapco Cooling Tower VSD fan and replace it in-kind with one Evapco Cooling Tower VSD fan.

x. Furnace Creek Water Plant Bulk Chlorine Storage Room

1. The facility is an insulated shipping contain, approximately 80 gross square feet holding an approximately 683 gallon tank approximately 6-foot diameter by 3.5 foot height.

2. No known asbestos, none assumed owing to age of construction, no attachments.

3. Remove and replace one single-zone mini-split system with one single-zone mini-split system.

4. Photographs of existing equipment.

xi. 343A Nevares Springs Road

1. The facility was constructed in 1997 and is 2,940 gross square feet.

The facility is a 4-plex apartment complex, this evaporative cooling unit serves unit D, approximately 735 GSF.

2. Asbestos assumed in this facility, see Attachment 5 - Asbestos Containing Materials Survey 2011.

a. Joint compound was assumed to be asbestos-containing materials.

3. Remove one evaporative cooler and replace it with one Master Cool ASA7112 side-ducted single-inlet evaporative coolers.

xii. 222A-F Skyline Drive

1. The facility was constructed in 1966, a historic unit, and is 4,386 gross square feet. The facility is a 6-plex apartment complex with units of differing sizes. All evaporative coolers shall be the same make and model with interchangeable parts.

2. Asbestos found in facility, see Attachment 5 - Asbestos Containing Materials Survey 2011.

a. Sheet flooring adhesive, beige (Assumed, note that tested sheet flooring adhesive was non-detect).

b. Some wallboard and joint compound.

c. 9”x9” tile and mastic.

d. Exterior stucco material, grey (assumed)

3. Remove six evaporative coolers and replace them with six Master Cool ASA7112 side-ducted single-inlet evaporative coolers.

4. Photograph of existing equipment. (Note, the units are on the roof.)

xiii. 120 Skyline Drive

1. The facility was constructed in 1958, a historic unit, and is 1,523 gross square feet.

2. Asbestos in facility, see Attachment 5 - Asbestos Containing

Materials Survey 2011.

a. Sheet flooring adhesive, black

b. Wallboard joint compound (most, but not all)

c. Spray applied acoustical finish, white (popcorn ceiling)

d. Covebase mastic (assumed)

e. 9”x9” tile and mastic

f. Exterior stucco material grey and white (assumed)

3. Remove one evaporative cooler and replace it with one Master Cool ASA7112 side-ducted single-inlet evaporative cooler.

xiv. Furnace Creek Water Plant Wellhead 1

2. Unknown asbestos, assumed none owning to age of facility, no attachments.

3. Remove one cabinet HVAC unit and replace it with one cabinet

HVAC unit.

xv. Furnace Creek Water Plant Wellhead 2

2. Unknown asbestos, assumed none owning to age of facility, no attachments.

3. Remove one cabinet HVAC unit and replace it with one cabinet

HVAC unit.

4. Submittals

a. The Contractor shall provide the following submittals at the required deadlines after award.

i. The following items shall be submitted a minimum of one week prior to the preconstruction conference. Contracting Officer will notify Contractor of tentative date for the preconstruction conference. All items listed must be provided to the Contracting Officer before the preconstruction conference is held. If all of these documents have not been received one week prior to the scheduled preconstruction conference date, the conference will be cancelled, the Notice to Proceed will not be issued, and the Contracting Office will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.

1. Letter designating the Project Superintendent.

2. Payment and Performance Bonds.

3. Construction schedule detailing mobilization/demobilization dates, dates detailing location and work being accomplished, any potential days where HVAC service may be down, and crew size and makeup.

4. Accident Prevention Plan.

5. Site Specific Safety Plan.

6. A list of Subcontractors for this project.

7. Written statements from subcontractors certifying compliance with applicable labor standard clauses.

8. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contractor and all subcontractors.

ii. Applicable licenses and/or certificates of all personnel. DEADLINE 30 days after award or before Notice to Proceed is Issued.

iii. Product submittals of proposed brand and model of equipment. DEADLINE 30 days after award or before Notice to Proceed is issued.

iv. Product manuals that include information related to operations, maintenance, and manufacturer’s warranty. If the manufacturer’s warranty exceeds the Contractor’s warranty, the Contractor shall provide all required documents to make a warranty claim. DEADLINE at time of acceptance.

v. Approximate tonnages of waste and recycled material, and copies of any hazardous materials manifests. DEADLINE at time of acceptance.

vi. Submit (1) copy of operation and maintenance manual with a preventative maintenance schedule, product cut sheets, specific warranties, guarantees, workmanship bonds, final certifications, and similar documents.

vii. Posted Operating Instructions: Furnish operating instructions attached to or posted adjacent to equipment. Include wiring diagrams, control sequence, start-up, adjustment, operation, lubrication, shut-down, safety precautions, procedures in the event of equipment failure, and other items of instruction recommended by the manufacturer.

viii. Deliver tools, spare parts, extra materials, and similar items to location designated by Contracting Officer. Label with manufacturer’s name and model number where applicable.

ix. Instruct NPS personnel in the basic operation, adjustment, and maintenance of products, equipment, and systems.

x. An optical disc containing electronic copies of all submittals. DEADLINE at time of acceptance.

xi. The Government does not anticipate as-built drawings will be required.

However, significant changes to electrical, mechanical, or other systems that are not inherently apparent shall be documented on as-built drawings. Examples include, but are not limited to, hidden electrical lines, hidden line sets, and changes to structural elements of the facilities. One set of not smaller than Ach D, or ISO equivalent size, red-line drawings shall be maintained at the site. Upon completion of the project, significant changes to electrical, mechanical, or other systems that are not inherently apparent shall be documented in three sets of as-built drawings not-smaller-than Arch D, or ISO equivalent size, shall be provided to the Park; one optical disc containing .dwg and .pdf electronic as-built drawings; and one electronic file transfer of .dwg and .pdf electronic as-built drawings.

5. Contractor Use of Premises

a. The Contractor Shall always adhere to the following while working within Death Valley

National Park.

i. There are five (5) historical units in the SOW. These historical units require special care. Significant changes to line sets, electrical runs, and unit placement must be approved prior to beginning work. This will include a walk through with the COR to determine if work will be outside of the Programmatic Categorical Exclusion (PCE 102978). This document is not included within the SOW or contracting documents. The units in question are the following:

1. 129 Skyline Drive

2. 1 Canyon View Court

3. Cow Creek 51

4. 222A-F Skyline Drive

5. 120 Skyline Drive

The PCE allows for the following

• in-kind replacement of HVAC thermostat, which may include upgraded digital components and software;

• repair or in-kind replacement of minor physical unit components (ductwork, pipes, valves, switches, etc.);

• installation of copper piping through existing exterior penetration that runs internally in attic crawl space to each power head;

• repair or in-kind replacement of major components and systems (e.g.

swamp coolers, condensers, compressors, motors, furnaces);

• repair or in-kind replacement of concrete pads for exterior system components; pads must be in the same location and same-sized;

• replacement of coolant or refrigerant;

• repair of electric systems within or associated with the unit(s).

The PCE also covers minor interior access needs in the event some components (e.g. refrigeration lines) within buildings need to be replaced and are blocked by a wall. In these cases, the interior walls may need to have small openings cut for access to the system. The PCE covers impacts to the walls that would be a maximum of 6'' by 6'' cuts and which would be repaired and repainted or covered to match existing colors and textures. In the Mission 66 buildings, the walls are wood frame with gypsum board. The CCC buildings with HVAC systems have non-historic interior walls, typically also made out of gypsum board, to provide space for utilities.

ii. Some of the project occurs in park housing area. Contractor shall be respectful of the tenants of the housing area and confine workspace and areas to not impede on tenants. Noise will be kept at a minimum and access to indoor spaces will be at the request of the contractor with not less than 24-hour notice to the tenant.

iii. Some of the project occurs in public areas of the Park. The Contractor shall be respectful of Park visitors and minimize impacts to the visitor experience.

iv. The Contractor shall be identifiable through the use of uniforms, name tags, marked vehicles, high-visibility vests, hats, or hardhats with company logo, or similar, and maintain a professional decorum and appearance.

v. The Contractor shall furnish a list of personnel with phone contact information.

vi. Do not drive vehicles off road or access non-project areas without permission from the contracting officer representative.

vii. Ensure all personnel (contractors, subcontractors, and vendors) entering or working in the park are familiar with and obey all park regulations. Law enforcement rangers will intervene if they perceive any unsafe or unlawful activity.

viii. Working hours shall be 06:00-16:30 for operational buildings and 07:00-17:00 for residential buildings Monday through Friday, excluding Government holidays.

Work outside regular hours requires approval from the contracting officer and the Park’s Chief Ranger (or their designee). Requests for work outside of regular hours must be submitted not-less-than two working days in advance.

ix. Contractor shall not enter housing units without an NPS escort.

x. Smoking is prohibited inside or outside within 25 feet of any buildings in the

Park. This applies to existing buildings, buildings under construction, and buildings under renovation. Discarding of tobacco products or debris anywhere other than into designated tobacco receptacles is considered littering and subject to fines.

xi. Confine storage of equipment and materials to the staging / lay-down/ storage areas identified by the COR or as established at the preconstruction meeting.

xii. The contractor shall park vehicles and heavy equipment in designated areas for contractor use or as established at the preconstruction meeting.

xiii. The Contractor shall keep driveways and entrances serving the premises clear and available to the Government, government employees, tenants, the public, and emergency vehicles always.

xiv. Prevent damage to natural surroundings. Restore damaged areas and replace damaged trees, vegetation, and grass at no expense to the Government.

6. Period of Performance

a. All tasks and deliverables shall be completed within 90 calendar days after notice to proceed.

7. Compliance

a. While performing work, the Contractor shall comply with all laws, regulations, and policies, to include, but not be limited to, the latest applicable versions of the following.

i. NFPA 101

ii. California Title 24 Building Energy Efficiency Standards

iii. California Refrigerant Management Program, Air Resources Board

iv. MUTCD Standards and Policies

v. Occupational Safety and Health Administration (OSHA) Regulations

vi. NFPA 58 Petroleum Gas Code

vii. NEC Code Article 690 with respect to California Code

viii. CCR Title 16 Division 8

b. Additional Requirements

i. Licensure: All work shall be performed by workers who hold appropriate licenses in one of the 50 States, the District of Columbia, Puerto Rico, or other US territory. Where allowed by the state issuing the license, work may be conducted by unlicensed workers provided the work is overseen by a licensed worker. With approval by the Contracting Officer, certification from North American Technician Excellence (NATE), or similar, may substitute for state licensure provided it does not prevent the Contractor from obtaining necessary materials.

ii. All affected areas must be left in a clean and tidy condition. Any damages to Government property will be fixed and repaired at no cost to the Government.

iii. All new equipment, supplies, and products must conform to the manufacturer’s instructions and guidelines.

iv. Contractor shall provide one-year parts and labor warranty.

v. Contractor shall respond within 72-hours’ notice of HVAC system service request

1 May – 30 September, and within 10 calendar days 1 October – 30 April.