Attachment 1 - SOW Grinder Pump Install and Sewer Stormwater Repairs 5-23-23.pdf

PDF 670 KB Posted

Attached to
Grinder Pump Install and Sewer & Stormwater Repairs Federal contract opportunity
Solicitation number
W50S8J-23-Q-0010
Issued by
Department of the Army New York Army National Guard

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Project Number VBDZ232109

Install Grinder Pump and Sewer & Stormwater Repair

DESCRIPTION:

Bid Line Scope Description Base bid Install Grinder Pump Sanitary line has insufficient change in elevation between the building cleanout and the nearest manhole discharge location.

Base bid Repair two (2) catch basins Catch basins separated from pavement Base bid Repair one manhole Manhole rim damaged Option 1 Replace a fire hydrant Building 19.

Option 2 Repair three fire hydrants Fire hydrants spray and leak when opened.

1. PROJECT SCOPE

1.1. Install grinder pump at Building 2A

1.1.1. Contractor is to excavate the area immediately outside of building 2A to approximately 6 to 7 feet in depth. OSHA compliant excavation protection and procedures are to be utilized. Excavation area is near a high traffic flow entranceway.

1.1.2. The existing cleanout structure is not positioned properly (currently tilted) and is to be removed and replaced with a new 4” cleanout that will be purchased and installed by the Contractor. Cleanout discharge piping is to connect to grinder pump, potentially with elbows to create a clean sweep and prevent potential clogging of solids prior to grinder pump inlet. Design and all connection fittings to be approved by COR prior to installation.

1.1.3. Contractor to purchase and install a new fully contained grinder pump station that contains a grinder pump, check valve, high density polyethylene (HDPE) tank, controls and alarm panel. Grinder pump is to have the following specifications:

1.1.3.1. Rated for flows of 700 gallons per day (gpd)

1.1.3.2. Holding capacity of 70 gallons

1.1.3.3. Outdoor installation

1.1.3.4. Hardwired model where the cable connects the motor controls to the level controls through watertight penetrations.

1.1.3.5. Concrete ballast to be installed with grinder pump tank to prevent buoyancy per manufacturer’s directions.

1.1.3.6. Grinder pump to be an eOne Extreme Series DH071, or equivalent per

Attachment 1.

1.1.3.7. Motor to be a 1 hp, 1,725 rpm, high torque, capacitor start, thermally protected, 120/240V, 60 Hz, 1 phase.

1.1.4. Contractor to install a new electric line from grinder pump to electric panel within

Building 2A electrical room. Installation will involve above ceiling work and routing a line between walls.

1.1.5. Contractor to install an alarm panel for high water on the outside of the building, or in a location approved by the COR.

1.1.6. Grinder pump to have a certified start-up with pressure testing by an independent contractor. Cost of start-up and testing is to be included in bid pricing by Contractor.

Contractor to arrange for testing.

1.1.7. Contractor to provide an as-built sketch of installation, 10-yr warranty (or longer) for grinder pump, and operation and maintenance manuals.

1.1.8. Outlet of grinder pump to have a lateral kit purchased and installed (see Attachment 2, or equivalent), and then discharge to enter a new 2” sewer line that will be positioned inside of an existing 6” sewer line. New sewer line is approximately 80’ long. The distances shall be verified by the contractor.

1.1.9. Manufacturer installation instructions should be followed. E-One instructions are included in Attachment 3. Alternate equivalents may be approved by the COR through a submittal process. Submittal to include manufacturer installation instructions.

1.1.10. All the wiring shall be in conduit except 12” loop left of cable left to allow for shifting and settling.

1.1.11. Bedding material shall be 6” of round aggregate ¾” max.

1.1.12. Final discharge piping modifications and concrete sealing at manhole is to occur to prevent content from discharge manhole from entering space between existing 6” SDR sewer line and new 2” discharge line from the grinder pump. Sealant is to be watertight.

1.1.13. Discharge within manhole shall be directed to downstream manhole outlet by installing PVC elbows as required. Design shall be approved by COR prior to installation and should not hinder flow from other locations that are discharging into the manhole.

1.1.14. Confined space entry will be required by Contractor. This manhole also receives sanitary waste from multiple other buildings (Building 1, Building 2A new addition, and lift station discharge that serves the fire station, POL facility, and vehicle maintenance). Work must be coordinated to occur within manhole on an alternating work schedule (AWS) day. AWS days occur in the base work schedule approximately one Friday, every two weeks. Schedule will be provided by COR to Contractor prior to the pre-construction meeting.

1.1.15. Site map is below. Currently, there is a 4” line exiting the building. The 4” line enters a cleanout that is improperly positioned. The distance between the cleanout and the closest sanitary manhole is approximately 75’. Currently, there is a 6” diameter SDR line between the cleanout and the manhole.

1.1.16. Contractor shall backfill using Class 1B, apply topsoil to grade, and seed. Complete contract payment will not be made until growth of seed is 90%, and all loose soil has been stabilized.

1.1.17. Backfill/grade must slope away from the cover.

1.1.18. Contractor shall insure no standing or trapped water are in inlet or discharge lines that are above the frostline.

1.1.19. Do not use existing soil as backfill.

Cleanout Pipe directions towards manhole

1.2. Repair catch basin asphalt near Building 1

1.2.1. Contractor shall saw cut and remove approximately 49 sf of pavement (7x7 feet square). The square in the pictures below is 6 x 6 feet. Contractor will excavate around the concrete structure deep enough in the affected area for 12 inches of compacted subbase and 4”of binder and 2” of top coat to be applied.

1.2.2. Contractor shall provide 12 inches of compacted and appropriately sloped NYSDOT Type 2 subbase in the excavated area.

1.2.3. The Contractor will apply 6 inches of NYSDOT Type 6F asphalt for the top course.

The top course will be compacted and pitched to provide appropriate flow to the catch basin.

1.2.4. The Contractor will seal the transition between new and old asphalt with joint sealant.

1.2.5. Contractor will be responsible for proper traffic management in the work area and safety cones and/or other marking.

1.3. Repair catch basin between Buildings 7 and 19 and catch basin in the parking lot between Building 12 and Building 19

Manhole near the cars

1.3.1. Contractor shall sawcut and remove approximately 30 sf of pavement. Contractor will excavate deep enough in the affected area for 12 inches of compacted subbase and 6 inches of asphalt (4” of binder and 2” of topcoat) to be applied.

1.3.2. Contractor shall remove the catch basin cover and frame.

1.3.3. Contractor shall repair the damaged riser, brick, or concrete tapered section under the frame.

1.3.4. Contractor shall set the frame in a full bed of mortar.

1.3.5. Contractor shall provide 12 inches of compacted and appropriately sloped

NYSDOT Type 2 subbase in the excavated area.

1.3.6. Contractor shall apply 6 inches of NYSDOT Type 6F asphalt for the top course.

The top course shall be compacted and pitched to provide appropriate flow to the catch basin.

1.3.7. Contractor shall seal the transition between new and old asphalt with joint sealant.

1.3.8. Contractor shall reset the curb near the catch basin.

Catch Basin Between Bldg 7 and 19 Catch Basin Between Bldg 7 and 19

Catch Basin Between Bldg 12 and 19

1.4. Repair manhole near Building 19

1.4.1. The manhole rim has cracked and needs replacement. Contractor shall sawcut and remove pavement around the manhole. Contractor will excavate deep enough in the affected area for 12 inches of compacted subbase and 6 inches of asphalt to be applied.

1.4.2. Contractor shall remove the damaged rim-frame.

1.4.3. Contractor shall set the new rim-frame in a full bed of mortar.

1.4.4. Contractor shall provide 12 inches of compacted and appropriately sloped

NYSDOT Type 2 subbase in the excavated area.

1.4.5. Contractor shall apply 6 inches of NYSDOT Type 6F asphalt for the top course.

The top course shall be compacted and flush with the rest of the asphalt.

1.4.6. Contractor shall seal the transition between new and old asphalt with joint sealant.

OPTION 1 Replace fire hydrant near building 19

1.1.1. Contractor shall replace Hydrant #11, located near Building 19.

1.1.2. New hydrant shall be A-423 Mueller Super Centurion 250 3-Way Fire Hydrant.

1.1.3. Contractor shall excavate each site.

1.1.4. The removed hydrants shall be disposed of in the bases’ metals recycle container.

The rest of the debris shall be removed from the site by Contractor.

1.1.5. Hydrants shall be installed with an acceptable variation of 22” height from grade/ground to hose cap nut.

1.1.6. Contractor will furnish all materials to properly install new fire hydrant per manufactures instructions. Contractor shall flow test the hydrant and paint it with the appropriate color based on the resulting flow.

1.1.7. Contractor shall coordinate with COR prior to performing any utility shutdown.

1.1.8. Contractor shall backfill, apply topsoil to grade, and seed. Complete contract payment will not be made until growth of seed is 90%, and all loose soil has been stabilized.

1.5. OPTION 2 repair three (3) fire hydrants

1.5.1. Contractor shall repair hydrants #15, #16, and #17. These hydrants leak and spray when opened.

1.5.2. Contractor shall replace these hydrants following the specifications in OPTION 1.

Hydrant #15 Hydrant #16 Hydrant #17

1.6. Materials for catch basin and cover repairs

1.6.1. Grout is to be non-shrink type grout with minimum compressive strength of 4000 psi at 24 hours per NYSDOT Section 701-05 Concrete Grouting Material.

1.6.2. Portland cement mortar is to be per NYSDOT Section 705-21.

1.6.3. Material for leveling and backfilling under and around catch basin, field inlet and sewer manhole structures is to be selected granular fill per NYSDOT Section 203.

1.6.4. Concrete to be used for construction, modification, or repair of catch basin/field inlet structures is to be class A concrete per NYSDOT Section 555 Structural Concrete.

1.6.5. Joint compound is to be Mainstay Joint Compound as manufactured by the Madewell Products Corporation, Sikaflex-1A as manufactured by Sika Corp, Sonolastic NPII as manufactured by Sonneborn, or approved equivalent.

1.6.6. Materials for adjustment, repair, or replacement of catch basin and manhole frame and cover shall conform to NYSDOT Sections 604-2.04 and 604-2.05

1.7. General

1.7.1. Appropriate measures are to be taken to prevent any damage to, or dirt, debris, construction materials, and any other extraneous materials from entering the existing storm water/sewer system including but not limited to sewer main, lateral and underdrain pipes, catch basins/field inlets, sewer manholes, junction chambers, and any other related appurtenances during construction of Project. Any such invasive materials are to be removed immediately and contaminated appurtenance thoroughly cleaned.

1.7.2. No structure is to be backfilled until all of mortar has completely set. This may involve a separate trip by Contractor on another day of work.

1.7.3. Sewer manhole frame and cover, catch basin/field inlet frame and grate, and catch basin access frame and cover are to be placed true to line and grade. Suitable measures are to be taken to ensure that cover/grate has continuous, full and uniform bearing contact with corresponding frame. Cover/grate is to be non-rocking when in place and under influence of traffic or other loads. Suitable methods to achieve non-rocking fit between cover/grate and corresponding frame will include, but not be limited to, following: ground mating surfaces, machined and milled mating surfaces (horizontal and vertical), match marked elements, locking elements.

1.7.4. Apply two coats of appropriate damp-proof material to all exterior and interior surfaces that will be worked on. Damp-proofing material for exterior portion of catch basin, field inlet and sewer manhole structures is to be two coats of Hi-Build Bituminous Coating 35-J-10 as manufactured by Mobil Corporation, or Koppers Bitumastic Super Service Black as manufactured by Koppers Company, Inc, or Tnemec Heavy Duty Black 46-449 as manufactured by Tnemec or approved equivalent.

2. CONTRACTOR REQUIREMENTS

2.1. Contractor will notify DigSafe and have a signed form from CES prior to any excavation.

The project will involve clearances from both external and internal utility owners. No digging shall occur until internal CES signed dig permit is received.

2.2. It is the contractor's responsibility during construction to protect any existing utilities.

Damage to existing utilities and property during construction shall be repaired and/or replaced at contractor's expense.

2.3. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.

2.4. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (AFI 31-101 and AFI 10-245), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

2.5. All contractor employees, to include subcontractor employees, requiring access to Government Installations, Facilities and Controlled Access areas shall complete AT Level I awareness training within 10 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. Certificates of completion for each affected contractor employee and subcontractor employee will be maintained by the COR or Antiterrorism Representative. AT level I Awareness Training is available through MyLearning by completing the Force Protection CBT. For Contractors that do not require issuance of a CAC, local training will be provided during badge issuance at SFS via informational binder.

2.6. Requirement for OPSEC Training. In accordance with AFI 10-701, Operations Security, OPSEC PMs/SMO/SMNCOs/Coordinators will provide OPSEC training or training materials to contract employees within 90 days of employees’ initial assignment to the contract and annually thereafter. General organizational orientations may need to be supplemented by duty-related orientations in the work center targeted toward specific critical information and vulnerabilities associated with the work. Initial training (OPSE 1301 - OPSEC Fundamentals) and refresher training (Protecting Sensitive Information) are both available on the MyLearning website. For Contractors that do not require issuance of a CAC, local training will be provided during badge issuance at SFS via informational binder.

2.7. The use and possession of controlled substances to include marijuana (medical or recreational use) on the installation is in violation of Title 10 US Code 912a. Art 112a.

Contractors are notified this policy is strictly enforced and violators will be denied entry.

Personnel caught on the installation can be prosecuted.

2.8. The Contractor shall provide all personnel and necessary equipment to establish an adequate and safe work zone. OSHA is applicable at the site and inspectors appear unexpectedly.

2.9. Contractor is responsible for site cleanliness and shall remove any waste or debris after the work is complete. All materials shall be secured to prevent loose objects from blowing and hindering flying operations in any manner.

2.10. The Contractor shall recycle to the greatest extent possible and turn in weight slips to 109 Environmental Management Office for construction debris.

2.11. The Contractor shall bring any unforeseen project conditions to the attention of the COR immediately. Unexpected or differing site conditions, which may alter the scope of work, shall be approved by the contracting officer (KO) prior to such work being performed.

2.12. The Contractor must get approval from the COR prior to any utility (including sewer) shutdowns. (do not have contractor contact production control directly)

2.13. The Contractor shall notify the COR prior to delivery of any material or equipment to the site. The Contractor shall ensure they have a Site Superintendent from their own company present to receive delivered materials and able to store them safely in an area to be coordinated with the COR. Any materials delivered without prior coordination and without having someone to take receipt, shall not be accepted and turned away.

2.14. Contractor hours are 0700-1530 Monday thru Friday, excluding Government holidays. Exception may apply due to special utility circumstances. No work is allowed on the weekends and holidays.

2.15. All concrete and paving work to be performed in weather conditions as defined by industry standards such as the American Concrete Institute (ACI), and the American Society for Testing and Materials (ASTM) Asphalt Specifications.

PROPOSED PROJECT SCHEDULE

The project will begin 14 days following the Notice to Proceed. The project shall be completed within 60 days following the notice to proceed.