Attachment 1 SOW 29 JUL 2021.pdf
PDF 1 MB Posted
- Attached to
- Aircraft Clear Water Rinse Facility Federal contract opportunity
- Solicitation number
- FA481921R0009
About this file
This document is a request for proposal for the repair and restoration of an aircraft clear water rinse facility at Tyndall Air Force Base in Florida. The scope of work includes demolishing existing structures, repairing and restoring interior and exterior elements, and potentially constructing a new facility. Offerors are encouraged to review the full solicitation and attached documents for details on tasks such as site preparation, demolition, construction, inspections, and project closeout. Proposals are due in accordance with the instructions contained in the solicitation. The selected contractor will be responsible for design, permitting, construction management, and all other services necessary to complete the project, which has an estimated period of performance of 300 calendar days from notice to proceed.
View the file
Other files for this federal contract opportunity
Show all 24
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA4819-XX-R-XXXX
28 July 2021
REQUEST FOR PROPOSAL
For
Repair (Restore) Aircraft Clear Water Rinse
Facility
TYNDALL AFB FLORIDA
Project Number: XLWU 20-8187
Contents
1.0 SCOPE
1.1 GENERAL REQUIREMENTS
2.0 APPLICABLE DOCUMENTS
3.0 GOVERNMENT PROPERTY INCLUDING GOVERNMENT FURNISHED INFORMATION,
EQUIPMENT, AND PROPERTY (GFI, GFE, GFP)
4.0 MANAGEMENT, PLANNING, AND REPORTING REQUIREMENTS
4.0A TABLE 1 - TABLE OF DELIVERABLES
4.1 WORK BREAKDOWN STRUCTURE (WBS)
4.2 SCHEDULE AND PLANNING REQUIREMENTS
4.2.1 Project Planning Chart (PPC) and/or Construction Planning Chart (CPC)
4.2.2 Integrated Master Schedule (IMS)
4.2.2.1 CONTRACT PROGRESS SCHEDULE (AF 3064)
4.3 STATUS REPORTING
4.3.1 Reporting Requirements for Firm Fixed Price (FFP)
4.4 MEETING AND CONFERENCE REQUIREMENTS
4.4.1 Meeting/Teleconference Support
4.4.2 Red Zone Meeting
4.4.3 Senior Advisory Group (SAG) and Senior Executive Review Group (SERG)
4.5 CONTRACTOR DOCUMENTATION
4.6 NOTIFICATION REQUIREMENTS
4.7 PERMITS
4.8 PHOTO DOCUMENTATION
4.10 SITE ACCESS BADGES
4.11 WORKSITE ACTIVITIES AND COORDINATION
4.11.1 Coordination of Activities
4.11.2 Radiological Waste, Hazardous Material and Hazardous Waste Permitting and Reporting
4.11.3 Recording and Preserving Historical and Archaeological Finds
4.12 PROJECT DATA/PROJECT DELIVERABLES
4.12.1 Protecting Unclassified DoD Data
4.12.2 Security Breach Notification
4.12.3 Data Collaboration Site
4.13 HEALTH AND SAFETY PLAN (HSP) OR (APP)
4.14 QUALITY SYSTEM PLAN (QSP)
4.15 TECHNICAL PLANS AND REPORTS
4.15.1 Construction Work Plan
4.15.2 Technical Reports
4.15.3 Environmental Protection Plan (EPP)
5.0 PROSECUTING THE WORK
5.1 SITE WORK
5.1.1 Conservation
5.1.2 Site Preparation
5.1.3 Demolition
5.2 CONSTRUCTION OPERATION SERVICES
5.2.1 Construction
5.2.2 Inspections
5.3 DEMOBILIZATION
5.4 EMERGENCY RESPONSE
5.5 MAINTENANCE AND REPAIR
5.6 ORDNANCE REMOVAL AND SUPPORT
5.7 SECURITY REQUIREMENTS:
5.8 GENERAL SAFETY REQUIREMENTS
5.9 GENERATED REFUSE
6.0 FACILITY CONSTRUCTION PROJECT DELIVERY METHODS
6.1 DESIGN BUILD (D-B)
6.1.1 Designers of Record (DOR)/Design Project Manager (PM)
6.1.2 Contractor Design Requirements after Award
6.1.3 User Requirements Design Meeting
6.1.4 Geotechnical/Hazardous Material Survey Requirements and Responsibilities
6.1.5 General Design Requirements
6.1.6 Design Review
6.2 DESIGN-BID-BUILD (D-B-B)
7.0 ADDITIONAL REQUIREMENTS
7.1 TYPES OF PROJECTS/WORK
7.1.1 Military Family Housing
7.1.2 Fueling System Projects
7.1.3 Range Construction
7.1.4 Pavement Systems (Airfield and Non-airfield)
7.1.5 Renovations (including historic buildings)
7.1.6 Construction of Classified or Highly Secure Facilities
7.2 AS-BUILT DOCUMENTATION
POINTS OF CONTACT (POCS)
Attachments:
Appendix A Scope of Work Appendix B Maps, Drawings, And Other Project Specifics Appendix L TAFB APPENDIX L - FRCS GUIDE 02-17-21
1.0 SCOPE
A. This is a Design-Build project to demo, repair and restore interior and exterior elements, or to provide a new facility. The project is comprised of one facility on Tyndall AFB and the related disciplines of work as specific tasks in Scope of Work (Appendix A). The
Design-Build Team will consist of a Construction and design team Designer of Record
(DOR) that shall perform the services herein and as described in this Statement of Work
(SOW).
B. The Contractor shall be responsible for all professional services, A/E design, permits, equipment, labor, tools, materials, and ancillary items necessary to complete the tasks defined by the SOW, including the disposal of all resulting waste materials and project clean up. The performed tasks shall be based on the project description, other data furnished in this SOW, and information covered during kick-off meeting.
C. This SOW sets forth the requirements for Design/Build (DB) contract site-specific design and construction effort to remove, repair and restore interior and exterior elements and related infrastructure within a building on Tyndall AFB, Florida.
D. See Appendix B for Supporting Documentation.
1.1 GENERAL REQUIREMENTS
A. Applicable provisions of the Contract Clauses in the contract will govern work under each section of the specifications.
B. This project has an estimated period of performance from Notification to Proceed (NTP) through completion and turnover of the facility back to the Government for mission operations of 300 calendar days.
C. Proposal Documents: The contractor shall complete the proposal schedule included in the solicitation and include the completed schedule with the submitted proposal documents.
D. Measurements: The GC is required to validate dimensions and quantities. The quantities are listed as approximations and GC field measurements and quaintly verification should be used for bidding package.
E. Field Changes:
a. Field Changes: The Contractor and the Government may agree to perform a no cost field change. Field changes are made when the change appears to be mutually beneficial to all parties and would not require changing the negotiated items. All field changes must be approved by the CO prior to execution. Only the CO may authorize field changes or deviations from the SOW.
b. No order, statement or direction of the Contracting Officer, an authorized representative of the Contracting Officer whether or not acting within the limits of his authority, or any other representatives of the Government, shall constitute a change order under the “Changes” clause of this contract or entitle the contractor(s) to an equitable adjustment of the price or delivery schedule, unless such a change is issued in writing and signed by the Contracting Officer.
F. Job Start Meeting: A job start meeting shall be accomplished with the Contractor, Contracting Officer, CE, and user upon acceptance of the 35%, 65%, or 95% design submission. The meeting objective is to review project details, determine construction start date, security procedures for site, dumpster locations, and any applicable requirements during construction. The Contractor shall visit the job site to verify location, conditions, and dimensions prior to starting work.
G. Facility Occupancy: The facility covered by this contract is located on the airfield, but is currently not used by aircraft and does not have any occupants. Due to the location of the facility and requirements to keep the remainder of the airfield in operation, the Contractor will take all necessary steps as detailed in section 5.0 of this document.
H. Bulletin Board: Immediately upon mobilization, the Contractor shall provide a bulletin board not less than 36 by 48 inches (915 by 1220 mm) in size for displaying various documents required within the contract. The bulletin board shall be located at the project site in a conspicuous place easily accessible to all employees, as approved by the
Contracting Officer due to the project being located on the airfield. All documents posted shall be legible and replaced as needed when unreadable. The board shall be displayed until the work is completed whereby the Contractor shall remove the board and remain the property of the Contractor. The contents of the board shall include, but not limited to, the following:
1. Contractor’s company name
2. Project name
3. MPLS number
4. Superintendent’s name and a 24 hour available response phone number
5. Equal Employment Opportunity poster
6. Wage determination
7. Wage Rate Information poster.
8. Other documents as needed or required.
I. Employee Parking: Contractor employees shall park privately owned vehicles in an area designated by CES and approved by the CO.
J. Job Site Tools and Equipment: All hand tools and equipment shall be maintained in good working conditions and properly stored when not in use. Construction attire shall be in accordance with applicable OSHA regulations.
K. Field Measurements: The Contractor shall be required to make his/her own field investigations to verify existing conditions, dimensions and other information shown on
Government available non-verified furnished reference drawings, solicitation documents and construction documents. Deviations, errors, or omissions in the government supplied reference materials or the design team’s construction documents shall be identified and addressed by the contractor during the design phase of the contract. They shall be annotated on the respective contract documents as well as on a consolidated register that will be made available to the government for simplified identification and review.
L. Notification Requirements: The Contractor shall notify the Government a minimum of ten
(10) days in advance of each mobilization. The Contractor is required to notify the CO and
Government Project Manager of critical issues that may affect the contract performance and/or human health and the environment. For critical issues pertaining to human health and the environment, the Contractor shall immediately notify the CO and stop work. Work shall only resume at the direction of the CO following resolution of the issue.
M. On-Site Field Oversight: The Contractor shall provide the manpower, equipment, material, services, and transportation necessary to ensure oversight services throughout accomplishment of the construction period for the contract. It is the responsibility of the
Contractor to establish and maintain open communications between salient authorities associated with accomplishment of this contract.
N. Federal Holidays:
1. The standard Federal legal holidays are observed:
a. New Year’s Day
b. Birthday of Martin Luther King, Jr.
c. Washington’s Birthday
d. Memorial Day
e. Independence Day
f. Labor Day
g. Columbus Day
h. Veterans Day
i. Thanksgiving Day
j. Christmas Day
k. Juneteenth
2. Any of the holidays falling on Saturday will be observed on preceding Friday; holidays falling on Sunday will be observed on the following Monday. In addition, the
Government may dictate the work day before or the work day after an observed holiday as a “Family Day.”
3. The Contractor should not perform work on observed holidays, Wing Down Days, Wing Safety Days or Family Days unless authorized by the Contracting Officer for the
TO. In the event work is authorized on observed holidays, the Contractor shall pay all applicable overtime and/or holiday pay rates required by law.
O. Working Hours: The normal duty hours of the facility are from 7:00 AM to 5:00 PM, Monday thru Friday excluding Federal Holidays. All work shall be performed during normal duty hours. All other hours to include weekend and holidays shall be requested through the CO for approval. This request shall be submitted no less than three (3) workdays prior to the time requested.
P. Availability and Use of Utility Services: The contractor should plan on having an offsite office location. The government does not guarantee office space will be provided. The
Government does not guarantee utilities will be provided for office space. The use of a generator and porta toilets may be required of office space is provided. To install and office space and laydown yard will require an 813 permit determination and could take up to 60 days to obtain the permit.
Q. Sanitation: The Contractor shall provide and maintain within the construction area minimum field-type sanitary facilities approved by the CO. Government toilet facilities will not be available to Contractor's personnel.
R. Clean Up: At the end of each working day the Contractor shall clean up the work site by the removal of all construction debris, waste materials, packaging material and the like. If the before mentioned items could become airborne they shall be placed in refuse containers immediately. Clean up of the work site shall include the construction area(s), construction office area(s), material storage area (s), parking and eating area(s), and any other area(s) affected by the construction process. Any dirt or mud which is tracked on to any Base street, parking area, sidewalk, patio, or driveway shall be cleaned away daily. Materials resulting from demolition activities which are salvageable shall be stored within the work area or at a supplemental storage area. Stored material not in trailers, whether new or salvaged, shall be neatly stacked when stored in an approved location. Due to location of project on the airfield, additional requirements for keeping the work area clean will apply and can be found in section 5.0 of this document.
S. Contractor’s Management and Use of Electromagnetic Emission Devices on Base:
(Electromagnetic emission devices include: Radio/Radar Transmitters; Navigational
Aids/Instrumentations; Signaling, Intrusion Detecting, and Identification Devices; Mobile and Fixed Business Radio Communications Equipment; and MARS, CBs, and Amateur
Radio Stations.) The Contractor shall comply with the Air Force Military Training Center
(AFMTC) Regulation 700-14, Jul 89.
T. Preparation of Progress Schedules and Reports: The reports contemplated by FAR Clause, 52.236-15, Schedules for Construction Contracts, shall be accomplished on and in accordance with instructions pertaining to AF Form 3064, Contract Progress Schedule, and
AF Form 3065, Contract Progress Report. Contract Schedules and Reports shall run from
Monday through Sunday and be submitted to the CO per table of deliverables located in
4.0 A Table 1 - Table of Deliverables.
U. Deteriorated Construction And Finish
1. Authority: The QA Inspector will be the governing authority in determining if existing construction and finishes are deteriorated and require repair and/or replacement.
V. Contractor Storage/Staging Area
1. Operations and Storage Approval: Notwithstanding Contract FAR Clause, FAR
52.236-10, Operations and Storage Areas, subject to approval by the CO and in turn, availability and need, a storage/staging area may be provided at the subject project site. If project site space is not available, then offsite storage may be required.
2. Utility ‘tie-ins’, where available, are the Contractor’s responsibility. See 1.1
GENERAL REQUIREMENTS, P. Availability and Use of Utility Services for additional information.
3. Storage Area Clean Up: Weekly discard trash and debris in the Contractor’s containers (dumpsters). Do not allow debris to accumulate. At work completion, clean the storage area. This area must be free of any materials, trash or debris before receipt of final payment.
4. In areas of high visibility, the job site construction fence shall have a screen fabric material applied to the fence fabric in order to block the view during the construction phase. The CO will make the determination at the pre-construction meeting if the subject project will require a screened fence or not. Remove fence upon completion.
Rehabilitate disturbed turfs and grass and if reseeding is required use Bermuda grass.
W. Hazardous component abatement for materials such as asbestos, lead-based paint, PCBs, and other hazardous materials shall be the responsibility of the Contractor. Abatement of mold resulting from water damaged materials shall be the responsibility of the Contractor.
X. The duration of days is considered calendar days unless otherwise noted.
Y. COVID-19 Requirements - During the COVID-19 pandemic it is vital to Tyndall AFB’s
Mission that the Contractor adhere to all Tyndall AFB Covid-19 directives to mitigate virus transmission. The contractor shall be responsible for the following: follow CDC guide lines, setting up teleconference meetings, wearing mask and social distancing when entering a government facility, the screening of their employees, and reporting COVID-19 cases to the 325th CONS and 325th CES project manage (PM). As Covid-19 directives are living documents, it is the Contractor’s responsibility to be informed and follow the most recent published directive.
Z. Project Signage: As required per the FAR.
1. As required, a job sign shall be required at the project site. The CO or the Government
Inspector will make a determination based on cost and visibility. The sign shall indicate the Contractor’s company name, project name and MPLS number, superintendent’s name and a 24 hour available response phone number. The size of the sign shall be 4’ x 8’ x ¾” thick plywood board mounted to a 2x4 wood frame and diagonal braces. The wood frame shall be supported on 4x4 wood supports and be mounted to the ground in concrete footings. Background color shall be in accordance with Federal Standard 595a color/number BROWN/10080 (Gloss). The color of the lettering shall be
WHITE/17875 (gloss) with Arial font. With base approval the background color shall be white with black lettering - Helvetica font. Due to the location of the project on the airfield, the job sign will be placed in an area approved by the CO.
2.0 APPLICABLE DOCUMENTS
A. The Contractor shall identify and comply with all applicable federal, state, and local laws;
statutes; Executive Orders; Department of Defense/Air Force manuals, handbooks, regulations, guidance, and policies. The contractor shall comply with the National Institute of Building Sciences’ Whole Building Design Guide Construction Criteria Base (CCB)
Unified Facility Criteria (UFC) 3-600-01 and all of the related libraries. The primary criteria are the Air Force Criteria from the Documents Library, but other agency criteria may be directed for use, depending on the customer agency for a particular TO. The
Unified Facilities Guide Specifications (UFGS) is the mandatory starting point for all specifications, and shall not be deleted, materially modified, or made less stringent without
Government approval. It is the contractor’s responsibility to identify and comply with all applicable requirements. It shall be the contractor’s responsibility as the Designer of
Record (DOR) to identify any design/construction criteria waivers that are warranted for the Project and to accomplish all necessary coordination activities necessary to obtain approval of these proposed waivers through the Contracting Officer (CO), and/or Project
Manager (PM).
B. In addition, the contractor shall refer to and comply with the current versions of the
Department of Defense Policy and Guidelines for Acquisitions Involving Environmental
Sampling or Testing and The United States Air Force Construction Management
Implementation Guide as well as the latest version of The USAF Project Manager’s Guide to Design and Construction. Base-specific documents are identified in the attached appendices.
C. The Contractor and Design Team shall adhere to the following guidance during design and construction phase(s) of this project: Those sections of the Southern Standard Building
Codes not incorporated in the UBC/International Building Code (IBC) for our respective area, International Concrete Repair Institute (ICRI) Guidelines, Air Force Standards, Department of Defense (DOD) Directives, Florida State Statutes, and the Tyndall AFB
Facility Excellence Plan (Base Regulations), Occupational Safety and Health
Administration (OSHA) Requirements, Department of Environmental Protection (DEP)
Regulations, Environmental Protection Agency (EPA) Regulations, and ABA
Accessibility Compliance Requirements.
D. In addition to adhering to the previous guidance, the Contractor shall review and adhere to the most recent version of the following code criteria as applicable at start of the design phase:
1. UFC 1-200-01 The DoD Building Code
2. UFC 1-200-02 High Performance and Sustainable Building Requirements
3. UFC 1-300-02 Unified Facilities Guide Specifications (UFGS) Standard
4. UFC 1-300-08 Criteria for Transfer and Acceptance of DoD Real Property
5. UFC 3-101-01 Architecture
6. UFC 3-110-03 Roofing
7. UFC 3-110-04 Roofing Maintenance and Repair
8. UFC 3-190-06 Protective Coatings and Paints
9. UFC 3-250-08FA Sealing Joints and Cracks
10. UFC 3-301-01 Structural Engineering
11. UFC 3-310-04 Seismic Design for Buildings
12. UFC 3-400-02 Design: Engineering Weather Data
13. UFC 3-401-01 Mechanical Engineering
14. UFC 3-410-01 Heating, Ventilating, and Air Conditioning
15. UFC 3-410-02 Direct Digital Control for HVAC
16. UFC 3-410-04 Industrial Ventilation
17. UFC 3-420-01 Plumbing Systems
18. UFC 3-430-09 Exterior Mechanical Utility Distribution
19. UFC 3-450-01 Noise and Vibration Control
20. UFC 3-500-01 Electrical Engineering
21. UFC 3-520-01 Interior Electrical Systems
22. UFC 3-530-01 Interior and Exterior Lighting and Controls
23. UFC 3-550-01 Exterior Electrical Power Distribution
24. UFC 3-560-01 Electrical Safety O&M
25. UFC 3-570-01 Cathodic Protection
26. UFC 3-575-01 Lightning and Static Electricity Protection
27. UFC 3-580-01 Telecommunications Interior Infrastructure
28. UFC 3-600-01 Fire Protection Engineering for Facilities
29. UFC 4-010-01 DOD Minimum Antiterrorism Standards for Buildings
30. UFC 4-010-05 Sensitive Compartmented Information Facilities
31. UFC 4-021-01 Mass Notification Systems
32. UFC 4-021-02 Electronic Security Systems
33. UFC 4-211-01 Aircraft Maintenance Hangars
34. USAF BIM Minimum Requirements Version 2.1
35. ASCE 7-10 Wind Loads
36. AFI 32-1065 Grounding System www.wbdg.org › FFC › AFI › afi_32_1065_2017 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-1-200-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-1-200-02 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-1-300-02 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-1-300-08 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-101-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-110-03 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-110-04 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-190-06 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-250-08fa https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-301-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-310-04 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-400-02 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-401-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-410-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-410-02 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-410-04 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-420-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-430-01fa https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-450-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-501-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-520-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-530-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-550-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-560-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-570-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-575-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-580-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-600-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-4-010-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-4-010-05 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-4-021-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-4-021-02 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-4-211-01 http://www.wbdg.org/FFC/AF/AFBIM/AF_Minimum_BIM_Requirements_V2.1.pdf
37. ASHRAE 62.1 Ventilation for Acceptable Indoor Air Quality
38. ASHRAE 90.1 Energy Standard for Bldgs. Except Low-Rise Residential
39. ASHRAE 100 Energy Conservation in Existing Buildings
40. ASHRAE 111 Testing, Adjusting, and Balancing of Building HVAC
Systems
41. ASHRAE 180 Inspection & Maintenance Commercial Bldg. HVAC
Systems
42. ASHRAE 202 Commissioning Process for Buildings and Systems
43. ASHRAE Guide 4 Prep of Operating and Maintenance Documentation
44. EM 385-1-1 USACE Safety and Health Requirements Manual
45. FAR Federal Acquisition Regulations
46. FS 553 Florida Building Code
47. IBC 2018 International Building Code, 2018 Edition
48. IMC International Mechanical Code
49. IPC International Plumbing Code
50. NBIMS US V3 National BIM Standard US Version 3
51. NEBB Standards for Whole Building Systems Commissioning
52. NFPA 13 Standard for the Installation of Sprinkler Systems
53. NFPA 70 National Electric Code
54. NFPA 72 National Fire Alarm Code
55. NFPA 101 Life Safety Code
56. NFPA 780 Standard for the Installation of Lightning Protection
System
57. SMACNA Guides Sheet Metal & Air Conditioning Contractors’ National
Assoc.
58. TAFB FEP TAFB Facility Excellence Plan
59. TAFB IFS TAFB Installation Facility Standard - https://www.tyndallifs.com/
60. USAF BIM Minimum Requirements Version 2.1
61. UFGS 23 09 00 Instrumentation and Control for HVAC
62. UFGS 23 09 13 Instrumentation and Control Devices for HVAC
63. UFGS 23 09 23.02 BACnet Direct Digital Control for HVAC and Other
Building Control Systems
64. UFGS 23 09 93 Sequences of Operations for HVAC Controls
65. UFGS 25 05 11 Cybersecurity for Facility-Related Control Systems
66. UFGS 23 08 10 Utility Monitoring and Control System Testing
67. UFGS 25 10 10 Utility Monitoring and Control System (UMCS) Front End and Integration
68. AFGM 2018-32-01 Civil Engineer Control Systems Cybersecurity
69. MEMORANDUM FOR AFCEC/CL - Tyndall AFB Design Wind Speeds and
Building Envelope Protection
70. J&A TYNDALL AFB SIEMENS FRCS
71. J&A TYNDALL AFB TRANE CHILLERS - Hurricane Michael Chiller System
Manufacturer Standardization Request
72. TYNDALL MASS NOTIFICATION SYSTEM MESSAGES
https://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf https://www.nationalbimstandard.org/files/NBIMS-US_V3_4.2_COBie.pdf http://www.wbdg.org/ffc/af-afcec/installation-facilities-standards-ifs/tyndall-afb-ifs http://www.wbdg.org/FFC/AF/AFBIM/AF_Minimum_BIM_Requirements_V2.1.pdf
73. TYNDALL REBUILD FRCS TECHNOLOGY SUMMARY –APPENDIX L –
FRCS GUIDE 02-17-21
74. MEMORANDUM FOR ALMAJCOM-FOA-DRU, Mandatory Use Policy for Air
Force Carpet Acquisitions within the Contiguous U.S.
E. Lightning Protection Requirement: Lightning Protection System (LPS) shall be designed and installed IAW the following references:
1. AFI 32-1065 Grounding System
2. NFPA 780 Standard for the installation of Lightning Protection System
3. UFC 3-575-01 Lightning and Static Electricity Protection System
4. UL 96 Lightning Protection Components
5. UL 96A Installation Requirements for Lightning Protection System
6. UL 467 Grounding and Bonding Equipment
7. NFPA 70 National Electric Code
F. Security Requirements:
1. MIL-HDBK-1013: DOD Military Handbook Design Guidelines for Physical
Security of Facilities
2. AFI 31-101: Air Force Instruction 31-101: The Air Force Installation
Security Program
3. DOD 5200.1.R Department of Defense 5200.1.R: Information Security
Program Construction Standards.
4. UFC 4-010-01 Unified Facilities Criteria Antiterrorism Standards for New and Existing Facilities
5. ICD-ICS-705 Tech Spec
6. UFC 4-010-05 Sensitive Compartmented Information Facilities
G. The Contractor shall perform all work IAW with AFI, ETL, UFC and industry standards.
Compliance with AF UFCs is mandatory unless the IFS has more stringent requirements.
If the Contractor determines that the work cannot be performed and/or included in the SOW
IAW with ETL’s/UFCs or industry standards, the Contractor shall notify the Tyndall AFB
POC listed in this document in writing immediately before award of the contract.
Otherwise, the Contractor shall be responsible for the required work.
H. All work shall be in compliance with all Public Laws (P.L.), Executive Orders (E.O.), Code of Federal Regulations (CFR), Department of Defense Instructions (DODI), Department of Defense Directives (DODD), or other higher authority documents as applicable. Many applicable compliance documents are authorized by DoD MIL-STD-3007F, and are available through the Government-sponsored Whole Building Design Guide located at https://www.wbdg.org.
I. If there is a conflict between these codes, regulations specifications, and/or guidance documents, the most stringent requirements shall apply, as determined by the CO through https://www.wbdg.org/FFC/FEDMIL/std3007f.pdf https://www.wbdg.org/ the Request for Information (RFI) process. These listed documents do not relieve the
Contractor from complying with other required regulatory documents not listed.
J. The government may take up to 30 days to review design documents. The contractor schedule activity for less days will be overridden by this time frame and will not be considered a delay by the government. The contractor schedule shall reflect the 30 day review time.
3.0 GOVERNMENT PROPERTY INCLUDING GOVERNMENT FURNISHED
INFORMATION, EQUIPMENT, AND PROPERTY (GFI, GFE, GFP)
A. Historical architectural and structural construction documents may be available for review, however field verification and documentation of existing conditions and configurations prior to construction is essential. The government takes no responsibility for errors and omissions contained in the reference material and field verification shall be performed by the contractor.
4.0 MANAGEMENT, PLANNING, AND REPORTING REQUIREMENTS
A. Design submittals, 35%, 65%, and/or 95%, and 100%, will be routed with an AF Form
3000 and will be reviewed and approved/disapproved within 30 calendar days.
B. No delay damages or time extensions will be allowed for time lost in late or lost submittals.
Government review times may take up to 30 days and is not considered a delay for design reviews. The contractor’s schedule shall include time for these 30 day reviews. The official review time starts when the CO acknowledges the receipt of the submittal.
C. Submittals pertaining to environmental issues may take up to 30-45 days for review and approval. Wetland permits may take greater than 60 days to process. Environmental 813 submittals shall include drawings, locates for utilities with depth, size of lines, length of runs, underground or above ground routing, spatial coordinates, duration of the laydown yard or temporary trailer, number of personnel, location of temporary porta toilets, etc.
Delays greater than the anticipated days listed herein do not constitute a governmental delay. Contractor will be allotted a no-cost PoP extension for days over and above those listed herein.
D. All other submittals will be reviewed and approved/disapproved within 10 work days.
Submittals will be reviewed for accuracy and relevance to the project and specifications.
Material Submittal documents shall be submitted with AF Form 3000, Material Approval
Submittal.
E. Submittal documents shall include required forms, reports, drawings, samples, pictures, media recordings, manufacturer data, certifications, test reports, equipment warranty information, and the like. Submittal documents shall be submitted by the Contractor to the by CO for approval. All submitted documentation shall become the complete property of the Government. The Contractor shall not purchase, install, or construct any equipment or facility component, for which a submittal is required, without first obtaining an approved signed submittal from the CO. Required submittals shall be listed on AF Form 66, Schedule of Material Submittals, and/or a Submittal Register approved by the CO.
F. Table of Deliverables: Project deliverables shall be as shown in section 4.0 A Table 1 -
Table of Deliverables. The dates in the table are hard dates not to be exceeded without CO approval. The deliverables and scheduled activities may be provided or completed early.
G. Coordinate scheduling, sequencing, preparing, and processing of submittals with performance of work so that work will not be delayed by submittal processing. The
Contractor is responsible for additional time required for Government reviews resulting from required resubmittals. The review period for each resubmittal is the same as for the initial submittal.
H. Submittals required by the contract documents are listed on the submittal register. If a submittal is listed in the submittal register but does not pertain to the contract work, the
Contractor is to include the submittal in the register and annotate it "N/A" with a brief explanation. Approval by the Contracting Officer does not relieve the Contractor of supplying submittals required by the contract documents but have been omitted from the register or marked "N/A."
I. Resubmit the submittal register and annotate it monthly with actual submission and approval dates. When all items on the register have been fully approved, no further resubmittal is required.
J. Contracting Officer Review will be completed within 30 calendar working days after the date of submission for submittals requiring Government approval.
4.0 A Table 1 - Table of Deliverables
Document
Copies
Max Delivery Timeframe 3
C
E S
C
O N le ct ro n ic
H a rd C o p y ct ro rd C o
Standard Meetings and Reports
Meeting Minutes 1 0 1 0 3 calendar days after each meeting
Progress Schedule(AF 3064 or approved equivalent) 1 0 1 0
5 calendar days after NTP or modification to extend PoP
Progress Report (AF 3065 or approved equivalent) 1 0 1 0
Weekly
3-week Look Ahead report 1 0 1 0 Weekly
Daily Logs - Form 1477 or equiv. 1 0 1 0 Daily
HAZMAT Forms 81 and 82 1 1 1 1 10 Days prior to job start meeting
Work Clearance Request (AF Form 103A) 1 1 1 1 10 Days prior to job start meeting
Material Approval (AF Form 3000) 1 0 1 0 At the 100% Final Design
Construction Material Testing Reports 1 0 1 0 As required
Welding/Burn Permit 1 0 1 0 Prior to commencing work
Production or Delivery Problem Report 1 1 1 1 At time of identification
Draft DD1354 1 0 1 0 When request for final inspection is submitted
Work Activities
IMS, WBS and AF 3064/3065 1 0 1 0 15 Days Prior to NTP
Kickoff meeting with all stakeholders 1 0 1 0 5 Days Prior to NTP
Health and Safety Plan (HSP) or (APP) 1 0 1 0 Prior to site visits
NTP 1 0 1 0 NA
Contractor Site Investigation 1 0 1 0 5 Days from NTP
Design Quality Plan (DQCP) or (DQSP) 1 0 1 0 Prior to Design Starting
Quality Control Pan (QCP) or (QSP) 1 0 1 0 Prior to construction activities
Construction Work Plan (CWP) 1 0 1 0 Prior to construction activities
Site Investigation Memorandum 1 0 1 0 10 Days from NTP
Charrette Meeting 20 Days from NTP
Charrette Meeting Minutes Acceptance and
Approval 1 0 1 0
10 Days from Charrette
The 35% and 65% design may be waived for small projects
NA
Max Delivery Timeframe 3
C
C
O ct ro rd C o ct ro rd C o
35% Design w/ AF Form 3000 1* 0 1* 0 N/A
35% Design Review and Meeting 1 0 1 0 N/A
35% Design Resubmittal if submittal was disapproved 1 0 1 0
N/A
35% Design Final Submittal and Approval 1 0 1 0 N/A
65% Design w/ AF Form 3000 1* 0 1* 0 60 Days from NTP
65% Design Review and Meeting 1 0 1 0 30 Days from 65% Design Submittal
65% Design Resubmittal if submittal was disapproved 1 0 1 0
10 Days from 65% Design Disapproval
65% Design Final Submittal and Approval 1 0 1 0
10 Days from 65% Design Re-
Submittal
95% Design w/ AF Form 3000 0 0 0 0 30 Days 65% Design Approval
95% Design Review and Meeting 1 0 1 0 30 Days from 95% Design Submittal
95% Design Resubmittal if submittal was disapproved 1 0 1 0
10 Days from 95% Design Disapproval
95% Design Final Submittal and Approval 1 0 1 0
10 Days from 95% Design Re-
Submittal
100% Design w/ AF Form 3000 1* 0 1* 0 20 Days from 95% Final Design
100% Design Review and Meeting 1 0 1 0 30 Days from 100% Design Submittal
100% Design Resubmittal if submittal was disapproved 1 0 1 0
10 Days from 100% Design
Disapproval
100% Design Final Submittal and Approval 1 0 1 0
10 Days from 100% Design Re-
Submittal
All Material Submittals 1 0 1 0
At 100% Design Approval or 30 Days from design Approval with CO approval.
Demolition Plan when demolition activities 1 0 1 0 Prior to 100% Design Approval
Environmental Plan 1 0 1 0 Prior to 100% Design Approval
Red Line drawings Submitted 1 0 1 0 15 Days prior to Start Work
Draft Phasing Plan 1 0 1 0 10 Days prior to Start Work
Final Phasing Plan 1 0 1 0 5 Days prior to Start Work
Mobilization of Contractor 0 0 0 0 After 100% Design Approval
Job Start Meeting 1 0 1 0 After 100% Design Approval
Implementation of the Design 90 Days
Max Delivery Timeframe 3
C
C
O ct ro rd C o ct ro rd C o
Red Zone Meeting 1 0 1 0 60 Days Prior to Beneficial Occupancy
Date (BOD)
Pre-Final Inspection 1 0 1 0 At end of Implementation
Pre-Final Inspection Report 1 0 1 0 5 Days prior to Final Inspection
Operations & Maintenance Manuals 1 1 1 1 5 Days prior to Final Inspection
HAZMAT Form 83 1 0 1 0 Prior to Final Inspection
Final Inspection 1 0 1 0 10 Days after Pre-Inspection
Final Inspection Report 1 0 1 0 5 Days After Final Inspection
O&M’s Review 1* 1 1* 0 5 Days After Final Inspection
As-Built Design Documents 1 0 1 0 5 Days After Final Inspection
As-Built Design Drawings 1* 0 1* 0 5 Days After Final Inspection
As Built Review Meeting 1 1 1 1 10 Days After Final Inspection
As Built Review Comments 1 0 1 0 15 Days After Final Inspection
O&M’s Acceptance 1* 1 1* 0 15 Days After Final Inspection
As Built Comments Acceptance 1 0 1 0 20 Days After Final Inspection
As Built Approval 1 0 1 0 20 Days After Final Inspection
Transfer & Acceptance of Military Real
Property (DD 1354) 1 1 1 0 5 Days after Final Design Approval
O&M’s to user 1 0 1 0 10 Days after Final Design Approval
User training 1* 1 1* 0 15 Days after Final Design Approval
Items in red may be tailored to fast track requirement
*Both Autodesk AutoCAD and Adobe Acrobat versions of drawings are required
K. Electronic copies of all design deliverable documents shall be provided on CD or DVD discs, formatted for use by the latest software version, and compatible with the
Government’s version of Microsoft Word, Excel, PowerPoint, Access, Outlook, the Adobe family of products, the Autodesk family of applications, the ANSYS family of applications, or other software platform as appropriate and as determined and directed by the CO.
Whenever possible, the electronic files given to the Government should be compatible with at least one software program application listed on the Air Force Evaluated Products List
(EPL) or the Defense Information Systems Agency (DISA) Approved Products List (APL).
For any submitted documents converted to one of the above formats from another software program, the Contractor shall also submit the electronic document file from the software program originally creating it, along with a statement describing what creating software program and version was used, as well as any programs used to convert files from one format to another. Submitted electronic files shall be unlocked and fully editable.
L. Builder Template
A builder template will be provided to the contractor to complete for real property items that were installed per the scope of work.
4.1 Work Breakdown Structure (WBS)
A. A 3064 or equivalent spreadsheet is used for the WBS. The task number, start and stop dates, Value for the task will be provided.
4.2 Schedule and Planning Requirements
A. See Section 1.1 GENERAL REQUIREMENTS
4.2.1 Project Planning Chart (PPC) and/or Construction Planning Chart (CPC)
A. Provided as needed.
4.2.2 Integrated Master Schedule (IMS)
4.2.2.1 Contract Progress Schedule (AF 3064)
A. The Contractor shall submit a signed AF 3064, Contract Progress Schedule, depicting an overall contract progress schedule for the main elements of work for the period of performance as described in the 4.0 A Table 1 - Table of Deliverables. The line items, associated project percentages, and dates shall accurately depict the planned work to be performed.
B. A template spreadsheet may be provided by the government to use for progress reporting.
C. The progress schedule shall be signed by CE recommending approval and approved by the
CO.
4.2.2.2 Contract Progress Report (AF 3065)
A. The Contractor shall submit AF 3065 as described in section 4.0 A Table 1 - Table of
Deliverables. This report shall be signed by the Contractor’s on-site representative in the
Remarks section of the AF 3065. The work elements and percentages of the total job identified on the AF 3065 shall be identical to the work elements and percentages on the
AF 3064. The Contractor shall obtain either the QA Inspector or the Government contract inspector’s acceptance by signature of the actual reported progress prior to submission to the CO. Additionally, the Contractor shall submit the updated AF 3064 as an attachment to the AF 3065.
4.2.2.3 Submitting Schedules and Reports
A. Contract Progress Report. Contract Schedules and Reports shall run from Monday through
Sunday and be submitted to the CO by Tuesday of the following week. Contractor will prepare reports covering activities for days work and give one to the Government Inspector for each week of work even if there was no work accomplished that week. The weekly report may be turned in for each week at the end of the week when construction begins.
B. A 3064/3064/schedule spreadsheet may be used to coordinate progress reporting. An example spreadsheet can be provided.
4.3 Status Reporting
4.3.1 Reporting Requirements for Firm Fixed Price (FFP)
4.3.1.1 Contractor’s Progress, Status, and Management Report (CPSMR)
A. A 3064 is used for this project.
4.4 Meeting and Conference Requirements
A. Upon award the Contractor shall attend the following meetings at a minimum: Project
Kickoff and Pre-Construction Job Start, 35%, 65%, and/or 95% Design Review, 100%
Design Review, Corrected Design Review, Incremental Site Inspection (as needed), Test and Balance (as needed), Commissioning (as needed), Pre-Final Inspection, Final
Inspection, and other meetings (as needed). The Contractor shall participate in other meetings as needed to facilitate the project’s work, and as required by the CO.
B. Kickoff and Pre-Construction Meeting
1. The Contractor shall attend a Project Kickoff and Pre-Construction Meeting at TAFB.
The Contractor shall review the most updated versions of codes, standards, and policies applicable to this project prior to the meeting. These documents should include TAFB design standards, DoD Unified Facility Criteria, and the Florida
Building Code, among others including those referenced in this document. The
Contractor shall, at the Project Kickoff and Pre-Construction Meeting, submit a memorandum stating that applicable codes, standards, and policies were reviewed;
stating which documents (title, revision number, date, source, etc.) were reviewed, and listing any RFI’s that resulted from the review.
2. The purpose of these meetings is to introduce project stakeholders, clarify the scope of work, review TAFB policies, and communicate information pertinent to the project.
Within the time listed in section 4.0 A Table 1 - Table of Deliverables of the meeting, the Contractor shall submit minutes for approval.
4.4.1 Meeting/Teleconference Support
A. Upon award the Contractor shall attend the following meetings at a minimum: Project
Kickoff, Charrette, and Pre-Construction Job Start, 35%, 65%, and/or 95% Design Review, 100% Design Review, Corrected Design Review, Incremental Site Inspection (as needed), Test and Balance (as needed), Commissioning (as needed), Red Zone meetings, Pre-Final
Inspection, Final Inspection, and other meetings (as needed). The Contractor shall participate in other meetings as needed to facilitate the project’s work, and as required by the CO.
B. Contractor will be responsible to take and distribute meeting minutes to all those in attendance.
C. Minutes shall be distributed to attendees for review, comment, and correction the time listed in section 4.0 A Table 1 - Table of Deliverables of meeting events.
D. Unedited digital copies of all Contractor recordings shall be provided to the Government within 3 days of the recording date.
4.4.2 Red Zone Meeting
A. Construction Red Zone Activities
Once construction is 80% complete for each facility or 60 days prior to beneficial
Occupancy Date (BOD), the Contractor shall conduct weekly Red Zone Meetings instead of the regular weekly Project Update meetings. Red Zone Meetings shall cover not only the construction progress, but also project close out activities, including commissioning activities, training activities, and the preparation of project close out documents. Meeting requirements and Attendees for the QA Inspector scheduled and conducted meeting can be found at P:\Projects\Templates\Red Zone Briefing.
B. Builder Template
A builder template will be provided to the contractor to complete for real property items that were installed per the scope of work. The template can be found at
P:\Projects\Templates\Red Zone Briefing.
4.4.3 Senior Advisory Group (SAG) and Senior Executive Review Group (SERG)
A. Not required for this project.
4.5 Contractor Documentation
A. The Contractor shall also create and submit for approval a 4.0 A Table 1 - Table of
Deliverables, which includes the documents required by the approved Submittal Register.
The Table of Deliverables shall indicate when documents shall be submitted for review and approval. The Contractor shall use AF Form 66, Schedule of Material Submittals. The modified submittal register shall include design phase submittals, construction phase submittals, and project close out submittals. It shall also include copies of any submittal forms likely needed by the construction Contractor. The submittal register shall include the documents listed below, in addition to other documents, as applicable.
B. Design Package
1. The Contractor shall prepare and submit for review and approval a design package.
The package shall be submitted at the 35%, 65%, and/or 95% and the 100% design level (4.0 A Table 1 - Table of Deliverables for deliverable dates.) The various required elements of the design package are discussed and detailed in other sections of this document.
2. Government Review: The Contracting Officer or the authorized representative may furnish the contractor review comments on the data submitted at the 35%, 65%, and/or
95% and 100% design phase submittals. The Government's review is intended to be limited to functional aspects, with limited technical review of a general cursory nature only. Any review by the Government of technical items shall not be construed to relieve the contractor of responsibility for technically correct and complete documents in compliance with applicable codes, industry standards, and the intent of this SOW.
Review comments for compliance with Federal Acquisition Regulations (FAR) will also be provided by the Contracting Officer. Government design review comments will be issued to the contractor within 30 days of design submittal receipt. If any review comment requires clarification and/or amplification to assure compliance, the contractor shall notify the Contracting Officer or the authorized representative in writing. After each review, the contractor will be furnished the comments to be annotated and returned to the Government. The contractor shall furnish these annotated comments to the Government no later than 5 calendar days after receiving the comments. The contractor shall comply with the review comments in the development of data for the next submittal.
3. The Contractor shall provide 100% Final Design package for approval. All previous
Government comments shall be addressed in this design package. No review conference is required for this design submittal. The submittal will be formally approved upon verification that the package is complete, and all previously provided review comments have been addressed.
C. Submittal Register
1. The Contractor shall use AF Form 66, Schedule of Material Submittals. The modified submittal register shall include design phase submittals, construction phase submittals, and project close out submittals. It shall also include copies of any submittal forms likely needed by the construction Contractor. The submittal register shall include the documents listed below, in addition to other documents, as applicable.
2. The Contractor shall provide 35%, 65%, and/or 95% and 100% design for review and comment (see section 4.0 A Table 1 - Table of Deliverables). This package shall be in a substantially complete design state. The Government will perform a design submittal review and provide the Contractor with review comments as defined in
Section 4.5 B.2. Contractor shall schedule and attend a final review conference meeting at Tyndall AFB, FL. Formal acceptance of the submittal will be issued when the government comments have been addressed in the construction documents. Refer to the Table 1 for submittal details.
3. Partial Design Submittal List of Requirements
a. AF Form 3000 documenting the submittal Contents.
b. Table of Contents.
c. Construction documents.
d. Fully populated AF Form 66; Schedule of Material Submittals.
4.6 Notification Requirements
A. The Contractor shall also create and submit for approval a 4.0 A Table 1 - Table of
Deliverables, which includes the documents required by the approved Submittal Register.
Table 1 shall indicate when documents shall be submitted for review and approval. The
Government shall have up to the time listed in Table 1 to review submittal documents.
4.7 Permits
A. The Contractor shall develop, coordinate, and be responsible for labor, professional services and other costs associated with acquiring any and all required state, local, and other applicable permits; base access (including off-base easements and leases), agreements, licenses, and certificates required to perform and complete the project. Before the start of work, the Contractor shall process an Air Force Form 103, Work Clearance
Request, through the local Base Civil Engineer (BCE) office. The Contractor shall comply with applicable permit conditions, environmental protection policies and appended guidelines.
B. The contractor shall comply with all applicable permit conditions and shall keep all permits
“current” until construction is 100% complete. The contractor may be required to provide the permits to the Government as required.
C. If any compliance/enforcement organization notifies the contractor that a certain permit is not required, the government requests a copy of the official…
This is the start of the file's text. The full file is on GovTribe.