Attachment 1 Scope of Work.pdf
PDF 1 MB Posted
- Attached to
- Install Concrete Ramp and Pathway Federal contract opportunity
- Solicitation number
- 12805B24Q0029
About this file
This statement of work outlines requirements for two concrete projects at the USDA Biosciences Research Laboratory in Fargo, North Dakota. The first project involves demolishing the existing concrete ramp, pad, and handrail, which have exceeded their lifespan, and pouring and installing a new ADA-compliant concrete ramp approximately six feet wide that slopes down from the pad into the parking lot at a 1:12 ratio over approximately ten feet in length. It also requires replacing the existing handrail. The second project entails raising the gradient of soil near a greenhouse doorway by ten inches and pouring an eight-foot-wide by twenty-two-foot-long concrete walkway connecting the doorway to the nearby parking lot. The contractor must adhere to all local, state, and federal regulations and deliver the projects within sixty days of award. Inspections will occur before payment.
The related federal contract opportunity is solicitation number 12805B24Q0029 to install the concrete ramp and pathway for the USDA Agricultural Research Service Field Research Implementation and Information Delivery Plains Area.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_12805B24Q0029_Amd_0002.pdf | ||
| Questions and Answers Amendment 0002.pdf | ||
| Wage Determination ND20230013.pdf | ||
| Attachment 1 Scope of Work Revision 1.pdf | ||
| Sol_12805B24Q0029_Amd_0001.pdf | ||
| Attachment 5 ARS-372.pdf | ||
| Attachment 2 Wage Determination ND20230006.pdf | ||
| Solicitation 12805B24Q0029.pdf | ||
| Attachment 3 Schedule of Pricing (MS Excel Interactive Document).xlsx | XLSX spreadsheet | |
| Attachment 4 ARS-371.pdf | ||
| Site Visit Information.docx | DOCX document |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work (SOW)
Project: Concrete Ramp and Walkway at USDA BRL
Location: Biosciences Research Laboratory, 1616 Albrecht Blvd N, Fargo, ND
58102
GENERAL INFORMATION
1.0 Performance Work Statement: USDA-ARS in Fargo, ND, has a requirement for two (2) concrete projects. The first is to install an ADA compliant ramp, pad, and handrail, and the second is to install an 8’ by 22’ walkway from roadway to greenhouse door with an inclined slope to minimize a trip hazard. Pictures are included.
2.0 Background: The existing concrete ramp, pad, and handrail have exceeded it’s lifespan and must be replaced. Additionally, the exit to a greenhouse poses a trip hazard due to the absence of a sloped walkway from door to roadway similar to those which extend from adjacent greenhouse doors.
CONTRACTOR REQUIREMENTS
3.0 Technical Requirements/Tasks:
A. ADA Compliant Ramp
• Demolish and remove from premises the existing concrete ramp, section of damaged concrete pad adjacent to the doorway, and the existing handrail.
• Pour and install new concrete pad adjacent to doorway to replace damaged section, approximately 7 feet wide, 7 feet long, and 8 inches in height.
• Pour and install new concrete ramp from pad into the parking lot. Ramp should be approximately 6 feet in width. Ramp should start at the same height as the concrete pad and then slope down into the parking lot resulting in approximately 10 feet in length.
o Ramp should have a 1:12 slope ratio o Ramp should have all edges protected to minimize risk of falling o Ramp should have bottom landing at least 60 inches in length o Ramp should contour with the existing curb and adjacence infrastructure.
o Ramp should merge seamlessly into the parking lot.
• Replace the existing handrail with appropriate railing that is ADA compliant.
B. Concrete Walkway to Greenhouse
• Raise gradient of soil near the greenhouse doorway by approximately 10 inches by adding additional soil.
• Pour a concrete pad walkway connecting the greenhouse doorway to the nearby parking lot that is approximately 22 feet long and 8 feet wide.
• Ensure all local, state, and federal regulations are adhered to during completion of this project.
4.0 Deliverable / Schedule: 60 days after award.
5.0 Government Furnished: Photographs of the existing concrete pad and ramp that needs to be demolished and removed is included in this request, as well as pictures of the existing walkways to greenhouses. A brief sketch of what we are requesting be installed to replace this demolished pad and ramp is also included.
6.0 Travel: Not Applicable.
7.0 Contractor’s Key Personnel: Point of contact’s name and phone number is required.
8.0 Security Requirements: Not Applicable.
9.0 Data Rights: Not Applicable.
10.0 Section 508 – Electronic and Information Technology Standards: Not Applicable.
11.0 Performance Requirement Measures: Items will be inspected before payment will be rendered.
Attachment
ADA Compliant Ramp (Photographs included below)
Front View
Side View 1
Rear View
Side View 2
Side of pad from Parking Lot
Side of pad from lawn
Concrete Walkway from roadway to Greenhouse Exit Door
Wide View
Close up of Door
Side View 1
Close up of Door
Side View 2
Existing ramp in area to match style
Sketches of requested work = ADA Compliant Ramp:
Project Progress and Completion
6.0 Travel: Not Applicable.
File details come from the government source that posted it. Updated .