Attachment 1 MOVERS Governance and Replan.pptx

PPTX presentation 3 MB Posted

Attached to
Request for Proposal (RFP) for Project Management Services
Solicitation number
300000267513765
Issued by
Missouri

About this file

This is a governance and implementation plan document for the MOVERS (a statewide enterprise resource planning system) project. The document outlines the organizational structure and phased deployment schedule for implementing an integrated ERP and Human Capital Management (HCM) system. The project is structured around four major releases: Release 1 (Recruit and Core HR functions) going live March 1, 2027; Release 2 (ERP modules including General Ledger, Fixed Assets, Accounts Payable/Receivable, Inventory, Costing, Purchasing, Budget Control, Expenses, Manufacturing, Order Management, Cash Management, Reporting, and Project Portfolio Management) going live July 1, 2027; Release 3 (HCM functions including Payroll, Time and Labor, Compensation, Benefits, Absence Management, Talent Management, and Employee Self-Service) going live January 1, 2028; and Release 4 (Narrative Reporting and 1099 functionality) also going live January 1, 2028. Implementation spans fiscal years 2026 through 2028.

The governance structure establishes three decision-making bodies: an Oversight Committee providing executive oversight and strategic direction, a Change Control Board responsible for approving material changes to program scope, schedule, budget, and delivery, and a Program Team managing day-to-day activities including scope, schedule, budget, stakeholder management, and resource oversight. Governance escalation thresholds are distributed across strategic decisions (approximately 5 percent), tactical decisions (approximately 20 percent), and operational decisions (approximately 75 percent). Following each release's post-implementation support period, ongoing Maintenance and Operations support will be provided for all modules, including ticket triage, quarterly and monthly updates, and Oracle service request management.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Governance Structure Overview

Governance Chart Oversight Committee Deliver executive oversight, establish strategic direction, and champion the project Resolve high-impact issues Approve key project milestones and changes Ensure resource commitment Change Control Board Approve material changes to the program baseline (scope, schedule, budget, delivery) Provide recommendations to Oversight Committee for strategic decisions Program Team Oversees day-to-day project activities including managing scope, schedule, budget Manage stakeholders and project resources Escalate issues as needed

Governance Escalation Thresholds

Strategic ~5% of decisions Tactical ~20% of decisions Operational ~75% of decisions

RePlan Schedule

CY2026CY2027CY2028
FY26FY27FY28

Release 2 (ERP): GL, Fixed Assets, AP, AR, Inventory, Costing, Purchasing, Budget Ctrl, Expenses, Manufacturing, Order Management, Cash Mgmt. Reporting, PPM COA, Leasing, PPM, Custom solution to keep balances in sync between MOVERS and SAMII (FCCS or Acct Hub), MoBGT Restructure (Pending Proof of Concept Approval)

Release 3 (HCM): Payroll, Time & Labor, Comp, Benefits, Absence Mgmt, Talent, Employee Self-Service, Remaining Core HR, Knowledge Center

Release 1: Recruit, Core HR, EDMCS

Release 4: Narrative Reporting (ACFR), 1099

Go Live March 1, 2027

Go Live July 1, 2027

Go Live January 1, 2028

Go Live January 1, 2028

Maintenance & Operations (M&O) Ongoing support for Planning & Budgeting, Solicitation, Learn (MOVERS Production) including JIRA/ServiceNow Ticket Triage, Quarterly/Monthly Updates & Oracle SR Triage. Will begin for each release following the post go-live support period.