Attachment 1 ENERGY AUDIT MASTER.xlsx

XLSX spreadsheet 29 KB Posted

Attached to
LED Lighting Conversion State and local contract opportunity
Solicitation number
25-BM14
Issued by
Dane County, Wisconsin

About this file

This document is an Energy Audit Master spreadsheet detailing energy efficiency improvement opportunities across multiple municipal facilities, including Station 1, Fleet Maintenance, City Hall, Westside, Public Works, and Museum. The comprehensive audit evaluates energy conservation measures (ECMs) across lighting, HVAC equipment, HVAC controls, and water fixtures, with proposed improvements aimed at reducing energy consumption, increasing efficiency, and generating cost savings. The audit includes detailed assessments for each facility, documenting annual building savings, total project costs, available incentives, net costs, and simple payback periods.

The audit also includes a solar installation analysis for three municipal locations: Fleet Maintenance, Public Works, and Station 1, with proposed solar array sizes ranging from 100 kW to 182.5 kW and projected annual energy savings between 13,520 and 25,716 kWh. The solar projects have estimated total costs between $300,000 and $547,500, with potential tax credits and Focus rebates reducing net project costs. The proposed improvements are primarily funded through Capital Improvement Program (CIP) funds and Building Maintenance (BM) funds, with most projects scheduled for implementation between 2025 and 2028. The solar installations have projected return on investment (ROI) periods of 15.4 to 16.2 years, and are strategically planned to coincide with planned roof replacements.

View the file

Other files for this state and local contract opportunity

Other files attached to LED Lighting Conversion, newest first.
File Type Posted
25-BM LED Lighting Conversion Bid.pdf PDF
Fire station 1 First Floor Plan 200_500BW.pdf PDF
Firestation 1 lighting floor plan 2.pdf PDF
RFB 25-BM14 LED Lighting Conversion.pdf PDF
WCSB 1st floor light power area A.pdf PDF
WCSB 1st floor power area B.pdf PDF
25-BM14 Notice of Intent to Award Letter.pdf PDF
Firestation 1 lighting floor plan.pdf PDF
25-BM14 Sign in Log.pdf PDF
Fire Station 1 Second Floor Plan 201_500BW.pdf PDF
25-BM14 Draft Contract.pdf PDF
Fleet Lighting Plan.pdf PDF
WCSB 1st floor lighting area B.pdf PDF
WCSB 2nd floor light power area B.pdf PDF
25-BM14 QA.pdf PDF
LED Fixture Schedule 2025.xlsx XLSX spreadsheet
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ENERGY EFFICIENCY

Added to 2026-2035 CIPFund via BM fund (Focus rebates)
STATION 1
ECR no.Area of WorkECR TitleReason for EvaluationAnnual Building SavingsTotal CostIncentivesNet CostsSimple Payback YearsCIP / BM FundNotes
Remove from request to Ben1LightingReplace Fluorescent Lighting with LED AlternativeInefficient Lighting$1,519$6,015$1,260$4,7553.1CIP282 lights need replacing; 50% reduction in power draw; unsure if pricing includes fixture upgrade/replacement. Already included in 2025 CIPlump sum for lighting in station 1, Fleet, Westside lighting replacements
2HVAC EquipmentReplace Furnaces with Heat Pump AlternativeInefficient Equipment$418$50,000$630$49,370118.1CIP (28/29)ECM blower motor (x4) + 3 ton HP (x2) + 6 ton HP (x2). Confirm if this unit is on the roof (Jon).
Energy efficient generator - MSA grant in 2025?Jon is requesting this for CIP 2026
3HVAC ControlImplement Demand Control Ventilation to Reduce Heating and Cooling NeedsLack of HVAC control$628$7,500$860$6,64010.6CIP (28/29)$239,803
4HVAC ControlInstall Programmable Thermostats to Reduce Heating and Cooling NeedsLack of HVAC control$95$1,100$360$7407.8BM Fund (2025)
5Water FixturesReplace Water Fixtures with Low Flow AlternativeInefficient Equipment$849$2,5703.0
Low Cost ECM Total$2,659$64,615$3,110$61,50523
FLEET MAINTENANCE
ECR no.Area of WorkECR TitleReason for EvaluationAnnual Building SavingsTotal CostIncentivesNet CostsSimple Payback YearsCIP / BM FundNotes
1LightingReplace Fluorescent Lamps with LED AlternativeInefficient Lighting$1,250$6,627$430$6,1985.0CIP80 lights need replacing; 50% reduction in power draw; unsure if pricing includes fixture upgrade/replacement. Already included in 2025 CIP
2LightingReplace Exterior CFL with LED AlternativeInefficient Lighting$103$184$48$1361.3CIP24 lights need replacing; 50% reduction in power draw; unsure if pricing includes fixture upgrade/replacement. Already included in 2025 CIP
3Lighting ControlInstall Dual Technology Occupancy Sensors in BathroomsInefficient Lighting Control$56$320$19$3015.4BM FundCan install internally w/BM staff
4HVAC equipmentReplace Hot Water Heater with Heat Pump AlternativeInefficient Equipment$81$5,700$100$5,60069.0CIP (27)The DHW heater is overdue for replacement (installed 2006). Natural gas powered DHW would cost $4500, so really there is only an increased cost of $1200 to upgrade to heat pump. Look into this - need to have regular usage of heat pump to prevent issues. Check with PD/FD on how often we use hot water heater.*did not include hot water heater upgrades in CIP
5HVAC ControlUse Demand Control Ventilation for RTUsLack of HVAC control$720$5,000$860$4,1405.8CIP (27)RTU DCV automatically adjusts the ventilation rate based on the needs of the space, optimizing energy efficiency and indoor air quality. Is this for the garage area? We believe we already have venitallation controls for offices & breakroom. ROSE TO CHECK WITH KEVIN. Lump w/city Hall
6Water FixturesReplace Water Fixtures with Low Flow AlternativeInefficient Equipment$167$6604.0
Low Cost ECM Total$2,211$17,831$1,456$16,3757.4*hot water heater heat pump upgrade for multiple facilities + HVAC controls
CITY HALL
ECR no.Area of WorkECR TitleReason for EvaluationAnnual Building SavingsTotal CostIncentivesNet CostsSimple Payback YearsCIP / BM FundNotes
1LightingInstall controls for lighting, vending and exhaust fansInefficient Lighting$482$885$155$7311.5BM FundMen & women's basement locker rooms, PD conference room, stairwell, 1st floor breakroom. Jon will look into this. Locker rooms were recently remodeled - may have lighting sensors installed. May need to contract out exhaust fans on sensors.
2HVAC EquipmentInstall a Heat Pump Type Domestic Hot Water HeaterInefficient Equipment$191$6,900$100$6,80035.6CIP2 existing water heaters. Do a bit more research. Already in CIP for 2026; $65,000 budgeted)
3HVAC EquipmentInstall a Condensing Boiler for Building Heating Hot WaterInefficient Equipment$1,918$62,000$10,000$52,00027.1CIPModulate between 90 - 180 deg F, between OAT of -20 - 60 deg F (compared to always 160F with existing unit). Scheduled for spring 2025. $236000. Highly efficient natural gas boiler.
4HVAC ControlInstall Variable Frequency Drives for HHW DistributionLack of HVAC control$311$3,092$240$2,8529.2CIP (27)Lump w/fleet
5HVAC ControlInstall Variable Frequency Drives for Cooling Tower FanLack of HVAC control$764$4,200$800$3,4004.5CIP (27)Lump w/fleet
6HVAC ControlInstall Variable Frequency Drives for AHU-1 FansLack of HVAC control$709$6,300$360$5,9408.4CIP (27)Lump w/fleet
7HVAC ControlCorrect Simulataneous Heating and Cooling with Controls ImprovementsLack of HVAC control$2,264$8,000$1,875$6,1252.7CIPHeat Pumps provide heating and cooling to office spaces through ventilation system; Perimeter radiation provides heating from boiler --> Two systems do not interact through BAS. *ALREADY CORRECTED BY HELM IN 2024*
8Water FixturesReplace Water Fixtures with Low Flow AlternativeInefficient Equipment$1,086$3,9883.7
Low Cost ECM Total$6,639$91,377$13,529$77,84811.7
WESTSIDE
ECR no.Area of WorkECR TitleReason for EvaluationAnnual Building SavingsTotal CostIncentivesNet CostsSimple Payback YearsCIP / BM FundNotes
1LightingReplace Fluorescent Lighting with LED alternative and Add Controls in Select SpacesInefficient Lighting$7,746$16,635$4,707$11,9281.5CIP555 lights need replacing; 55% reduction in power draw; unsure if pricing includes fixture upgrade/replacement. Already included in 2025 CIP
2HVAC ControlCorrect Building Heating Plant Controls to Improve OperationLack of HVAC control$6,664$9,750$0$9,7501.5CIPBoilers are capable of condensing, but are not operating that way. Johnson Controls was out recently - confirm if they fixed this (Jon).
3HVAC ControlReduce Ventilation to Community Spaces during Unoccupied PeriodsLack of HVAC control$781$3,000$430$2,5703.3CIPUse occupancy sensors to control lighting and HVAC operation - occupied / unoccupied heating and cooling setpoints; Also use to control for ventilation and compare indoor CO2 to outdoor. Lump with city hall & fleet
4HVAC ControlCorrect Chilled Water Distribution Pump OperationLack of HVAC control$191$1,500$0$1,5007.9CIPCurrent estimated wasted run-time of motor (25% loaded) - Occupied Hours below 60 deg F: 1805 hours. Johnson Controls was out recently - confirm if they fixed this (Jon).
Hot water heater replacement lumped into City hall HWH replacement. Consider heat pumps?
5Water FixturesReplace Water Fixtures with Low Flow AlternativeInefficient Equipment$2,337$4,7252.0
Low Cost ECM Total$15,381$30,885$5,137$25,7481.7
PUBLIC WORKS
ECR no.Area of WorkECR TitleReason for EvaluationAnnual Building SavingsTotal CostIncentivesNet CostsSimple Payback YearsCIP / BM FundNotes
1LightingReplace Fluorescent and Metal Halide Lamps with LED AlternativeInefficient Lighting$1,573$20,000$2,220$17,78011.3CIP 27/2893 lights need replacing; 50% reduction in power draw; unsure if pricing includes fixture upgrade/replacement.
2HVAC EquipmentReplace Gas Hot Water Heater with Heat Pump AlternativeInefficient Equipment$56$5,400$100$5,30094.0CIPAlready in CIP for 2026. lumped in with City Hall & Westside.
3HVAC ControlEnable Demand Control Ventilation for FurnacesLack of HVAC control$923$5,000$860$4,1404.5CIP (27)Lump in
4HVAC ControlInstall Dual Technology Occupancy Sensors in BathroomsLack of HVAC control$82$240$48$1922.3BM Fund1st floor men & women's bathrooms
Energy efficient windows / better insulated garage doors for 2027 already in CIP
5Water FixturesReplace Water Fixtures with Low Flow AlternativeInefficient Equipment$181$1,0906.0
Low Cost ECM Total$2,634$30,640$3,228$27,41210.4
Controls savings & cost:$4,836$34,092
MUSEUM
ECR no.Area of WorkECR TitleReason for EvaluationAnnual Building SavingsTotal CostIncentivesNet CostsSimple Payback YearsCIP / BM FundNotes
1LightingReplace Basement Lights with LED alternativeInefficient Lighting$28$1,500$33$1,46751.7BM Fund (26/27)13 lights need replacing; 50% reduction in power draw; unsure if pricing includes fixture upgrade/replacementWere these upgraded earlier this year? Our staff replaced lighting/fixtures in basement. ~6 bulbs replaced in basement; can likely do the rest in house.
2LightingInstall Dual Technology Occupancy Sensor to Control Bath Lighting and FanInefficient Lighting Control$74$470$245$2263.0BM Fund1st floor men & women's bathrooms; can install internally
3HVAC EquipmentReplace Dehumidifier with an ENERGY STAR AlternativeInefficient Equipment$67$250$0$2503.8CIP (28)Permanent system connected to furnace. Existing unit doesn't reach all basement areas where collections are stored.What type of dehumidifier is in the museum? Permanent or moveable?
4HVAC EquipmentReplace Electric Water Heater with a Heat Pump AlternativeInefficient Equipment$140$4,750$100$4,65033.2CIP (28)Items 3-5 --> $25,000
5HVAC EquipmentReplace Furnace and AC with an Air-Source Heat PumpInefficient Equipment$287$10,000$240$9,76034.0CIP (28)6 ton HP (x1)
6HVAC ControlInstall Programmable Thermostat to Operate HVAC SystemLack of HVAC control$46$200$60$1403.0BM Fundone thermostat
7Water FixturesReplace Water Fixtures with Low Flow AlternativeInefficient Equipment$147$6604.5
Low Cost ECM Total$642$17,170$678$16,49225.7

SOLAR

FLEET MAINTENANCEPUBLIC WORKSSTATION 1
Size182.5kWSize172kWSize100kW
Production239,226kWh/yrProduction227,445kWh/yrProduction125,774kWh/yr
Annual Energy Savings$ 25,716.80(conservative)Annual Energy Savings$ 24,450.34(conservative)Annual Energy Savings$ 13,520.71(conservative)
Cost$ 547,500.00(conservative)Cost$ 516,000.00(conservative)Cost$ 300,000.00(conservative)
Tax Credit$ (139,612.50)(conservative)Tax Credit$ (131,580.00)(conservative)Tax Credit$ (76,500.00)(conservative)
Focus Rebate$ (9,125.00)Focus Rebate$ (8,600.00)Focus Rebate$ (5,000.00)
TOTAL$ 398,762.50TOTAL$ 375,820.00TOTAL$ 218,500.00
ROI15.5yearsROI15.4yearsROI16.2years
Roof installed in 2007, replace in 2027Metal roof in good condition. Very long lifespan.CIP 2032 (move roof replacement to 2032 and add solar to this item.)
Fleet roof & solar replacement in 2030 CIP - $775,000Solar in CIP 2032 - $450,000 (planning/design/install)$500,000 for roof & solar (includes planning/design & installation)
*add to 2032 CIP due to uncertainty with future use case of existing PW facility
*remove duplications of roof replacements and lump in with solar installations.
$ 993,082.50
239802.75
$ 1,232,885.25