Attachment 1 - Add Walk-in Blast Booth Building SOW.pdf
PDF 115 KB Posted
- Attached to
- Add Paint Blast Booth Federal contract opportunity
- Solicitation number
- FA301020R0035
About this file
This document is a solicitation for the addition of a paint blast booth at Keesler Air Force Base. The proposed construction cost is between $1,000,000 and $5,000,000, and it is being issued as a set-aside for Service-Disabled Veteran-Owned Small Businesses. An organized site visit for interested contractors is scheduled for August 4th at 9:00 AM, with instructions provided in Section 52.236-27. The solicitation notes that funds are not presently available and no award will be made until funding is in place. Contractors are directed to Sections L and M for proposal preparation and evaluation factors. The closing date for receipt of proposals is not specified.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Solicitation Amendment FA301020R00350002 SF 30.pdf | ||
| Attachment 3 - Addendum 01_DWG_21 Aug 2020.pdf | ||
| Attachment 11 - Provision 52.204-24 & Clause 52.204-25.pdf | ||
| Solicitation Amendment FA301020R00350001 SF 30.pdf | ||
| Site Visit Sign In Sheet.pdf | ||
| Attachment 8 - SF 1444.pdf | ||
| Attachment 2 - Add Walk-in Blast Booth Building SPECS.pdf | ||
| Attachment 6 - Past Performance Questionnaire.pdf | ||
| Solicitation - FA301020R0035.pdf | ||
| Attachment 5 - AF 66.xlsx | XLSX spreadsheet | |
| Attachment 4 - Wage Determination.pdf | ||
| Attachment 3 - Add Walk-in Blast Booth Building DWG.pdf | ||
| Attachment 10 - DoD Building Code - AHJ defined.pdf | ||
| Attachment 9 - Notice of Compliance.pdf | ||
| Attachment 7 - Past Performance Reference List.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
May 28, 2020
V3-CONS-5/27 Page 1 of 16
STATEMENT OF WORK
ADDITIONS TO WALK-IN BLAST BOOTH BUILDING
Project #MAHG191072
WO #82188
1.0 INTRODUCTION:
The Contractor shall furnish all equipment, labor, supervision and materials necessary to provide an addition to the existing Walk-in Blast Booth building for Keesler AFB. All work is to be performed in accordance with this statement of work and is subject to the terms and conditions of the contract.
2.0 ACRONYMS/DEFINITIONS:
ACM – Asbestos Containing Material AF – Air Force AFB - Air Force Base AFI – Air Force Instruction AHJ – Authorities Having Jurisdiction APR – Air Purifying Respirator BMP – Best Management Practice BOS- Base Operating Service C&D – Construction and Demolition CE - Civil Engineering CES – Civil Engineering Squadron CEV- Civil Engineering Environmental
CFR – Code of Federal Regulations CM - Contract Monitor CO - Contracting Officer DOD – Department of Defense EISA – Energy Independence and Security Act
EPA – Environmental Protection Agency
FPCON – Force Protection Condition FOIA – Freedom of Information Act FOUO – For Official Use Only FT - Foot GFCI – Ground Fault Circuit Interrupter
HEPA- High Efficiency Particulate Air (filter)
IAW – In Accordance With IBC – International Building Code IN - Inch LBP – Lead Based Paint MDEQ - MS Department of Environmental Quality
NEC – National Electric Code NFPA – National Fire Protection Association
OSHA – Occupational Safety and Health Act
PM - Project Manager POC – Point of Contact PPE – Personal Protection Equipment RAMS – Random Antiterrorism Measures
RCRA – Resource Conservation and Recovery Act
RFI – Request for Information SDS – Safety Data Sheets SF – Square Foot SOW - Statement of Work SWPPP – Storm Water Pollution Prevention Plan
SY – Square Yard UFC – United Facilities Guide WO – Work Order TAB - Test, Adjust and Balance
V3-CONS-5/27 Page 2 of 16
3.0 TASK DESCRIPTION:
3.1 LOCATION: This contract is to be performed at building # 4302.
3.2 DESCRIPTION OF WORK:
3.2.1 The Contractor is encouraged to examine the site and make note of all requirements of the Work before submitting any bids. Any accessories or incidental items not specifically shown on the Drawings and detailed in the Statement of Work herein, which are necessary and/or required to complete the work within the intent of these documents, shall be included by the Contractor without additional cost to the Government. All work shall be performed in strict accordance with the SOW/specifications/drawings and subject to the terms and conditions of the contract.
3.2.2 Utilities for the work will be provided by the Government unless otherwise noted.
3.2.3 It is not anticipated that hazardous material will be encountered during the course of work.
However, should such material be encountered, the Contractor is to immediately stop work and contact the CO. All hazardous material will be dealt with according to paragraphs 4.6, 4.7, 4.8 of this Statement of Work.
3.2.4 SCOPE:
Work shall consist of the addition to the existing Walk-in Blast Booth Building, B4302 according to project manual and drawings. The addition is to provide space to house the existing cabinet blast booths (2 each), located in another facility, decontamination stations (air blast booth and overhead shower station), laundry, and his and her restrooms with showers and PPE storage lockers. Specific trades involved are, but not limited to, standing seam metal roof system, structural steel, precast concrete walls, gutters and downspouts, reinforced concrete foundation, reinforced masonry walls, flooring, ceiling, walls, doors, painting, lighting, electrical power, fire alarm, communication, plumbing and HVAC. Contractor relocate the existing blast booths (approx. 12’w x 12’l x 6’h each) to the new facility.
Door Hardware: Reference Section 087100: Contractor shall provide o Contractor shall install and use temporary ‘construction cores’. Contractor shall not install permanent cores.
o All permanent lock cores shall be Small Format Interchangeable Core (Base Standard).
o Provide all permanent blank cores to the Contracting Officer for the Base Locksmith to key and install at approximately 75% project completion.
o All blank keys shall be provided to the Contracting Officer for the Base Locksmith to key.
o Provide 3 blank keys for each lock.
• ATTACHED SPECIFICATIONS AND DRAWINGS:
Specifications:
SECTION 00102 List of Drawings SECTION 03 30 00 Cast-in-Place Concrete
V3-CONS-5/27 Page 3 of 16
SECTION 03 45 00 Precast (Prestressed) Structural Concrete SECTION 04 20 00 Unit Masonry SECTION 05 12 00 Structural Steel SECTION 05 21 00 Steel Joist Framing SECTION 05 30 00 Steel Decks SECTION 05 50 13 Miscellaneous Metal Fabrications SECTION 06 10 00 Rough Carpentry SECTION 06 20 00 Finish Carpentry SECTION 07 21 16 Mineral Fiber Blanket Insulation SECTION 07 22 00 Roof and Deck Insulation SECTION 07 27 19.01 Self-Adhering Air Barriers SECTION 07 60 00 Flashing and Sheet Metal SECTION 07 61 15.00 20 Aluminum Standing Seam Roofing SECTION 07 84 00 Firestopping SECTION 07 92 00 Joint Sealants SECTION 08 11 13 Steel Doors and Frames SECTION 08 33 23 Overhead Coiling Doors SECTION 08 71 00 Door Hardware SECTION 08 91 00 Metal Wall Louvers SECTION 09 22 00 Supports for Plaster and Gypsum Board SECTION 09 29 00 Gypsum Board SECTION 09 30 10 Ceramic, Quarry and Glass Tiling SECTION 09 51 00 Acoustical Ceilings SECTION 09 65 00 Resilient Flooring (Floor Base) SECTION 09 90 00 Paints and Coatings SECTION 10 14 00.20 Interior Signage SECTION 10 28 13 Toilet Accessories SECTION 10 44 16 Fire Extinguishers SECTION 10 51 13 Metal Lockers SECTION 21 13 13.00 20 Wet Pipe Sprinkler System, Fire Protection SECTION 22 00 00 Plumbing, General Purpose SECTION 23 00 00 Air Supply, Distribution, Ventilation, and Exhaust Systems SECTION 23 03 00.00 20 Basic Mechanical Materials and Methods SECTION 23 05 93 Testing, Adjusting and Balancing for HVAC SECTION 23 07 00 Thermal Insulation for Mechanical Systems SECTION 23 11 25 Facility Gas Piping SECTION 23 31 13.00 40 Metal Ducts SECTION 23 81 00 Decentralized Unitary HVAC Equipment SECTION 26 00 00.00 20 Basic Electrical Materials and Methods SECTION 26 05 00.00 40 Common Work Results for Electrical SECTION 26 05 19.10 10 Insulated Wire and Cable SECTION 26 05 26.00 40 Grounding and Bonding for Electrical Systems SECTION 26 20 00 Interior Distribution System SECTION 26 41 00 Lightning Protection System SECTION 26 51 00 Interior Lighting
V3-CONS-5/27 Page 4 of 16
Drawings:
1. T100 TITLE PAGE
2. LS101 LIFE SAFETY PLAN
3. V100 EXISTING SITE SURVEY
4. C100 SITE DEMOLITION PLAN
5. C200 SITE PLAN
6. C300 DRAINAGE SITE PLAN
7. C400 UTILITIES SITE PLAN
8. C500 CONSTRUCTION DETAILS
9. C600 CONSTRUCTION DETAILS
10. C700 EROSION CONTROL PLAN AND DETAILS
11. S100 DESIGN CRITERIA
12. S200 FOUNDATION PLAN
13. S300 FRAMING PLAN
14. S400 BUILDING SECTION
15. S500 FOUNDATION DETAILS
16. S600 FRAMING DETAILS
17. D100 FLOOR PLAN - DEMOLITION
18. A101 FLOOR PLAN - NEW CONSTRUCTION
19. A102 REFLECTED CEILING PLAN
20. A103 ROOF PLAN
21. A201 EXTERIOR ELEVATIONS
22. A202 PRECAST PANEL ELEVATIONS
23. A301 BUILDING SECTIONS
24. A302 WALL SECTIONS
25. A303 WALL SECTIONS
26. A401 RESTROOM DETAILS
27. A501 DETAILS
28. A601 SCHEDULES
29. A602 HJS DETAILS
30. FP100 FIRE PROTECTION
31. M001 HVAC ABBREVIATIONS AND NOTES
32. M100 HVAC SCHEDULES AND DETAILS
33. M101 HVAC DETAILS CONT'D
34. M102 HVAC PLAN
35. M103 HVAC CONTROLS
36. P001 PLUMBING SCHEDULES
37. P002 PLUMBING DETAILS
38. P100 SITE PLAN
39. P101 UNDERGROUND SANITARY SEWER
40. P102 ABOVE FLOOR SANITARY SEWER
41. P103 RISER PLAN
42. P104 DOMESTIC WATER
43. P105 DOMESTIC WATER RISER
44. P106 GAS AND PNEUMATIC
V3-CONS-5/27 Page 5 of 16
45. E000 ELECTRICAL LEGEND, SCHEDULE, DETAILS, AND RISERS
46. E001 GROUNDING AND LIGHTNING PROTECTION DETAILS
47. E100 LIGHTING PLAN
48. E101 POWER PLAN
49. E102 MECHANICAL SYSTEMS AND FIRE ALARM PLAN
50. E103 LIGHTNING PROTECTION PLAN
51. E200 ELECTRICAL PANEL SCHEDULES
52. E201 METERING DETAILS
3.2.5 Reference AF Form 66 Schedule of Material Submittals for submittals that must be approved. The Contractor shall provide all items listed on AF 66 on the AF Form 3000 Material Approval Submittal. Item number on the AF Form 3000 must match the same Item name/number listed on the AF Form 66.
3.2.5.1 Submit via email one (1) copy of product data, shop drawings, and Certification of Compliance, and Manufacturer Recommendations, or as otherwise noted in the AF Form 66, as directed in the Pre-Construction Conference.
3.2.5.2 Submit three (3) hard copies of color schedules, and one (1) copy of samples, or as otherwise noted in the AF Form 66, as directed in the Pre-Construction Conference.
3.2.5.3 All submittal documents received that do not clearly delineate and display the information which is being submitted will be returned to the Contractor.
3.2.5.4 The CO's approval or acceptance of submittals is not to be construed as a complete check, and indicates only that the general method of construction, materials, detailing and other information are satisfactory, to meet the Solicitation and Accepted Proposal. Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist.
3.2.6 Material: All material furnished by the Contractor for this job shall be new and unused material of high quality unless otherwise noted. The Contractor is responsible for the proper storage of all material until it is installed.
3.3 PERFORMANCE TIME: 240 Days after the ‘Notice to Proceed’ has been signed.
3.3.1 No Work shall begin until all Submittals related to that work have been received and approved.
3.3.2 Punch list items noted in the closeout process shall be fixed before the end of the Period of
Performance or the project will be considered past due.
3.4 PERFORMANCE OF WORK:
3.4.1 Services shall be conducted in conformity with applicable regulations to contribute maximum satisfaction to responsible base offices. All work shall be done in a neat and workmanlike manner and in keeping with generally accepted standards for similar work.
Services shall be performed in accordance with schedules, once established. All work shall be done with minimum disturbance and maximum protection of property. The CM shall be notified 72 hours prior to work starting.
V3-CONS-5/27 Page 6 of 16
3.4.2 The Contractor must within 24 hours of notice that a delay will be incurred notify the CO in writing. This letter must identify why there will be a delay, and how long. Also the Contractor shall take any actions in his control to prevent delay from occurring.
3.4.3 In order to complete the work on this job, certain Government -owned facilities may have to be removed or altered in some way and others may be inadvertently damaged. It is the responsibility of the Contractor to return these facilities to a condition acceptable to the
CO.
3.4.3.1 Damage to located underground utilities will be repaired at the Contractor’s expense. Repairs shall replace the damaged section “in kind” for storm, sanitary, gas, and water; or replace the entire run to the current standard in the case of communication or electrical.
3.5 JOBSITE MAINTENANCE AND STORAGE AREAS: The Contractor shall maintain the jobsite and staging areas in conformance with the standards below and as directed by the CO.
3.5.1 Lay down/staging areas shall be kept neat and free of loose debris at all times. Grass shall be cut and maintained regularly. Height and maintenance shall be consistent with normal Base standards and consistent with the immediate area.
3.5.2 Jobsites and lay down/staging areas shall be enclosed with a 6’ chain link fence with brown fabric screening unless otherwise noted. Materials and equipment may be stored inside storage units. Items stored in the lay down area shall be arranged neatly.
3.5.3 All temporary storage trailers and storage containers shall present a neat and clean appearance and shall be in a state of good repair and shall be located within the fenced area described in paragraph above.
3.5.4 If allowed by the contract and if approved by the CO, an office mobile unit may be located outside of a fenced area. At a minimum, this unit shall be in a paved area and shall present a neat, professional appearance. Unit shall be of Keesler standard colors, shall have presentable skirting and access stairs. Ancillary items, such as porches and canopies, shall be neat and painted Keesler brown. Contractor shall submit a picture of the proposed unit for approval and before unit is moved to Base.
3.5.5 Execution of work may require excavation or other type of work both at and away from primary work area. These areas shall be secured and work times shall be kept to a minimum. Open excavations shall be directly in progress or shall be covered directly after work complete. Open excavations requiring extended period of inactivity shall be temporarily backfilled. In no case shall an excavation be open for more than 72 hours.
Barricades, fences and other warning devices shall be maintained neatly at all times.
3.5.6 The Contractor shall maintain the premises, including any staging area or storage areas, free from accumulations of waste, debris, and rubbish caused by the Contractor’s work and shall minimize the spread of dust and flying particles. As work is completed, or at the end of each day, the site shall be cleaned and all waste material shall be properly disposed of properly.
V3-CONS-5/27 Page 7 of 16
3.5.1 Should warnings of winds of gale force or stronger be issued, the Contractor shall take every practical precaution to minimize danger to persons and damage to property. These precautions shall be coordinated through the CO and shall include closing all openings;
removing all loose materials, tools, and equipment from exposed locations; securing all material, tools, equipment and construction work; as well as removing or securing scaffolding and other temporary work. The Contractor shall also coordinate all efforts with the CO and follow the Base Commander’s direction in the event of an upcoming storm or hurricane which may range from securing sites to complete demobilization of all equipment and material from the base.
3.6 SUPERVISION: Contractors shall provide competent supervision familiar with the project and are on-site at all times when work is in progress. Contractor is responsible for scheduling and coordinating various trade activities. Contractor is also responsible for assuring that all work accomplished and materials used are in accordance with industry standards.
3.7 ACCESS: The CO shall have access at any and all times to the Contractor's equipment, materials, supplies, assigned areas and sites of operation for inspection purposes.
3.8 HOURS OF OPERATION: The Contractor will be able to accomplish this work between the hours of 7:00 AM and 5:00 PM. The Contractor will not normally be permitted to work on weekends or on the following federal holidays (or the day the Federal Government observes these holidays) unless approved by the CO. To be approved by the CO, the Contractor shall provide documentation showing work performed outside the hours of work will benefit the project’s mission. If approved by the CO, the Contractor shall coordinate such work with the CM at least seventy-two (72) hours in advance:
New Year's Day Labor Day Martin Luther King, Jr.'s Birthday Columbus Day Washington's Birthday Veteran's Day Memorial Day Thanksgiving Day
Independence Day Christmas Day
The following days are not federal holidays but may require work stoppage:
Special Olympics- Thursday through Sunday of First NON-Training weekend in May
3.9 PERMITS:
3.9.1 Contractors will be required to obtain permits as required by Keesler in the performance of their work. Contractors shall post or have readily available all permits before work is commenced
3.9.1.1 The following permits must be obtained anytime referenced work is required.
DIG PERMIT, Vectrus Customer Service BURN PERMIT, Keesler AFB Fire Department CONFINED ENTRY PERMIT, (certified personnel only)
Obtain permit from Vectrus CM or Safety Office.
Notification to Fire Department of actual day and time work is accomplished.
V3-CONS-5/27 Page 8 of 16
3.10 INTERRUPTION OF SERVICES:
3.10.1 If interruption of any building utility services such as but not limited to the following, chilled water, electrical power, domestic water, fire protection water supply, or communications etc. are required, the Contractor shall perform the work on normal work week hours after receiving approval, during the weekend, or on non-training Fridays.
The Contractor shall coordinate the interruption of the utilities 14 days in advance with the CM and user regardless of the option chosen. The Contractor shall include any additional cost of performing the work in their original bid.
3.10.2 The Contractor shall fill out a “utility service outage request form” and submit it to the Contracting Officer. The Contracting Officer may require the Contractor to attend a coordination meeting to assess the purpose, intent, and impact of the outage request with the facility and any or all operations departments. Contractors shall not shut-down or start-up any mechanical, electrical and/or plumbing system without the coordination and/or permission of the CO.
3.11 JOBSITE SAFETY:
3.11.1 The Contractor shall take all necessary and prudent safety precautions to ensure the safety of the workforce and other exposed personnel. The Contractor shall observe all Safety, Security, Traffic and Fire regulations presently enforced at Keesler Air Force Base and comply with latest issue of OSHA requirements. Contractors shall comply with the Occupational Safety and Health Act (OSHA, Public Law 91-596) and the resulting standards, OSHA Standards 29 CFR 1910 and 1926. The detailed provisions of the act for accident prevention are directly applicable to all Contractor operations. Prime Contractors are also responsible for ensuring any Contractors also adhere to OSHA Guidance. OSHA compliance officers can visit Contractor worksites on the installation.
3.11.2 Contractors are responsible for ensuring all industrial safety provisions are followed.
Take immediate corrective action to comply with safety regulations if informed of a violation by the CO.
3.11.3 Contractors must report all accidents involving Air Force people, property, or equipment damage, and any Contractor personnel injured in the performance of the air force contract to the CO.
3.11.4 Contractor shall comply with all aspects of the National Fire Protection Association (NFPA) Standard 241, "Standard For Safeguarding Construction, Alteration, And Demolition Operations," current edition, and United Facilities Criteria (UFC) 3-600-01, “Fire Protection Engineering For Facilities,” current edition.
3.11.5 Provide safety protection and precautions for any electrical exposure. Temporary lighting shall have metal cages around the lamp and shall be turned off when not in use and no fire watch is present.
3.11.6 Ground Fault Circuit Interrupters: Whenever Contractor uses portable electrical tools or equipment in an outside location where operator will be in contact with a grounded
V3-CONS-5/27 Page 9 of 16 surface or in an interior wet location where floor is conductive such as concrete, Contractor shall provide and use a portable ground fault circuit interrupter (GFCI). This shall apply wherever electric power is supplied through government-owned facilities.
Contractor shall be responsible for maintaining the GFCI in operating condition and testing it before each use.
3.12 PASSES:
3.12.1 Contractor Notification Responsibilities: The Contractor shall provide a written notification to the CO. The notification shall include the names and contact information (phone number, and email) of a minimum of two Contractor representatives (preferably the contracting agent and the project supervisor) that will be responsible for this project and have 24 hour contact availability to answer any questions or address any issues that may arise that are related to this project.
3.12.2 Passes for Contractor employees may be requested through the assigned CM. Requests shall include full name of employee as it appears on their identification, length of pass needed (up to 30 days), and days needed (if other than standard working hours).
3.12.3 Paperwork required for passes:
3.12.3.1 For vehicle operators: 1] Current driver license for each employee in support of work on Keesler AFB. 2] Vehicle Registration and Proof of Insurance.
3.12.3.2 For non-vehicle operators: Current driver license, official ID card, or passport.
3.13 REPORTING REQUIREMENTS: The Contractor shall comply with AFI 71-l0l, Volume1, Criminal Investigations and Volume-2, Protective Service Matters, requirements. Contractor personnel shall report to an appropriate authority, any information or circumstances of which they are aware may pose a threat to the security of DOD personnel, Contractor personnel, resources, and classified or unclassified defense information. Contractor employees shall be briefed by their immediate supervisor upon initial on-base assignment and as required thereafter.
3.14 PHYSICAL SECURITY:
3.14.1 Areas controlled by Contractor employees shall comply with Base Operations Plans/instructions for FPCON procedures, Random Antiterrorism Measures (RAMS) and local search/identification requirements. The Contractor shall safeguard all government property, including controlled forms, provided for Contractor use. At the close of each work period, government training equipment, ground aerospace vehicles, facilities, support equipment, and other valuable materials shall be secured.
3.14.2 The Contractor shall not employ persons for work on this contract if such employee is identified by the government or BOS Contract officials as a potential threat to the health, safety, security, general well-being or operational mission of the installation and its population.
3.15 VEHICLE SAFETY AND TRAFFIC LAWS:
3.15.1 The Contractor and its employees shall comply with base traffic laws and regulations.
V3-CONS-5/27 Page 10 of 16
3.15.2 The Contractor shall ensure employees have a current and valid driver’s license and commercial permits/licenses for the type of vehicle operated, before allowing the employee to operate a Contractor-owned or rental vehicle on Keesler AFB.
3.15.3 The Contractor shall provide all vehicles to perform the requirements of the contract. All vehicles shall be in operable condition and meet local, state and federal safety requirements, and be specifically designed for the purpose intended for use. Vehicles shall have, clearly visible on each side, the Contractor company name, a unique vehicle identification number, in addition to all required Department of Transportation (DOT) markings and information.
3.15.4 Air Field Driving: All Contractors must receive airfield drivers training prior to receiving notice to proceed or prior to driving on the airfield IAW (AFI 13-213, 2.1.3.39.7.) This training will be provided by Airfield Management at B0233 PH: 228-377-2215.
3.15.5 Cellular Phones: The use of cellular phones while operating a vehicle is prohibited while on Keesler AFB property.
3.16 FREEDOM OF INFORMATION ACT PROGRAM (FOIA): The Contractor shall comply with DOD5400.7-R_AFMAN 33-302, Freedom of Information Act Program (FOIA), and requirements. The regulation sets policy and procedures for the disclosure of records to the public and for marking, handling, transmitting, and safeguarding For Official Use only (FOUO) material.
4.0 ENVIRONMENTAL:
4.1 RECYCLED CONTENT AND BIO BASED PRODUCTS: Executive Order 13514 dated 5 Oct 09, outlines the federal government’s special responsibility to lead the way in building markets for recycled goods. Green procurement is the name given by the Air Force to this buy-recycled purchasing program. The intent of the program is to stimulate recycling by providing a market for new products manufactured with bio-based or recycled materials. The legal authority for the Green Procurement Program comes from the Resource Conservation and Recovery Act (RCRA) Section 6002. It requires federal agencies to give preference in their purchasing programs to products and practices conserving and protecting natural resources and the environment. If applicable, material and product submittals for all recycled-content items should list the recycled and recovered materials used and the percentage content (by weight).
Submittals for bio-based products should describe the bio-based materials used and the percentage content (by weight). This data is required to be submitted by the Contractor on an AF Form 3000 (Material Approval Submittal) to the CO upon completion of performance (construction).
4.2 ENVIRONMENTAL PROTECTION: Contractor personnel shall, at all times, perform all work and take such steps required to prevent any interference or disturbances to the ecological balance of the environment. All work must be performed in accordance with applicable Federal, State, Local, and Air Force environmental regulations. Use good management practices to protect air, water, land and wildlife and to prevent noise, solid waste, radiant energy, dust and radioactive pollutants. In the event of a chemical or hazardous material spill, V3-CONS-5/27 Page 11 of 16 the Contractor must immediately notify the Keesler Fire Department at 911 (identify that you are located on Keesler AFB) and the Keesler BOS Contractor environmental representative at 228-377-1262.
4.3 WASTE MATERIALS: Unless otherwise specified, all waste materials, excess dirt and rubble, empty containers, etc., shall be disposed of at an approved off-base location in accordance with all applicable Federal, State, County and Municipal laws.
4.3.1 Solid Waste Management:
4.3.1.1 Designate individuals on the Contractor’s staff who are responsible for
Construction and Demolition (C&D) waste prevention and management.
4.3.1.2 Develop procedures for collecting and storing C&D waste on project sites, including designating locations for waste containers, sorting or separating methods, handling and transporting of wastes, special handling requirements, and scheduling for waste and recycling collection.
4.3.1.3 Develop descriptions of how the C&D materials will be recycled or reissued. The information should include any on-site storage and processing areas and a description of the processing and equipment.
4.3.1.4 Records shall be maintained for all C&D projects to document the quantity of waste generated; the quantity of waste diverted through sale, reuse, or recycling;
and the quantity of waste disposed by land filling or by incineration.
4.3.1.5 Contractors shall provide these records to the CO in accordance with contract requirements.
4.3.1.6 In accordance with Executive Order 13514, Keesler AFB will divert 60% of all C&D waste.
4.3.1.7 Manage solid waste in accordance with the Keesler AFB Integrated Solid Waste Management Plan.
4.3.1.8 For any questions regarding solid waste, please contact VECTRUS/ CEV at 228- 377-1262.
4.4 HAZARDOUS MATERIALS: In the event that hazardous materials will be used in the execution of this contract, the Contractor will be required to provide a list of materials, quantities, and Safety Data Sheets (SDS) to the Contracting Officer before work begins. The hazardous materials must be approved through the Keesler Hazardous Materials Management Program prior to being brought onto Keesler AFB. This approval process may take up to two weeks, which should be considered in the performance period of this contract. Unless otherwise specified, all unused hazardous materials should be removed from the base at the end of the project.
4.5 STORM WATER MANAGEMENT: If ground disturbing activities will take place as part of this project, the following items must be completed:
4.5.1 For any construction activity greater than 5,000 square feet of ground disturbance, the Contractor shall comply with all provisions of the Energy Independence and Security Act (EISA) concerning storm water run-off from Federal development projects.
V3-CONS-5/27 Page 12 of 16
4.5.2 The construction Contractor shall complete all paperwork necessary, including the Storm Water Pollution Prevention Plan (SWPPP) to apply for the appropriate Large (>5 acres) or Small (>1 acre but <5 acres) Construction Storm Water General Permit (Permit) from the Mississippi Department of Environmental Quality (MDEQ).
4.5.3 The Contractor shall furnish Vectrus/CEV copies of the Permit application, SWPPP, Permit, confirmation letter from the MDEQ and any other pertinent storm water information related to the project.
4.5.4 The initial storm water permit application and original SWPPP shall be submitted to Vectrus/CEV for review and comment prior to or at the time of submittal to the MDEQ.
4.5.5 The Contractor shall comply with all provisions of the Permit throughout the duration of the project.
4.5.6 Any construction site/land disturbance activity greater than 20,000 sq/ft, but < 1 acre shall have a SWPPP prepared and approved by Vectrus/CEV prior to construction or implementation of the land disturbance activity.
4.5.7 The Keesler AFB Small Municipal Separate Storm Sewer System (MS4) Permit requires Keesler AFB to maintain a file for each construction site. The file must contain the storm water training credentials of all Contractor personnel involved in storm water management at each construction site. The Contractor shall furnish Vectrus/CEV copies of storm water training credentials for all pertinent employees prior to commencement of construction activities. Vectrus/CEV training information is available to the Contractor.
4.5.8 The Contractor shall modify the SWPPP at any time to ensure the SWPPP is current with the existing site conditions at any time for the duration of the project.
4.5.9 The Contractor shall maintain all appropriate post construction storm water (BMPs) until final site stabilization is achieved.
4.6 REQUIRED ASBESTOS ABATEMENT AND MANAGEMENT PROCEDURES: These steps are in accordance with Air Force Instruction (AFI), EPA, and MDEQ. OSHA regulations govern all worker safety requirements and must be complied with at all times by the Contractors and sub-Contractors. These requirements are summarized in the Keesler Air Force Base Asbestos Operations and Management Plan.
4.6.1 The following steps are required by all personnel or Contractors doing work on Keesler
AFB.
4.6.1.1 If the personnel or Contractor encounters what they think may be asbestos, they are required to stop and call the KAFB Asbestos Point of Contact (APOC) at the Keesler Environmental Section, which is Dale Woodall at 228-377-1262 or EMCS (228- 377-4179) after hours.
4.6.1.2 Once it is determined by the APOC that asbestos is present, the following actions described below are required (Only the APOC and Bioenvironmental are certified to make that determination).
V3-CONS-5/27 Page 13 of 16
4.7 NO ABATEMENT WORK IS TO BEGIN WITHOUT WRITTEN APPROVAL FROM THE
APOC: A Mississippi State certified asbestos abatement Contractor must be used to conduct the abatement. Please note that non-friable asbestos can easily be made friable and become regulated.
4.7.1 Before: The following documents must be submitted to the Asbestos POC and approved in writing before abatement can begin:
4.7.1.1 10 Day MDEQ notification and return acknowledgment letter.
4.7.1.2 Asbestos Hazard Abatement Plan (to be certified by a Mississippi Certified
Management Planner and/or Certified Industrial Hygienist).
4.7.1.3 Asbestos Work Plan (scope of work, removal procedures, worker protection, air monitoring, disposal location, containment procedures).
4.7.1.4 MDEQ Asbestos Abatement Certification for the Company.
4.7.1.5 Supervisor’s qualifications and state certification.
4.7.1.6 CURRENT State Certifications (applications will not be accepted) for all individuals working on site.
4.7.1.7 Respirator fit tests for all individuals.
4.7.1.8 Physicals for all individuals.
4.7.2 During: Once the submittals are approved in writing, the following actions are required.
4.7.2.1 The Contractor is required to set up their containment areas, negative air machine, and critical barriers and obtain approval from the Asbestos POC to begin work.
4.7.2.2 The Asbestos POC routinely checks the abatement work to ensure that the containment area and critical barriers are secure, that the workers are wearing the appropriate personal protective equipment that the asbestos-containing material is being bagged appropriately, and that air monitoring is being conducted on the workers and outside the abatement area. This also includes reviewing the daily log maintained on site to assure that no uncertified individuals are performing abatement work.
4.7.2.3 Upon completion of the abatement work, the Contractor contacts the Asbestos POC to conduct a walk-through of the area and approve that all abatement has been completed and that the area has been cleaned of asbestos fibers. This action will require at least a 24-hour period. Please reference cleaning procedures in the Asbestos Management and Operations Plan.
4.7.2.4 Air sampling results are required to be collected and submitted for approval by the Asbestos POC before the containment area, negative air machine, and critical barriers can be removed.
4.7.2.5 All asbestos waste must be handled and disposed of in accordance with State law.
The Asbestos POC must review the waste prior to leaving the base and the manifest will be signed by a designated Keesler government representative.
Contractors will not sign manifests for asbestos containing material (ACM).
4.7.3 After: After the abatement has been complete and approved by the Asbestos POC, the Contractor shall submit the following items in a post-job submittal to be maintained in the Asbestos Abatement Files.
V3-CONS-5/27 Page 14 of 16
4.7.3.1 Air sampling results.
4.7.3.2 Daily report logs.
4.7.3.3 Daily worker sign in/out sheets.
4.7.3.4 Waste manifest (Generator Copy)
4.7.4 The Asbestos POC and Environmental Section (VECTRUS/ CEV) are available at any time to provide asbestos awareness training and consultation to CM’s, PM’s, Contractors and Sub-Contractors prior to beginning the project.
4.8 REQUIRED LEAD-BASED PAINT MANAGEMENT PROCEDURES: Appropriate OSHA worker protection is the responsibility of the employer. All projects will be monitored and inspected by VECTRUS/ CEV. The purpose of these instructions is to provide guidance to safely remove or encapsulate lead-based paint without causing a hazard. All work must be performed in accordance with OSHA, MDEQ and any local regulations for all work and disposal. The regulations are divided into two parts; a) lead-based paint on non-child occupied/non-target housing buildings and b) child occupied/target housing buildings.
4.8.1 Non-child occupied/ commercial buildings:
4.8.1.1 For non-child-occupied/commercial buildings, the minimum requirement for
Contractors is to protect workers IAW OSHA requirements, use poly lay-down to collect paint chips, and turn into VECTRUS/ CEV for disposal. At minimum the supervisor of the project should be LBP trained and supply proof of certification before work begins. The Contractor shall notify VECTRUS/ CEV before start of any project. Contractor must place plastic on the ground sufficient to capture all loosened paint chips and control water run-off. Removal methods preferred at Keesler AFB are the use of an approved chemical stripper or wet sanding methods for better collection of LBP chips and waste. These processes minimize lead dust and allow for maximum collection of LBP chips.
4.8.1.2 The Contractor shall meet with VECTRUS/ CEV prior to beginning the project to discuss protective measures, best management practices (BMP’s), any landfill disposal, and maintenance of chips and their collection (until they are turned over to VECTRUS/ CEV).
4.8.1.3 Any buildings with lead-based paint, if bead blasted to remove old paint, shall be supervised by a Contractor with proper training. Bead blasting upon prior approval only (see preferred method above).
4.8.1.4 The Contractor, under OSHA rules, must comply with the lead based paint rules (including notification to VECTRUS/ CEV, if the job is abatement), certify appropriate training, and maintain personal monitors on workers until it is demonstrated there is no airborne lead risk.
4.8.1.5 VECTRUS/CEV will inspect all projects involving Lead Based Paint removal and any required documentation must be provided to VECTRUS/ CEV prior to beginning work.
4.8.2 Child-occupied/target housing buildings:
V3-CONS-5/27 Page 15 of 16
4.8.2.1 Any child-occupied/target housing building older than 1978 must be painted using Lead Paint Protocol, including poly-lay-down, collection of paint chips, and the Contractor must always have a minimum of lead hazard training for all workers.
The Contractor shall notify VECTRUS/CEV before start of any project.
4.8.2.2 A paint Contractor must collect paint chips in their own clean buckets and have VECTRUS/CEV dispose (if contract requires VECTRUS/ CEV dispose).
Contractor must place plastic on the ground sufficient to capture all loosened paint chips and control water run-off.
4.8.2.3 For work on child-occupied/target housing buildings falling under the Lead Paint Protocol, the Contractor must use water or amended water when scraping or chipping. All members of the Contractor’s work force must wear protective clothing and comply with all OSHA rules and regulations. OSHA regulation compliance is the employer’s responsibility and is subject to inspection by OSHA and the Base. Suggested PPE include foot protection (ex. Rubber Boots) worn while on the poly. All PPE shall be stored on the protective plastic when not in use and shall be decontaminated or disposed of in an approved manner.
Minimum respiratory protection for any OSHA “trigger task” such as scraping, manual sanding, demolition, heat gun and power tool cleaning is a half-mask air purifying respirator (APR) with HEPA filter that is at least 99.97 percent efficient (i.e. P100). APR fit tests evidence must be provided for inspection. Other circumstances may warrant higher protection. PPE determination is the responsibility of the Contractor.
5.0 DELIVERABLES:
5.1 INSPECTION AND ACCEPTANCE: Inspection and Acceptance of services will be performed at Keesler AFB, Mississippi by the User, Facility Commander, and/or a member of 81st CES, along with the Vectrus Keesler BOS Contract Monitor (CM), and Contracting Officer. Inspection and acceptance will be conducted in accordance with this SOW.
5.2 INSTALLED EQUIPMENT:
5.2.1 Contractor will furnish manufacturer warranties as needed for any component incorporated into this project such as equipment; any component installed in or made a part of the existing structure and any exterior or interior finishes, etc.
5.2.1.1 A 1 year warranty on material and labor.
5.2.1.2 The manufacturer’s warranty, if applicable.
5.2.1.3 Submit two (2) hard copies and one (1) electronic copy.
5.2.2 All Operations and Maintenance manuals for any equipment supplied as part of the project.
5.2.2.1 Submit two (2) hard copies in notebook binder, and one (1) electronic copy.
5.3 REPORTS: The Contractor shall supply any third party reports, test and balance reports, communication signal tests, etc. to the CM as soon as they are available or before project acceptance.
V3-CONS-5/27 Page 16 of 16
5.4 AS BUILT DRAWINGS: The service provider shall provide as-built drawings regardless of any deviation from the original design. The drawings shall be RED lined markups (from either In-house Design or AE Design drawings) and shall be updated daily as necessary and turned in to the CM at the end of the contract.
5.5 DAILY PROJECT REPORTS: Contractor shall submit reports for the project every Tuesday of each week to cover the previous Tuesday thru Monday dates. (Only accepted on Vectrus Forms)
6.0 CONTRACT TECHNICAL MONITOR:
6.1 The Contract Monitor (CM) is a Vectrus Keesler BOS employee assigned to interface with the Contractor. The CM is authorized to provide technical direction within the scope of the Contract. All technical direction shall be issued to the Contractor via a Request For Information (RFI) countersigned by the CO.
The PM for this Contract is:
Name: George Reed Phone: 228-377-5823 Email: george.reed.6.ctr@us.af.mil Mailing Address:
508 L Street (B4705) Keesler, AFB, MS 39534
The CM for this Contract is:
Name: Dennis Fink Phone: 228-377-2207 Email: dennis.fink.ctr@us.af.mil Mailing Address:
508 L Street (B4705) Keesler, AFB, MS 39534
6.2 The CM can assist the Contractor in the interpretation of technical requirements and performance of the effort required. The CM shall have no authority to impose additional requirements or to change or delete existing requirements of the Contract. Any clarification provided by the CM concerning the work to be performed shall not be construed as a change to the Contract. Any changes to the original Scope of Work must be approved in writing by the Contracting Officer prior to work being performed.
--End of Section--
STATEMENT OF WORK