Attachment 01_Schedule of Items_Red_River_Sewer.pdf

PDF 163 KB Posted

Attached to
Red River Wastewater Solenoid
Solicitation number
1282B123Q0156
Issued by

About this file

This document contains a schedule of items for a solicitation to provide wastewater electric distribution and solenoid valve project services for the Red River Work Center and RV Dump Station. The solicitation is being conducted by the USDA Forest Service Red River Ranger District in Idaho County, Idaho under solicitation number 1282B123Q0156. The schedule of items lists 9 bid items including mobilization, construction staking, demolition, effluent distribution vault piping, electrical control wiring, instrumentation and controls, an effluent meter pit flexible coating, and 4 foot manhole sealing. Quantities and units of measure are provided for each item. The contractor will be selected based on a lump sum price for items 101, 102, 103, 107, and 108, and actual quantities for items 105, 106, and 109.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation No: 1282B123Q0156

SCHEDULE OF ITEMS

Red River Work Center& RV Dump Station – Wastewater Electric Distribution and Solenoid Valve Project

USDA-Nez Perce-Clearwater National Forests Red River Ranger District

Idaho County, Idaho

Bid Item Description Method of Measurement*

Unit Quantity Cost Per Unit

Item Cost

101 MOBILIZATION-

DEMOBILIZATION, BONDING,

INSURANCE AND GENERAL

REQUIRMENTS

LSQ LS 1

102 CONSTRUCTION STAKING LSQ LS 1

103 DEMOLITION LSQ LS 1

104 Not included in this Contract – Exists in contract drawings and Specifications completed 2021

N/A _ _

105 EFFLUENT DISTRIBUTION VAULT

PIPING

AQ EA 2

106 ELECTRICAL CONTROL WIRING AQ LF 1130

107 INSTRUMENTATION AND

CONTROLS

LSQ LS 1

108 EFFLUENT METER PIT FLEXIBLE

COATING

LSQ LS 1

109 4 FOOT MANHOLE SEALING AQ LF 84

TOTAL AMOUNT:

* Designated Method of Measurement ** Item 104 Was completed by another action and is not included in this contract but is recognized in the specifications and the drawings.

AQ – Actual Quantity CQ – Contract Quantity LSQ – Lump Sum Quantity

File details come from the government source that posted it. Updated .