Tripoli Road Bridge 2, White Mountain National Forest, NH Special Provision 27003 – Drill and Epoxy HEB Engineers Project #2020-095 Page 1 of 1 USDA Forest Service Latest Revision: 08/01/20 Previous Revision: - -/- -/- -
S P E C I A L P R O V I S I O N
SECTION 27003 – DRILL AND EPOXY
This special provision provides for the drilling and epoxy installation for reinforcing steel dowels into existing concrete.
Description
1.1 This work shall consist of drilling concrete and installing epoxy adhesive for the doweling of reinforcing steel into existing concrete.
Materials
2.1 Epoxy adhesive shall have been tested in accordance with American Concrete Institute (ACI)
355.4 and ICC-ES AC308 for cracked and un-cracked concrete.
Construction Requirements
3.1 Drilling shall be into sound concrete to the depth noted in the plans and in accordance with adhesive manufacturer’s recommendations. Epoxy adhesive shall be installed in accordance with the manufacturer’s recommendations. Allowable with hammer-drill, hollow drill bit system, and core drilling methods.
Method of Measurement
4.1 The item will be measured by the required length of reinforcing steel embedment as noted in the plans. Over drilling of holes, which may be required by the epoxy adhesive manufacturer, will be considered subsidiary to the item.
Basis of Payment
5.1 The work outlined in this specification will be paid by the linear foot.
Pay items and unit:
27003 Drill and Epoxy LF
END OF SECTION