Att_01 Schedule of Items.pdf
PDF 290 KB Posted
- Attached to
- Green Mountain National Forest GAOA Hapgood Pond Recreation Area Improvements and Boat Launch
- Solicitation number
- 12445525Q0064
- Issued by
-
Department of Agriculture Forest Service
About this file
The document is a Schedule of Items for the Hapgood Pond Recreation Area Improvements project in the Green Mountain National Forest. The base bid includes multiple line items for a construction project, with estimated quantities for various activities such as mobilization, construction survey and staking, soil erosion control, trail excavation, earthwork, foundation fill, riprap placement, trail surface aggregate, precast concrete slabs, seeding, mulching, and erosion control products. The pay units include lump sum (LS), cubic yards (CY), and square yards (SY), with estimated quantities ranging from 1 to 120 units across different line items. The document provides a template for contractors to fill in unit prices and calculate the total project cost, with designated spaces for the contractor's name and Unique Entity Identifier (UEI).
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Att_03 Hapgood Pond Rec Improvements_FSSS.pdf | ||
| 12445525Q0064 pdf.pdf | ||
| Att_02 SOW.docx | DOCX document | |
| Att_04 Plans.pdf | ||
| Att_05 Wage Determination VT20250062 Bennington Cty.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PAY ITEM DESCRIPTION PAY UNIT
ESTIMATED
QUANTITY
UNIT PRICE SUBTOTAL ESTIMATE
15101 MOBILIZATION LS 1
15201
CONSTRUCTION SURVEY AND
STAKING, METHOD 1,
TOLERANCE A
LS 1
15713
SOIL EROSION & POLLUTION
CONTROL
LS 1
20101
CLEARING AND GRUBBING,
DISPOSAL METHOD SCATTER
LS 1
20407 TRAIL EXCAVATION CY 30
20701
EARTHWORK
GEOSYNTHETICS, NON-
WOVEN, CLASS 1 TYPE A
SY 120
20802 FOUNDATION FILL CY 10
25101 PLACED RIPAP, CLASS 3 CY 12
39901
TRAIL SURFACE AGGREGATE,
COMPACTION METHOD B
CY 20
60101
CONCRETE, PRECAST
REINFORCED SLABS
LS 1
62503 SEEDING, DRY METHOD LS 1
62505 MULCHING, DRY METHOD LS 1
62901
ROLLED EROSION CONTROL
PRODUCT, TYPE 5.A
SY 16
Total
Hapgood Pond Recreation Area Improvements
Schedule of Items
Base Bid
Contractor Name___________________________