Atch 1_USDA Electrical Service Specs.pdf

PDF 342 KB Posted

Attached to
Electrical Connection, Bldg 21, USDA Campus, Ames
Solicitation number
12639522R0029
Issued by

About this file

This solicitation is for an electrical connection project at Building 21 on the USDA campus in Ames, Iowa. Work involves disconnecting the existing 13.8kV feeder from the City of Ames and connecting the building to the NVSL North Campus electrical service originating at Building 153 via two new 13.2kV feeders. Scope includes installing new ductbanks, manholes, cables, and making connections at the double-ended substation in Building 21. The contractor must also connect the site's power monitoring system, remove an existing generator connection, and reroute service to a panel. The response due date is not provided. The Department of Agriculture Animal and Plant Health Inspection Service Marketing and Regulatory Programs Business Services is the issuing agency.

View the file

Other files

File Type Posted
12639522R0029-0006.pdf PDF
12639522R0029-0005.pdf PDF
12639522R0029-0004.pdf PDF
12639522R0029-0003.pdf PDF
Amendment 12639522R0029-0002.pdf PDF
Amendment 12639522R0029-0001.pdf PDF
Cut sheets for switchgear_USS-1.pdf PDF
05092022 Site Visit Sign In Sheet.pdf PDF
Atch 2_Project Drawings.pdf PDF
12639522R0029.pdf PDF
Atch 3_DOL construction wage rates.pdf PDF
Atch 4_E01 Replacement Drawing.pdf PDF
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

©Stanley Consultants, Inc. 2011 00 01 01.doc

Project Manual for

USDA/NVSL/CVB

Building 21 Electrical Service Contract #AG-32KW-C-07-006

U.S. Department of Agriculture Ames, Iowa

August 2011

12639522R0029, Attachment 1

20162.09.00 TABLE OF CONTENTS

ms1116 SECTION 00 01 10 - Page 1

USDA/NVSL/CVB BUILDING 21 ELECTRICAL SERVICE

CONTRACT #AG-32KW-C-07-006

U. S. DEPARTMENT OF AGRICULTURE

AMES, IOWA

PROCUREMENT AND CONTRACTING REQUIREMENTS GROUP

DIVISION 00 PROCUREMENT AND CONTRACTING REQUIREMENTS

Document Title Page 00 01 15 Drawing List 1

SPECIFICATIONS GROUP

GENERAL REQUIREMENTS SUBGROUP

Section Title Page

DIVISION 01 GENERAL REQUIREMENTS

01 11 00 Summary of Work 1 thru 2 01 30 00 Administrative Procedures 1 thru 3 01 33 00 Submittal Procedures 1 thru 6 Submittal Transmittal Form 1 01 33 10 Submittal Register 1 thru 2 01 40 00 Quality Requirements 1 thru 4 01 60 00 Product Requirements 1 thru 2 01 70 00 Execution and Closeout Requirements 1 thru 2 01 73 29 Cutting and Patching 1 thru 2 01 74 23 Final Cleaning 1

Resp.

Charge Section Title Page

FACILITY SERVICES SUBGROUP

DIVISION 26 ELECTRICAL

GGG 26 05 05 Common Work Results for Electrical Packaged Equipment 1 thru 5 GGG 26 05 33 Above-Grade Raceway 1 thru 5 GGG 26 05 43 Below-Grade Raceway 1 thru 7

SITE AND INFRASTRUCTURE SUBGROUP

DIVISION 33 UTILITIES

GGG 33 71 49 Medium Voltage Cable and Accessories 1 thru 7

20162.09.00 DRAWING LIST

ms1116 SECTION 00 01 15 - Page 1

Drawing No. Title Rev. No.

GG1 Cover Sheet, Vicinity Map, and Drawing Index 0 GG2 General Legend and Notes 0 EO1 Building 21 One Line Diagram Modifications 0 EO2 Building 21 Power Riser Diagram 0 EO3 Building 158 One Line Diagram 0 EU1 Site Plan 0 EU2 Site Plan Details 0 EP1 Building 21 Basement Floor Plan 0 EP2 Building 21 Penthouse Floor Plan 0 EP3 Building 21 Enlarged Penthouse Plan 0

REFERENCE DRAWINGS

The following drawings are issued for information only and do not form a part of this contract Drawing No. Title Rev. No.

C2.01 Civil Utility Site Plan 0 C2.02 Civil Utility Site Plan 0 C4.01 Civil Details 0

20162.09.00 SUMMARY OF WORK

ms1116 SECTION 01 11 00 - Page 1

PART 1 GENERAL

1.01 WORK COVERED BY CONTRACT DOCUMENTS

A. Work of this Agreement comprises of the demolition of existing 13.8 kV electrical service from the City of Ames to Building 21, and installation of a new dual 13.2 kV feeder from the NCAH north campus electrical system supplied by Alliant Energy originating at Building 153.

B. Existing emergency generator located in Building 22 provides circuit for Panel OSD4-P1 that services Building 21 emergency loads. New service from Building 153 has emergency generator tie in so this circuit will no longer be required as long as generators in Building 153 will be on line within 10 seconds to meet NFPA 101 requirements.

C. Installation of two new four-way, 5 inch cell concrete encased ductbanks from existing manholes MH- A6 and MH-B6 to new Manholes MH-A12 and MH-B12 and onto new Manholes MH-A13 and MH-B13.

Place one of the new Manholes MH-A13 or MH-B13 directly over the existing City of Ames 13.8kV service. From MH-A13 and MH-B13 provide a single one way 4 inch cell concrete encased from each manhole to existing service conduits stubbed out from Building 21. If contractor can use existing conduit that the City of Ames has currently provided their service into Building 21 with and it is continuous into the new manhole this is allowed.

D. Provide three, 1/C 500kcmil, 15kV cables from Bus A and Bus B line connections at existing exterior 15kV switchgear line compartment to Building 21 double ended substation per drawings. Existing switchgear shop drawings provided indicated line side lugs are available for above conductors. There are also spare cells in the existing ductbank sections from Manhole MH-A6 and MH-B6 to the existing exterior switchgear.

E. Coordinate with City of Ames to take a minimal outage to connect new service to double ended substation. Disconnect existing City of Ames 13.8kV feeder and connect new 13.2kV service from Building 153. Reset transformer taps of double ended substation transformers for new 13.2kV service and remove 15kV cable jumper between medium voltage switches at Unit Substation USS1 in Building 21.

F. Remove existing 13.8kV service from the City of Ames and open the conduit in new manhole that was placed over the existing City of Ames conduit.

G. Install the second 13.2kV feeder from Building 153 via exterior 15kV switchgear to Building 21 double ended substation medium voltage switch in the raceway of the removed City of Ames feeder.

H. Connect the site Power Monitoring & Control System (PMCS) communication connections from the existing digital power metering at the double ended substation in the Building 21 penthouse to the existing data switch located in the communication room on the ground floor of Building 21. Provide required conduits and Category 6 cabling and required interfaces, (modbus or ethernet as required) from the double ended substation, remote 4 or 8 port switch at double ended substation, and ethernet Category 6 cable in 1 inch conduit to existing conduit sleeves through floor as shown on drawings to existing switch in rack in communication room.

I. Provide the programming, integration, and control functions for the PMCS. Programming should also include the development of a Building 21 main plant graphics screen for monitoring and control at the main site PMCS in Building 153.

J. Remove existing conductors from Generator in Building 22 to ATS #1 located in Building 21.

K. Remove the automatic transfer switch ATS#1 and route the 1,600 Amp service in new raceway system including new conduits and existing where possible for a direct connection point for through service to Panel OSD4-P1.

SUMMARY OF WORK 20162.09.00

Page 2 - SECTION 01 11 00 ms1116

1.02 WORK SEQUENCE

A. Construct Work in stages to accommodate Owner's use of premises during construction period;

coordinate construction schedule and operations with Contracting Officer’s Representative (COR).

1. Schedule Work to minimize use of street barricades and detours.

2. Stages of construction are those indicated in Drawings.

1.03 CONTRACTOR USE OF PREMISES

A. Coordinate use of premises under direction of the COR. Contractor shall confine construction equipment, storage of materials and equipment and operations of workers to areas permitted by law, ordinances, permits, or requirements of Contract Documents, and shall not unreasonably encumber premises with construction equipment or other material or equipment.

B. Assume full responsibility for protection and safekeeping of items under this Agreement, stored on Site.

C. Move any stored items, under Contractor's control, which interfere with operations of Owner or separate contractor.

D. Obtain and pay for use of additional storage or Work areas needed for operations.

1.04 OWNER OCCUPANCY

A. Owner will occupy premises during entire period of construction for conduct of its normal operations.

Cooperate with Owner's Representative in all construction operations to minimize conflict, and to facilitate Owner usage.

B. Contractor shall at all times conduct its operations as to ensure least inconvenience to Owner.

PART 2 PRODUCTS

NOT USED

PART 3 EXECUTION

END OF SECTION

20162.11.00 ADMINISTRATIVE REQUIREMENTS

ms1116 SECTION 01 30 00 - Page 1

1.01 COORDINATION AND PROJECT CONDITIONS

A. Coordinate scheduling, submittals, and Work of the various sections of the Project Manual to ensure efficient and orderly sequence of installation of interdependent construction elements, with provisions for accommodating items installed later.

B. Verify utility requirements and characteristics of operating equipment are compatible with building utilities. Coordinate work of various sections having interdependent responsibilities for installing, connecting to, and placing in service, such equipment.

C. Coordinate space requirements, supports, and installation of electrical Work indicated diagrammatically on Drawings. Follow routing shown for pipes, ducts, and conduit, as closely as practicable; place runs parallel with lines of building. Utilize spaces efficiently to maximize accessibility for other installations, for maintenance, and for repairs.

D. In finished areas except as otherwise indicated, conceal pipes, ducts, and wiring within the construction. Coordinate locations of fixtures and outlets with finish elements.

E. Coordinate completion and clean up of Work of separate sections in preparation for Substantial Completion and Government's occupancy.

F. After Substantial Completion, coordinate access to site for correction of defective Work and Work not in accordance with Contract Documents, to minimize disruption of Government's activities.

1.02 COPIES OF DRAWINGS AND PROJECT MANUALS

A. After Notice of Award, Contractor may obtain, at no charge, up to 5 sets of printed or hard copies of the Project Manual and one set in electronic format. Additional copies will be furnished upon request at the cost of reproduction plus handling charge. If Contractor's requirements for additional project manuals necessitates reprinting of project manuals, Contractor shall pay entire cost of such reprinting. Partial sets of project manuals will not be provided.

B. After Notice of Award, Contractor may obtain, at no charge, up to 5 printed or hard copies of the Drawings and Project Manual and one set in electronic format. Additional copies will be furnished upon request at the cost of reproduction plus handling charge.

C. Revised Drawings and project manuals, if required, will be provided by Government to show authorized changes or extra Work under following conditions:

1. Project manuals: Furnished at no charge, in same quantity as original issuance.

2. Half-size Drawings:

a. Half-size Drawings will not be available as revised Drawings.

b. One revised, complete set of half-size Drawings will be issued, at no charge, for each half-size set originally issued and for each half-size set purchased by Contractor after Notice of Award.

3. Full-size Drawings:

a. One revised, complete set of full-size Drawings will be issued, at no charge, for each full-size set and each reproducible set originally issued.

b. One revised, complete set of full-size Drawings will be issued, at no charge, for each full-size set originally issued, and for each full-size set purchased by Contractor after Notice of Award, up to 4 copies maximum.

4. One full-size reproducible set will be issued to accommodate fifth and subsequent sets purchased by Contractor. Contractor shall use reproducible set to complete printing for additional Drawings in its possession.

ADMINISTRATIVE REQUIREMENTS 20162.11.00

Page 2 - SECTION 01 30 00 ms1116

1.03 PROJECT SITE ADMINISTRATION

A. Contractor shall provide competent, suitably qualified personnel to survey and lay out Work and perform construction as required by Contract Documents. Contractor shall at all times maintain good discipline and order at site.

B. Except in connection with safety or protection of persons or Work or property at site or adjacent thereto, and except as otherwise indicated in Contract Documents, all Work at site shall be performed during regular working hours, and Contractor shall not permit overtime work or performance of Work on Saturday, Sunday, or any legal holiday without Government's written consent given after prior written request.

C. Incompetent or incorrigible employees shall be dismissed from Work by Contractor or its representative when requested by Engineer, and such persons shall not again be permitted to return to Work without written consent of Engineer.

D. Workmanship shall be of best quality.

1.04 PROJECT MEETINGS

A. Representatives of Contractor, Subcontractors and suppliers attending meetings shall be qualified and authorized to act on behalf of entity each represents.

B. Preconstruction meeting:

1. Government will schedule a meeting after 15 days after Contract Award

2. Location: A site, convenient for all parties, designated by Government

3. Attendance:

a. Government's representatives.

b. Resident Project Representative.

c. Contractor's superintendent.

d. Major Subcontractors.

e. Others as appropriate.

4. Agenda:

a. Submission of executed bonds and insurance certificates.

b. Distribution of Contract Documents.

c. Submission of list of Subcontractors, list of products, schedule of values, and progress schedule.

d. Designation of personnel representing the parties in Contract

e. Procedures and processing of field decisions, submittals, substitutions, applications for payments, proposal request, Change Orders, and Contract closeout procedures.

f. Scheduling.

5. Contractor shall record minutes and distribute copies within 3 days after meeting to participants, with one electronic copy to each participant, and to those affected by decisions made.

C. Progress meetings:

1. Schedule and administer meetings throughout progress of the Work at periodic intervals with a maximum monthly intervals.

2. Government will hold called meetings as required by progress of Work.

3. Location of meetings: Location in Building 20 or 21 as designated by Government.

4. Make arrangements for meetings, prepare agenda with copies for participants, preside at meetings.

5. Attendance:

a. Government and its professional consultants as needed.

b. Contractor and Subcontractors as appropriate to agenda.

c. Suppliers as appropriate to agenda.

d. Others.

20162.11.00 ADMINISTRATIVE REQUIREMENTS

ms1116 SECTION 01 30 00 - Page 3

6. Suggested agenda:

a. Review, approval of minutes of previous meeting.

b. Review of Work progress since previous meeting.

c. Field observations, problems, conflicts.

d. Problems which impede construction schedule.

e. Review of off-site fabrication, delivery schedules.

f. Corrective measures and procedures to regain projected schedule.

g. Revisions to construction schedule.

h. Progress, schedule, during succeeding Work period.

i. Coordination of schedules.

j. Review submittal schedules; expedite as required.

k. Maintenance of quality standards.

l. Pending changes and substitutions.

m. Review proposed changes for:

1) Effect on construction schedule and on completion date.

2) Effect on other contracts of Project.

3) Other business.

7. Record minutes and distribute copies within 3 days after meeting to participants, with 1copy and one electronic copy to Government, participants, and those affected by decisions made.

PART 2 PRODUCTS

20162.09.00 SUBMITTAL PROCEDURES

ms1116 SECTION 01 33 00 - Page 1

1.01 SUBMITTAL PROCEDURES

A. Deliver submittals to person listed below when required by Specification Sections:

1. Engineer: Company Name: _______________________________

Street Address: _______________________________ City, State, Zip: _______________________________

B. Submittals shall be in English language.

C. Weights, measures, and units shall be English units.

D. Symbols and drawings shall conform to ANSI Y32.2/IEEE 315/CSA Z99.

1.02 CONTRACTOR RESPONSIBILITIES

A. Review submittals prior to submission.

B. Determine and verify:

1. Field measurements.

2. Field construction criteria.

3. Catalog numbers and similar data.

4. Conformance to Specifications.

C. Coordinate each submittal with other submittals and with requirements of Work and of Contract Documents.

D. Notify Engineer in writing, at time of submission, of any deviations in submittals from requirements of Contract Documents. Any such deviations permitted by Engineer will require modifications of Contract Documents.

E. Provide space on Shop Drawings for Contractor and Engineer stamps.

F. When Shop Drawings are revised for resubmission, identify all changes made since previous submission.

G. Submittals containing language imposing duties on others (such as verification of dimensions or supply of related information) inconsistent with contract language shall be null and void.

H. Submittals shall not be used as media for inquiries for information or for verification of information that must be supplied by others to Contractor. Inquiries or verification of information shall be made by separate Contractor submittal using Request for Information (RFI) process.

I. Begin no Work which requires submittal review until return of submittals by Engineer with stamp, as either "Reviewed", “Reviewed as Noted", or “Reviewed as Noted-Resubmit.”

J. Distribute copies of reviewed submittals that carry Engineer stamp as either "Reviewed" or "Reviewed as Noted" as appropriate. Instruct parties to promptly report any inability to comply with requirements.

K. Submittals not requested will not be recognized or processed.

1.03 ENGINEER DUTIES

A. Review required submittals with reasonable promptness and in accord with schedule, only for general conformance to design concept of Project and compliance with information given in Contract

SUBMITTAL PROCEDURES 20162.09.00

Page 2 - SECTION 01 33 00 ms1116

Documents. Review shall not extend to means, methods, sequences, techniques, or procedures of construction or to safety precautions or program incident thereto. Review of a separate item as such will not indicate approval of assembly in which item functions.

B. Affix stamp and initials or signature, and indicate requirements for resubmittal, or review of submittal.

Engineer's action on submittals is classified as follows:

1. Reviewed: Submittal has been reviewed and appears to be in conformance to design concept of

Project and Contract Documents. Contractor may proceed with fabrication of work in submittal.

2. Reviewed As Noted: Submittal has been reviewed and appears to be in conformance to design concept of Project and Contract Documents, except as noted by reviewer. Contractor may proceed with fabrication of work in submittal with modifications and corrections as indicated by reviewer.

3. Reviewed As Noted-Resubmit: Submittal has been reviewed and appears to be in conformance to design concept of Project and Contract Documents, except as noted by reviewer. Contractor may proceed with fabrication of work in submittal with modifications and corrections as indicated by reviewer. Contractor shall make any corrections indicated by reviewer and resubmit for review.

4. Resubmit: Submittal has been reviewed and appears not to be in conformance to design concept of Project or with Contract Documents. Contractor shall not proceed with fabrication of work in submittal, but instead shall make any corrections required by reviewer and resubmit for review.

5. Returned without Review: Submittal is being returned without having been reviewed because: 1) not required by Contract Documents; 2) grossly incomplete; 3) indicates no attempt at conformance to Contract Documents; 4) cannot be reproduced; 5) lacks Contractor's completed approval stamp; or 6) lacks design professional's seal when required by law or Contract Documents. If submittal is required by Contract Documents, Contractor shall not proceed with Work as detailed in submittal, but instead shall correct defects and resubmit for review.

6. For Information Only: Submittal has not been reviewed but is being retained for informational purposes only.

7. Void: Submittal is voided because it is no longer required or has been superseded by another submittal.

C. Return 1 copy of submittals to Contractor. Contractor shall make additional copies as required.

D. Review of submittals shall not relieve Contractor from responsibility for any variation from Contract Documents unless Contractor has, in writing, called Engineer's attention to such variation at time of submission, and Engineer has given written concurrence pursuant to Contract Documents to specific variation, nor shall any concurrence by Engineer or other reviewer relieve Contractor from responsibility for errors or omissions in submittals.

1.04 SHOP DRAWINGS SUBMITTALS

A. Submit for review for limited purpose of checking for conformance to information given and design concept expressed in Contract Documents. Produce copies and distribute in accordance with article “Submittal Procedures” and for record documents purposes as described in Section 01 70 00.

B. Designate in construction schedule, or in separate coordinated submittal schedule, dates for submission and dates that reviewed submittals will be needed.

C. Make submittals promptly in accordance with approved schedule, and in such sequence as to cause no delay in Work or in work of other contractors.

D. Present in clear and thorough manner, complete with respect to dimensions, design criteria, materials of construction, and like information to enable review of information as required.

E. Details shall be identified by reference to sheet and detail, schedule or room numbers shown on Drawings.

F. Schedule submittals to expedite Project. Coordinate submission of related items.

ms1116 SECTION 01 33 00 - Page 3

G. For each submittal for review, allow 15 days excluding delivery time to and from Contractor.

H. Identify variations from Contract Documents and product or system limitations which may be detrimental to successful performance of completed Work.

I. Shop Drawings may be submitted in electronic format.

1. Submit electronic copy on CD, E-mail files, or post in FTP site.

2. Text documents shall be submitted in .pdf format.

3. Drawings shall be submitted in .pdf or .tif format.

4. Electronic submittal shall be suitable for reproduction in black and white.

J. Number required:

1. Submit number of opaque reproductions which Contractor, Owner and/or approving agency (ies) requires, plus 2 copies which will be retained by Engineer.

2. If Shop Drawings are not submitted in electronic format, submit 5 copies of each Shop Drawing.

3. Copies of Shop Drawings submitted shall be black line on white background.

4. Shop Drawings shall be suitable for reproduction in black and white. Shop Drawings submitted which are not suitable for reproduction will not be reviewed.

5. Drawings larger than 8-1/2” x 11” shall be rolled.

K. Submittals shall contain:

1. Date of submission and dates of any previous submissions.

2. Project title and number.

3. Contract identification.

4. Names of:

a. Contractor.

b. Supplier.

c. Manufacturer.

5. Identification of product, with Specification section number and article number.

6. Field dimensions, clearly identified as such.

7. Relation to adjacent or critical features of Work or materials.

8. Applicable standards, such as ASTM or Federal Specification numbers.

9. Identification of deviations from Contract Documents.

10. Identification of revisions on resubmittals.

11. An 8" x 3" blank space for Contractor and reviewer stamps.

12. Indication of Contractor's approval, initialed or signed, with wording substantially as follows:

"Contractor represents to Owner and Engineer that Contractor has either determined and verified all quantities, dimensions, field construction criteria, materials, catalog numbers, and similar data, or assumes full responsibility for doing so and has reviewed or coordinated each submittal with requirements of Work and Contract Documents."

L. Product Data:

1. Mark each copy to identify applicable products, models, options, and other data. Supplement manufacturers' standard data to provide information specific to this Project.

M. Test reports:

1. Submit for Engineer's knowledge as contract administrator or for Owner.

2. Submit test reports for information for limited purpose of assessing conformance with information given and design concept expressed in Contract Documents.

N. Certificates:

1. When specified in individual specification sections, submit certification by manufacturer, installation/application subcontractor.

2. Indicate material or product conforms to or exceeds specified requirements. Submit supporting reference data, affidavits, and certifications as appropriate.

Page 4 - SECTION 01 33 00 ms1116

3. Certificates may be recent or previous test results on material or product, but must be acceptable to reviewer.

O. Manufacturer's instructions:

1. When specified in individual specification sections, submit printed instructions for delivery, storage, and installation, to Engineer for delivery to Owner in quantities specified for Product Data.

2. Indicate special procedures, perimeter conditions requiring special attention, and special environmental criteria required for application or installation.

1.05 RESUBMISSION REQUIREMENTS

A. Make any corrections or changes in submittals required by Engineer and resubmit until stamped as either "Reviewed," "Reviewed as Noted," or “For Information Only.”

B. Text and depictions changed on Submittal shall be back-circled (clouded).

C. Engineer will assume that portions of Submittal not back-circled have not been changed by Contractor from previous submission.

D. Indicate revision number and date in document revision block.

1.06 DISTRIBUTION

A. Distribute reproductions of Shop Drawings which carry Engineer stamp as either "Reviewed" or "Reviewed as Noted" to:

1. Job site file.

2. Record Documents file.

3. Other affected contractors.

4. Subcontractors.

5. Supplier or fabricator.

B. Distribute Samples which carry Engineer stamp as either "Reviewed" or "Reviewed as Noted" as directed by Engineer.

1.07 CONSTRUCTION PROGRESS DOCUMENTATION

A. Construction progress schedules:

1. Submit initial schedules to Owner within 15 days after date established in Notice to Proceed. After review, resubmit required revised data within ten days.

B. Form of schedules:

1. Prepare schedules in form of horizontal bar chart.

a. Provide separate horizontal bar for each trade or operation.

b. Horizontal time scale: Identify first work day of each week.

c. Scale and spacing: To allow space for notations and future revisions.

d. Minimum sheet size: 8-1/2” x 11”.

2. Prepare construction progress schedules as specified in Section 01 32 16.

3. Format of listings: Chronological order of start of each item of Work.

C. Construction progress schedule shall show:

1. Complete sequence of construction by activity, with Contract Price breakdown at each stage.

2. Dates for beginning, and completion of, each major element of construction specifically listing:

a. Site clearing.

b. Site utilities.

c. Subcontractor Work.

d. Installations.

e. Finishes.

ms1116 SECTION 01 33 00 - Page 5

D. Submittal schedule shall show dates for Contractor's submittals.

E. Prepare and submit subschedules for each separate stage of Work specified in Section 01 11 00.

F. Provide subschedules to define critical portions of prime schedules.

G. Progress revisions:

1. Indicate progress of each activity to date of submission.

2. Show changes occurring since previous submission of schedule:

a. Major changes in scope.

b. Activities modified since previous submission.

c. Revised projections of progress and completion.

d. Other identifiable changes.

3. Provide narrative report as needed to define:

a. Problem areas, anticipated delays, and impact on schedule.

b. Corrective action recommended, and its effect.

c. Effect of changes on schedules of other prime contractors.

H. Distribution copies of reviewed schedules to:

1. Job site file.

2. Subcontractors.

3. Other concerned parties.

I. Instruct recipients to report promptly to Contractor, in writing, any problems anticipated by projects shown in schedules.

1.08 SAFETY PROCEDURES MANUAL

A. Prepare and submit to Owner safety procedures manual defining Contractor's safety program for work on site. Manual shall include:

1. Safety responsibilities of Contractor's personnel.

2. Description of Contractor's safety program.

3. Requirements of use of personal protective equipment.

4. General safety-related rules of conduct.

5. Fire prevention measures.

6. Accident reporting procedures.

7. Procedures for hot work (welding, cutting, etc.), overhead work, and work in enclosed, confined spaces (tank, boiler, etc.). Reference 29 CFR Part 1910.

1.09 SUBMITTAL TRANSMITTAL FORM PROCEDURES

A. Submittals shall be accompanied by completed copies of Submittal Transmittal form, bound herein.

An electronic version of transmittal form is available and may be obtained from Engineer. Reproduce additional copies required.

B. Submit 1 copies of transmittal form for initial submittals and resubmittals. Sequentially number transmittal form. Revise submittals with original number and sequential alphabetic suffix.

C. Prior to submittal, complete information under heading “Contractor's Transmittal.”

D. Engineer will complete information under “Reviewer's Action.”

E. Do not include submittals for more than one section of Specifications on Submittal Transmittal form.

F. Identify project title, location, and number and contract title and number.

G. Identify preparer name and, submittal number, including preparer’s submittal revision number.

Page 6 - SECTION 01 33 00 ms1116

H. A brief description under "Title" should clearly identify specific application of equipment or material covered by Submittal, utilizing where possible same title used in Drawings and Specifications.

I. Identify Specification Section number.

J. Apply Contractor's stamp, signed or initialed certifying that review, approval, verification of products required, field dimensions, adjacent construction Work, and coordination of information is in accordance with requirements of Work and Contract Documents.

SC3001 R4 0907 SHOP DRAWING TRANSMITTAL

Date Received Date Distributed SUBMITTAL TRANSMITTAL Transmittal No.

Project Title Project No. Contract No.

Project Location Contract Title

CONTRACTOR'S TRANSMITTAL

ENGINEER’S/ARCHITECT’S ACTION

Status Abbreviations:

R - Reviewed RS – Resubmit RN - Reviewed as Noted RET - Returned Without Review RNR – Reviewed as Noted Resubmit FIO - For Information Only

V - Void

Preparer Preparer Submittal No.

Rev.

No. Title Section

No.

SC

Submittal No.

Status Distribution (No.)

Cont RPR Own Des

Contractor Remarks

Address

By _________________________________ Date ______________________________

By Signature above, the Contractor shall certify that they have reviewed the submittal and that they comply with all applicable specification sections and contract drawings. Action of any kind on submittal by Engineer/Architect does not relieve Contractor from responsibility for errors, correctness of details, or conformance to the contract.

Engineer/Architect Remarks

By

Date ms1116 Submittal Register Page 1

UNITES STATES DEPARTMENT OF AGRICULTURE

Submittal Requirements

Section # Section Title Submittal Requirements

01 30 00 ADMINISTRATIVE REQUIREMENTS A. Submission of executed bonds and insurance certificates.

B. Distribution of Contract Documents.

C. Submission of list of Subcontractors, list of products, schedule of values, and progress schedule

01 40 00 QUALITY REQUIREMENTS A. Testing and Inspection Reports

01 60 00 PRODUCT REQUIREMENTS A. Within 30 days after the Notice to Proceed, submit to Government five copies of complete list of major products which are proposed for installation.

B. Test And Balance reports

01 70 00 EXECUTION AND CLOSEOUT REQUIREMENTS A. Submit written certification that Contract Documents have been reviewed, Work has been inspected, and that Work is complete in accordance with Contract Documents and ready for Engineer's review.

B. Application for Payment

C. Test And Balance Reports

D. Record Specifications and Drawings

E. Operation and maintenance data.

F. Product Warranties And Product Bonds

26 05 05 COMMON WORK RESULTS FOR ELECTRICAL

PACKAGED EQUIPMENT

A. Product Data

B. Shop Drawings

C. Quality assurance data

26 05 33 ABOVE-GRADE RACEWAY A. Product Data

B. Quality assurance data

26 05 49 BELOW-GRADE RACEWAY A. Product Data

B. Quality assurance data ms1116 Submittal Register Page 2

UNITES STATES DEPARTMENT OF AGRICULTURE

Submittal Requirements

33 71 49 MEDIUM VOLTAGE CABLE AND ACCESSORIES A. Shop Drawings and Data Sheets

B. Quality assurance data

20162.09.00 QUALITY REQUIREMENTS

ms1116 SECTION 01 40 00 - Page 1

1.01 QUALITY CONTROL AND CONTROL OF INSTALLATION

A. Monitor quality control over suppliers, manufacturers, products, services, site conditions, and workmanship, to produce Work of specified quality.

B. Comply with manufacturers' instructions, including each step in sequence.

C. Should manufacturers' instructions conflict with Contract Documents, request clarification from Engineer before proceeding.

D. Comply with specified standards as minimum quality for the Work except where more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.

E. Perform Work by persons qualified to produce required and specified quality.

F. Verify that field measurements are as indicated on Shop Drawings or as instructed by manufacturer.

1.02 TOLERANCES

A. Monitor fabrication and installation tolerance control of products to produce acceptable Work. Do not permit tolerances to accumulate.

B. Adjust products to appropriate dimensions; position before securing products in place.

1.03 BUILDING CODES AND PERMITS

1.04 Obtain and pay for all construction permits and licenses. Owner shall assist Contractor, when necessary, in obtaining such permits and licenses.

A. Give all notices and comply with all laws, ordinances, building and construction codes, rules, and regulations applicable to Work. If Contractor observes that Specifications or Drawings are at variance therewith, give Engineer prompt written notice thereof, and any necessary changes shall be adjusted by appropriate Modification.

B. If Contractor performs any Work knowing or having reason to know that it is contrary to such laws, ordinances, rules, and regulations, and without such notice to Engineer, Contractor shall bear all costs arising therefrom; however, it shall not be Contractor's primary responsibility to make certain that Specifications and Drawings are in accordance with such laws, ordinances, rules, and regulations.

1.05 REFERENCES

A. For products or workmanship specified by association, trade, or other consensus standards, comply with requirements of the standard, except when more rigid requirements are specified or are required by applicable codes.

B. Conform to reference standard by date of issue current on date for receiving bids.

C. Obtain copies of standards where required by product specification sections.

D. Should specified reference standards conflict with Contract Documents, request clarification from the Engineer before proceeding.

QUALITY REQUIREMENTS 20162.09.00

Page 2 - SECTION 01 40 00 ms1116

E. Neither contractual relationships, duties, nor responsibilities of the parties in Contract nor those of the Engineer shall be altered from the Contract Documents by mention or inference otherwise in any reference document.

F. Abbreviations used in Drawings and Specifications are as specified in ASME Y14.38 and IEEE 260.

G. Schedule of references:

1. ANSI - American National Standards Institute

2. ASME - American Society of Mechanical Engineers

3. AWS - American Welding Society

4. ETL - Electrical Testing Laboratory

5. ICEA - Insulated Cable Engineers Association

6. ISO - International Standards Organization

7. NEMA - National Electrical Manufacturers' Association

8. NFPA - National Fire Protection Association

9. OSHA – U. S. Department of Labor, Occupational Safety and Health Administration

10. UL - Underwriters' Laboratories, Inc.

1.06 TESTING AND INSPECTION SERVICES

A. Contractor shall employ and pay for services of an independent testing agency or laboratory acceptable to the Owner to perform specified testing.

1. Prior to start of Work, submit testing laboratory name, address, and telephone number, and names of full time specialist and responsible officer.

2. Submit copy of report of laboratory facilities inspection made by Materials Reference Laboratory of

National Bureau of Standards during most recent inspection, with memorandum of remedies of any deficiencies reported by the inspection.

B. The independent firm will perform tests, inspections and other services specified in individual specification sections and as required by the Owner.

1. Laboratory: Authorized to operate in location in which Project is located.

2. Laboratory staff: Maintain a full time specialist on staff to review services.

3. Testing equipment: Calibrated at reasonable intervals with devices of accuracy traceable to either

National Bureau of Standards or accepted values of natural physical constants.

C. Testing, inspections and source quality control may occur on or off the project site. Perform off-site testing as required by the Engineer or the Owner.

D. Reports will be submitted by the independent firm to the Engineer and Owner, indicating observations and results of tests and indicating compliance or non-compliance with Contract Documents.

E. Cooperate with independent firm; furnish samples of materials, design mix, equipment, tools, storage, safe access, and assistance by incidental labor as requested.

1. Notify Engineer/Owner and independent firm 24 hours prior to expected time for operations requiring services.

2. Make arrangements with independent firm and pay for additional samples and tests required for

Contractor's use.

F. Testing and employment of testing agency or laboratory shall not relieve Contractor of obligation to perform Work in accordance with requirements of Contract Documents.

G. Re-testing or re-inspection required because of nonconformance to specified requirements shall be performed by the same independent firm on instructions by the Engineer/Owner. Payment for re-testing or re-inspection will be charged to the Contractor by deducting testing charges from the Contract Sum/Price.

H. Agency responsibilities:

20162.09.00 QUALITY REQUIREMENTS

ms1116 SECTION 01 40 00 - Page 3

1. Test samples of mixes submitted by Contractor.

2. Provide qualified personnel at site. Cooperate with Engineer/Owner and Contractor in performance of services.

3. Perform specified sampling and testing of products in accordance with specified standards.

4. Ascertain compliance of materials and mixes with requirements of Contract Documents.

5. Promptly notify Engineer/Owner and Contractor of observed irregularities or non-conformance of

Work or products.

6. Perform additional tests required by Engineer/Owner.

7. Attend preconstruction meetings and progress meetings.

I. Agency reports: After each test, promptly submit two copies of report to Engineer/Owner and to Contractor. When requested by Engineer/Owner, provide interpretation of test results. Include the following:

1. Date issued.

2. Project title and number.

3. Name of inspector.

4. Date and time of sampling or inspection.

5. Identification of product and specifications section.

6. Location in the Project.

7. Type of inspection or test.

8. Date of test.

9. Results of tests.

10. Conformance with Contract Documents.

J. Limits on testing authority:

1. Agency or laboratory may not release, revoke, alter, or enlarge on requirements of Contract

Documents.

2. Agency or laboratory may not approve or accept any portion of the Work.

3. Agency or laboratory may not assume any duties of Contractor.

4. Agency or laboratory has no authority to stop the Work.

3.01 EXAMINATION

A. Verify that existing site conditions and substrate surfaces are acceptable for subsequent Work.

Beginning new Work means acceptance of existing conditions.

B. Verify that existing substrate is capable of structural support or attachment of new Work being applied or attached.

C. Examine and verify specific conditions described in individual specification sections.

D. Verify that utility services are available, of the correct characteristics, and in the correct locations.

3.02 PREPARATION

A. Clean substrate surfaces prior to applying next material or substance.

B. Seal cracks or openings of substrate prior to applying next material or substance.

C. Apply manufacturer required or recommended substrate primer, sealer, or conditioner prior to applying any new material or substance in contact or bond.

QUALITY REQUIREMENTS 20162.09.00

Page 4 - SECTION 01 40 00 ms1116

3.03 FIELD PERFORMANCE TESTS

A. Notify Engineer/Owner when Work is considered to be complete, in operating condition, and ready for inspection and tests.

B. If new installations fail to function properly, Contractor shall make necessary corrections, including replacement, at no cost to Owner.

20162.09.00 PRODUCT REQUIREMENTS

ms1116 SECTION 01 60 00 - Page 1

1.01 PRODUCTS

A. Provide products of qualified manufacturers suitable for intended use. Provide products of each type by a single manufacturer unless specified otherwise.

1.02 PRODUCT DELIVERY REQUIREMENTS

A. Transport and handle products in accordance with manufacturer's instructions.

B. Promptly inspect shipments to ensure that products comply with requirements, quantities are correct, and products are undamaged.

1.03 RECEIVING, UNLOADING AND STORING

A. Receive and unload shipments to plant site from suppliers of equipment under this Contract.

B. Unload equipment as soon as possible after arrival.

C. Pay freight car and truck demurrage, detention, and any other costs which may be billed to Owner due to failure to unload cars or trucks within time required by freight companies.

D. Contractor shall take custody of equipment and materials received and shall be solely responsible for damage and shortages until acceptance of Contractor’s work by Owner.

E. Storage areas will be allocated by Owner for Contractor’s use. Equipment shall be stored in assigned lay-down areas.

F. Equipment and materials shall be stored and maintained in accordance with manufacturer’s recommendations and these specifications.

G. Contractor shall provide materials, equipment, and labor required for such storage and maintenance.

Contractor shall be accountable for any deterioration of materials or equipment occasioned by improper storage or maintenance, and shall recondition, repair, or replace any such materials or equipment without additional cost to Owner.

1.04 ENCLOSED STORAGE

A. Store products subject to damage by elements in substantial weathertight enclosures.

B. Maintain temperature and humidity within ranges required by manufacturer's instructions.

1.05 EXTERIOR STORAGE

A. Store loose granular materials on clean, solid surfaces such as pavement, or on rigid sheet materials, to prevent mixing with foreign matter.

B. Provide surface drainage to prevent flow or ponding of rainwater.

C. Prevent mixing of refuse or chemically injurious materials or liquids.

1.06 PRODUCTS LIST

A. Within 30 days after effective date of Agreement, submit to Engineer five copies of complete list of major products which are proposed for installation.

PRODUCT REQUIREMENTS 20162.09.00

SECTION 01 60 00 - Page 2 ms1116

B. Tabulate products by Specification section number and title.

C. For products specified only by reference standards, list for each such product:

1. Name and address of manufacturer.

2. Trade name.

3. Model or catalog designation.

4. Manufacturer's data:

a. Reference standards.

b. Performance test data.

1.07 PRODUCT OPTIONS

A. For products specified only by reference standard, select product meeting that standard, by any manufacturer.

B. For products specified by naming only one product and manufacturer, there is no option and no substitution will be allowed.

C. Whenever Specifications call for item by manufacturer's name and type and additional features of item are specifically required by Specifications, additional features specified shall be provided whether or not they are normally included in standard manufacturer's item listed.

20162.09.00 EXECUTION AND CLOSEOUT REQUIREMENTS

ms1116 SECTION 01 70 00 - Page 1

1.01 CLOSEOUT PROCEDURES

A. Submit written certification that Contract Documents have been reviewed, Work has been inspected, and that Work is complete in accordance with Contract Documents and ready for Engineer's review.

B. Provide submittals to Engineer/Owner that are required by governing or other authorities.

C. Submit final Application for Payment identifying total adjusted Contract Sum, previous payments, and sum remaining due.

D. Owner will occupy portions of the roadway work as specified in Section 01 11 00.

1.02 FINAL CLEANING

A. Execute final cleaning prior to final project assessment.

B. Clean site; sweep paved areas, rake clean landscaped surfaces.

C. Remove waste and surplus materials, rubbish, and construction facilities from the site.

1.03 PROTECTING INSTALLED CONSTRUCTION

A. Protect installed Work and provide special protection where specified in individual specification sections.

B. Provide temporary and removable protection for installed products. Control activity in immediate work area to prevent damage.

C. Provide protective coverings at walls, projections, jambs, sills, and soffits of openings.

D. Protect finished floors, stairs, and other surfaces from traffic, dirt, wear, damage, or movement of heavy objects, by protecting with durable sheet materials.

E. Prohibit traffic from landscaped areas.

1.04 PROJECT RECORD DOCUMENTS

A. Maintain on site one set of the following record documents; record actual revisions to the Work:

1. Drawings.

2. Specifications.

3. Addenda.

4. Change Orders and other modifications to the Contract.

5. Reviewed Shop Drawings, Product Data, and Samples.

6. Manufacturer's instruction for assembly, installation, and adjusting.

B. Ensure entries are complete and accurate, enabling future reference by Owner.

C. Store record documents separate from documents used for construction.

D. Record information concurrent with construction progress, not less than weekly.

E. Specifications: Legibly mark and record at each product section description of actual products installed, including the following:

1. Manufacturer's name and product model and number.

EXECUTION AND CLOSEOUT REQUIREMENTS 20162.09.00

Page 2 - SECTION 01 70 00 ms1116

2. Product substitutions or alternates utilized.

3. Changes made by Addenda and modifications.

F. Record Drawings: Legibly mark each item to record actual construction including:

1. Measured horizontal and vertical locations of underground utilities and appurtenances, referenced to permanent surface improvements.

2. Field changes of dimension and detail.

3. Details not on original Contract Drawings.

G. Submit documents to Engineer 30 days prior to claim for application for Payment.

1.05 PRODUCT WARRANTIES AND PRODUCT BONDS

A. Obtain warranties and bonds executed in duplicate by responsible subcontractors, suppliers, and manufacturers, within ten days after completion of the applicable item of work.

B. Execute and assemble transferable warranty documents and bonds from subcontractors, suppliers, and manufacturers.

C. Verify that documents are in proper form, contain full information, and are notarized.

D. Co-execute submittals when required.

E. Submit prior to final Application for Payment.

1.06 MAINTENANCE SERVICE

A. Furnish service and maintenance of components indicated in specification sections for 1 year from date of Substantial Completion.

B. Maintenance service shall not be assigned or transferred to any agent or Subcontractor without prior written consent of the Owner.

PART 2 PRODUCTS

NOT USED

PART 3 EXECUTION

20162.09.00 CUTTING AND PATCHING

ms1116 SECTION 01 73 29 - Page 1

1.01 CUTTING AND PATCHING REQUIREMENTS

A. Contractor shall be responsible for cutting, fitting, and patching, including attendant excavation and backfill, required to complete Work or to:

1. Uncover portions of Work to provide for installation of ill-timed Work.

2. Remove and replace defective Work.

3. Remove and replace Work not conforming to requirements of Contract Documents.

4. Remove samples of installed Work as specified for testing.

1.02 SUBMITTALS

A. Submit written request to Engineer well in advance of executing cutting or alteration which affects:

1. Work of Owner or any separate contractor.

2. Structural value or integrity of any element of Project.

3. Integrity or effectiveness of weather-exposed or moisture-resistant elements or systems.

4. Efficiency, operational life, maintenance, or safety of operational elements.

5. Visual qualities of sight-exposed elements.

B. Request shall include:

1. Identification of Project.

2. Description of affected Work.

3. Necessity for cutting, alteration, or excavation.

4. Effect on work of Owner or separate contractor, or structural or weatherproof integrity of Project.

5. Description of proposed Work:

a. Scope of cutting, patching, alteration, or excavation.

b. Trades who will execute Work.

c. Products proposed to be used.

d. Extent of refinishing to be done.

6. Alternatives to cutting and patching.

7. Cost proposal, when applicable.

8. Written permission of any separate Contractor whose work will be affected.

C. Should conditions of Work or schedule indicate change of products from original installation, Contractor shall submit request for substitution.

D. No cutting or alteration for which written request is submitted shall be performed without written acceptance of Engineer.

E. Submit written notice to Engineer designating date and time Work will be uncovered.

PART 2 PRODUCTS

2.01 MATERIALS

A. Comply with specifications and standards for each specific product involved.

PART 3 EXECUTION

3.01 INSPECTION

A. Inspect existing conditions of Project, including elements subject to damage or to movement during cutting and patching.

B. After uncovering Work, inspect conditions affecting installation of products, or performance of Work.

CUTTING AND PATCHING 20162.09.00

Page 2 - SECTION 01 73 29 ms1116

C. Report unsatisfactory or questionable conditions to Engineer in writing; do not proceed with Work until Engineer has provided further instructions.

3.02 PREPARATION

A. Provide adequate temporary support as necessary to assure structural value or integrity of affected portion of Work.

B. Provide devices and methods to protect other portions of Project from damage.

C. Provide protection from elements for that portion of Project which may be exposed by cutting and patching Work, and maintain excavations free from water.

3.03 PERFORMANCE

A. Execute cutting and demolition by method which will prevent damage to other Work, and will provide proper surfaces to receive installation of repairs.

B. Execute excavating and backfilling by methods which will prevent settlement or damage to other Work.

C. Employ original installer or fabricator to perform cutting and patching for:

1. Weather-exposed or moisture-resistant elements.

2. Sight-exposed finished surfaces.

D. Execute fitting and adjustment of products to provide finished installation to comply with specified products, functions, tolerances, and finishes.

E. Restore Work which has…