Atch 01 SOW_210830.pdf
PDF 342 KB Posted
- Attached to
- TWO-TON CRANE REPLACEMENT BLDG 10 BAY C
- Solicitation number
- W25G1V-22-Q-0001
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Atch 05 SiteVisit Pics_20211102.pdf | ||
| Vendor Q and A_20211101.xlsx | XLSX spreadsheet | |
| Vendor Q and A_20211028.xlsx | XLSX spreadsheet | |
| Atch 02 Salient Characteristics.pdf | ||
| RFQ W25G1V22Q0001_SF1449.pdf | ||
| Atch 04 Pictures.pdf | ||
| Atch 03 Configuration.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TOBYHANNA ARMY DEPOT
Building 10, Bay C
11 Hap Arnold Blvd Tobyhanna, PA 18466
Statement of Work (SOW) 30 August 2021
Replacement of Two Each 2‐Ton Bridge Cranes
SOLICITATION/RFQ NUMBER:
W25G1V‐22‐Q‐0001
TABLE OF CONTENTS
1.0 BACKGROUND
2.0 SCOPE ...........................................................................................................3‐5
3.0 WARRANTY
4.0 GENERAL REQUIREMENTS
5.0 RESPONSIBILITIES
5.1 Government
5.2 Contractor
6.0 SUBMITTALS/DOCUMENTATION ................................................................7,8
7.0 FINAL ACCEPTANCE
8.0 OTHER REQUIREMENTS:
A. Security Requirements ..............................................................................8,9 B. Smoking Restrictions C. Station Permits D. PCB, Hazardous Materials, Asbestos & Lead Material E. Contractor Safety Standards F. On‐Site Procedures & Compliance ............................................................10‐18 G. Environmental Protection Requirements .................................................18‐20 H. General Requirements ..............................................................................20,21 J. Depot Access .............................................................................................21,22 K. AT/OPSEC Requirements ...........................................................................22,23
1.0 BACKGROUND: Tobyhanna Army Depot (TYAD) requires the removal and replacement of 2 each 2‐ ton bridge cranes that are deemed beyond economical repair (BER). These bridge cranes are needed on a daily basis for servicing trailers and other systems by removing and replacing large generators and electronic control units (ECU), typically ranging from 250 lbs to 4,000 lbs in weight. The BER cranes are currently located and installed in Building (BLDG) 10 Bay C at TYAD.
1.1 Note: The term “crane” used throughout this statement of work refers to all the components to make up a useable bridge crane, that is: the columns, braces and supports, bridge, trolley and hoist and hardware to erect and provide a useable bridge crane.
1.2 The following list of documents, though not physically attached to this document, are hereby incorporated as part of this statement of work…
DOCUMENT NAME DESCRIPTION of DOCUMENT
Atch 02 Salient Characteristics Brand Name or Equal Minimum Required Specifications of the Two Each Bridge Cranes to be Supplied and Installed.
Atch 03 Configuration CAD Drawings/Sketches of Building 10 and Layout of Cranes in Bay C.
Atch 04 Pictures Photographs of BER Cranes Currently Installed in Bay C of Building 10.
2.0 SCOPE: This Statement of Work (SOW) defines the requirements for the 2 each bridge crane removal of, furnishing of, and installation of, for the Mobile Electric Power & ECU Division of TYAD, located in Tobyhanna, PA 18466.
2.1 The contractor shall provide all of the requisite supervision, personnel/labor, tooling, parts, material and equipment necessary for the removal of 2 each unserviceable bridge cranes and supply and installation of 2 each, new 2‐ton bridge cranes.
2.1.1 Any high reach equipment, such as ladders, forklifts, etc., that the contractor uses in the removal and/or installation of the bridge cranes, shall meet or exceed all relevant OSHA safety requirements.
2.1.2 All design, fabrication, freight, rigging, etc., for the removal and installation of the cranes and corresponding accessories and/or components, shall be the responsibility of the contractor.
2.1.3 TYAD personnel, tenants, and equipment, such as material handling, shall not be employed for any transporting, lifting, and/or other such duties alike, regarding the crane removal and installation processes.
2.1.4 Crane Removal ‐ Crane components to be removed such as the runway rails, bridge, hoist, conductor rails and miscellaneous accessories shall be palletized and staged outside on the West side of Building 10C for the government to turn‐in/recycle. The same safety standards apply to the removal process as the installation process.
2.2 Detailed drawings of the bridge and crane structure, approved and stamped by the crane manufacturer or contractor's structural engineer shall be provided as submittals within 30 days of contract award and a minimum of 30 days prior to crane installation.
2.3 The contractor shall provide, as needed, any barricades and/or other means of controlling/detouring personnel entry and other foot traffic in and out of the immediate and surrounding areas in which the cranes will be removed and installed.
2.3.1 To accommodate BER crane removal and new crane installation, the contractor shall coordinate with the Contracting Officer’s Representative (COR) in all matters, (other than the preceding paragraph, (PARA)), requiring the reduction of personnel and equipment in the immediate and/or surrounding areas of BLDG 10 Bay C. NOTE: Any portion of the removal and/or installation process that requires such areas to be 100% devoid of personnel, shall be done after regular business hours, from 5:00 PM through 6:00 AM weekdays, and 4:00 PM Friday through 6:00 AM, Monday for weekends. In the case of Friday, Regular Days Off (RDO), work may begin Thursday after 5:00 PM and go through the time identified for weekends. (All times are EST).
2.4 Period of Performance (PoP) – The contractor shall complete all work, from start to finish, within 90 days after date of contract award (ADC). The exact PoP start and end dates are TBD at contract award.
2.5 Safety Compliance –
2.5.1 As it relates to the complete system(s), including the removal and installation, all performance must conform to the applicable requirements of the latest edition(s) of the following:
(a) Occupational Safety and Health Act (OSHA);
(b) State and Local Codes;
(c) American Gear Manufacturers Standards (AGMA);
(d) American National Standards Institute (ANSI);
B30.10 – Hooks;
B30.17 – Top Running Single Girder Bridge Cranes;
B30.16 – Overhead Hoists (underhung);
HST‐1M – Performance Standard for Electric Chain Hoists;
HST‐4M – Performance Standard for Overhead Electric Wire Rope Hoists.
(e) Crane Manufacturers Association of America (CMAA);
CMAA Specification #70, for electric underhung cranes;
CMAA Specification #74, for electric underhung cranes.
(f) Hoist Manufacturers Institute (HMI);
HMI 100‐74 Specifications for electric wire rope hoists.
(g) National Electric Manufacturing Association, Inc.;
(h) National Electric Code (NFPA 70);
(i) Motors – NEMA MG‐1;
(j) Control Enclosures – NEMA Rated.
2.5.2 As it relates to the complete system(s), including the removal and installation, any and all WELDING, BURNING, or GRINDING, shall comply with the following:
(a) If connection of any sections of the overhead railways or any other component of the crane structure requires welding, the welding shall be performed by certified welders for the material that is being welded. Contractor is responsible for obtaining a TYAD welding/burning permit.
(b) Any welding, burning (oxygen cutting), or grinding shall require the use of the proper Personal Protective Equipment (PPE). Examples of which are welding helmet, burning goggles, flame resistant gloves & jacket, etc. The contractor shall ensure that all personnel in the vicinity of the welding wear the proper Personal Protective Equipment (example: safety glasses approved for use in an area where arc welding is taking place).
(c) The contractor shall provide a visual barrier to the arc for TYAD employees within the area whenever welding is being conducted. This barrier shall be approved by the COR prior to commencement of work.
(d) Any grinding, burning, or welding in the vicinity of the crane – where it may be possible for a spark or splash to fall into or onto any of the items that cannot be removed from the area ‐ shall require the use of fire blankets to completely cover those items. Any contractor expecting to perform welding any time during the installation of the service platform, whether the welding is performed in Building 3 Bay 1 or in the vicinity of the building, should ensure that fire blankets are on site during those times that welding is taking place.
(e) Grinding sparks shall not be allowed to come in contact with flammable materials.
(f) The contractor shall ensure that multiple fire extinguishers are on site any time welding, burning, or grinding is taking place. The contractor shall be aware of TYAD’s fire extinguisher signage and the location of additional extinguishers and fire hoses.
(g) High‐pressure gas cylinders shall be properly constrained or secured to a cart that meets OSHA requirements. If being lifted, cylinders shall be properly secured to a lifting cart, again, that meets OSHA requirements.
(h) Contractor shall ensure that fire watch personnel are present any time welding, burning, or grinding is taking place. Fire watch personnel will remain at the site of the welding, burning, or cutting for at least an hour after work has ceased to ensure that no material is smoldering or burning as a result of the welding, burning, or cutting.
(i) Due to the nature of this project, installing overhead equipment and material, it is in the governments and the contractors best interest to plan on doing any major welding efforts during off shift hours from 4:30 PM to 7:00 AM, Regular Day Off (RDO) Fridays and weekends, (all times are EST). Major welding efforts shall be considered any efforts requiring more than 2 hours of welding.
3.0 WARRANTY: The bridge crane and workmanship furnished under this specification shall be warranted for workmanship for a period of 1 year from the date of final acceptance. IN THE CASE OF
ANY COMPONENTS OR SUBSYSTEMS WHICH COME WITH A WARRANTY FROM THE MANUFACTURE
THAT IS LONGER THAN 1 YEAR, THAT WARRANTY WILL BE PROVIDED TO THE GOVERNMENT WITH THE
OTHER REQUIRED DOCUMENTATION. THE EXISTENCE OF WARRANTIES FOR COMPONENTS OR
SUBSYSTEMS WHICH HAVE AURATION OF LONGER THAN ONE YEAR, IN NO WAY NEGATES OR
DIMINISHES THE RESPONSIBILITY OF THE CONTRACTOR FOR PROVIDING WARRANTY OF THOSE
COMPONENTS OR SUBSYSTEMS FOR A PERIOD OF ONE YEAR AFTER INSTALLATION. There shall be single contractor accountability to prevent confusion of responsibility if a problem or breakdown occurs.
4.0 GENERAL REQUIREMENTS: The contractor shall follow all TYAD safety and environmental rules and all other TYAD rules and policies regarding proper conduct (see section 8.0, PARAs A‐K of this SOW.)
4.1 General Safety – As work will be performed at a significant height, the (Contractor supplied) equipment that enables installers to reach that height will be equipped with all required safety harnesses or other equipment specified in OSHA CFR 1910. All personnel working at that significant height (as it is in near vicinity of the ceiling superstructure) – as well as any personnel below – will wear safety helmets/hard hats.
4.2 General Environmental Considerations –
(a) The contractor shall supply Safety Data Sheets (SDS) for any hazardous materials associated with the installation.
(b) No Class I Ozone Depleting Substances (ODS) or other materials containing, or manufactured with Class I ODS, will be utilized at any time during the installation of the crane.
4.3 General Compliance – Installation of all electrical components shall comply with the National Electric Code and an OSHA CFR 1910 requirement. All components of the equipment, as a result of the installation will be in compliance with any rules regarding the proper installation and operation of bridge cranes.
5.0 RESPONSIBILITIES:
5.1 Government Responsibilities:
(a) Providing clear access to get equipment, parts, and materials into and out of the installation areas. This includes ensuring that areas where columns and support will be installed are cleared of equipment and material.
(b) Identify a Contracting Officer Representative (COR) to serve as a single point of contact to coordinate contractor’s efforts with depot operations and personnel.
(c) Providing a staging area for contractor’s tools and materials.
(d) Provide a location for the contractors dumpster if required.
(e) Electrically disconnect the power to the unserviceable cranes to be removed.
5.2 Contractor Responsibilities – Include but may not be limited to the following:
(a) Project Management & on‐site supervision;
(b) Coordination with TYAD’s COR regarding the removal and installation of bridge crane(s);
(c) Provide all required submittals & documentation within a timely manner, (Refer to PARA 6.1 of this SOW);
(d) Provide for Quality Control for both material and workmanship;
(e) Provide and Erect safety barriers and precautions around work area;
(f) Provide necessary tools and equipment to complete the removal of the existing cranes and the installation of the new cranes;
(g) Organization of the parts/material staging area and work site (tools, parts, and materials);
(h) Provide dumpster and necessary means for removal and disposal of debris and waste material;
(i) Removal of the dumpster at the completion of the work and all costs associated with the disposal of the debris and dumpster;
(j) Neatness and organization of the work site, free of debris accumulation (daily);
(k) Providing all required material handling equipment/lifting equipment to handle all parts and materials and to perform all work in a safe manner (government personnel or equipment shall not be used at any time to assist handling of any materials, parts or components);
(l) Connection, disconnection and reconnection of any utilities necessary to perform the specified removal and installation. Contractor shall comply with lockout/tagout procedures as part of this responsibility. (Refer to section S.10.8 of this SOW for procedures);
(m) The Contractor shall specify any special utility requirements not currently existing in the area if necessary for the removal and/or installation;
(n) Connection and installation, (if needed), of all the electrical controls and utilities to place the cranes in service. (Note: All electrical work shall be coordinated with and approved by TYAD Garrison DPW Engineering group prior to any electrical work being performed);
(o) Provide notification to the COR 15 days prior to the commencement of on‐site work.
6.0 SUBMITTALS / DOCUMENTATION: May be provided via hard copy, or electronic media, such as email. The contractor shall provide all of the required submittals/documentation in a timely manner.
6.1 REQUIRED FROM CONTRACTOR:
(a) Project Work Schedule – (No later than (NLT) 20 days ADC);
(b) Warranty – (as described in PARA 3.0 of this SOW);
(c) List of Personnel – (Refer to PARA 8.0 section “A. Security Requirements” of this SOW.);
(d) On‐Site Safety Program;
(e) Binder of SDS(s) on‐site for Right to Know Policy – (Refer to PARA 4.2(a) of this SOW);
(f) Listing of all Repair Parts and Material being installed;
(g) Detailed Structural Drawings of Bridge and Crane – (Refer to PARA 2.2 of this SOW);
(h) Utility Requirements for the operation of the contractor’s equipment – (if other than the standard requirements).
6.2 The government shall have 10 days from date of contractor submission, to review and/or approve all submittals/documentation.
7.0 FINAL ACCEPTANCE:
7.1 Acceptance Testing will consist of:
(a) The Contractor's technical representative demonstrating that the fit and finish of the bridge crane meets or exceeds TYAD’s specifications and all OSHA requirements;
(b) Documents certifying load testing and demonstration of crane functions.
(c) Removal of all tools, materials, and other debris, including dumpster.
7.2 In the event that the crane fails to comply with any aspect of this specification, the Contractor shall correct any deficiencies within 15 working days of the acceptance test. It shall be at the discretion of TYAD’s Contracting Officer as to whether all, part, or none of the acceptance test procedure shall be performed again.
8.0 OTHER REQUIREMENTS:
A. SECURITY REQUIREMENTS: Contractor’s personnel working on the Tobyhanna Army Depot shall be fully identified. Contractors shall register with TYAD Security in Building 606. All Contractor’s employees, staff, and subcontractor personnel, etc., requiring access to TYAD must present to the security personnel at the desk in Building 606 the following information prior to gaining access:
(a) Full name
(b) Drivers License
(c) Nationality (if non‐U.S. Citizen, alien registration number)
If contractor’s vehicles are required for use on TYAD, the following ID is required:
(a) Make
(b) Model
(c) State Registration
(d) Insurance
(e) License Plate #
Contractor’s personnel must confine themselves to the work sites specified in their contract.
Visiting other areas is prohibited.
Alcoholic beverages, weapons, cameras, sound recorders, proscribed drugs and explosives are prohibited on Government property.
Use of Government property without prior written approval of the On Site Representative is prohibited.
TYAD will arrange for special Contractor parking if required. Contractor’s personnel must not park in numbered spaces, areas reserved for car pools, grassy areas or other prohibited areas.
Posted speed limits and traffic restrictions must be observed at all times.
Accidents or problems of a security/safety nature must be reported to the Security (570.895.7550) and TYAD’s Contracting Officer Representative immediately.
Contractor’s personnel working on station for less than 30 days may be required to log in and out at the Visitor's Center (Building 606) each day and will not be issued an Extended Entry Contractor's Badge. The On‐Site Representative will provide information on how to obtain an Extended Entry Contractor's Badge if one is required.
Pursuant to federal regulations, all personnel and vehicles on Government property are subject to search by authorized personnel at any time.
All Contractor’s personnel are required to display the TYAD issued identification badge on their person at all times while present at the depot. Access to the depot will not be allowed without this identification badge. The badge is to be displayed on the person outer clothing, above the waist and in full view. Identification badges and vehicle passes issued to Contractor’s personnel remain the property of the U.S. Government and must be surrendered upon completion of the work each day or when requested by the Government.
A list of all personnel working under this contract should be turned in immediately after award in order to allow sufficient time to process security information.
B. SMOKING RESTRICTIONS: The bearing and use of lighted cigarettes, vaping products, cigars, pipes, or any tobacco product is prohibited in the following areas:
A. All buildings including private offices, lobbies, and restrooms B. Alleys and passages between buildings C. Stairways and ramps leading to building entries and exits D. Within 50 feet of building entries and exits E. Within 20 feet of heating, ventilation, and air conditioning intake ducts F. Hazardous areas containing flammable liquids, gases, vapors, and all other locations where there is a collection of readily ignitable combustible material
C. STATION PERMITS: Permits are required for but not limited to welding and burning.
Burning/fire permits must be obtained daily from the Fire Department. The COR will provide assistance obtaining any required permits.
D. PCB, HAZARDOUS MATERIALS, ASBESTOS AND LEAD MATERIAL:
If material is encountered which may contain PCB’s, hazardous materials, asbestos and or lead and must be disturbed, do not touch the material. Should the discovery of such suspected material affect the Contractor's planned work schedule, the contractor shall redirect the work crew to other portions of the unaffected work and modify the schedule at no additional cost to the Government. The On Site Representative shall be notified immediately regarding the discovery of the suspected material and of any adverse impact the contractor may expect to incur due to this situation. Within 10 calendar days, the On Site Representative will have laboratory tests performed to determine if the material is a hazard. If there is not a danger, the site Representative will direct the Contractor to proceed in the identified area without change.
If the material is identified as hazardous, before proceeding, discussions will be held with the On Site Representative to determine the most cost‐effective means for removal. The hazardous material will be removed, abated or rendered harmless before work commences.
E. SAFETY REQUIREMENTS:
CONTRACTOR SAFETY STANDARDS FOR TYAD – (Revised Feb. 2021) Below are some “installation specific” safety standards which contractors are required to adhere to while performing any work on Tobyhanna Army Depot. It is the contractor’s responsibility to incorporate these particular requirements into their daily operations at all times while under contract and to institute these specifics into their overall site safety controls. These do not substitute or deflect in any way the requirement to institute and adhere to all OSHA 1910 & 1926, ARMY 385‐10, USACE EM385‐1‐1, and DoD 6055.01 job site safety standards as well while performing contract work under the provisions of FAR Clause 52.236‐13 on Tobyhanna Army Depot.
It is the responsibility of the contractor to enforce the below requirements as well as all current revisions of the above referenced standards. Failure to enforce safety requirements on the depot can result in immediate stop works, safety stand down orders and even complete termination of the contract.
Important Phone Numbers:
Fire or Emergency: 911 Fire Department – (Non‐Emergency): 570‐615‐7300 Security: 570‐615‐7550 Safety Office ‐ 570‐615‐7027
F. ON‐SITE PROCEDURE & COMPLIANCE:
S.10.0 THE CONTRACTOR IS SOLELY RESPONSIBLE AND LIABLE FOR JOB‐ SITE SAFETY:
1. Review of the project plans and other documents by any government appointed official does not constitute an acceptance of Federal responsibility or liability for the adequacy of the safety measures identified for the job or for the Contractor's compliance with all applicable safety rules and regulations.
2. The Contractor remains solely responsible and liable for job‐site safety at all times during the term of the contract. No outside personnel (other than ET, COR, TYAD Safety, or other government appointed contract personnel) are allowed onto the job site at any time during contract without prior permissions and/or escort by the ET, COR or KO.
3. Tobyhanna Army depot has restrictions on the use of fossil fuels in all buildings. The contractor must follow the TYAD fossil fuel memorandum of understanding requirements pertaining to such uses as noted below:
TYAD has restrictions on the use of fossil fuels in all buildings. When it is determined that electric or other alternatively‐fueled vehicles are insufficient or unavailable for movement of material within the buildings on the installation, fossil‐fueled vehicles can be used only when all alternatives of accepted electric material movement equipment have been considered, and the last option is use of a fossil fuel vehicle or project failure. This includes any situations where safety of employees and equipment may be jeopardized. Convenience will never be an acceptable justification to utilize fossil‐fueled vehicles. The Government Designated Representative (GDR) will notify the appropriate supervisor(s) or leader(s) in the area where the need to utilize a fossil fuel vehicle is required. The supervisor / leader will take the necessary steps to notify the employees in the work area of the option to leave the area during the material movement process. The GDR and Contractor will also document all actions the Contractor took to utilize electric or other alternatively‐fueled vehicles. The documentation will specifically state why electric or alternatively‐fueled vehicles are insufficient. The documentation may be in the form of signed memo or email and must be completed within 24‐ hours after the usage of the fossil‐fueled vehicle. A copy of the documentation will be provided to the Union and the Safety Division.
4. All direct construction supervision, including subcontractors, must as a minimum, complete an OSHA 10 hour safety course for construction. These certificates must be submitted as part of the site safety plan BEFORE construction activities start.
5. RED CARD PROGRAM ‐ Tobyhanna Army Depot utilizes a program to allow employees to stop an action which is considered unsafe. Employees carry small red cards that can be thrown down when employee sees an action they consider unsafe. Work ceases until TYAD management can decide if it is safe or not. Contractors are required to comply with this program. If a TYAD employee presents the red card to the contractor, the contractor must stop working until the COR and Safety Office can determine if there is a safety hazard or not.
6. All contractor personnel, to include subcontractors, vendors, suppliers, or visitors, when performing any type of work activity, or gaining access through an occupied area or shop ‐ must have all applicable PPE that is required for the area to include, but not limited to, hardhats, safety glasses, hearing protection, and respirator protection. Notify both COR & Area Supervision, for access approval and prior to any work activities being performed.
S.10.1 CODE COMPLIANCE:
Tobyhanna Army Depot requires full contractor compliance with all safety regulations and standards.
The Contractor is responsible for maintaining, monitoring and enforcing all rules, regulations and codes, by ALL personnel working for the contractor including all subcontractors. These codes include:
Title 29 Code of Federal Regulations‐1910 (OSHA General Industry Standards)
Title 29 Code of Federal Regulations‐1926 (Construction Industry Standards)
National Fire Protection Association Codes
Uniform Facilities Code
Department of Army 385‐10, Department of Defense 6055.1
Unified Facilities Guide Specifications (UFGS)
USACE EM385‐1‐1
All other codes as required to maintain safety standards.
S.10.2 JOB HAZARD ANALYSIS (JHA) / ACTIVITY HAZARD ANALYSIS (AHA):
Prior to the start of work, the contractor shall prepare a JHA / AHA for each phase of work that will be done under the contract. This will be completed in accordance with all applicable OSHA safety requirements. A phase is any operations involving a certain type of work. Examples include demolition, excavation, masonry work, concrete pouring, roofing, and electrical wiring. Work done by each subcontractor is also a phase. The JHA / AHA will:
1. List the activity being performed and identify the sequence of work steps.
2. List the hazards associated with each step, and the procedures and training required to eliminate or reduce the risk to an acceptable level.
S.10.3 SITE SPECIFIC SAFETY & ACCIDENT PREVENTION PLANS:
Contractors will submit a written Site Specific Safety / Contractor Accident Prevention Plan prior to beginning construction. The plan must follow the guidelines in OSHA 1926:
1. Who will implement the plan, including who is responsible for safety and accident prevention?
2. A means for coordinating and controlling subcontractors and suppliers.
3. Safety training.
4. Who will investigate accidents?
5. Emergency response.
6. Job site cleanup and safe access.
7. Public safety requirements such as signs and barricades.
S .10.4 FALL PROTECTION:
1. Personnel performing works at a height six feet or more from any lower level, shall comply with OSHA 29 CFR 1926.500 through 1926.503 safety standards.
2. There are no certified anchorage points or permanent guardrail systems on any TYAD roof. Most roofs of the depot are more than 20 feet high.
3. Contractors and their employees must be protected from falling off the edge of the roof, regardless of how briefly the employees are at the edge of the roof.
S.10.5 ELECTRICAL SAFETY:
Follow the current Tobyhanna Army Depot standard. This standard is based on NFPA 70E.
Copies of the TYAD Electrical standard may be obtained by request from the ET, COR or KO on the project or service contract.
S.10.6 DEPOT REQUIRED PERMITS / APPROVALS:
Permits are required for:
1. Excavation: Contractors must utilize the PA 1 Call system and coordinate with contracting officer representative (COR) for excavations prior to any groundbreaking including digging, drilling and stake driving. See appendix L for permitting details.
2. Trenching: Contractors will adhere to OSHA requirements and receive approval from TYAD Safety office before any trenching deeper than 5 feet is performed. Notifications of such activities will be provided to the COR along with required plans, requests and permits prior to any trenching works being performed. Contractor is responsible for field verifying all utilities and underground entities.
Excavation or trench greater than 4 foot in depth that remains open greater than (1) day OR left unattended for any period of time shall have a safety orange construction fence installed around the perimeter of the opening. Caution tape or cones for this purpose is unacceptable.
3. Confined Space: All confined space works on TYAD are to be considered as permit required entries and Contractor must first request and be provided with an approved "signed" permit from TYAD Safety Office prior to any confined space entry. Contractor will refer to all OSHA requirements and must have a confined space plan and all appropriate safety equipment. Contractor is to request approval from TYAD Safety office through COR prior to entry.
4. Burning / fire: Hot work permits must be obtained daily from the Fire Department.
5. Cranes: For use of cranes and all WHE and LHE at TYAD see S.10.13
6. Army Radiation Permits: Non‐Army agencies (including other military Services, vendors, and civilian contractors) require an Army Radiation Permit (ARP) to use, store, or possess ionizing radiation sources on TYAD (see 32 CFR 655). Non‐Army applicants will apply by letter with supporting documentation to the Depot Commander. The letter should be submitted so that the Depot Commander receives the application at least 30 days before the requested start date of the permit. The ARP application will specify start and stop dates for the ARP and describe the intended use of the radioactive material.
For sealed sources of radiation, i.e. Moisture Soil Density Gauges, the application must include a valid Nuclear Regulatory Commission (NRC) Radioactive Materials License that allows the applicant to use the source as specified in the ARP application, current leak test certificates, operator training records and calibration certificates for any equipment that may be utilized at TYAD.
For machine produced ionizing radiation sources, i.e. X‐ray Equipment, the application must include the appropriate state authorization that allows the applicant to use the source as specified in the ARP application along with operator training records and calibration certificates for any equipment that may be utilized at TYAD.
ARPs will not be issued for more than 12 months at a time.
S.10.7 CONFINED SPACES
1. A ll Confined Spaces at TYAD are considered as Permit‐Required Confined Spaces.
2. Contractors must fully comply with all OSHA regulations for Confined Space Operations, including on‐site use and availability of a Confined Space Entry Permit / Checklist.
3. Contractors must notify the COR and receive TYAD Safety Office approval prior to entry and only after they’ve received permissions and acceptance of their Accident Prevention Plan and associated Activity Hazard Analysis (AHAs). The contractor and / or the COR will then notify Fire and Emergency Services of the Confined Space Entry.
4. Upon completion, the contractor will notify the TYAD Safety Office and discuss whether any new hazards were added to the Confined Space and will submit the completed Confined Space Entry Permit / Checklist for record.
S.10.8 LOCKOUT/TAGOUT PROCEDURE
1. The Contractor shall perform this work in accordance with 29 CFR § 910.147‐The Control of Hazardous Energy requirements.
2. The Contractor shall notify the COR that a lockout/tag out system is going to be used.
3. The contractor is to request the COR to notify them if TYAD is using any lockouts / tag outs in the construction area.
4. The Contractor shall locate and identify all isolating devices.
5. The Contractor shall shut down the equipment normally.
6. The Contractor shall isolate all energy using appropriate methodology.
7. After all work is complete, the Contractor shall remove the energy isolating device and restore the equipment to service.
8. The Contractor shall notify the COR that energy is again restored.
S.10.9 PROTECTION TO THE DRINKING WATER SYSTEM
1. The contractor will not perform any work on the depot potable water system until prior approval is obtained from the Environmental Branch and the certified operator through the Directorate of Installation Services COR.
S.10.10 PROTECTION OF PERSONNEL
At no time is any depot employee to be put at risk to illness or injury. No construction actions are exempt from this requirement.
1. Where pedestrian and driver safety is endangered, use appropriate traffic barricades. Use anchor barricades to prevent displacement by wind. Institute PA DOT regulations and OSHA requirements.
Notify the COR prior to beginning such work.
2. Where demolition is required, a Demolition Plan describing the steps and individual Definable Features of Works (DFOWs) as well as safety protocols, controls and oversight is required to be submitted to the COR for review prior to works being performed. Continuously evaluate the condition of the structure being demolished and take action to protect personnel working around the project site. No structural element will be left standing without sufficient support to prevent collapse.
3. Contractor shall provide personal protective equipment (PPE) and provide training for use, for all visitors requiring entry into the regulated area.
4. Subcontractors, vendors, and delivery personnel are the responsibility of the prime contract and must follow the same regulations the prime contractor does.
S.10.11 FIRE AND EMERGENCY SERVICES
Hot Work Permits will be issued by Fire Department upon request. All requests must be made at least thirty (30) minutes prior to the expected start time by contracting the fire department.
1. Contractors are required to have fully charged and operable contractor provided fire extinguisher, in quantities and properly spaced per OSHA requirements that are appropriate for the type of possible fire. Fire extinguisher shall be immediately available for inspection by the fire department upon an inspection of the worksite and shall remain at the work site at all times. At a minimum, 10 pound class 4A, 60B or C multi‐purpose dry chemical fire extinguisher or equivalent shall be provided.
2. A fire watch must be in place during the hot work and for 30 minutes after the HWP operation.
Upon completion of the thirty (30) minute, post hot work fire watch, the contractor shall contact the fire department to report the work is complete.
3. Use of a plasma torch will require special approval by the fire department.
4. Any fire, even one that is extinguished, must be reported to the fire department.
5. Ambulance services are provided at a cost to contractors. The contracted ambulance service provider will transport to the nearest hospital. Advanced Life Support, helicopter transport, etc. is all at the contractor's expense.
6. The fire department will respond to all fire, ambulance, hazmat and confined space incidents.
S.10.12 IF AN INCIDENT HAPPENS
1. Any serious injury or medical emergency: Immediately call emergency responders
• Dial 911 and give accurate location and nature of emergency. Make sure to tell the operator that you are calling from Tobyhanna Army Depot.
• Send someone to the nearest exit to assist responders.
• Treat victims to the best of your ability.
• Notify COR / call work order desk at 570‐615‐7805 if there is any blood or body fluids that must be cleaned up.
2. In the event of the smell of natural gas:
Call dial 911and give accurate location and nature of emergency. Make sure to tell the operator that you are calling from Tobyhanna Army Depot.
Have all personnel evacuate the area if the smell is significant.
Upon arrival of fire personnel, provide information as to specific equipment and exact location of potential leak.
3. In the case of a fire:
• If the fire is small, use a fire extinguisher and call 911.
• Otherwise, dial 911 and pull the fire alarm.
• Evacuate the building.
S.10.13 CRANE LIFT OPERATIONS AT TOBYHANNA ARMY DEPOT
A Lift Plan for Crane Operations will be submitted to the ET/COR for approval by the TYAD Safety Office at least 14 days prior to a lift operation. It will conform to all applicable OSHA regulations and requirements and shall include:
1. A description of the operation to be performed, specific personnel assignments (Lift Director, Safety Coordinator, Operator, rigger, etc.) and signaling and any other details pertaining to activities during the lift.
2. A drawn Site Plan with specifications including work zone, support equipment locations, evacuation area, traffic control, electrical power line clearances (if applicable), lift path, surface conditions at crane location, etc.
3. Training/Certifications (scans) for crane operator and other lift‐team members included in the lift operation.
4. Equipment nomenclature and a certificate of comprehensive annual inspection records, including any deficiencies and corrective action.
5. Load chart for crane, with target capacities specific to the crane/boom configuration and lift details clearly marked.
6. Lift calculations, including rigging components and configuration.
7. Weather conditions are always part of the ongoing safety assessment and may result in rescheduling of the lift.
8. Only approved operators are allowed to operate or move the crane for any reason.
A Production Lift Plan pertains to repetitive lifts within a work project and may be outlined with one lift plan depicting the nomenclature and general capacities of the equipment to be utilized.
Besides the eight items above, the plan will also include how often the crane will be used and how traffic and personnel safety will be handled. A separate traffic plan will be required for vetting and approval prior to any lifts taking place.
S.10.14 APPLICATION OF ANY ODOR PRODUCING MATERIAL
1. Any application of any paint, epoxy, adhesive or anything else that produces an offensive odor must be coordinated with the COR or POC before starting. This is particularly true of the construction work in a building occupied by Tobyhanna employees.
2. It is highly recommend that this type of work be planned for off hours, weekends, or holidays to avoid shutdowns of operations due to these offensive odors. Odors during curing times for products shall also be considered.
IN ANY CONFLICT BETWEEN STANDARDS, THE STRICTER OF THE TWO SHALL APPLY. IF UNSURE
CONTACT THE COR / ET VIA PROPER RFI PROTOCOLS FOR VERIFICATION THROUGH THE TYAD
SAFETY OFFICE.
G. ENVIRONMENTAL PROTECTION REQUIREMENTS:
In addition to the following requirements the Contractor shall provide and maintain, during the life of the Contract, environmental protection. Plan for and provide environmental protective measures during normal construction practice. Plan for and provide environmental protective measures required to correct conditions that develop during the construction of permanent or temporary environmental features associated with the project. Comply with all Federal, State of Pennsylvania, and local environmental regulations pertaining to the environment, including but not limited to, hazardous waste, stormwater discharge, erosion control, water, air, soil, and noise pollution.
1.0 ASBESTOS
The Contractor will ensure that no Asbestos‐Containing Materials (ACM) are used in the performance of this contract.
Unless specified for abatement in the contract, the contractor will not disturb any existing ACM in the performance of this contract. If ACM, or suspect ACM might be disturbed by the work, the Contractor shall avoid coming in contact with the material and immediately notify the Contracting Officer Representative (COR) and the Contract Administrator in writing (fax or e‐mail acceptable) of the possible ACM. The COR will coordinate with the Environmental Management Division (EMD) to obtain laboratory tests to determine if there is ACM. If the material is determined to be ACM, and disturbing it cannot be avoided, the COR will notify the Contracting Officer. The Contracting Officer will direct a change pursuant to the contract clauses entitled “Changes” and “Differing Site Conditions.” If ACM, or suspect ACM has been disturbed, the contractor shall immediately notify the COR and call the EMD at (570) 895‐ 7098. The Contractor will shut down and not move any equipment or supplies near the damaged ACM.
The Contractor will evacuate all non‐contaminated contractor personnel from the immediate vicinity.
Any Contractor personnel thought to be contaminated with asbestos (e.g., evidence of dust on clothing) should remain in the area, but as far away as possible from the damage, until the EMD responds. If the damaged material is determined to be ACM and there is potential for further damage, the Contracting Officer will direct a change pursuant to the clauses of the contract clauses entitled “Changes” and “Differing Site Conditions.”
Asbestos abatement required under the contract as originally awarded shall be in accordance with Section 13280, Removal and Disposal of Asbestos Materials, and as otherwise required in the contract.
Asbestos abatement not required under the contract as originally awarded, can be incorporated into the existing contract via contract modification, or with the government taking responsibility for the asbestos abatement. The method of acquiring the abatement is at the discretion of the Government.
2.0 Backflow
The Contractor shall have a backflow prevention device installed on all contractor equipment that is connected to the depot's water distribution system. The Contractor shall have a water meter installed to monitor water consumption of all new buildings constructed.
3.0 Burning and Air Pollution Control
The Contractor shall not burn refuse and debris anywhere on the depot. The Contractor shall not allow any pollutant or particulate matter to enter the atmosphere that may be seen or visible from outside of the depot's boundary.
4.0 Emergency/Spills
While on the depot, the contractor shall report spills/releases by calling 911 on a depot phone or 895‐ 7300 and then notify the COR. The Contractor shall ensure all personnel working on site are trained in the proper procedure according to 29 CFR 1910.120 (if applicable) to initiate a spill response to handle the hazardous substances they are working with. The Contractor will take the necessary actions to prevent and contain spills of hazardous materials.
5.0 Energy
The Contractor shall make every effort to employ energy conservation measures during the course of this contract.
6.0 Mercury & Lead
The Contractor shall not install any equipment, switches, or devices (including thermostats) that contain mercury or lead.
7.0 Fluorescent and Mercury Bearing Lamps
The Contractor is to collect, containerize, recycle, and manage florescent and mercury bearing lamps in accordance with 40 CFR 273.
8.0 Hazardous Materials Stored and Labeled
The Contractor shall ensure all hazardous materials at the work site are properly stored and labeled.
The contractor shall not leave any hazardous material behind at the completion of the job for any reason.
9.0 Hazardous Waste
The Contractor shall ensure that all hazardous wastes at the work site are properly stored and labeled in a pre‐approved location. The contractor shall provide copies of any shipping documents for Hazardous Waste/Universal Waste/Toxic Substances Control Act waste. If hazardous waste or waste requiring special handling (e.g., asbestos) is being turned over to the government for disposal, the contactor shall notify the COR when the waste is ready to be moved.
10.0 ISO 14001
TYAD is an ISO 14001 certified facility. All Contractor and Subcontractor employees on site must comply with TYAD Regulation 200‐5, “Environmental Management System.” See http://www.tobyhanna.army.mil/ ; go to Site Map; go to Certifications, ISO 14001; and click on Environmental Management System (EMS) Document.
11.0 Safety Data Sheets (MSDSs)
The Contractor shall submit SDSs for all hazardous materials proposed for use including paints, solvents, adhesives, etc. These copies of SDSs will be provided to the COR five (5) working days prior to material being brought on post.
12.0 Noise
The Contractor shall not allow the noise level to exceed 65 decibels at any point outside depot property.
If noise levels exceed 65 decibels, a plan must be prepared by the Contractor to mitigate this noise levels and submit to the COR.
13.0 Paints
The Contractor shall not use paints containing zinc chromate or strontium chromate pigments and paints containing lead in excess of 0.06 percent by weight of the total nonvolatile content (calculated as lead metal).
14.0 Pest Management
At no time during the execution of this contract shall the Contractor provide a food source or harborage for any pests. The contractor shall coordinate through the COR to the EMD prior to application any pesticide usage. Pesticides are required to be approved by the EMD. The contractor shall report all usage of pesticides through the COR to the EMD. After completion of the Contract, the Contractor shall ensure there is no passage for pests to enter facilities or structures related to work performed by the Contractor.
15.0 Polychlorinated Biphenyls (PCBs)
The Contractor shall not bring items containing PCBs onto the depot.
16.0 Recycling The Contractor shall comply with TYAD’s general recycling plan for aluminum, steel, cardboard, paper, and plastics.
H. GENERAL REQUIREMENTS:
1.0 REMOVAL OF CONTRACTOR MATERIALS:
The Contractor shall remove from the site prior to the acceptance of work by the government, all materials not identified to remain in place, including excess paints, building materials, and equipment purchased by the contractor for the execution of this project.
2.0 STORAGE OF MATERIALS AND EQUIPMENT
Government furnished storage facilities may not be available to the contractor in the vicinity of the work site. The Contractor shall be provided suitable storage facilities as required, located as approved by the On Site Representative, if he intends to leave materials and equipment in the work area overnight or on weekends. The security of the Contractor's property or his personnel's property shall be the full responsibility of the contractor. The Government will accept no liability in case of loss due to fire or theft.
3.0 AVAILABILITY OF UTILITY SERVICES
The Government will furnish water and power in the quantity not to exceed the amount necessary for the normal prosecution of the work, at the nearest available outlet. The Contractor shall make all piping and wiring connections thereto and shall extend the services to the site of the work. On completion of the work, the contractor shall remove all such temporary connections and any removed or damaged portions of the Government services at the points of connection shall be repaired or replaced.
A. Other Utilities: The Contractor shall make arrangements to obtain all utilities not furnished by the Government, at his/her own expense.
B. The Government will not provide refuse facilities. The Contractor will be required to dispose of all garbage and other waste materials generated by his work at a licensed off‐site landfill.
J. DEPOT ACCESS: A background check and approval from TYAD Security Branch is required for all contractor and subcontractor personnel prior to on‐site access at TYAD. All persons seeking entrance to TYAD shall submit to and comply with all security standards and requirements in force at the time such persons are seeking entry. All contractors, regardless of resident status or citizenship, will be subject to vehicle search and intense in‐processing by TYAD security personnel prior to being granted access to TYAD. This security screening process may be time consuming and access may be delayed or denied. The contractor shall ensure ELTY Form 648‐C is completed for all contractor and subcontractor personnel requiring depot access to include warranty services. The TYAD point of contact (POC) will provide ELTY Form 648‐C, Request Access to Tobyhanna Army Depot, to the contractor/vendor at least ten days prior to the expected visit date for completion. The contractor/vendor shall return the completed ELTY Form 648‐C to the TYAD POC in a timely manner so the same may be submitted to Security for processing no later than seven days prior to the visit. All of the required fields on the form shall be complete and accurate by the contractor/vendor for timely processing. This requirement is inclusive of on‐site supervisory or managerial personnel and sub‐contractor personnel that the Contractor anticipates will be performing work or visiting on‐site. This security screening does not relieve the contractor of any responsibilities to conduct thorough pre‐employment background checks and drug screening. Contractor workers will not be granted access to the work site until security screening is completed and access is approved. Any contractor personnel on‐site who fail screening will not be permitted further access to TYAD. See “Access and General Protection/Security Policy and Procedures” below.
Please submit the completed ELTY Forms 648‐C form(s) to the COR or POC.
K. ANTITERRORISM (AT) / OPERATIONS SECURITY (OPSEC) REQUIREMENTS
All security training certificates shall be provided to the Contracting Officer’s Representative (COR)/Point of Contact (POC) and the Contract Specialist/Purchasing Agent.
Antiterrorism (AT) Level I Training. All contractor employees, to include subcontractor employees, requiring access to Army installations, facilities, and controlled access areas shall complete AT Level I awareness training prior to…