This is a Request for Qualifications (RFQ) issued by Greenwood County, South Carolina, for architectural and engineering services to design a new Fire Station 60 located at 5214 Highway 702, Ninety Six, SC. The project involves the design of a new approximately 7,500-square-foot full-time fire and emergency medical services station to replace an existing three-bay metal structure built in the late 1970s. The proposed facility will feature five bays, sleeping quarters for up to eight personnel, 3.5 bathrooms, a full kitchen, utility room with washer/dryer, and multiple office and meeting rooms, with design similarities to Fire Station 45 in Ware Shoals, SC. The RFQ was released on July 16, 2026, with a question submission deadline of July 29, 2026, at 2:00 p.m. and a proposal submission deadline of August 13, 2026, at 2:00 p.m. No pre-proposal meeting is scheduled. Responses must be submitted electronically through Greenwood County's e-Procurement Portal. Proposals must remain firm for a minimum of 90 days following submission.
The selected architectural and engineering firm must provide comprehensive services including surveying, asbestos testing and survey of existing buildings, geotechnical exploration, preliminary design, 50 and 100 percent design stages with architectural, structural, landscaping and MEP drawings and specifications, bidding assistance, construction administration, and construction closeout services. The firm must address South Carolina building codes, Greenwood County zoning ordinances, and SCDES and SCDOT standards, and must complete code compliance reviews with county planning/zoning, engineering, and building departments and obtain necessary permits. Evaluation criteria weight experience with comparable fire station projects at 50 percent, qualifications and experience of individuals directly involved at 25 percent, references at 15 percent, and proximity to the project site at 10 percent. The successful proposer must provide comprehensive general liability insurance with limits of $1,000,000 per person and per accident for bodily injury and property damage, workers' compensation insurance, fleet liability coverage, and professional liability insurance. The contractor will be subject to liquidated damages of $200 per calendar day for delays beyond substantial completion. Greenwood County reserves the right to reject any or all proposals and cancel the procurement if deemed in the county's best interest.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
For more information, please visit our online supplier portal, located at https://procurement.opengov.com/portal/greenwoodsc
County of Greenwood, SC
REQUEST FOR QUALIFICATION
2026-RFQ-024
ARCHITECTURAL/ENGINEERING SERVICES FOR THE DESIGN OF A NEW
LOWER LAKE-FIRE STATION 60
RELEASE DATE: July 16, 2026
RESPONSE DEADLINE: August 13, 2026, 2:00 pm
Please refer to the project timeline in this document for all important deadlines.
2026-RFQ-024 Architectural/Engineering Services for the Design of a New Lower Lake-Fire Station 60
INTRODUCTION
SUMMARY
Greenwood County (“Owner”) is requesting professional services from qualified Architectural/Engineering firms for the design of new fire station located at 5214 Highway 702, Ninety Six, SC 29666 (parcel ID #7815-
261-666). The proposed fire station will replace the existing Fire Station 60-Lower Lake located at that site, a three bay, metal building built in the late 1970's. The existing metal building and adjacent accessory brick building will be razed for a new, approximately 7500 SF, full-time Fire/EMS station. The new Lower Lake
Station 60 is proposed to have 5 bays, sleeping quarters for up to 8, 3.5 bathrooms, a full kitchen, utility room with washer/dryer, and multiple office/meeting rooms. Greenwood County is seeking a station similar in size, function and layout as Fire Station 45 located at 128 Greenwood Avenue South, Ware Shoals, SC. Plans attached.
This request seeks to identify the qualifications submitted that are in the best interests of Greenwood County.
The submitted proposals will be evaluated utilizing the Selection Guidelines outlined in this Request for
Qualifications. The owner is seeking a cost-effective and highly qualified partner. Greenwood County reserves the right to reject any an all subittals.
TIMELINE
Bid Release Date: July 16, 2026
Question Submission Deadline: July 29, 2026, 2:00pm
Question Response Deadline: August 6, 2026, 2:00pm
Proposal Submission Deadline: August 13, 2026, 2:00pm
PRE-PROPOSAL MEETING
No Pre-Proposal Meeting is scheduled for this project.
QUESTIONS
Questions concerning this RFQ specifications, or the identity of any omissions or discrepancies be submitted via the e-Procurement Portal located at https://procurement.opengov.com/portal/greenwoodsc, by
Wednesday, July 29, 2026at 2:00 pm (local time).
All answers to inquiries will be posted on the County’s e-Procurement Portal. Bidders may also click “Follow” on this bid to receive an email notification when answers are posted. It is the responsibility of the bidder to check the website for answers to inquiries.
ADDENDUM
Only changes made in writing by addendum and posted to the County’s e-Procurement Portal will be considered official. Answers provided verbally should not be considered.
Bidders are required to register for an account via the County’s e-Procurement Portal hosted by OpenGov.
Once the bidder has completed registration, they will receive addenda notifications to their email by clicking
“Follow” on this project. Ultimately, it is the sole responsibility of each bidder to periodically check the site for any addenda at https://procurement.opengov.com/portal/greenwoodsc.
SCOPE OF WORK
PERFORMANCE STANDARDS
The selected A/E firm, as a portion of its required scope of services and prior to sumbitting its cost proposal will discuss and clarify with the Owner the cost breakdown of the Architect/Engineering Agreement with detailed cost components to address the Owner's project requirements. The selected firm will need to be able to provide the folloing categories of services:
• surveying,
• asbestos testing/survey of existing buildings
• geotechical exploration report,
• preliminary design,
• 50% design stage,
• 100% design stage (architectural, structural, landscaping and MEP drawings and specs)
• bidding assistance,
• construction administration
• construction closeout services
The selected A/E team shall address the particular laws governing the development of buildings and/or fire stations in South Carolina, including, but not limited to:
• Building Codes,
• Greenwood County Zoning Ordinances, and
• Codes relative to SCDES and SCDOT standards
The selected A/E firm shall complete Greenwood County's code compliance review, which includes the following departments:
• Planning/Zoning,
• Engineering and
• Building Department
The selected A/E firm shall apply for and obtain any neccessary SCDES permits or SCDOT permits (especially encroachment, if necessary).
INFORMATION TO PROPOSERS
PROPOSERS RESPONSIBILITIES
Each Proposer shall become familiar with the project site, the scope of the proposed work, and the quantity of work and will be held responsible to examine, and to fully comply with all the Contract Documents, to be defined in the contract.
QUALIFICATION SUBMISSIONS
Response Submissions must be submitted electronically through the County’s e-Procurement Portal:
Greenwood County e-Procurement Portal on Thursday, August 13, 2026 at 2:00 pm(local time).
ACCEPTANCE OR REJECTION OF PROPOSALS
The County reserves the right to reject any or all proposals. Without limiting the generality of the foregoing, any proposal which is incomplete, obscure, conditional, or otherwise irregular, or which has erasures or corrections in prices, or in which unit prices are omitted or are obviously unbalanced, may be rejected.
However, the County Manager reserves the right to waive informalities on the basis of its best interests.
QUALIFICATIONS OF PROPOSERS
Before any award is made, the County may require satisfactory evidence to show that the Proposer is fully prepared in every way to perform the management, furnish specified labor, equipment, supplies, and certifications required to renovate this project. Proposers must be located within a reasonable distance of the project location to ensure minimal travel cost and timely response to problems that may occur after project completion.
LIMIT OF PROPOSAL WITHDRAWAL
No proposal may be withdrawn within NINETY (90) days after scheduled time for proposal submittal.
PAYMENT OF WAGES, RELEASE OF LIEN, AND PERIODIC PAYMENTS
The contractor shall pay all employees for all hours worked in accordance with applicable laws. Monthly invoices may be submitted for progress payments. County may request that each invoice shall include certified payrolls for all employees working on the project. Invoices for stored materials shall be accompanied by proof of the stored materials, i.e., invoices.
LOCATION OF WORK
The proposed project is located in Greenwood County, 5214 Highway 702, Ninety Six, SC, 29666 (Parcel ID #
7815-261-666).
COLLUSIVE PROPOSALS
More than one proposal or one contract from an individual, a firm or partnership, corporation, or an association under the same name or different names will not be considered. Reasonable grounds for believing that the Proposer is interested in more than one proposal for the same work will cause the rejection of all proposals in which such Proposer is interested. Any or all proposals will be rejected if there is any reason for believing that collusion exists among any of the Proposers; participants in such collusion will not be considered in future proposals.
PROHIBITION OF GRATUITIES
It shall be unethical for any person to offer, give, or agree to give any County employee, or for any County employee to solicit, demand, accept, or agree to accept from another person, a gratuity or an offer of employment in connection with any decision, approval, disapproval, recommendation, or preparation of any part of a purchase request, influencing the content of any specification or procurement standard, rendering of advice, investigation, auditing, or in any other advisory capacity in any proceeding or application, request for ruling, determination, claim or controversy, or other particular matter, pertaining to any program requirement or an agreement or subcontract, or to any solicitation or qualification therefore.
RIGHT TO PROTEST
Any prospective bidder or offeror who is aggrieved in connection with the solicitation of a contract or intended award shall protest to the Procurement Officer. The protest must be in writing, submitted to the
Procurement Officer, and shall set forth the grounds of the protest and the relief requested with enough particularity to give notice of the issues to be decided. Protests must be received by mail or hand delivered within seven (7) days from the date of intended award to the following address:
Greenwood County Annex
Attn: Anita Baylor, Procurement Officer
1025 Deadfall Rd East
Greenwood, SC 29649
AWARD OF CONTRACT
All bidders must certify that if awarded a contract they will comply with all applicable provisions of The Drug-free Workplace Act, Title 44, Chapter 107 of the South Carolina Code of Laws, as amended.
INSURANCE
Successful Proposer shall be required to provide insurance as stated below and as required by other provisions of the RFQ. This insurance is to be on the comprehensive form, shall protect the Successful Proposer, and shall be written to include Greenwood County against any/all claims arising from injuries to the public, or damage to property of others arising out of any act or omission of the Successful Proposer, its agents, employees or subcontractors.
The required insurance policy must be written by a company licensed to do business in the State of South
Carolina at the time of issue.
The information described below sets forth minimum amounts and coverages and is not to be construed in any way as a limitation on the Successful Proposer’s liability.
Workman's Compensation and Employer’s Liability Insurance
The Successful Proposer and all Subcontractors shall carry Workman’s Compensation and Employer’s Liability
Insurance covering all employees employed by him or Subcontractors in accordance with the Statutes of the
State of South Carolina and any applicable laws, while engaged under any awarded Contract issued from this
RFQ.
Statutory Limits, Employers Liability- $100,000 minimum
Comprehensive General Liability Insurance
General liability coverage as required in the RFQ shall contain no exclusion relative to blasting, explosion, collapse of buildings, or damage to underground property.
The Successful Proposer shall carry comprehensive general liability insurance with limits of liability not less than:
Bodily Injury:
$1,000,000.00 - Each Person
$1,000,000.00 - Each Accident
Property Damage:
$1,000,000.00 - Each Accident
$1,000,000.00 - Aggregate
Fleet Liability
The Contractor shall carry a comprehensive fleet liability policy with limits of liability not less than:
Bodily Injury:
$1,000,000.00 - Each Person
$1,000,000.00 - Each Accident
Property Damage: $1,000,000.00 - Each Accident
Fire, Windstorm, and Vandalism
Fire, Windstorm, and Vandalism insurance shall be carried and maintained by the Successful Proposer in the name of the Owner and Successful Proposer as their interest may appear.
The Successful Proposer and Subcontractors shall submit certificates of insurance to the Owner at the same time as signed contracts and bonds.
AGREEMENT REQUIREMENTS
S.C. LAW CLAUSE
Upon award of an agreement for these services, the person, partnership, association, or corporation to whom the award is made must comply with local and State laws which require such person or entity to be authorized and/or licensed to do business in Greenwood County. Notwithstanding the fact that applicable statutes may exempt or exclude the successful company from requirements excluding the company from being authorized and/or licensed to do business in Greenwood County, these requirements are in effect. By submission of this signed proposal, the company agrees to subject itself to the jurisdiction and process of the Eighth Judicial
Circuit Court of Greenwood County, as to all matters and disputes arising or to arise under the agreement and the performance thereof including any questions as to the liability for taxes, licenses or fees levied by State or local government.
COMPANY RESPONSIBILITY
Each company shall fully acquaint itself with conditions relating to the scope and restrictions attending the execution of the work under the conditions of this Request for Qualifications. The failure or omission of a company to acquaint itself with existing conditions shall in no way relieve them of any obligation with respect to this Request for Qualifications or to the agreement.
AFFIRMATIVE ACTION
The company will take affirmative action in complying with all Federal and State requirements concerning fair employment and employment of the disabled and concerning the treatment of all employees, without regard or discrimination by reason of race, religion, sex, national origin, or physical disability.
PRIME CONTRACTOR RESPONSIBILITIES
The Company will be required to assume sole responsibility for the complete effort, as required by this RFQ.
The County will consider the company to be the sole point of contact with regard to contractual matters.
SUBCONTRACTING
If any part of the work covered by this RFQ is to be subcontracted, the company shall identify the subcontracting organization and the contractual arrangements made with same. All subcontractors must be approved by the County. The successful company will also furnish the corporate or company name and the names of the officers of any subcontractors engaged by the vendor. The County reserves the right to reject any or all subcontractors and require substitution of a firm qualified to participate in the work as specified herein. Subcontractors will be bound by this agreement and this obligation must be included in Prime and
Subcontractors agreements.
OWNERSHIP OF MATERIAL
Ownership of all data, material, and documentation; including, but not limited to, architectural plans and drawings, originated and prepared for the County pursuant to this agreement shall belong exclusively to the
County. The County has the ability to utilize all data, material, and documentation in any manner or format deemed in the best interest of the County in the County’s sole discretion for this project and for any future project as determined in the best interest of Greenwood County. The use and/or reuse shall be at no additional cost to Greenwood County.
NONRESIDENT TAXPAYERS
If the company is a South Carolina nonresident taxpayer and the agreement amount is $10,000 or more, the company acknowledges and understands that in the event it is awarded an agreement, the Company shall submit a Nonresident Taxpayer Registration Affidavit (State form #1-312-6/94), before an agreement can be signed. Affidavit must certify that the nonresident taxpayer is registered with the S.C. Department of Revenue or the S.C. Secretary of State’s Office, in accordance with Section 12-9-310(A) (2) (3) of S.C. Code of Laws
(1976) as amended.
INDEMNITY
The Company hereby agrees to indemnify and save harmless the County, its officers, agents, and employees from and against any and all liability, claims, demands, damages, fines, fees, expenses, penalties, suits, proceedings, actions and cost of actions, including attorney’s fees for trial and on appeal of any kind and nature arising or growing out of or in any way connected with the performance of the Agreement, whether by act of omissions of the company, its agents, servants, employees or others, or because of or due to the mere existence of the Agreement between the parties.
TERMINATION FOR DEFAULT
The County Manager has the right to terminate for default if the company fails to perform the Work, if the company fails to perform the Work within the time specified in the Agreement, or if the company fails to perform any other provisions of the Agreement. If exercised, the County becomes the owner of documents that are paid for and may utilize them in any manner the County deems appropriate.
TERMINATION FOR CONVENIENCE
The County may without cause terminate this agreement in whole or in part at any time for its convenience. In such instance, an adjustment shall be made to the company for the reasonable costs of the work performed through the date of termination. Termination costs do not include lost profits, consequential damages, delay damages, unabsorbed or under absorbed overhead of the company or its subcontractors. The failure of the
Company to include a termination for convenience clause into its subcontracts and material purchase orders shall not expose the County to liability for lost profits in conjunction with a termination for convenience settlement or equitable adjustment. The company expressly waives any claims for lost profit or consequential damages, delay damages, or indirect costs which may arise from the County’s election to terminate this agreement in whole or in part for its convenience. The County has the ability to utilize all data, material, and documentation in any manner or format deemed in the best interest of the County in the County’s sole discretion.
NON-APPROPRIATION OF FUNDS
This agreement shall be subject to the availability and appropriation of funds by Management, and
Greenwood County Council. If County Council does not appropriate the funding needed for this product, Greenwood County will not be obligated to pay the contract price. No act or omission by Greenwood County, which is attributable to non-appropriation of funds, shall constitute a breach of or default under this agreement.
LIQUIDATED DAMAGES
The Contractor agrees and acknowledges that the County shall retain the sum of Two Hundred and no/100
($200.00) from the amount of compensation to be paid to Contractor for each calendar day that actual
Substantial Completion exceeds the Contract Time for Substantial Completion. This amount is agreed upon as the proper measure of Liquidated Damages, which the County sustains per day by the failure of the Contractor to complete the Work in the stipulated time and is not to be construed in any sense as a penalty. Time is of the essence.
SUBSTANTIAL COMPLETION
Substantial Completion is the stage in the progress of the Work when the Work or a designated portion thereof is sufficiently complete in accordance with the Agreement so that the County can occupy or utilize the project for its intended use.
PROPOSAL CONTENT AND SELECTION PROCESS
All qualification statements must be submitted by an authorized representative who certifies having read this
Request for Qualifications (RFQ) in its entirety and who has the legal authority to bind the entity.
PROPOSAL CONTENTS
To facilitate review of your Qualification Statement by Greenwood County, it is requested that your submission be no longer than fifteen (15) pages and conform to the following format:
A. Bid Holding and Authorization Form – Proposers must download and complete the Bid Holding and
Authorization Form located in the VENDOR SUBMISSION CHECKLIST section of this RFQ.
B. Experience of the Firm – provide a listing of your team’s prior experience and qualifications in renovations for projects similar in size, scope, and complexity. Provide a list of similar projects completed within the past 5 years.
C. References – Provide the name, address, and contact information for at least three (3) references familiar with the quality of the work completed by the Contractor on similar projects or projects with similar elements.
INSURANCE
Provide a a copy of the firm’s certificate of insurance, showing the firm’s current limits of commercial general liability, employer’s liability, business automobile liability and professional liability.
Upload a copy of your Certificate of Insurance in the VENDOR SUBMISSION CHECKLIST section of this RFP.
PROPRIETARY INFORMATION
Companies must clearly mark as “Confidential” each part of their submittal which they consider to be proprietary information that could be exempt from disclosure under Section 30-4-40, Code of Laws of South
Carolina, 1976 as amended (Freedom of Information Act). If any part is designated as “confidential”, there must be attached to that part an explanation of how this information fits within one or more categories listed in Section 30-4-40.
Greenwood County reserves the right to determine whether this information should be exempt from disclosure and no legal action may be brought against Greenwood County and/or its agents for any determination in this regard.
SELECTION PROCESS
Upon receipt of the Qualification Statement packages from each General Contract, Greenwood County
Administration will verify that each submission is complete. Acceptable proposals will be forwarded to the
Selection Committee for evaluation.
https://procurement.opengov.com/portal/greenwoodsc/projects/281366/document?section=undefined https://procurement.opengov.com/portal/greenwoodsc/projects/281366/document?section=2714809
EVALUATION CRITERIA
No. Evaluation Criteria Scoring Method Weight (Points)
1. Previous Experience with Comparable
Projects
Knowledge of, and experience with, the design of Fire Stations and/or Emergency Services
Buildings.
Points Based 50 (50% of Total)
2. Qualificatoins and Experience of Individuals
Directly Involved with the Project Points Based 25
(25% of Total)
3. REFERENCES
Information gathered from three provided references for which the firm has performed similar work.
Points Based 15 (15% of Total)
4. Proximity of the Firm to the Project Site
Also referred to as "local preference".
Points Based 10 (10% of Total)
TERMS OF CONTRACT
A. All entries shall remain firm for a period of not less than ninety (90) days.
B. This solicitation does not commit Greenwood County to award an agreement, to pay any costs incurred in the preparation of a qualification and of any supplementary presentation, or to procure or contract for the articles of goods or services. Greenwood County reserves the right to accept or reject any or all Requests for Qualifications received as a result of this solicitation, to negotiate with all qualified firms, or to cancel in part or in its entirety this solicitation if it is in the best interest of the
County to do so.
C. The contract agreement will be made between the County and the successful Design Professionals on the County standard contract forms.
D. A contract may be awarded to the Proposer whose statement of qualification is within the competitive range and determined to be in the best interest of Greenwood County.
E. Greenwood County reserves the right to accept or reject any and all proposals received in response to this Request for Qualification. Greenwood County will not pay for any costs incurred by the submitting
Design Professionals in preparation of a response to the Request for Qualifications, or any costs associated with negotiations prior to the awarding of a contract.
F. Greenwood County reserves the right to cancel this Request for Qualifications, or cancel any negotiations resulting from this RFQ, or decline to enter into a contract for the proposed work of this project is such action if deemed to be in the best interest of the County.
G. Greenwood County reserves the right to retain all proposals submitted and to use any ideas in a proposal regardless of whether that proposal is selected. Submission of a proposal indicates acceptance by the company of the conditions contained in this Request for Qualifications unless clearly and expressly noted in the proposal submitted and confirmed in the contract between Greenwood
County and the firm selected.
H. Failure to submit all required information may in the sole determination of Greenwood County be deemed as a nonresponsive proposal.
VENDOR SUBMISSION CHECKLIST
Bid Holding & Authorization Form*
Please download the below documents, complete, and upload.
• Bid_Holding_and_Authorizati...
*Response required
Cover Sheet
List the project title, A/E firm or team name(s), address, telephone number, and name of a contact person for any questions concerning the submittal.
Experience of Firm*
Upload your Experience of your Firm here.
*Response required
Qualifications and Experience of Individuals Directly Involved with Project*
Upload the individuals that will be directly involved with this design project and give a description of their qualifications and experience.
*Response required
References*
Upload your References here.
*Response required
Certificate of Insurance*
Upload a copy of your Certificate(s) of Insurance here.
*Response required
Drug Free Workplace Certification*
By submitting a Bid, the Bidder certifies that, if awarded a contract, the Bidder will comply with all applicable provisions of The Drug-free Workplace Act, Title 44, Chapter 107 of the South Carolina Code of Laws, as amended.
☐ Please confirm
*Response required
Non-Discrimination Statement*
The Company certifies that:
• No person shall be excluded from participation in, denied the benefit of, or otherwise discriminated against on the basis of race, color, national origin, or gender in connection with any RFQ submitted to
Greenwood County or the performance of any agreement resulting there from.
https://government-project.s3.us-west-2.amazonaws.com/150218/5ec69060-4c9d-45ea-ae3a-ad026d926c60_Bid_Holding_and_Authorization_Form.docx?X-Amz-Algorithm=AWS4-HMAC-SHA256&X-Amz-Content-Sha256=UNSIGNED-PAYLOAD&X-Amz-Credential=ASIA47RIURE4HM4E46HR%2F20260716%2Fus-west-2%2Fs3%2Faws4_request&X-Amz-Date=20260716T192028Z&X-Amz-Expires=72000&X-Amz-Security-Token=IQoJb3JpZ2luX2VjEIP%2F%2F%2F%2F%2F%2F%2F%2F%2F%2FwEaCXVzLXdlc3QtMiJHMEUCIQCPC2cXjeQoE0dsPQIgQcpUgBn5frv5MfIld0XoOWjuAgIgaxYP3eQxjzp2tOfhBOD9p9UV55QU%2FfeNRb6TqqA2aYcqjAUITBACGgw4OTIzNjQ2ODc2NzIiDBbndB7qyEtRbi4uFCrpBCfstSNqppTOBZVKonq8BiMO0aYB%2BH4GogGytq42cMAtK%2BYD57oxDaFOPnIbvXkW02KyCWfyy%2B0mN46i2GnSBoFX2uxlGIETRAKg0IMre%2Fph4MnGH8Ea0tCBY3mDK2bsknp3%2FQLQzsIxrfNt7iBO4Pk0cJQWPER9hDmEqqhsd3bDA0y5rEmcG%2Bnbndqu6al%2BBC%2FrP823rQgwnvD0f6a2Z%2F8VWvy9llj4TyAjulcAa5trTBbSF2VV1%2FywKM2IGK0blcFeBVgntXpUtdNWzMAhmRZwC2QlYS0lHC1iPWVlGyYh42CWEYRHiFXniS%2Btj5S2PGQycmWrvSIWG8hRH8%2Fpnttkd786zWKH4oJ%2BUHcWMlvIasimd%2FHW8TVDY35E67C7ujT%2FfPnlralF1eSm8LcZcp2YDsOtWsWzNJjp9VoxZPqAzJkB%2F1mu0up%2BrRukD3x8yRAUAksJVAqn8ljZIlZCf6q1bOH5bpEgX%2FD3gMRb2Lok%2FtHs0RnCdABkj8k1RKoxO9Zo0Vx5%2FMlSMK3dnMkC5lJkhXaef7T%2BtTVcloPaSb56btD%2FtLRP%2F%2F7cK64ka3vMWir9%2FfNbktbBys0L3TXSyBWbGOBxqF%2BEVs8BGVnfJmbuqw8IIRVagkc6jz8ojjJAdPs2Tb6ZNVoD9UEEtjBVOCK9AXojSmU00f98VB3XllEJbGayI4b0NjtU94clR2RnGuvv2oAY8Gjd8OGHCoHQa5JDoSb5QK4mgyiMkR3uO1zHZFesiOFDYEHLD6hfSl8GarGHucpd7Lhqg6xCbSsLjG5md2gz%2B3kQ2K3oFj%2BYHqSTm%2FQUQ%2F3kNbD8MMfb5NIGOpkBM4Rx6X64xwBg242tCiOPYf%2F1BUyJplU4XoCbt8XSWXf6%2BaAL0HjAtGK0a3gFAejUHMKB1DT%2FRriD8Q20ww08EPT0ul47snMDbgZMBfKTZBD16hKppEOlySS8LROydvJB9gHdBpJCQ00CY6Oyw4YCQxHg0Qf5CPvbOOMQLXvVPfhdHJezRIearPJbcvpL%2B9CbvQbZQEvBdRW8&X-Amz-Signature=aca51441b11e16803b0630749bb59550c15f96b5eccfa02b7478515b349e419a&X-Amz-SignedHeaders=host&response-content-disposition=attachment%3B%20filename%3D%22Bid_Holding_and_Authorization_Form.docx%22&x-id=GetObject
• That it is and shall be the policy of this Company to provide equal opportunity to all businesspersons seeking to contract or otherwise interested in contracting with this Company, including those companies owned and controlled by racial minorities, cultural minorities, and women;
• In connection herewith, we acknowledge and warrant that this Company has been made aware of, understands and agrees to take affirmative action to provide such companies with the maximum practicable opportunities to do business with this Company.
• That the promises of non-discrimination as made and set forth herein shall be and are hereby deemed to be made as part of and incorporated by reference into any agreement or portion thereof which this company may hereafter obtain and;
• That the failure of this Company to satisfactorily discharge any of the promises of non-discrimination as made and set forth herein shall constitute a material breach of agreement entitling the Greenwood
County to declare the agreement in default and to exercise any and all applicable rights and remedies, including, but not limited to, cancellation of the agreement, termination of the agreement, suspension and debarment from future contracting opportunities, and withholding and or forfeiture of compensation due and owing on an agreement.
☐ Please confirm
*Response required
Copy of PROPOSAL CONTENT AND SELECTION PROCESS
All qualification statements must be submitted by an authorized representative who certifies having read this
Request for Qualifications (RFQ) in its entirety and who has the legal authority to bind the entity.
PROPOSAL CONTENTS
To facilitate review of your Qualification Statement by Greenwood County, it is requested that your submission be no longer than fifteen (15) pages and conform to the following format:
A. Cover Sheet – list project title, General Contract name, address, telephone number, and name of a contact person for questions concerning the Qualification submitted.
B. Experience of the Firm – provide a listing of your team’s prior experience and qualifications in renovations for projects similar in size, scope, and complexity. Provide a list of similar projects completed within the past 5 years.
C. References – Provide the name, address, and contact information for at least three (3) references familiar with the quality of the work completed by the Contractor on similar projects or projects with similar elements.
PROPOSAL CONTENTS
To facilitate review of your Qualification Statement by Greenwood County, it is requested that your submission be no longer than fifteen (15) pages and conform to the following format:
A. Bid Holding and Authorization Form – Proposers must download and complete the Bid Holding and
Authorization Form located in the VENDOR SUBMISSION CHECKLIST section of this RFQ.
B. Experience of the Firm – provide a listing of your team’s prior experience and qualifications in renovations for projects similar in size, scope, and complexity. Provide a list of similar projects completed within the past 5 years.
C. References – Provide the name, address, and contact information for at least three (3) references familiar with the quality of the work completed by the Contractor on similar projects or projects with similar elements.
INSURANCE
Provide a a copy of the firm’s certificate of insurance, showing the firm’s current limits of commercial general liability, employer’s liability, business automobile liability and professional liability.
Upload a copy of your Certificate of Insurance in the VENDOR SUBMISSION CHECKLIST section of this RFP.
PROPRIETARY INFORMATION
https://procurement.opengov.com/portal/greenwoodsc/projects/281366/document?section=undefined https://procurement.opengov.com/portal/greenwoodsc/projects/281366/document?section=2714809
Companies must clearly mark as “Confidential” each part of their submittal which they consider to be proprietary information that could be exempt from disclosure under Section 30-4-40, Code of Laws of South
Carolina, 1976 as amended (Freedom of Information Act). If any part is designated as “confidential”, there must be attached to that part an explanation of how this information fits within one or more categories listed in Section 30-4-40.
Greenwood County reserves the right to determine whether this information should be exempt from disclosure and no legal action may be brought against Greenwood County and/or its agents for any determination in this regard.
SELECTION PROCESS
Upon receipt of the Qualification Statement packages from each General Contract, Greenwood County
Administration will verify that each submission is complete. Acceptable proposals will be forwarded to the
Selection Committee for evaluation.
| INTRODUCTION |
| SUMMARY |
| TIMELINE |
| PRE-PROPOSAL MEETING |
| QUESTIONS |
| ADDENDUM |
| SCOPE OF WORK |
| PERFORMANCE STANDARDS |
| INFORMATION TO PROPOSERS |
| PROPOSERS RESPONSIBILITIES |
| QUALIFICATION SUBMISSIONS |
| ACCEPTANCE OR REJECTION OF PROPOSALS |
| QUALIFICATIONS OF PROPOSERS |
| LIMIT OF PROPOSAL WITHDRAWAL |
| PAYMENT OF WAGES, RELEASE OF LIEN, AND PERIODIC PAYMENTS |
| LOCATION OF WORK |
| COLLUSIVE PROPOSALS |
| PROHIBITION OF GRATUITIES |
| RIGHT TO PROTEST |
| AWARD OF CONTRACT |
| INSURANCE |
| AGREEMENT REQUIREMENTS |
| S.C. LAW CLAUSE |
| COMPANY RESPONSIBILITY |
| AFFIRMATIVE ACTION |
| PRIME CONTRACTOR RESPONSIBILITIES |
| SUBCONTRACTING |
| OWNERSHIP OF MATERIAL |
| NONRESIDENT TAXPAYERS |
| INDEMNITY |
| TERMINATION FOR DEFAULT |
| TERMINATION FOR CONVENIENCE |
| NON-APPROPRIATION OF FUNDS |
| LIQUIDATED DAMAGES |
| SUBSTANTIAL COMPLETION |
| PROPOSAL CONTENT AND SELECTION PROCESS |
| PROPOSAL CONTENTS |
| INSURANCE |
| PROPRIETARY INFORMATION |
| SELECTION PROCESS |
| EVALUATION CRITERIA |
| TERMS OF CONTRACT |
| VENDOR SUBMISSION CHECKLIST |
| Bid Holding & Authorization Form* |
| Cover Sheet |
| Experience of Firm* |
| Qualifications and Experience of Individuals Directly Involved with Project* |
| References* |
| Certificate of Insurance* |
| Drug Free Workplace Certification* |
| Non-Discrimination Statement* |
| Copy of PROPOSAL CONTENT AND SELECTION PROCESS |
| PROPOSAL CONTENTS |
| PROPOSAL CONTENTS |
| INSURANCE |
| PROPRIETARY INFORMATION |
| SELECTION PROCESS |
File details come from the government source that posted it. Updated .