Appendix 7.7 Construction Schedule.pdf

PDF 2 MB Posted

Attached to
Hadnot Point Initial Outfitting Project Federal contract opportunity
Solicitation number
W9127S20Q6002
Issued by
Department of the Army Corps of Engineers Engineering District Little Rock

About this file

This is a solicitation for initial outfitting services at Hadnot Point in North Carolina. The solicitation seeks quotes for outfitting spaces including furniture, fixtures, and equipment. Quotes are due by June 8, 2020. The requirement is set aside for competitive 8(a) small businesses. The solicitation will follow simplified acquisition procedures from FAR Parts 12 and 13. The NAICS code is 337127 and size standard is 500 employees. The solicitation and any amendments must be reviewed and acknowledged. The U.S. Army Corps of Engineers Engineering District in Little Rock is the contracting agency.

View the file

Other files for this federal contract opportunity

Other files attached to Hadnot Point Initial Outfitting Project, newest first.
File Type Posted
Appendix 7.6 - REVISED Bid Schedule W9127S20Q6002.xlsx XLSX spreadsheet
W9127S20Q6002 AMENDMENT 0002.pdf PDF
Appendix 7.12 LVS DWGS and Supplemental Cutshees.pdf PDF
W9127S20Q6002 ProjNet Report.pdf PDF
W9127S20Q6002 REVISED Solicitation.docx DOCX document
W9127S20Q6002 AMENDMENT 0001.pdf PDF
Appendix 7.4 Submittal Examples.pdf PDF
W9127S20Q6002 Combined Synopsis Solicitation.pdf PDF
Appendix 7.8 CID.pdf PDF
Appendix 7.6 - Price Schedule.xlsx XLSX spreadsheet
Appendix 7.10 Equip Plans-List-Cutsheets Compressed.pdf PDF
Appendix 7.5 - Change Tracker.xlsx XLSX spreadsheet
Appendix 7.1 Glossary.pdf PDF
Appendix 7.9 SID.pdf PDF
Appendix 7.11 DMLSS.pdf PDF
Appendix 7.2 Monthly Risk Report.xlsx XLSX spreadsheet
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Activity ID Activity Name Orig Dur

Rem Dur

Compl

Early Start Early Finish Total Float

Scheduled Value

P4041 - Dental ClinP4041 - Dental ClinicP4041 - Dental ClinicP4041 - Dental ClinicP4041 - Dental ClinicP4041 - Dental ClinicP4041 - Dental ClinicP4041 - Dental ClinicP4041 - Dental Clinic Project MilestonesProject MilestonesProject MilestonesProject MilestonesProject MilestonesProject MilestonesProject MilestonesProject MilestonesProject Milestones

MILE 100 Project Award 0 0 0% 27-Sep-19 0 $0.00 MILE 105 Project NTP 0 0 0% 18-Oct-19 0 $0.00 MILE 110 Preconstruction/Partnering Meeting 1 1 0% 29-Oct-19 29-Oct-19 0 $10,000.00 MILE 115 SOG Completion 0 0 0% 07-May-20 0 $0.00 MILE 120 Structure Completion 0 0 0% 26-Aug-20 57 $0.00 MILE 125 Roof Dry-In 0 0 0% 07-Oct-20 73 $0.00 MILE 130 Glass Close-In 0 0 0% 21-Jan-21 87 $0.00 MILE 135 Energize 0 0 0% 28-Apr-21 25 $0.00 MILE 140 Red Zone Mtg Kick-off (approx. - to be scheduled mutually by all pa 1 1 0% 28-Apr-21 28-Apr-21 89 $3,500.00 MILE 145 HVAC Start-Up 0 0 0% 13-May-21 54 $0.00 MILE 150 BOD 0 0 0% 04-Oct-21 0 $0.00 MILE 155 Facility Operational 0 0 0% 19-Oct-21 0 $0.00 MILE 160 Demo Exist Facilities Complete & Contract Complete (CCD = 30Oct 0 0 0% 29-Oct-21* 0 $0.00

PreconstructionPreconstructionPreconstructionPreconstructionPreconstructionPreconstructionPreconstructionPreconstructionPreconstruction Generation & SubmGeneration & Submission of Key SubmittalsGeneration & Submission of Key SubmittalsGeneration & Submission of Key SubmittalsGeneration & Submission of Key SubmittalsGeneration & Submission of Key SubmittalsGeneration & Submission of Key SubmittalsGeneration & Submission of Key SubmittalsGeneration & Submission of Key Submittals

SUB 100 Generate & Submit QC Plan, Safety Plan, Environmental Plan & C 15 15 0% 09-Oct-19 29-Oct-19 31 $30,000.00 SUB 105 Generate & Submit AHU Submittals 40 40 0% 18-Oct-19 17-Dec-19 60 $3,500.00 SUB 110 Generate & Submit CFMF Shop Drawings 40 40 0% 18-Oct-19 17-Dec-19 83 $8,250.00 SUB 115 Generate & Submit Masonry Veneer Submittals/Mockup 40 40 0% 18-Oct-19 17-Dec-19 98 $7,500.00 SUB 120 Generate & Submit Doorframe Submittals (for masonry) 40 40 0% 18-Oct-19 17-Dec-19 117 $3,500.00 SUB 125 Generate & Submit SSM Roofing Submittals 40 40 0% 18-Oct-19 17-Dec-19 184 $3,500.00 SUB 130 Generate & Submit Windows/Storefront Submittals 40 40 0% 18-Oct-19 17-Dec-19 186 $3,500.00 SUB 135 Generate & Submit ATU & FCU Submittals 40 40 0% 18-Oct-19 17-Dec-19 200 $3,500.00 SUB 140 Generate & Submit Spray Fireproofing Submittals 40 40 0% 18-Oct-19 17-Dec-19 200 $3,500.00 SUB 145 Generate & Submit GFRC Submittals 40 40 0% 18-Oct-19 17-Dec-19 227 $3,500.00 SUB 150 Generate & Submit Boiler Submittals 40 40 0% 18-Oct-19 17-Dec-19 236 $3,500.00 SUB 155 Generate & Submit HVAC Pump Submittals 40 40 0% 18-Oct-19 17-Dec-19 236 $3,500.00 SUB 160 Generate & Submit Exterior Framing Submittals/Design 40 40 0% 18-Oct-19 17-Dec-19 236 $3,500.00 SUB 165 Generate & Submit Sprinkler Design 40 40 0% 18-Oct-19 17-Dec-19 240 $10,000.00 SUB 170 Generate & Submit Chiller Submittals 40 40 0% 18-Oct-19 17-Dec-19 262 $3,500.00 SUB 175 Generate & Submit Prefinished Metal Cornice Submittals 40 40 0% 18-Oct-19 17-Dec-19 268 $3,500.00 SUB 180 Generate & Submit Controls Submittals 40 40 0% 18-Oct-19 17-Dec-19 294 $3,500.00 SUB 185 Generate & Submit ACT Submittals 40 40 0% 18-Oct-19 17-Dec-19 295 $3,500.00 SUB 190 Generate & Submit Lighting Submittals 40 40 0% 18-Oct-19 17-Dec-19 302 $5,000.00 SUB 195 Generate & Submit Xfrmer Submittals 40 40 0% 18-Oct-19 17-Dec-19 302 $3,500.00 SUB 200 Generate & Submit Doors/Hardware Submittals 40 40 0% 18-Oct-19 17-Dec-19 314 $5,000.00 SUB 205 Generate & Submit Elevator Submittals 40 40 0% 18-Oct-19 17-Dec-19 316 $5,000.00 SUB 210 Generate & Submit Casework/Millwork Submittals 40 40 0% 18-Oct-19 17-Dec-19 326 $3,500.00 SUB 215 Generate & Submit Plumbing Fixture Submittals 40 40 0% 18-Oct-19 17-Dec-19 331 $3,500.00 SUB 220 Generate & Submit Flooring Submittals 40 40 0% 18-Oct-19 17-Dec-19 341 $3,500.00 SUB 225 Generate & Submit F/A Submittals 40 40 0% 18-Oct-19 17-Dec-19 341 $5,000.00 SUB 230 Generate & Submit Telecom Submittals 40 40 0% 18-Oct-19 17-Dec-19 345 $3,500.00 SUB 235 Generate & Submit Security System Submittals 40 40 0% 18-Oct-19 17-Dec-19 345 $5,000.00 SUB 240 Prepare & Submit Foundation Rebar Shop Drawings 15 15 0% 30-Oct-19 20-Nov-19 27 $5,000.00

Oct Nov Dec Jan Feb Mar Apr M Jun Jul Aug Sep Oct Nov Dec Jan F Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2020 2021

Project Award Project NTP

Preconstruction/Partnering Meeting SOG Completion

Structure Completion Roof Dry-In

Glass Close-In Energize Red Zone Mtg Kick-off (approx. - to be s

HVAC Start-Up

BOD

Facility Op Demo Ex

Generate & Submit QC Plan, Safety Plan, Environmental Plan & CPM Schedule Generate & Submit AHU Submittals Generate & Submit CFMF Shop Drawings Generate & Submit Masonry Veneer Submittals/Mockup Generate & Submit Doorframe Submittals (for masonry) Generate & Submit SSM Roofing Submittals Generate & Submit Windows/Storefront Submittals Generate & Submit ATU & FCU Submittals Generate & Submit Spray Fireproofing Submittals Generate & Submit GFRC Submittals Generate & Submit Boiler Submittals Generate & Submit HVAC Pump Submittals Generate & Submit Exterior Framing Submittals/Design Generate & Submit Sprinkler Design Generate & Submit Chiller Submittals Generate & Submit Prefinished Metal Cornice Submittals Generate & Submit Controls Submittals Generate & Submit ACT Submittals Generate & Submit Lighting Submittals Generate & Submit Xfrmer Submittals Generate & Submit Doors/Hardware Submittals Generate & Submit Elevator Submittals Generate & Submit Casework/Millwork Submittals Generate & Submit Plumbing Fixture Submittals Generate & Submit Flooring Submittals Generate & Submit F/A Submittals Generate & Submit Telecom Submittals Generate & Submit Security System Submittals

Prepare & Submit Foundation Rebar Shop Drawings

Remaining Level of Effort Actual Work Remaining Work

Critical Remaining Work Milestone

P4041 Dental/Medical Clinics - Camp Lejeune Whiting-Turner Contracting Company

Proposed Baseline Schedule - Full Detail & Scheduled Values

Attachment A

Rem Dur

Compl

Early Start Early Finish Total Float

Scheduled Value

SUB 245 Generate & Submit Demo & Abatement Submittals 20 20 0% 30-Oct-19 27-Nov-19 0 $5,000.00 SUB 250 Prepare & Submit Structural Steel Shop Drawings 20 20 0% 30-Oct-19 27-Nov-19 34 $10,000.00 SUB 255 Generate & Submit MDP Submittals 40 40 0% 30-Oct-19 02-Jan-20 256 $3,500.00 SUB 260 Generate & Submit Generator Submittals 40 40 0% 30-Oct-19 02-Jan-20 295 $3,500.00 SUB 265 Generate & Submit Exterior Finishes Board 40 40 0% 18-Nov-19 21-Jan-20 164 $3,500.00

NAVFAC Review & ANAVFAC Review & Approval of Key SubmittalsNAVFAC Review & Approval of Key SubmittalsNAVFAC Review & Approval of Key SubmittalsNAVFAC Review & Approval of Key SubmittalsNAVFAC Review & Approval of Key SubmittalsNAVFAC Review & Approval of Key SubmittalsNAVFAC Review & Approval of Key SubmittalsNAVFAC Review & Approval of Key Submittals REV 100 NAVFAC Review & Approve QC Plan, Safety Plan, Environmental P 20 20 0% 30-Oct-19 27-Nov-19 31 $500.00 REV 105 NAVFAC Review & Approve Foundation Rebar Shop Drawings 20 20 0% 21-Nov-19 20-Dec-19 27 $500.00 REV 110 NAVFAC Review & Approve Structural Steel Shop Drawings 20 20 0% 02-Dec-19 02-Jan-20 34 $500.00 REV 115 NAVFAC Review & Approve Demo & Abatement Submittals 30 30 0% 02-Dec-19 16-Jan-20 0 $500.00 REV 120 NAVFAC Review & Approve Demo & Abatement Submittals 30 30 0% 02-Dec-19 16-Jan-20 0 $500.00 REV 125 NAVFAC Review & Approve AHU Submittals 20 20 0% 18-Dec-19 21-Jan-20 60 $500.00 REV 130 NAVFAC Review & Approve CFMF Shop Drawings 20 20 0% 18-Dec-19 21-Jan-20 83 $500.00 REV 135 NAVFAC Review & Approve Masonry Veneer Submittals/Mockup 20 20 0% 18-Dec-19 21-Jan-20 98 $500.00 REV 140 NAVFAC Review & Approve Doorframe Submittals (for masonry) 20 20 0% 18-Dec-19 21-Jan-20 117 $500.00 REV 145 NAVFAC Review & Approve SSM Roofing Submittals 20 20 0% 18-Dec-19 21-Jan-20 184 $500.00 REV 150 NAVFAC Review & Approve Windows/Storefront Submittals 20 20 0% 18-Dec-19 21-Jan-20 186 $500.00 REV 155 NAVFAC Review & Approve ATU & FCU Submittals 20 20 0% 18-Dec-19 21-Jan-20 200 $500.00 REV 160 NAVFAC Review & Approve Spray Fireproofing Submittals 20 20 0% 18-Dec-19 21-Jan-20 200 $500.00 REV 165 NAVFAC Review & Approve GFRC Submittals 20 20 0% 18-Dec-19 21-Jan-20 227 $500.00 REV 170 NAVFAC Review & Approve Boiler Submittals 20 20 0% 18-Dec-19 21-Jan-20 236 $500.00 REV 175 NAVFAC Review & Approve HVAC Pump Submittals 20 20 0% 18-Dec-19 21-Jan-20 236 $500.00 REV 180 NAVFAC Review & Approve Exterior Framing Submittals/Design 20 20 0% 18-Dec-19 21-Jan-20 236 $500.00 REV 185 NAVFAC Review & Approve Chiller Submittals 20 20 0% 18-Dec-19 21-Jan-20 262 $500.00 REV 190 NAVFAC Review & Approve Prefinished Metal Cornice Submittals 20 20 0% 18-Dec-19 21-Jan-20 268 $500.00 REV 195 NAVFAC Review & Approve Controls Submittals 20 20 0% 18-Dec-19 21-Jan-20 294 $500.00 REV 200 NAVFAC Review & Approve ACT Submittals 20 20 0% 18-Dec-19 21-Jan-20 295 $500.00 REV 205 NAVFAC Review & Approve Lighting Submittals 20 20 0% 18-Dec-19 21-Jan-20 302 $500.00 REV 210 NAVFAC Revuew & Approve Xfrmer 20 20 0% 18-Dec-19 21-Jan-20 302 $500.00 REV 215 NAVFAC Review & Approve Doors/Hardware Submittals 20 20 0% 18-Dec-19 21-Jan-20 314 $500.00 REV 220 NAVFAC Review & Approve Elevator Submittals 20 20 0% 18-Dec-19 21-Jan-20 316 $500.00 REV 225 NAVFAC Review & Approve Casework/Millwork Submittals 20 20 0% 18-Dec-19 21-Jan-20 326 $500.00 REV 230 NAVFAC Review & Approve Plumbing Fixtures Submittals 20 20 0% 18-Dec-19 21-Jan-20 331 $500.00 REV 235 NAVFAC Review & Approve Flooring Submittals 20 20 0% 18-Dec-19 21-Jan-20 341 $500.00 REV 240 NAVFAC Review & Approve F/A Submittals 20 20 0% 18-Dec-19 21-Jan-20 341 $500.00 REV 245 NAVFAC Review & Approve Telecom Submittals 20 20 0% 18-Dec-19 21-Jan-20 345 $500.00 REV 250 NAVFAC Review & Approve Security System Submittals 20 20 0% 18-Dec-19 21-Jan-20 345 $500.00 REV 255 NAVFAC Review & Approve Sprinkler Design 30 30 0% 18-Dec-19 04-Feb-20 240 $500.00 REV 260 NAVFAC Review & Approve MDP Submittals 20 20 0% 03-Jan-20 31-Jan-20 256 $500.00 REV 265 NAVFAC Review & Approve Generator Submittals 20 20 0% 03-Jan-20 31-Jan-20 295 $500.00 REV 270 NAVFAC Review & Approve Exterior Finishes Board 20 20 0% 22-Jan-20 19-Feb-20 164 $500.00

Fabrication & AvailaFabrication & Availability of Key Materials / EquipmentFabrication & Availability of Key Materials / EquipmentFabrication & Availability of Key Materials / EquipmentFabrication & Availability of Key Materials / EquipmentFabrication & Availability of Key Materials / EquipmentFabrication & Availability of Key Materials / EquipmentFabrication & Availability of Key Materials / EquipmentFabrication & Availability of Key Materials / Equipment FAB 100 Fabrication & Availability of Foundation Rebar 15 15 0% 23-Dec-19 16-Jan-20 27 $0.00 FAB 105 Fabrication & Availability of Structural Steel 50 50 0% 03-Jan-20 16-Mar-20 34 $0.00 FAB 110 Fabrication & Availability of Exterior Framing Materials 10 10 0% 22-Jan-20 04-Feb-20 236 $0.00 FAB 115 Fabrication & Availability of CFMF Materials 40 40 0% 22-Jan-20 18-Mar-20 83 $0.00 FAB 120 Fabrication & Availability of AHUs (to be set during steel framing) 50 50 0% 22-Jan-20 01-Apr-20 60 $0.00

Oct Nov Dec Jan Feb Mar Apr M Jun Jul Aug Sep Oct Nov Dec Jan F Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2020 2021

Generate & Submit Demo & Abatement Submittals Prepare & Submit Structural Steel Shop Drawings

Generate & Submit MDP Submittals Generate & Submit Generator Submittals

Generate & Submit Exterior Finishes Board

NAVFAC Review & Approve QC Plan, Safety Plan, Environmental Plan & CPM Schedule NAVFAC Review & Approve Foundation Rebar Shop Drawings

NAVFAC Review & Approve Structural Steel Shop Drawings NAVFAC Review & Approve Demo & Abatement Submittals NAVFAC Review & Approve Demo & Abatement Submittals NAVFAC Review & Approve AHU Submittals NAVFAC Review & Approve CFMF Shop Drawings NAVFAC Review & Approve Masonry Veneer Submittals/Mockup NAVFAC Review & Approve Doorframe Submittals (for masonry) NAVFAC Review & Approve SSM Roofing Submittals NAVFAC Review & Approve Windows/Storefront Submittals NAVFAC Review & Approve ATU & FCU Submittals NAVFAC Review & Approve Spray Fireproofing Submittals NAVFAC Review & Approve GFRC Submittals NAVFAC Review & Approve Boiler Submittals NAVFAC Review & Approve HVAC Pump Submittals NAVFAC Review & Approve Exterior Framing Submittals/Design NAVFAC Review & Approve Chiller Submittals NAVFAC Review & Approve Prefinished Metal Cornice Submittals NAVFAC Review & Approve Controls Submittals NAVFAC Review & Approve ACT Submittals NAVFAC Review & Approve Lighting Submittals NAVFAC Revuew & Approve Xfrmer NAVFAC Review & Approve Doors/Hardware Submittals NAVFAC Review & Approve Elevator Submittals NAVFAC Review & Approve Casework/Millwork Submittals NAVFAC Review & Approve Plumbing Fixtures Submittals NAVFAC Review & Approve Flooring Submittals NAVFAC Review & Approve F/A Submittals NAVFAC Review & Approve Telecom Submittals NAVFAC Review & Approve Security System Submittals

NAVFAC Review & Approve Sprinkler Design NAVFAC Review & Approve MDP Submittals NAVFAC Review & Approve Generator Submittals

NAVFAC Review & Approve Exterior Finishes Board

Fabrication & Availability of Foundation Rebar Fabrication & Availability of Structural Steel

Fabrication & Availability of Exterior Framing Materials Fabrication & Availability of CFMF Materials

Fabrication & Availability of AHUs (to be set during steel framing)

Remaining Level of Effort Actual Work Remaining Work

Critical Remaining Work Milestone

P4041 Dental/Medical Clinics - Camp Lejeune Whiting-Turner Contracting Company

Proposed Baseline Schedule - Full Detail & Scheduled Values

Rem Dur

Compl

Early Start Early Finish Total Float

Scheduled Value

FAB 125 Fabrication & Availability of Masonry Veneer Materials 50 50 0% 22-Jan-20 01-Apr-20 98 $0.00 FAB 130 Fabrication & Availability of Doorframe Materials (for masonry) 50 50 0% 22-Jan-20 01-Apr-20 117 $0.00 FAB 135 Fabrication & Availability of ATUs & FCUs 50 50 0% 22-Jan-20 01-Apr-20 200 $0.00 FAB 140 Fabrication & Availability of Boilers 50 50 0% 22-Jan-20 01-Apr-20 236 $0.00 FAB 145 Fabrication & Availability of HVAC Pumps 50 50 0% 22-Jan-20 01-Apr-20 236 $0.00 FAB 150 Fabrication & Availability of Chillers 50 50 0% 22-Jan-20 01-Apr-20 262 $0.00 FAB 155 Fabrication & Availability of Prefinished Metal Cornice Components 50 50 0% 22-Jan-20 01-Apr-20 268 $0.00 FAB 160 Fabrication & Availability of Controls Systems 50 50 0% 22-Jan-20 01-Apr-20 294 $0.00 FAB 165 Fabrication & Availability of ACT Materials 50 50 0% 22-Jan-20 01-Apr-20 295 $0.00 FAB 170 Fabrication & Availability of Lightng Materials 50 50 0% 22-Jan-20 01-Apr-20 302 $0.00 FAB 175 Fabrication & Availability of Xfrmer 50 50 0% 22-Jan-20 01-Apr-20 302 $0.00 FAB 180 Fabrication & Availability of Doors/Hardware Materials 50 50 0% 22-Jan-20 01-Apr-20 314 $0.00 FAB 185 Fabrication & Availability of Elevator Materials 50 50 0% 22-Jan-20 01-Apr-20 316 $0.00 FAB 190 Fabrication & Availability of Casework/Millwork Materials 50 50 0% 22-Jan-20 01-Apr-20 326 $0.00 FAB 195 Fabrication & Availability of Plumbing Fixture Materials 50 50 0% 22-Jan-20 01-Apr-20 331 $0.00 FAB 200 Fabrication & Availability of Flooring Materials 50 50 0% 22-Jan-20 01-Apr-20 341 $0.00 FAB 205 Fabrication & Availability of F/A Materials 50 50 0% 22-Jan-20 01-Apr-20 341 $0.00 FAB 210 Fabrication & Availability of Telecom Materials 50 50 0% 22-Jan-20 01-Apr-20 345 $0.00 FAB 215 Fabrication & Availability of Security System Materials 50 50 0% 22-Jan-20 01-Apr-20 345 $0.00 FAB 220 Fabrication & Availability of MDP 40 40 0% 03-Feb-20 30-Mar-20 256 $0.00 FAB 225 Fabrication & Availability of Generator 50 50 0% 03-Feb-20 13-Apr-20 295 $0.00 FAB 230 Fabrication & Availability of Sprinkler Materials for R/Is 15 15 0% 05-Feb-20 26-Feb-20 240 $0.00 FAB 235 Fabrication & Availability of Sprinkler Equipment 15 15 0% 05-Feb-20 26-Feb-20 240 $0.00 FAB 240 Fabrication & Availability of SSM Roofing Materials 50 50 0% 20-Feb-20 29-Apr-20 164 $0.00 FAB 245 Fabrication & Availability of Windows/Storefront Systems 50 50 0% 20-Feb-20 29-Apr-20 166 $0.00 FAB 250 Fabrication & Availability of GFRC Components 50 50 0% 20-Feb-20 29-Apr-20 207 $0.00

Delivery/Payment foDelivery/Payment for Key Materials / EquipmentDelivery/Payment for Key Materials / EquipmentDelivery/Payment for Key Materials / EquipmentDelivery/Payment for Key Materials / EquipmentDelivery/Payment for Key Materials / EquipmentDelivery/Payment for Key Materials / EquipmentDelivery/Payment for Key Materials / EquipmentDelivery/Payment for Key Materials / Equipment DEL 100 Deliver Foundation Rebar 1 1 0% 16-Jan-20 16-Jan-20 27 $155,000.00 DEL 105 Deliver Structural Steel 1 1 0% 16-Mar-20 16-Mar-20 34 $1,200,000.00 DEL 110 Deliver CFMF Materials 1 1 0% 18-Mar-20 18-Mar-20 83 $165,000.00 DEL 115 Deliver Masonry Veneer Materials 1 1 0% 01-Apr-20 01-Apr-20 98 $280,000.00 DEL 120 Deliver Boilers 1 1 0% 01-Apr-20 01-Apr-20 236 $100,000.00 DEL 125 Deliver HVAC Pumps 1 1 0% 01-Apr-20 01-Apr-20 236 $75,000.00 DEL 130 Deliver AHUs (to be set during steel framing) 1 1 0% 02-Apr-20 02-Apr-20 60 $350,000.00 DEL 135 Deliver Xfrmr 1 1 0% 02-Apr-20 02-Apr-20 302 $60,000.00 DEL 140 Deliver Generator 1 1 0% 13-Apr-20 13-Apr-20 295 $150,000.00 DEL 145 Deliver Doorframe Materials (for masonry) 1 1 0% 07-May-20 07-May-20 91 $10,000.00 DEL 150 Deliver Chillers 1 1 0% 15-Jul-20 15-Jul-20 189 $300,000.00 DEL 155 Deliver SSM Roofing Materials 1 1 0% 07-Oct-20 07-Oct-20 52 $350,000.00 DEL 160 Deliver MDP 1 1 0% 07-Oct-20 07-Oct-20 123 $10,000.00 DEL 165 Deliver ATUs & FCUs 1 1 0% 04-Dec-20 04-Dec-20 30 $90,000.00 DEL 170 Deliver GFRC Components 1 1 0% 08-Dec-20 08-Dec-20 55 $95,000.00 DEL 175 Deliver Sprinkler Materials for R/Is 1 1 0% 11-Dec-20 11-Dec-20 40 $80,000.00 DEL 180 Deliver Sprinkler Equipment 1 1 0% 11-Dec-20 11-Dec-20 40 $30,000.00 DEL 185 Deliver Prefinished Metal Cornice Components 1 1 0% 14-Dec-20 14-Dec-20 92 $85,000.00 DEL 190 Deliver Windows/Storefront Systems 1 1 0% 21-Dec-20 21-Dec-20 5 $225,000.00 DEL 195 Deliver Exterior Framing Materials 1 1 0% 06-Jan-21 06-Jan-21 7 $490,000.00

Oct Nov Dec Jan Feb Mar Apr M Jun Jul Aug Sep Oct Nov Dec Jan F Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2020 2021

Fabrication & Availability of Masonry Veneer Materials Fabrication & Availability of Doorframe Materials (for masonry) Fabrication & Availability of ATUs & FCUs Fabrication & Availability of Boilers Fabrication & Availability of HVAC Pumps Fabrication & Availability of Chillers Fabrication & Availability of Prefinished Metal Cornice Components Fabrication & Availability of Controls Systems Fabrication & Availability of ACT Materials Fabrication & Availability of Lightng Materials Fabrication & Availability of Xfrmer Fabrication & Availability of Doors/Hardware Materials Fabrication & Availability of Elevator Materials Fabrication & Availability of Casework/Millwork Materials Fabrication & Availability of Plumbing Fixture Materials Fabrication & Availability of Flooring Materials Fabrication & Availability of F/A Materials Fabrication & Availability of Telecom Materials Fabrication & Availability of Security System Materials Fabrication & Availability of MDP

Fabrication & Availability of Generator Fabrication & Availability of Sprinkler Materials for R/Is Fabrication & Availability of Sprinkler Equipment

Fabrication & Availability of SSM Roofing Materials Fabrication & Availability of Windows/Storefront Systems Fabrication & Availability of GFRC Components

Deliver Foundation Rebar Deliver Structural Steel Deliver CFMF Materials

Deliver Masonry Veneer Materials Deliver Boilers Deliver HVAC Pumps Deliver AHUs (to be set during steel framing) Deliver Xfrmr

Deliver Generator Deliver Doorframe Materials (for masonry)

Deliver Chillers Deliver SSM Roofing Materials Deliver MDP

Deliver ATUs & FCUs Deliver GFRC Components Deliver Sprinkler Materials for R/Is Deliver Sprinkler Equipment Deliver Prefinished Metal Cornice Components Deliver Windows/Storefront Systems

Deliver Exterior Framing Materials

Remaining Level of Effort Actual Work Remaining Work

Critical Remaining Work Milestone

P4041 Dental/Medical Clinics - Camp Lejeune Whiting-Turner Contracting Company

Proposed Baseline Schedule - Full Detail & Scheduled Values

Rem Dur

Compl

Early Start Early Finish Total Float

Scheduled Value

DEL 200 Deliver ACT Materials 1 1 0% 12-Apr-21 12-Apr-21 40 $230,000.00 DEL 205 Deliver Lighting Materials 1 1 0% 21-Apr-21 21-Apr-21 40 $250,000.00 DEL 210 Deliver Plumbing Fixture Materials 1 1 0% 05-May-21 05-May-21 59 $375,000.00 DEL 215 Deliver F/A Materials 1 1 0% 05-May-21 05-May-21 69 $78,000.00 DEL 220 Deliver Telecom Materials 1 1 0% 05-May-21 05-May-21 73 $77,500.00 DEL 225 Deliver Security System Materials 1 1 0% 05-May-21 05-May-21 73 $75,000.00 DEL 230 Deliver Elevator Materials 1 1 0% 10-May-21 10-May-21 41 $240,000.00 DEL 235 Deliver Controls Systems 1 1 0% 13-May-21 13-May-21 31 $75,000.00 DEL 240 Deliver Doors/Hardware Materials 1 1 0% 13-May-21 13-May-21 36 $90,000.00 DEL 245 Deliver Casework/Millwork Materials 1 1 0% 13-May-21 13-May-21 48 $215,000.00 DEL 250 Deliver Flooring Materials 1 1 0% 04-Jun-21 04-Jun-21 48 $175,000.00

ConstructionConstructionConstructionConstructionConstructionConstructionConstructionConstructionConstruction Mobilization, InitialMobilization, Initial Erosion ControlMobilization, Initial Erosion ControlMobilization, Initial Erosion ControlMobilization, Initial Erosion ControlMobilization, Initial Erosion ControlMobilization, Initial Erosion ControlMobilization, Initial Erosion ControlMobilization, Initial Erosion Control

MOB 100 Mobilization of Offices to Site 8 8 0% 28-Nov-19 10-Dec-19 28 $50,000.00 MOB 105 Site Survey, Utility Locates & LOD Flagging 2 2 0% 09-Dec-19 10-Dec-19 28 $38,000.00 MOB 110 Construction Entrances & Initial E/C Measures 4 4 0% 11-Dec-19 17-Dec-19 28 $85,000.00

Building DemolitionBuilding DemolitionBuilding DemolitionBuilding DemolitionBuilding DemolitionBuilding DemolitionBuilding DemolitionBuilding DemolitionBuilding Demolition DEMO 100 Building Surveys Prior to Demolition 15 15 0% 23-Dec-19 16-Jan-20 0 $15,000.00 DEMO 105 Mobilize Abatement Subcontractor 10 10 0% 17-Jan-20 31-Jan-20 0 $0.00 DEMO 110 Asbestos & Lead Paint Abatement - Building 408 3 3 0% 03-Feb-20 05-Feb-20 0 $30,000.00 DEMO 115 IH Monitoring and Reports 3 3 0% 03-Feb-20 05-Feb-20 0 $25,000.00 DEMO 120 Asbestos & Lead Paint Abatement - Building 441 5 5 0% 06-Feb-20 12-Feb-20 9 $25,000.00 DEMO 125 Demo Building 408 9 9 0% 06-Feb-20 19-Feb-20 0 $157,500.00 DEMO 130 Demo Building 441 4 4 0% 13-Feb-20 19-Feb-20 8 $55,000.00 DEMO 135 Asbestos & Lead Paint Abatement - Building 331 5 5 0% 13-Feb-20 20-Feb-20 239 $25,000.00 DEMO 140 Asbestos & Lead Paint Abatement - Building 332 5 5 0% 21-Feb-20 27-Feb-20 239 $25,000.00 DEMO 145 Demo Building 331 4 4 0% 24-Feb-20 27-Feb-20 208 $48,000.00 DEMO 150 Demo Building 332 4 4 0% 02-Mar-20 05-Mar-20 208 $48,000.00

Initial Earthwork & Initial Earthwork & Building PadInitial Earthwork & Building PadInitial Earthwork & Building PadInitial Earthwork & Building PadInitial Earthwork & Building PadInitial Earthwork & Building PadInitial Earthwork & Building PadInitial Earthwork & Building Pad ES 100 Construct Building Pad 4 4 0% 20-Feb-20 26-Feb-20 0 $125,000.00 ES 105 Selective Demolition - Site Utilities 4 4 0% 20-Feb-20 26-Feb-20 225 $65,000.00 ES 110 Selective Demolition - Remaining Items 5' outside bldg' 12 12 0% 20-Feb-20 11-Mar-20 217 $180,000.00 ES 115 Initial grading and storm sewer - main site 16 16 0% 20-Feb-20 17-Mar-20 213 $215,000.00

Concrete/Masonry Concrete/Masonry FoundationsConcrete/Masonry FoundationsConcrete/Masonry FoundationsConcrete/Masonry FoundationsConcrete/Masonry FoundationsConcrete/Masonry FoundationsConcrete/Masonry FoundationsConcrete/Masonry Foundations FND 100 Concrete Foundations - Block 1 8 8 0% 27-Feb-20 11-Mar-20 0 $195,600.00 FND 105 Elevator Jackhole 2 2 0% 12-Mar-20 13-Mar-20 2 $22,000.00 FND 110 Perimeter Foundation Stem Walls - Block 1 8 8 0% 12-Mar-20 24-Mar-20 0 $112,000.00 FND 115 Concrete Foundations - Block 2 12 12 0% 16-Mar-20 02-Apr-20 2 $138,000.00 FND 120 Construct Elevator Pit 6 6 0% 01-Apr-20 08-Apr-20 10 $35,000.00 FND 125 Perimeter Foundation Stem Walls - Block 2 8 8 0% 03-Apr-20 15-Apr-20 2 $79,000.00

Below-Slab R/Is anBelow-Slab R/Is and SOGBelow-Slab R/Is and SOGBelow-Slab R/Is and SOGBelow-Slab R/Is and SOGBelow-Slab R/Is and SOGBelow-Slab R/Is and SOGBelow-Slab R/Is and SOGBelow-Slab R/Is and SOG SOG 100 Below-Slab Sprinkler R/I - Block 1 2 2 0% 27-Feb-20 02-Mar-20 6 $12,000.00 SOG 105 Below-Slab Plumbing R/I - Block 1 8 8 0% 18-Mar-20 31-Mar-20 0 $97,500.00 SOG 110 Below-Slab Electrical R/I - Block 1 8 8 0% 01-Apr-20 13-Apr-20 4 $174,000.00 SOG 115 Below-Slab Plumbing R/I - Block 2 12 12 0% 01-Apr-20 17-Apr-20 0 $100,500.00 SOG 120 Below-Slab HVAC Pipe R/I - Block 1 4 4 0% 14-Apr-20 17-Apr-20 4 $85,000.00 SOG 125 Below-Slab Electrical R/I - Block 2 4 4 0% 20-Apr-20 23-Apr-20 0 $138,000.00

Oct Nov Dec Jan Feb Mar Apr M Jun Jul Aug Sep Oct Nov Dec Jan F Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2020 2021

Deliver ACT Materials Deliver Lighting Materials

Deliver Plumbing Fixture Materials Deliver F/A Materials Deliver Telecom Materials Deliver Security System Materials Deliver Elevator Materials Deliver Controls Systems Deliver Doors/Hardware Materials Deliver Casework/Millwork Materials

Deliver Flooring Materials

Mobilization of Offices to Site Site Survey, Utility Locates & LOD Flagging Construction Entrances & Initial E/C Measures

Building Surveys Prior to Demolition Mobilize Abatement Subcontractor Asbestos & Lead Paint Abatement - Building 408 IH Monitoring and Reports Asbestos & Lead Paint Abatement - Building 441 Demo Building 408 Demo Building 441 Asbestos & Lead Paint Abatement - Building 331 Asbestos & Lead Paint Abatement - Building 332 Demo Building 331 Demo Building 332

Construct Building Pad Selective Demolition - Site Utilities

Selective Demolition - Remaining Items 5' outside bldg' Initial grading and storm sewer - main site

Concrete Foundations - Block 1 Elevator Jackhole

Perimeter Foundation Stem Walls - Block 1 Concrete Foundations - Block 2 Construct Elevator Pit Perimeter Foundation Stem Walls - Block 2

Below-Slab Sprinkler R/I - Block 1 Below-Slab Plumbing R/I - Block 1

Below-Slab Electrical R/I - Block 1 Below-Slab Plumbing R/I - Block 2 Below-Slab HVAC Pipe R/I - Block 1 Below-Slab Electrical R/I - Block 2

Remaining Level of Effort Actual Work Remaining Work

Critical Remaining Work Milestone

P4041 Dental/Medical Clinics - Camp Lejeune Whiting-Turner Contracting Company

Proposed Baseline Schedule - Full Detail & Scheduled Values

Rem Dur

Compl

Early Start Early Finish Total Float

Scheduled Value

SOG 130 Prep & Place SOG - All Sectors 12 12 0% 20-Apr-20 07-May-20 0 $190,000.00

Structural WorkStructural WorkStructural WorkStructural WorkStructural WorkStructural WorkStructural WorkStructural WorkStructural Work STR 100 Deliver Structural Steel & Shakeout 4 4 0% 04-May-20 07-May-20 0 $50,000.00 STR 105 Erect Structural Steel Framing - 1st Half 8 8 0% 08-May-20 20-May-20 0 $99,500.00 STR 110 2nd Floor Decking & Steel Detailing - 1st Half 4 4 0% 21-May-20 27-May-20 4 $39,000.00 STR 115 Erect Structural Steel Framing - 2nd Half 8 8 0% 21-May-20 03-Jun-20 0 $89,500.00 STR 120 2nd Floor Decking & Steel Detailing - 2nd Half 4 4 0% 04-Jun-20 09-Jun-20 0 $42,000.00 STR 125 2nd Floor Studs 2 2 0% 10-Jun-20 11-Jun-20 0 $0.00 STR 130 Test Studs & Submit Report 2 2 0% 11-Jun-20 15-Jun-20 0 $0.00 STR 135 Prep & Place SOMD - 1st Half 4 4 0% 16-Jun-20 22-Jun-20 0 $65,000.00 STR 140 Prep & Place SOMD - 2nd Half 4 4 0% 18-Jun-20 24-Jun-20 0 $65,000.00 STR 145 Cure SOMD - 1st Half 3 3 0% 23-Jun-20 25-Jun-20 0 $0.00 STR 150 Erect High Roof Framing - structural steel 8 8 0% 25-Jun-20 08-Jul-20 0 $85,000.00 STR 155 Set & Protect AHUs 1a, 1b & 2 for 2nd Floor Mech Rm 3 3 0% 29-Jun-20 01-Jul-20 0 $35,000.00 STR 160 Attic-Level Steel Decking 8 8 0% 02-Jul-20 15-Jul-20 0 $41,500.00 STR 165 Erect Light Gauge Metal Trusses 12 12 0% 16-Jul-20 05-Aug-20 0 $122,000.00 STR 170 High Roof Decking 8 8 0% 13-Aug-20 26-Aug-20 12 $58,000.00 STR 175 Install Low-Roof Light-Gauge Metal Framing & Deck 12 12 0% 03-Sep-20 23-Sep-20 0 $80,000.00

Roofing & Roof-ToRoofing & Roof-Top WorkRoofing & Roof-Top WorkRoofing & Roof-Top WorkRoofing & Roof-Top WorkRoofing & Roof-Top WorkRoofing & Roof-Top WorkRoofing & Roof-Top WorkRoofing & Roof-Top Work RF 100 Install Permanent Fall Protection System 8 8 0% 27-Aug-20 10-Sep-20 53 $60,000.00 RF 105 Roof Edge Blocking 16 16 0% 27-Aug-20 23-Sep-20 49 $24,000.00 RF 110 High Roof Ice & Water Shield 8 8 0% 17-Sep-20 30-Sep-20 49 $70,000.00 RF 115 Low Roof Ice & Water Shield 8 8 0% 24-Sep-20 07-Oct-20 61 $55,000.00 RF 120 Install Roof Hatches, Access Ladders & Vents 4 4 0% 01-Oct-20 07-Oct-20 49 $38,000.00 RF 125 Install SSM Roofing High Roof 12 12 0% 08-Oct-20 27-Oct-20 49 $200,000.00 RF 130 Install SSM Roofing Low Roof 12 12 0% 28-Oct-20 17-Nov-20 49 $137,000.00

Exterior CladdingExterior CladdingExterior CladdingExterior CladdingExterior CladdingExterior CladdingExterior CladdingExterior CladdingExterior Cladding Building EnclosurBuilding EnclosureBuilding EnclosureBuilding EnclosureBuilding EnclosureBuilding EnclosureBuilding EnclosureBuilding EnclosureBuilding Enclosure

CL 100 Exterior Door Frames @ Masonry Closure 4 4 0% 08-May-20 13-May-20 77 $18,000.00 CL 105 Exterior Foundation - Waterproofing and Sealants 4 4 0% 23-Jul-20 29-Jul-20 10 $16,000.00 CL 110 Exterior CMU - 2nd Flr Level to Upper Attic-Level 12 12 0% 23-Jul-20 12-Aug-20 0 $60,000.00 CL 115 Air Barrier - 2nd Flr Level to Upper Attic-Level 2 2 0% 18-Aug-20 19-Aug-20 0 $48,000.00 CL 120 Exterior Brick Veneer - 2nd Flr Level to Upper Attic-Level 8 8 0% 20-Aug-20 02-Sep-20 0 $59,000.00 CL 125 Ground Level CMU Closure & Rigid Insulation Board 24 24 0% 24-Sep-20 03-Nov-20 0 $218,500.00 CL 130 Ground Level Air Barrier 4 4 0% 03-Nov-20 06-Nov-20 5 $50,000.00 CL 135 Brick Veneer Ground Level & Remainder of Upper Level 24 24 0% 10-Nov-20 17-Dec-20 5 $275,000.00 CL 140 Upper Level Windows 8 8 0% 22-Dec-20 06-Jan-21 5 $157,500.00 CL 145 Lower Level Windows & Storefront 8 8 0% 07-Jan-21 21-Jan-21 5 $172,500.00

Canopy StructuresCanopy Structures, Ramp & Cladding FinishesCanopy Structures, Ramp & Cladding FinishesCanopy Structures, Ramp & Cladding FinishesCanopy Structures, Ramp & Cladding FinishesCanopy Structures, Ramp & Cladding FinishesCanopy Structures, Ramp & Cladding FinishesCanopy Structures, Ramp & Cladding FinishesCanopy Structures, Ramp & Cladding Finishes CL 200 Erect Entry Canopy Steel & Decking 4 4 0% 16-Jul-20 22-Jul-20 117 $42,000.00 CL 205 Access Ramp Footings & CIP Wall 4 4 0% 08-Oct-20 14-Oct-20 29 $25,000.00 CL 210 Access Ramp CMU 4 4 0% 15-Oct-20 21-Oct-20 29 $23,500.00 CL 215 Access Ramp Drains & Backfill 4 4 0% 22-Oct-20 27-Oct-20 29 $15,000.00 CL 220 Access Ramp Concrete Slab & Steps 4 4 0% 28-Oct-20 03-Nov-20 29 $19,000.00 CL 225 Access Ramp Veneer 4 4 0% 10-Nov-20 17-Nov-20 25 $16,000.00 CL 230 Entry Canopy SSM Roof 4 4 0% 18-Nov-20 23-Nov-20 49 $7,500.00 CL 235 Frame Entry Canopy Soffit 4 4 0% 24-Nov-20 01-Dec-20 49 $20,000.00

Oct Nov Dec Jan Feb Mar Apr M Jun Jul Aug Sep Oct Nov Dec Jan F Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2020 2021

Prep & Place SOG - All Sectors

Deliver Structural Steel & Shakeout Erect Structural Steel Framing - 1st Half 2nd Floor Decking & Steel Detailing - 1st Half Erect Structural Steel Framing - 2nd Half 2nd Floor Decking & Steel Detailing - 2nd Half 2nd Floor Studs Test Studs & Submit Report Prep & Place SOMD - 1st Half Prep & Place SOMD - 2nd Half Cure SOMD - 1st Half

Erect High Roof Framing - structural steel Set & Protect AHUs 1a, 1b & 2 for 2nd Floor Mech Rm

Attic-Level Steel Decking Erect Light Gauge Metal Trusses

High Roof Decking Install Low-Roof Light-Gauge Metal Framing & Deck

Install Permanent Fall Protection System Roof Edge Blocking High Roof Ice & Water Shield Low Roof Ice & Water Shield Install Roof Hatches, Access Ladders & Vents

Install SSM Roofing High Roof Install SSM Roofing Low Roof

Exterior Door Frames @ Masonry Closure Exterior Foundation - Waterproofing and Sealants

Exterior CMU - 2nd Flr Level to Upper Attic-Level Air Barrier - 2nd Flr Level to Upper Attic-Level

Exterior Brick Veneer - 2nd Flr Level to Upper Attic-Level Ground Level CMU Closure & Rigid Insulation Board Ground Level Air Barrier

Brick Veneer Ground Level & Remainder of Upper Level Upper Level Windows

Lower Level Windows & Storefront

Erect Entry Canopy Steel & Decking Access Ramp Footings & CIP Wall Access Ramp CMU Access Ramp Drains & Backfill Access Ramp Concrete Slab & Steps

Access Ramp Veneer Entry Canopy SSM Roof

Frame Entry Canopy Soffit

Remaining Level of Effort Actual Work Remaining Work

Critical Remaining Work Milestone

P4041 Dental/Medical Clinics - Camp Lejeune Whiting-Turner Contracting Company

Proposed Baseline Schedule - Full Detail & Scheduled Values

Rem Dur

Compl

Early Start Early Finish Total Float

Scheduled Value

CL 240 SSM Roof Trim @ Suspended Canopies 4 4 0% 24-Nov-20 01-Dec-20 62 $55,000.00 CL 245 OH Electrical R/I @ Entry Canopy 4 4 0% 02-Dec-20 07-Dec-20 49 $16,000.00 CL 250 Above-Ceiling Inspection @ Entry Canopy 1 1 0% 08-Dec-20 08-Dec-20 49 $3,500.00 CL 255 GFRC Columns & Stucco Portico 12 12 0% 09-Dec-20 28-Dec-20 49 $35,000.00 CL 260 Install Suspended Canopies 4 4 0% 14-Dec-20 17-Dec-20 5 $28,000.00 CL 265 Prefinished Metal Cornice System 16 16 0% 15-Dec-20 12-Jan-21 81 $65,000.00 CL 270 Brickwash 2 2 0% 18-Dec-20 21-Dec-20 5 $15,000.00 CL 275 Louvers 2 2 0% 22-Dec-20 23-Dec-20 138 $17,500.00 CL 280 Access Ramp Rails & Misc. Metal Trim 2 2 0% 22-Dec-20 23-Dec-20 138 $17,500.00 CL 285 Exterior Caulking 3 3 0% 22-Dec-20 28-Dec-20 119 $35,000.00 CL 290 Building-Attached Exterior Lights 4 4 0% 22-Dec-20 29-Dec-20 136 $76,800.00 CL 295 Exterior Doors & Hardware 4 4 0% 22-Dec-20 29-Dec-20 136 $20,000.00 CL 300 Install Light in Entry Canopy Soffit 1 1 0% 29-Dec-20 29-Dec-20 136 $5,000.00 CL 305 Paint GFRC / Stucco 4 4 0% 29-Dec-20 05-Jan-21 93 $10,000.00

Interior WorkInterior WorkInterior WorkInterior WorkInterior WorkInterior WorkInterior WorkInterior WorkInterior Work Level 1Level 1Level 1Level 1Level 1Level 1Level 1Level 1Level 1

Level 1, Sector A/BLevel 1, Sector A/B/CLevel 1, Sector A/B/CLevel 1, Sector A/B/CLevel 1, Sector A/B/CLevel 1, Sector A/B/CLevel 1, Sector A/B/CLevel 1, Sector A/B/CLevel 1, Sector A/B/C

Partions & Rough-IPartions & Rough-Ins - L1, S ABCPartions & Rough-Ins - L1, S ABCPartions & Rough-Ins - L1, S ABCPartions & Rough-Ins - L1, S ABCPartions & Rough-Ins - L1, S ABCPartions & Rough-Ins - L1, S ABCPartions & Rough-Ins - L1, S ABCPartions & Rough-Ins - L1, S ABC

R/I 1 1000 Spray Fireproofing - L1,S A/B/C 5 5 0% 04-Nov-20 10-Nov-20 0 $10,500.00 R/I 1 1005 Duct Mains - L1,S A/B/C 15 15 0% 12-Nov-20 04-Dec-20 0 $77,000.00 R/I 1 1010 Interior Wall Framing - L1,S A/B/C 15 15 0% 19-Nov-20 11-Dec-20 8 $105,000.00 R/I 1 1015 In-Wall Electrical R/I - L1,S A/B/C 15 15 0% 30-Nov-20 18-Dec-20 85 $59,000.00 R/I 1 1020 In-Wall Plumbing R/I (all systems) - L1,S A/B/C 10 10 0% 07-Dec-20 18-Dec-20 8 $45,000.00 R/I 1 1025 Set ATUs & FCUs & Complete Branch Duct - L1,S A/B/C 10 10 0% 07-Dec-20 18-Dec-20 30 $36,000.00 R/I 1 1030 Refrigerant R/I Connections to ATUs - L1,S A/B/C 15 15 0% 07-Dec-20 29-Dec-20 40 $32,000.00 R/I 1 1035 In-Wall Blocking - L1, S A/B/C 5 5 0% 14-Dec-20 18-Dec-20 20 $10,000.00 R/I 1 1040 Sprinkler R/I - L1,S A/B/C 8 8 0% 14-Dec-20 23-Dec-20 40 $11,000.00 R/I 1 1045 OH Electrical R/I - All Systems - L1,S A/B/C 20 20 0% 14-Dec-20 14-Jan-21 85 $75,000.00 R/I 1 1050 OH Plumbing Supply R/I (all Systems) - L1,S A/B/C 5 5 0% 21-Dec-20 29-Dec-20 35 $40,500.00 R/I 1 1055 Controls Connections to Above-Ceiling HVAC - L1,S A/B/C 5 5 0% 21-Dec-20 29-Dec-20 40 $36,000.00 R/I 1 1060 Electrical Connections to Above-Ceiling HVAC - L1,S A/B/C 5 5 0% 21-Dec-20 29-Dec-20 122 $14,000.00 R/I 1 1065 Above-Floor Plumbing R/I - DWV - L1,S A/B/C 10 10 0% 21-Dec-20 07-Jan-21 8 $45,000.00 R/I 1 1070 Plumbing In-Wall Insulation - L1,S A/B/C 2 2 0% 08-Jan-21 11-Jan-21 8 $18,000.00 R/I 1 1075 Plumbing OH Insulation - L1,S A/B/C 3 3 0% 12-Jan-21 14-Jan-21 25 $25,000.00 R/I 1 1080 Pull Wire for F/A & LV Systems - L1,S A/B/C 5 5 0% 15-Jan-21 22-Jan-21 107 $18,000.00 R/I 1 1085 Pull Wire for Lights & Power - L1,S A/B/C 10 10 0% 15-Jan-21 29-Jan-21 102 $36,000.00 R/I 1 1090 Duct Insulation - L1,S A/B/C 10 10 0% 16-Feb-21 01-Mar-21 0 $36,000.00

GWB & Ceiling GrGWB & Ceiling Grid - L1, S ABCGWB & Ceiling Grid - L1, S ABCGWB & Ceiling Grid - L1, S ABCGWB & Ceiling Grid - L1, S ABCGWB & Ceiling Grid - L1, S ABCGWB & Ceiling Grid - L1, S ABCGWB & Ceiling Grid - L1, S ABCGWB & Ceiling Grid - L1, S ABC

DW 1 10 In-Wall Inspections & Corrections - L1,S A/B/C 5 5 0% 12-Jan-21 19-Jan-21 8 $3,500.00 DW 1 10 Hang GWB Walls - L1,S A/B/C 15 15 0% 22-Jan-21 11-Feb-21 6 $105,000.00 DW 1 10 Fire Stopping & Interior Caulking - L1,S A/B/C 5 5 0% 05-Feb-21 11-Feb-21 6 $6,800.00 DW 1 10 Framing for Corridor Bulkheads & Soffits - L1,S A/B/C 5 5 0% 12-Feb-21 19-Feb-21 6 $23,000.00 DW 1 10 Mech/Elec Attachments to Blkhd/Soffit Framing - L1,S A/B/C 5 5 0% 22-Feb-21 26-Feb-21 6 $19,000.00 DW 1 10 Framing for Hard Ceilings - L1,S A/B/C 5 5 0% 23-Feb-21 01-Mar-21 0 $27,000.00 DW 1 10 Hang Corridor Bulkhd/Soffit GWB - L1,S A/B/C 10 10 0% 01-Mar-21 12-Mar-21 6 $27,000.00 DW 1 10 Mech/Elec Attachments to Hard Clg Framing - L1,S A/B/C 5 5 0% 02-Mar-21 08-Mar-21 0 $11,000.00 DW 1 10 Hang & Finish Hard Ceiling GWB - L1,S A/B/C 9 9 0% 09-Mar-21 19-Mar-21 0 $22,000.00

Oct Nov Dec Jan Feb Mar Apr M Jun Jul Aug Sep Oct Nov Dec Jan F Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2020 2021

SSM Roof Trim @ Suspended Canopies OH Electrical R/I @ Entry Canopy Above-Ceiling Inspection @ Entry Canopy

GFRC Columns & Stucco Portico Install Suspended Canopies

Prefinished Metal Cornice System Brickwash Louvers Access Ramp Rails & Misc. Metal Trim Exterior Caulking Building-Attached Exterior Lights Exterior Doors & Hardware Install Light in Entry Canopy Soffit Paint GFRC / Stucco

Spray Fireproofing - L1,S A/B/C Duct Mains - L1,S A/B/C Interior Wall Framing - L1,S A/B/C In-Wall Electrical R/I - L1,S A/B/C In-Wall Plumbing R/I (all systems) - L1,S A/B/C Set ATUs & FCUs & Complete Branch Duct - L1,S A/B/C

Refrigerant R/I Connections to ATUs - L1,S A/B/C In-Wall Blocking - L1, S A/B/C Sprinkler R/I - L1,S A/B/C

OH Electrical R/I - All Systems - L1,S A/B/C OH Plumbing Supply R/I (all Systems) - L1,S A/B/C Controls Connections to Above-Ceiling HVAC - L1,S A/B/C Electrical Connections to Above-Ceiling HVAC - L1,S A/B/C

Above-Floor Plumbing R/I - DWV - L1,S A/B/C Plumbing In-Wall Insulation - L1,S A/B/C Plumbing OH Insulation - L1,S A/B/C Pull Wire for F/A & LV Systems - L1,S A/B/C Pull Wire for Lights & Power - L1,S A/B/C

Duct Insulation - L1,S A/B/C

In-Wall Inspections & Corrections - L1,S A/B/C Hang GWB Walls - L1,S A/B/C Fire Stopping & Interior Caulking - L1,S A/B/C Framing for Corridor Bulkheads & Soffits - L1,S A/B/C Mech/Elec Attachments to Blkhd/Soffit Framing - L Framing for Hard Ceilings - L1,S A/B/C

Hang Corridor Bulkhd/Soffit GWB - L1,S A/B/C Mech/Elec Attachments to Hard Clg Framing - L1

Hang & Finish Hard Ceiling GWB - L1,S A/B/C

Remaining Level of Effort Actual Work Remaining Work

Critical Remaining Work Milestone

P4041 Dental/Medical Clinics - Camp Lejeune Whiting-Turner Contracting Company

Proposed Baseline Schedule - Full Detail & Scheduled Values

Rem Dur

Compl

Early Start Early Finish Total Float

Scheduled Value

DW 1 10 Finish GWB Walls & Corridor Blkhd/Soffits - L1,S A/B/C 15 15 0% 09-Mar-21 29-Mar-21 0 $23,000.00 DW 1 10 Prime Paint GWB Surfaces in Advance of Grid - L1,S A/B/C 10 10 0% 30-Mar-21 12-Apr-21 21 $14,500.00 DW 1 10 Install Ceiling Grid - L1,S A/B/C 12 12 0% 13-Apr-21 28-Apr-21 40 $52,000.00

Fixtures & FinishesFixtures & Finishes - L1, S ABCFixtures & Finishes - L1, S ABCFixtures & Finishes - L1, S ABCFixtures & Finishes - L1, S ABCFixtures & Finishes - L1, S ABCFixtures & Finishes - L1, S ABCFixtures & Finishes - L1, S ABCFixtures & Finishes - L1, S ABC

FIN 1 100 Interior Glazing - L1,S A/B/C 5 5 0% 13-Apr-21 19-Apr-21 91 $10,000.00 FIN 1 100 Hard Tile Finishes - L1,S A/B/C 10 10 0% 13-Apr-21 26-Apr-21 21 $45,000.00 FIN 1 101 Sprinkler Drops to Grid & Trimout - L1,S A/B/C 10 10 0% 22-Apr-21 05-May-21 40 $8,500.00 FIN 1 101 HVAC Attachments to Grid - L1,S A/B/C 10 10 0% 22-Apr-21 05-May-21 40 $14,000.00 FIN 1 102 Lights in Grid - L1,S A/B/C 10 10 0% 22-Apr-21 05-May-21 40 $40,000.00 FIN 1 102 Electrical Wall Trimout - L1,S A/B/C 10 10 0% 22-Apr-21 05-May-21 69 $18,000.00 FIN 1 103 Remainder of Prime Paint & Intermediate Finish Coats - L1,S A/B/C 5 5 0% 29-Apr-21 05-May-21 42 $3,500.00 FIN 1 103 Final Above-Ceiling Inspections - L1,S A/B/C 5 5 0% 06-May-21 12-May-21 40 $3,500.00 FIN 1 104 Set Plumbing Fixtures - L1,S A/B/C 5 5 0% 06-May-21 12-May-21 59 $53,000.00 FIN 1 104 Pendant Lights - L1,S A/B/C 5 5 0% 06-May-21 12-May-21 64 $13,500.00 FIN 1 105 Telecom Devices - L1,S A/B/C 5 5 0% 06-May-21 12-May-21 73 $17,000.00 FIN 1 105 Security Devices - L1,S A/B/C 5 5 0% 06-May-21 12-May-21 73 $19,000.00 FIN 1 106 HVAC Wall Trimout - L1,S A/B/C 5 5 0% 06-May-21 12-May-21 74 $19,000.00 FIN 1 106 Sealed Concrete Floors - L1,S A/B/C 5 5 0% 06-May-21 12-May-21 74 $2,500.00 FIN 1 107 MIsc. Wall Protection Devices - L1,S A/B/C 5 5 0% 06-May-21 12-May-21 74 $10,000.00 FIN 1 107 F/A Devices - L1,S A/B/C 10 10 0% 06-May-21 19-May-21 69 $18,000.00 FIN 1 108 Set Vanities - L1,S A/B/C 5 5 0% 13-May-21 19-May-21 59 $50,000.00 FIN 1 108 Install Ceiiling Tiles - L1,S A/B/C 7 7 0% 14-May-21 24-May-21 39 $15,000.00 FIN 1 109 Interior Doors & Hardware - L1,S A/B/C 10 10 0% 14-May-21 27-May-21 36 $13,500.00 FIN 1 109 Install Medical Specialties & Casework - L1, S A/B/C 15 15 0% 14-May-21 04-Jun-21 43 $12,000.00 FIN 1 110 Casework & Millwork - L1,S A/B/C 15 15 0% 14-May-21 04-Jun-21 48 $59,500.00 FIN 1 110 Final Plumbing Connections - L1,S A/B/C 5 5 0% 20-May-21 26-May-21 59 $28,000.00 FIN 1 111 Bathroom Accessories & Partitions - L1,S A/B/C 5 5 0% 27-May-21 03-Jun-21 59 $35,000.00 FIN 1 111 Resilient Flooring - L1,S A/B/C 10 10 0% 07-Jun-21 18-Jun-21 48 $25,000.00 FIN 1 112 Interior Signage - L1,S A/B/C 5 5 0% 21-Jun-21 25-Jun-21 48 $13,000.00 FIN 1 112 Final Paint Touch-Up - L1,S A/B/C 5 5 0% 21-Jun-21 25-Jun-21 48 $5,000.00

Level 1, Sector DFGLevel 1, Sector DFGLevel 1, Sector DFGLevel 1, Sector DFGLevel 1, Sector DFGLevel 1, Sector DFGLevel 1, Sector DFGLevel 1, Sector DFGLevel 1, Sector DFG

Partions & Rough-IPartions & Rough-Ins - L1, S DFGPartions & Rough-Ins - L1, S DFGPartions & Rough-Ins - L1, S DFGPartions & Rough-Ins - L1, S DFGPartions & Rough-Ins - L1, S DFGPartions & Rough-Ins - L1, S DFGPartions & Rough-Ins - L1, S DFGPartions & Rough-Ins - L1, S DFG

R/I 1 2000 Spray Fireproofing - L1,S D/F/G 5 5 0% 12-Nov-20 18-Nov-20 10 $10,500.00 R/I 1 2005 Duct Mains - L1,S D/F/G 15 15 0% 07-Dec-20 29-Dec-20 0 $61,000.00 R/I 1 2010 Interior Wall Framing - L1,S D/F/G 15 15 0% 14-Dec-20 07-Jan-21 8 $95,000.00 R/I 1 2015 In-Wall Electrical R/I - L1,S D/F/G 15 15 0% 21-Dec-20 14-Jan-21 70 $41,000.00 R/I 1 2020 In-Wall Plumbing R/I (all systems) - L1,S D/F/G 10 10 0% 30-Dec-20 14-Jan-21 8 $35,000.00 R/I 1 2025 Set ATUs & FCUs & Complete Branch Duct - L1,S D/F/G 10 10 0% 30-Dec-20 14-Jan-21 15 $28,000.00 R/I 1 2030 Refrigerant R/I Connections to ATUs - L1,S D/F/G 15 15 0% 30-Dec-20 22-Jan-21 40 $26,000.00 R/I 1 2035 In-Wall Blocking - L1, S D/F/G 5 5 0% 08-Jan-21 14-Jan-21 20 $5,000.00 R/I 1 2040 Sprinkler R/I - L1,S D/F/G 8 8 0% 08-Jan-21 20-Jan-21 40 $11,000.00 R/I 1 2045 OH Electrical R/I - All Systems - L1,S D/F/G 20 20 0% 08-Jan-21 05-Feb-21 70 $41,000.00 R/I 1 2050 OH Plumbing Supply R/I (all Systems) - L1,S D/F/G 5 5 0% 15-Jan-21 22-Jan-21 35 $30,500.00 R/I 1 2055 Controls Connections to Above-Ceiling HVAC - L1,S D/F/G 5 5 0% 15-Jan-21 22-Jan-21 40 $30,000.00 R/I 1 2060 Electrical Connections to Above-Ceiling HVAC - L1,S D/F/G 5 5 0% 15-Jan-21 22-Jan-21 124 $7,500.00 R/I 1 2065 Above-Floor Plumbing R/I - DWV - L1,S D/F/G 10 10 0% 15-Jan-21 29-Jan-21 8 $35,000.00 R/I 1 2070 Plumbing In-Wall Insulation - L1,S D/F/G 2 2 0% 01-Feb-21 02-Feb-21 8 $14,000.00

Oct Nov Dec Jan Feb Mar Apr M Jun Jul Aug Sep Oct Nov Dec Jan F Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2020 2021

Finish GWB Walls & Corridor Blkhd/Soffits - L1 Prime Paint GWB Surfaces in Advance of G

Install Ceiling Grid - L1,S A/B/C

Interior Glazing - L1,S A/B/C Hard Tile Finishes - L1,S A/B/C

Sprinkler Drops to Grid & Trimout - L1,S HVAC Attachments to Grid - L1,S A/B/C Lights in Grid - L1,S A/B/C Electrical Wall Trimout - L1,S A/B/C Remainder of Prime Paint & Intermedia Final Above-Ceiling Inspections - L1,S Set Plumbing Fixtures - L1,S A/B/C Pendant Lights - L1,S A/B/C Telecom Devices - L1,S A/B/C Security Devices - L1,S A/B/C HVAC Wall Trimout - L1,S A/B/C Sealed Concrete Floors - L1,S A/B/C MIsc. Wall Protection Devices - L1,S A F/A Devices - L1,S A/B/C Set Vanities - L1,S A/B/C Install Ceiiling Tiles - L1,S A/B/C Interior Doors & Hardware - L1,S A/ Install Medical Specialties & Case Casework & Millwork - L1,S A/B/C

Final Plumbing Connections - L1,S A Bathroom Accessories & Partitions

Resilient Flooring - L1,S A/B/C Interior Signage - L1,S A/B/C Final Paint Touch-Up - L1,S A/

Spray Fireproofing - L1,S D/F/G Duct Mains - L1,S D/F/G

Interior Wall Framing - L1,S D/F/G In-Wall Electrical R/I - L1,S D/F/G In-Wall Plumbing R/I (all systems) - L1,S D/F/G Set ATUs & FCUs & Complete Branch Duct - L1,S D/F/G Refrigerant R/I Connections to ATUs - L1,S D/F/G

In-Wall Blocking - L1, S D/F/G Sprinkler R/I - L1,S D/F/G

OH Electrical R/I - All Systems - L1,S D/F/G OH Plumbing Supply R/I (all Systems) - L1,S D/F/G Controls Connections to Above-Ceiling HVAC - L1,S D/F/G Electrical Connections to Above-Ceiling HVAC - L1,S D/F/ Above-Floor Plumbing R/I - DWV - L1,S D/F/G Plumbing In-Wall Insulation - L1,S D/F/G

Remaining Level of Effort Actual Work Remaining Work

Critical Remaining Work Milestone

P4041 Dental/Medical Clinics - Camp Lejeune Whiting-Turner Contracting Company

Proposed Baseline Schedule - Full Detail & Scheduled Values

Rem Dur

Compl

Early Start Early Finish Total Float

Scheduled Value

R/I 1 2075 Plumbing OH Insulation - L1,S D/F/G 3 3 0% 03-Feb-21 05-Feb-21 25 $19,000.00 R/I 1 2080 Pull Wire for F/A & LV Systems - L1,S D/F/G 5 5 0% 08-Feb-21 12-Feb-21 109 $12,000.00 R/I 1 2085 Pull Wire for Lights & Power - L1,S D/F/G 10 10 0% 08-Feb-21 22-Feb-21 104 $24,000.00 R/I 1 2090 Duct Insulation - L1,S D/F/G 10 10 0% 16-Feb-21 01-Mar-21 15 $28,000.00

GWB & Ceiling GrGWB & Ceiling Grid - L1, S DFGGWB & Ceiling Grid - L1, S DFGGWB & Ceiling Grid - L1, S DFGGWB & Ceiling Grid - L1, S DFGGWB & Ceiling Grid - L1, S DFGGWB & Ceiling Grid - L1, S DFGGWB & Ceiling Grid - L1, S DFGGWB & Ceiling Grid - L1, S DFG

DW 1 200 In-Wall Inspections & Corrections - L1,S D/F/G 5 5 0% 03-Feb-21 09-Feb-21 8 $3,500.00 DW 1 200 Hang GWB Walls - L1,S D/F/G 15 15 0% 12-Feb-21 05-Mar-21 6 $95,000.00 DW 1 201 Fire Stopping & Interior Caulking - L1,S D/F/G 5 5 0% 01-Mar-21 05-Mar-21 6 $6,800.00 DW 1 201 Framing for Hard Ceilings - L1,S D/F/G 5 5 0% 04-Mar-21 10-Mar-21 8 $23,000.00 DW 1 202 Framing for Corridor Bulkheads & Soffits - L1,S D/F/G 5 5 0% 08-Mar-21 12-Mar-21 6 $19,000.00 DW 1 202 Mech/Elec Attachments to Hard Clg Framing - L1,S D/F/G 5 5 0% 11-Mar-21 17-Mar-21 8 $9,000.00 DW 1 203 Mech/Elec Attachments to Blkhd/Soffit Framing - L1,S D/F/G 5 5 0% 15-Mar-21 19-Mar-21 6 $17,000.00 DW 1 203 Hang Corridor Bulkhd/Soffit GWB - L1,S D/F/G 10 10 0% 22-Mar-21 02-Apr-21 6 $23,000.00 DW 1 204 Hang & Finish Hard Ceiling GWB - L1,S D/F/G 9 9 0% 30-Mar-21 09-Apr-21 0 $23,000.00 DW 1 204 Finish GWB Walls & Corridor Blkhd/Soffits - L1,S D/F/G 15 15 0% 30-Mar-21 19-Apr-21 0 $19,000.00 DW 1 205 Prime Paint GWB Surfaces in Advance of Grid - L1,S D/F/G 10 10 0% 20-Apr-21 03-May-21 16 $14,500.00 DW 1 205 Install Ceiling Grid - L1,S D/F/G 12 12 0% 04-May-21 19-May-21 42 $42,000.00

Fixtures & FinishesFixtures & Finishes - L1, S DFGFixtures & Finishes - L1, S DFGFixtures & Finishes - L1, S DFGFixtures & Finishes - L1, S DFGFixtures & Finishes - L1, S DFGFixtures & Finishes - L1, S DFGFixtures & Finishes - L1, S DFGFixtures & Finishes - L1, S DFG

FIN 1 200 Interior Glazing - L1,S D/F/G 5 5 0% 04-May-21 10-May-21 76 $5,000.00 FIN 1 200 Hard Tile Finishes - L1,S D/F/G 10 10 0% 04-May-21 17-May-21 16 $45,000.00 FIN 1 201 Sprinkler Drops to Grid & Trimout - L1,S D/F/G 10 10 0% 13-May-21 26-May-21 42 $8,500.00 FIN 1 201 HVAC Attachments to Grid - L1,S D/F/G 10 10 0% 13-May-21 26-May-21 42 $12,000.00 FIN 1 202 Lights in Grid - L1,S D/F/G 10 10 0% 13-May-21 26-May-21 42 $29,000.00 FIN 1 202 Electrical Wall Trimout - L1,S D/F/G 10 10 0% 13-May-21 26-May-21 54 $12,000.00 FIN 1 203 Casework & Millwork - L1,S D/F/G 15 15 0% 14-May-21 04-Jun-21 48 $45,500.00 FIN 1 203 Remainder of Prime Paint & Intermediate Finish Coats - L1,S D/F/G 5 5 0% 20-May-21 26-May-21 44 $3,500.00 FIN 1 204 Final Above-Ceiling Inspections - L1,S D/F/G 5 5 0% 27-May-21 03-Jun-21 42 $3,500.00 FIN 1 204 Set Plumbing Fixtures - L1,S D/F/G 5 5 0% 27-May-21 03-Jun-21 44 $38,000.00 FIN 1 205 Pendant Lights - L1,S D/F/G 5 5 0% 27-May-21 03-Jun-21 49 $8,000.00 FIN 1 205 Telecom Devices - L1,S D/F/G 5 5 0% 27-May-21 03-Jun-21 58 $12,000.00 FIN 1 206 HVAC Wall Trimout - L1,S D/F/G 5 5 0% 27-May-21 03-Jun-21 59 $12,000.00 FIN 1 206 Security Devices - L1,S D/F/G 5 5 0% 27-May-21 03-Jun-21 59 $11,000.00 FIN 1 207 Sealed Concrete Floors - L1,S D/F/G 5 5 0% 27-May-21 03-Jun-21 59 $2,500.00 FIN 1 207 MIsc.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .