Appendix 7.7 Construction Schedule.pdf

PDF 1 MB Posted

Attached to
Wallace Creek Initial Outfitting Project Federal contract opportunity
Solicitation number
W9127S20Q6003
Issued by
Department of the Army Corps of Engineers Engineering District Little Rock

About this file

This is a solicitation for a combined synopsis and commercial items prepared in accordance with FAR Subpart 12.6 for the Wallace Creek Initial Outfitting Project. The solicitation is a request for quote issued as a total competitive 8(a) set-aside under NAICS code 337127 with a size standard of 500 employees. Quotes are due by May 27, 2020 at 1:00pm Central Time. Interested offerors must contact Timothy Pighee of the US Army Corps of Engineers Little Rock District to obtain solicitation attachments and provide their company name, employee name, email, and telephone number. The solicitation documents and provisions are current through FAC 2020-05.

View the file

Other files for this federal contract opportunity

Show all 22

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Activity ID Activity Name Orig Dur

Rem Dur

% Comp Start Finish Total Float

P4042 - Dental ClinicP4042 - Dental Clinic 546 546 27-Sep-19 29-Oct-21 0

Project MilestonesProject Milestones 546 546 27-Sep-19 29-Oct-21 0

MILE 100 Project Award 0 0 0% 27-Sep-19 0 MILE 105 Project NTP 0 0 0% 18-Oct-19 0 MILE 110 Preconstruction/Partnering Meeting 1 1 0% 29-Oct-19 29-Oct-19 0 MILE 115 SOG Completion 0 0 0% 27-May-20 5 MILE 120 Structure Completion 0 0 0% 31-Aug-20 82 MILE 125 Roof Dry-In 0 0 0% 02-Nov-20 82 MILE 130 Glass Close-In 0 0 0% 23-Dec-20 47 MILE 135 Energize 0 0 0% 11-Feb-21 98 MILE 145 HVAC Start-Up 0 0 0% 05-Mar-21 85 MILE 140 BOD (CCD = 30Oct21, a sunday) 0 0 0% 29-Oct-21* 0

PreconstructionPreconstruction 115 115 16-Oct-19 24-Mar-20 382

Generation & SubmGeneration & Submission of Key Submittals 50 50 16-Oct-19 24-Dec-19 382

SUBM 1155 Generate & Submit QC Plan, Safety Plan, Environmental Plan & CPM 20 20 0% 16-Oct-19 12-Nov-19 0 SUBM 1165 Generate & Submit Piledriving Submittals 5 5 0% 30-Oct-19 05-Nov-19 13 SUBM 1175 Prepare & Submit Strutcural Steel Shop Drawings 40 40 0% 30-Oct-19 24-Dec-19 46 SUBM 1170 Prepare & Submit Foundation Rebar Shop Drawings 15 15 0% 30-Oct-19 19-Nov-19 53 SUBM 1160 Generate & Submit AHU Submittals 40 40 0% 30-Oct-19 24-Dec-19 93 SUBM 1115 Prepare & Submit CFMF Shop Drawings 40 40 0% 30-Oct-19 24-Dec-19 99 SUBM 1000 Generate & Submit Doorframe Submittals (for masonry) 40 40 0% 30-Oct-19 24-Dec-19 119 SUBM 1055 Generate & Submit Masonry Veneer Submittals/Mockup 40 40 0% 30-Oct-19 24-Dec-19 129 SUB 1150 Generate & Submit Exterior Finishes Board 40 40 0% 30-Oct-19 24-Dec-19 129 SUBM 1135 Generate & Submit Spray Fireproofing Submittals 40 40 0% 30-Oct-19 24-Dec-19 199 SUBM 1040 Generate & Submit Windows/Storefront Submittals 40 40 0% 30-Oct-19 24-Dec-19 223 SUBM 1035 Generate & Submit SSM Roofing Submittals 40 40 0% 30-Oct-19 24-Dec-19 226 SUBM 1030 Generate & Submit ATU & FCU Submittals 40 40 0% 30-Oct-19 24-Dec-19 238 SUBM 1120 Generate & Submit Sprinkler Design 40 40 0% 30-Oct-19 24-Dec-19 263 SUBM 1010 Generate & Submit Boiler Submittals 40 40 0% 30-Oct-19 24-Dec-19 290 SUBM 1015 Generate & Submit HVAC Pump Submittals 40 40 0% 30-Oct-19 24-Dec-19 290 SUBM 1025 Generate & Submit Chiller Submittals 40 40 0% 30-Oct-19 24-Dec-19 299 SUBM 1130 Generate & Submit Exterior Framing Submittals/Design 40 40 0% 30-Oct-19 24-Dec-19 301 SUBM 1060 Generate & Submit ACT Submittals 40 40 0% 30-Oct-19 24-Dec-19 316 SUBM 1075 Generate & Submit Lighting Submittals 40 40 0% 30-Oct-19 24-Dec-19 330 SUBM 1085 Generate & Submit Med Specialties Submittals 40 40 0% 30-Oct-19 24-Dec-19 333 SUBM 1080 Generate & Submit Flooring Submittals 40 40 0% 30-Oct-19 24-Dec-19 337 SUBM 1090 Generate & Submit Controls Submittals 40 40 0% 30-Oct-19 24-Dec-19 337 SUBM 1070 Generate & Submit Doors/Hardware Submittals 40 40 0% 30-Oct-19 24-Dec-19 342 SUBM 1020 Generate & Submit Elevator Submittals 40 40 0% 30-Oct-19 24-Dec-19 357 SUBM 1065 Generate & Submit Casework/Millwork Submittals 40 40 0% 30-Oct-19 24-Dec-19 362 SUBM 1110 Generate & Submit Plumbing Fixture Submittals 40 40 0% 30-Oct-19 24-Dec-19 367 SUBM 1095 Generate & Submit F/A Submittals 40 40 0% 30-Oct-19 24-Dec-19 377 SUBM 1100 Generate & Submit Telecom Submittals 40 40 0% 30-Oct-19 24-Dec-19 382 SUBM 1105 Generate & Submit Security System Submittals 40 40 0% 30-Oct-19 24-Dec-19 382

NAVFAC Review &NAVFAC Review & Approval of Key Submittals 68 68 06-Nov-19 07-Feb-20 364

REV 1025 NAVFAC Review & Approve Piledriving Submittals 15 15 0% 06-Nov-19 26-Nov-19 13 REV 1020 NAVFAC Review & Approve QC & Safety Plans 10 10 0% 13-Nov-19 26-Nov-19 0 REV 1030 NAVFAC Review & Approve Foundation Rebar Shop Drawings 15 15 0% 20-Nov-19 10-Dec-19 53 REV 1170 NAVFAC Review & Approve Structural Steel Shop Drawings 15 15 0% 25-Dec-19 14-Jan-20 46 REV 1175 NAVFAC Review & Approve AHU Submittals 15 15 0% 25-Dec-19 14-Jan-20 93 REV 1150 NAVFAC Review & Approve CFMF Shop Drawings 15 15 0% 25-Dec-19 14-Jan-20 99 ep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2020 2021

Project Award Project NTP

Preconstruction/Partnering Meeting SOG Completion

Structure Completion Roof Dry-In

Glass Close-In Energize

HVAC Start-Up

BOD (CC

Generate & Submit QC Plan, Safety Plan, Environmental Plan & CPM Schedule Generate & Submit Piledriving Submittals

Prepare & Submit Strutcural Steel Shop Drawings Prepare & Submit Foundation Rebar Shop Drawings

Generate & Submit AHU Submittals Prepare & Submit CFMF Shop Drawings Generate & Submit Doorframe Submittals (for masonry) Generate & Submit Masonry Veneer Submittals/Mockup Generate & Submit Exterior Finishes Board Generate & Submit Spray Fireproofing Submittals Generate & Submit Windows/Storefront Submittals Generate & Submit SSM Roofing Submittals Generate & Submit ATU & FCU Submittals Generate & Submit Sprinkler Design Generate & Submit Boiler Submittals Generate & Submit HVAC Pump Submittals Generate & Submit Chiller Submittals Generate & Submit Exterior Framing Submittals/Design Generate & Submit ACT Submittals Generate & Submit Lighting Submittals Generate & Submit Med Specialties Submittals Generate & Submit Flooring Submittals Generate & Submit Controls Submittals Generate & Submit Doors/Hardware Submittals Generate & Submit Elevator Submittals Generate & Submit Casework/Millwork Submittals Generate & Submit Plumbing Fixture Submittals Generate & Submit F/A Submittals Generate & Submit Telecom Submittals Generate & Submit Security System Submittals

NAVFAC Review & Approve Piledriving Submittals NAVFAC Review & Approve QC & Safety Plans

NAVFAC Review & Approve Foundation Rebar Shop Drawings NAVFAC Review & Approve Structural Steel Shop Drawings NAVFAC Review & Approve AHU Submittals NAVFAC Review & Approve CFMF Shop Drawings

Actual Work Remaining Work Critical Remaining Work

Milestone P4042 - New Dental/Medical Clinics Whiting-Turner Contracting Company

Proposed Detailed Baseline Schedule - Full Detail

Page 1 of 15 © Oracle Corporation

Rem Dur

% Comp Start Finish Total Float

REV 1035 NAVFAC Review & Approve Doorframe Submittals (for masonry) 15 15 0% 25-Dec-19 14-Jan-20 119 REV 1090 NAVFAC Review & Approve Masonry Veneer Submittals/Mockup 15 15 0% 25-Dec-19 14-Jan-20 129 REV 1180 NAVFAC Review & Approve Exterior Finishes Board 15 15 0% 25-Dec-19 14-Jan-20 129 REV 1165 NAVFAC Review & Approve Spray Fireproofing Submittals 15 15 0% 25-Dec-19 14-Jan-20 199 REV 1075 NAVFAC Review & Approve Windows/Storefront Submittals 15 15 0% 25-Dec-19 14-Jan-20 223 REV 1070 NAVFAC Review & Approve SSM Roofing Submittals 15 15 0% 25-Dec-19 14-Jan-20 226 REV 1065 NAVFAC Review & Approve ATU & FCU Submittals 15 15 0% 25-Dec-19 14-Jan-20 238 REV 1155 NAVFAC Review & Approve Sprinkler Design 33 33 0% 25-Dec-19 07-Feb-20 263 REV 1045 NAVFAC Review & Approve Boiler Submittals 15 15 0% 25-Dec-19 14-Jan-20 290 REV 1050 NAVFAC Review & Approve HVAC Pump Submittals 15 15 0% 25-Dec-19 14-Jan-20 290 REV 1060 NAVFAC Review & Approve Chiller Submittals 15 15 0% 25-Dec-19 14-Jan-20 299 REV 1160 NAVFAC Review & Approve Exterior Framing Submittals/Design 15 15 0% 25-Dec-19 14-Jan-20 301 REV 1095 NAVFAC Review & Approve ACT Submittals 15 15 0% 25-Dec-19 14-Jan-20 316 REV 1110 NAVFAC Review & Approve Lighting Submittals 15 15 0% 25-Dec-19 14-Jan-20 330 REV 1120 NAVFAC Review & Approve Med Specialties Submittals 15 15 0% 25-Dec-19 14-Jan-20 333 REV 1115 NAVFAC Review & Approve Flooring Submittals 15 15 0% 25-Dec-19 14-Jan-20 337 REV 1125 NAVFAC Review & Approve Controls Submittals 15 15 0% 25-Dec-19 14-Jan-20 337 REV 1105 NAVFAC Review & Approve Doors/Hardware Submittals 15 15 0% 25-Dec-19 14-Jan-20 342 REV 1055 NAVFAC Review & Approve Elevator Submittals 15 15 0% 25-Dec-19 14-Jan-20 357 REV 1100 NAVFAC Review & Approve Casework/Millwork Submittals 15 15 0% 25-Dec-19 14-Jan-20 362 REV 1145 NAVFAC Review & Approve Plumbing Fixtures Submittals 15 15 0% 25-Dec-19 14-Jan-20 367 REV 1130 NAVFAC Review & Approve F/A Submittals 15 15 0% 25-Dec-19 14-Jan-20 377 REV 1135 NAVFAC Review & Approve Telecom Submittals 15 15 0% 25-Dec-19 14-Jan-20 382 REV 1140 NAVFAC Review & Approve Security System Submittals 15 15 0% 25-Dec-19 14-Jan-20 382

Fabrication & AvaiFabrication & Availability of Key Materials / Equipment 85 85 27-Nov-19 24-Mar-20 382

FAB 1010 Fabrication & Availability of Test Piles & Production Piles 30 30 0% 27-Nov-19 07-Jan-20 13 FAB 1015 Fabricate & Availability of Foundation Rebar 15 15 0% 11-Dec-19 31-Dec-19 53 FAB 1145 Fabricate & Availability of Structural Steel 50 50 0% 15-Jan-20 24-Mar-20 46 FAB 1150 Fabricate & Deliver AHUs (to be set during steel framing) 50 50 0% 15-Jan-20 24-Mar-20 93 FAB 1135 Fabricate CFMF Materials 40 40 0% 15-Jan-20 10-Mar-20 99 FAB 1020 Fabricate & Deliver Doorframe Materials (for masonry) 50 50 0% 15-Jan-20 24-Mar-20 119 FAB 1075 Fabricate & Deliver Masonry Veneer Materials 50 50 0% 15-Jan-20 24-Mar-20 129 FAB 1060 Fabricate & Deliver Windows/Storefront Systems 50 50 0% 15-Jan-20 24-Mar-20 223 FAB 1055 Fabricate & Deliver SSM Roofing Materials 50 50 0% 15-Jan-20 24-Mar-20 226 FAB 1050 Fabricate & Deliver ATUs & FCUs 50 50 0% 15-Jan-20 24-Mar-20 238 FAB 1030 Fabricate & Deliver Boilers 50 50 0% 15-Jan-20 24-Mar-20 290 FAB 1035 Fabricate & Deliver HVAC Pumps 50 50 0% 15-Jan-20 24-Mar-20 290 FAB 1045 Fabricate & Deliver Chillers 50 50 0% 15-Jan-20 24-Mar-20 299 FAB 1140 Fabricate & Deliver Exterior Framing Materials 10 10 0% 15-Jan-20 28-Jan-20 301 FAB 1080 Fabricate & Deliver ACT Materials 50 50 0% 15-Jan-20 24-Mar-20 316 FAB 1095 Fabricate & Deliver Lightng Materials 50 50 0% 15-Jan-20 24-Mar-20 330 FAB 1105 Fabricate & Deliver Med Specilaties Materials 50 50 0% 15-Jan-20 24-Mar-20 333 FAB 1100 Fabricate & Deliver Flooring Materials 50 50 0% 15-Jan-20 24-Mar-20 337 FAB 1110 Fabricate & Deliver Controls Systems 50 50 0% 15-Jan-20 24-Mar-20 337 FAB 1090 Fabricate & Deliver Doors/Hardware Materials 50 50 0% 15-Jan-20 24-Mar-20 342 FAB 1040 Fabricate & Deliver Elevator Materials 50 50 0% 15-Jan-20 24-Mar-20 357 FAB 1085 Fabricate & Deliver Casework/Millwork Materials 50 50 0% 15-Jan-20 24-Mar-20 362 FAB 1130 Fabricate & Deliver Plumbing Fixture Materials 50 50 0% 15-Jan-20 24-Mar-20 367 FAB 1115 Fabricate & Deliver F/A Materials 50 50 0% 15-Jan-20 24-Mar-20 377 FAB 1120 Fabricate & Deliver Telecom Materials 50 50 0% 15-Jan-20 24-Mar-20 382 FAB 1125 Fabricate & Deliver Security System Materials 50 50 0% 15-Jan-20 24-Mar-20 382 FAB 1155 Fabricate & Deliver Sprinkler Materials for R/Is 15 15 0% 10-Feb-20 28-Feb-20 263 ep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2020 2021

NAVFAC Review & Approve Doorframe Submittals (for masonry) NAVFAC Review & Approve Masonry Veneer Submittals/Mockup NAVFAC Review & Approve Exterior Finishes Board NAVFAC Review & Approve Spray Fireproofing Submittals NAVFAC Review & Approve Windows/Storefront Submittals NAVFAC Review & Approve SSM Roofing Submittals NAVFAC Review & Approve ATU & FCU Submittals

NAVFAC Review & Approve Sprinkler Design NAVFAC Review & Approve Boiler Submittals NAVFAC Review & Approve HVAC Pump Submittals NAVFAC Review & Approve Chiller Submittals NAVFAC Review & Approve Exterior Framing Submittals/Design NAVFAC Review & Approve ACT Submittals NAVFAC Review & Approve Lighting Submittals NAVFAC Review & Approve Med Specialties Submittals NAVFAC Review & Approve Flooring Submittals NAVFAC Review & Approve Controls Submittals NAVFAC Review & Approve Doors/Hardware Submittals NAVFAC Review & Approve Elevator Submittals NAVFAC Review & Approve Casework/Millwork Submittals NAVFAC Review & Approve Plumbing Fixtures Submittals NAVFAC Review & Approve F/A Submittals NAVFAC Review & Approve Telecom Submittals NAVFAC Review & Approve Security System Submittals

Fabrication & Availability of Test Piles & Production Piles Fabricate & Availability of Foundation Rebar

Fabricate & Availability of Structural Steel Fabricate & Deliver AHUs (to be set during steel framing)

Fabricate CFMF Materials Fabricate & Deliver Doorframe Materials (for masonry) Fabricate & Deliver Masonry Veneer Materials Fabricate & Deliver Windows/Storefront Systems Fabricate & Deliver SSM Roofing Materials Fabricate & Deliver ATUs & FCUs Fabricate & Deliver Boilers Fabricate & Deliver HVAC Pumps Fabricate & Deliver Chillers

Fabricate & Deliver Exterior Framing Materials Fabricate & Deliver ACT Materials Fabricate & Deliver Lightng Materials Fabricate & Deliver Med Specilaties Materials Fabricate & Deliver Flooring Materials Fabricate & Deliver Controls Systems Fabricate & Deliver Doors/Hardware Materials Fabricate & Deliver Elevator Materials Fabricate & Deliver Casework/Millwork Materials Fabricate & Deliver Plumbing Fixture Materials Fabricate & Deliver F/A Materials Fabricate & Deliver Telecom Materials Fabricate & Deliver Security System Materials

Fabricate & Deliver Sprinkler Materials for R/Is

Actual Work Remaining Work Critical Remaining Work

Milestone P4042 - New Dental/Medical Clinics Whiting-Turner Contracting Company

Page 2 of 15 © Oracle Corporation

Rem Dur

% Comp Start Finish Total Float

FAB 1160 Fabricate & Deliver Sprinkler Equipment 15 15 0% 10-Feb-20 28-Feb-20 263 ConstructionConstruction 475 475 27-Nov-19 21-Sep-21 11

Mobilization, InitiaMobilization, Initial Erosion Control 13 13 27-Nov-19 13-Dec-19 0

MOB 100 Mobilization of Offices to Site 8 8 0% 27-Nov-19 06-Dec-19 0 MOB 105 Site Survey & LOD Flagging 2 2 0% 27-Nov-19 28-Nov-19 6 MOB 110 Construction Entrances & Initial E/C Measures 5 5 0% 09-Dec-19 13-Dec-19 0

Clearing, Site DemClearing, Site Demo, Earthwork & Building Pad 30 30 16-Dec-19 24-Jan-20 0

ES 100 Clearing & Grubbing 15 15 0% 16-Dec-19 03-Jan-20 0 ES 105 Construct Temp Sediment Basins 1, 2 & 3 5 5 0% 06-Jan-20 10-Jan-20 0 ES 110 Bench Excavation & Lightweight Fill 10 10 0% 13-Jan-20 24-Jan-20 0 ES 120 Establish Surcharge for Patient Parking Areas 5 5 0% 13-Jan-20 17-Jan-20 3 ES 115 Initial Building Zone Grading in Advance of Piles 5 5 0% 13-Jan-20 17-Jan-20 5

Piles & Concrete/MPiles & Concrete/Masonry Foundations 93 93 18-Jan-20 27-May-20 5

FND 1000 Surcharge Period for Patient Parking Zones 120 120 0% 18-Jan-20 16-May-20 5 FND 1005 Install Partial Stonebase for Laydown Areas - South 5 5 0% 20-Jan-20 24-Jan-20 20 FND 1010 Deliver Test Piles 1 1 0% 27-Jan-20 27-Jan-20 0 FND 1015 Drive Test Piles 2 2 0% 28-Jan-20 29-Jan-20 0 FND 1020 Restrike Piles (1 week later) 5 5 0% 30-Jan-20 05-Feb-20 0 FND 1025 Produce & Submit Report to NAVFAC 2 2 0% 06-Feb-20 07-Feb-20 0 FND 1030 NAVFAC Review & Approve Production Piles 10 10 0% 10-Feb-20 21-Feb-20 0 FND 1035 Drive Production Piles 12 12 0% 24-Feb-20 10-Mar-20 0 FND 1040 Pile Cap Cut-Offs 5 5 0% 09-Mar-20 13-Mar-20 0 FND 1050 Elevator Jackholes 2 2 0% 11-Mar-20 12-Mar-20 7 FND 1055 Construct Elevator Pit Slab & Walls 10 10 0% 11-Mar-20 24-Mar-20 36 FND 1045 Concrete Foundations & Grade Beams - Sector 2 10 10 0% 16-Mar-20 27-Mar-20 0 FND 1060 Concrete Foundations & Grade Beams - Sector 3 10 10 0% 23-Mar-20 03-Apr-20 1 FND 1065 Perimeter Foundation Block - Sector 2 5 5 0% 30-Mar-20 03-Apr-20 0 FND 1070 Concrete Foundations & Grade Beams - Sector 1 10 10 0% 30-Mar-20 10-Apr-20 6 FND 1075 Full-Height CIP Concrete Wall - Sector 3 15 15 0% 06-Apr-20 24-Apr-20 1 FND 1080 Perimeter Foundation Block - Sector 1 5 5 0% 13-Apr-20 17-Apr-20 6 FND 1085 Remove Surcharge Period for Patient Parking Zones 3 3 0% 18-May-20 20-May-20 4 FND 1090 Install Partial Stonebase for Laydown Areas - North 5 5 0% 21-May-20 27-May-20 5

Below-Slab R/Is anBelow-Slab R/Is and SOG 38 38 06-Apr-20 27-May-20 0

SOG 1000 Below-Slab Plumbing R/I - Sector 2 8 8 0% 06-Apr-20 15-Apr-20 0 SOG 1005 Below-Slab Plumbing R/I - Sector 1 8 8 0% 16-Apr-20 27-Apr-20 0 SOG 1010 Below-Slab Electrical R/I - Sector 2 8 8 0% 16-Apr-20 27-Apr-20 2 SOG 1015 Below-Slab Plumbing R/I - Sector 3 7 7 0% 28-Apr-20 06-May-20 0 SOG 1020 Below-Slab Electrical R/I - Sector 1 5 5 0% 28-Apr-20 04-May-20 2 SOG 1030 Below-Slab HVAC Pipe R/I - Sector 2 5 5 0% 28-Apr-20 04-May-20 7 SOG 1025 Below-Slab Sprinkler R/I - Sector 2 1 1 0% 28-Apr-20 28-Apr-20 11 SOG 1035 Prep & Place SOG - All Sectors 15 15 0% 07-May-20 27-May-20 0 SOG 1040 Below-Slab Electrical R/I - Sector 3 5 5 0% 07-May-20 13-May-20 0

Structural WorkStructural Work 103 103 28-May-20 19-Oct-20 0

STR 1000 Deliver Structural Steel & Shakeout 5 5 0% 28-May-20 03-Jun-20 0 STR 1005 Erect Structural Steel Framing 20 20 0% 04-Jun-20 01-Jul-20 0 STR 1010 2nd Floor Decking & Steel Detailing 10 10 0% 02-Jul-20 15-Jul-20 0 STR 1050 Studs 6 6 0% 10-Jul-20 17-Jul-20 0 STR 1015 Prep & Place SOMD 5 5 0% 20-Jul-20 24-Jul-20 0 STR 1020 Cure SOMD 5 5 0% 27-Jul-20 31-Jul-20 0 STR 1025 Erect Light Gauge High Roof Framing 15 15 0% 28-Jul-20 17-Aug-20 0 ep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2020 2021

Fabricate & Deliver Sprinkler Equipment

Mobilization of Offices to Site Site Survey & LOD Flagging

Construction Entrances & Initial E/C Measures

Clearing & Grubbing Construct Temp Sediment Basins 1, 2 & 3

Bench Excavation & Lightweight Fill Establish Surcharge for Patient Parking Areas Initial Building Zone Grading in Advance of Piles

Surcharge Period for Patient Parking Zones Install Partial Stonebase for Laydown Areas - South Deliver Test Piles Drive Test Piles Restrike Piles (1 week later) Produce & Submit Report to NAVFAC

NAVFAC Review & Approve Production Piles Drive Production Piles Pile Cap Cut-Offs Elevator Jackholes

Construct Elevator Pit Slab & Walls Concrete Foundations & Grade Beams - Sector 2 Concrete Foundations & Grade Beams - Sector 3 Perimeter Foundation Block - Sector 2 Concrete Foundations & Grade Beams - Sector 1

Full-Height CIP Concrete Wall - Sector 3 Perimeter Foundation Block - Sector 1

Remove Surcharge Period for Patient Parking Zones Install Partial Stonebase for Laydown Areas - North

Below-Slab Plumbing R/I - Sector 2 Below-Slab Plumbing R/I - Sector 1 Below-Slab Electrical R/I - Sector 2

Below-Slab Plumbing R/I - Sector 3 Below-Slab Electrical R/I - Sector 1 Below-Slab HVAC Pipe R/I - Sector 2

Below-Slab Sprinkler R/I - Sector 2 Prep & Place SOG - All Sectors

Below-Slab Electrical R/I - Sector 3

Deliver Structural Steel & Shakeout Erect Structural Steel Framing

2nd Floor Decking & Steel Detailing Studs Prep & Place SOMD Cure SOMD

Erect Light Gauge High Roof Framing

Actual Work Remaining Work Critical Remaining Work

Milestone P4042 - New Dental/Medical Clinics Whiting-Turner Contracting Company

Page 3 of 15 © Oracle Corporation

Rem Dur

% Comp Start Finish Total Float

STR 1030 Set & Protect AHU 2-1 for 2nd Floor Mech Rm 1 1 0% 03-Aug-20 03-Aug-20 0 STR 1035 High Roof Decking 15 15 0% 11-Aug-20 31-Aug-20 5 STR 1040 Erect Low-Roof CFMF Roof Structure 5 5 0% 06-Oct-20 12-Oct-20 0 STR 1045 Decking for Low Roof 5 5 0% 13-Oct-20 19-Oct-20 0

Roofing & Roof-ToRoofing & Roof-Top Work 60 60 01-Sep-20 23-Nov-20 82

RF 1000 Roof Edge Blocking 20 20 0% 01-Sep-20 28-Sep-20 82 RF 1005 Install Permanent Fall Protection System 10 10 0% 01-Sep-20 14-Sep-20 87 RF 1010 High Roof Ice & Water Shield 10 10 0% 22-Sep-20 05-Oct-20 82 RF 1015 Install Roof Hatches, Access Ladders & Vents 5 5 0% 06-Oct-20 12-Oct-20 82 RF 1025 Install SSM Roofing High Roof 15 15 0% 13-Oct-20 02-Nov-20 82 RF 1020 Low Roof Ice & Water Shield 10 10 0% 20-Oct-20 02-Nov-20 82 RF 1030 Install SSM Roofing Low Roof 15 15 0% 03-Nov-20 23-Nov-20 82

Exterior CladdingExterior Cladding 117 117 18-Aug-20 27-Jan-21 171

Building EnclosureBuilding Enclosure 92 92 18-Aug-20 23-Dec-20 47

CL 1000 Exterior CMU - 2nd Flr Level to Upper Attic-Level 20 20 0% 18-Aug-20 14-Sep-20 0 CL 1005 Exterior Door Frames @ Masonry Closure 5 5 0% 18-Aug-20 24-Aug-20 15 CL 1010 Ground Level CMU Closure & Rigid Insulation Board 30 30 0% 25-Aug-20 05-Oct-20 15 CL 1015 Air Barrier - 2nd Flr Level to Upper Attic-Level 2 2 0% 18-Sep-20 21-Sep-20 0 CL 1020 Exterior Brick Veneer - 2nd Flr Level to Upper Attic-Level 10 10 0% 22-Sep-20 05-Oct-20 0 CL 1025 Ground Level Air Barrier 5 5 0% 02-Oct-20 08-Oct-20 48 CL 1030 Brick Veneer Ground Level & Remainder of Upper Level 30 30 0% 06-Oct-20 16-Nov-20 47 CL 1035 Upper Level Windows 10 10 0% 26-Nov-20 09-Dec-20 47 CL 1040 Lower Level Windows & Storefront 10 10 0% 10-Dec-20 23-Dec-20 47

Canopy Structures, Canopy Structures, Ramp & Cladding Finishes 102 102 08-Sep-20 27-Jan-21 171

CL 2000 Access Ramp Footings & CIP Wall 5 5 0% 08-Sep-20 14-Sep-20 72 CL 2005 Access Ramp CMU 5 5 0% 15-Sep-20 21-Sep-20 72 CL 2010 Access Ramp Drains & Backfill 5 5 0% 22-Sep-20 28-Sep-20 72 CL 2015 Access Ramp Concrete Slab & Steps 5 5 0% 29-Sep-20 05-Oct-20 72 CL 2020 Access Ramp Veneer 5 5 0% 06-Oct-20 12-Oct-20 77 CL 2025 Erect Entry Canopy Steel & Decking 5 5 0% 20-Oct-20 26-Oct-20 102 CL 2030 Install Suspended Canopies 5 5 0% 17-Nov-20 23-Nov-20 47 CL 2035 Brickwash 2 2 0% 24-Nov-20 25-Nov-20 47 CL 2040 Entry Canopy SSM Roof 5 5 0% 24-Nov-20 30-Nov-20 82 CL 2105 Install Cementitious Trim/Fascias @ Eaves 20 20 0% 26-Nov-20 23-Dec-20 76 CL 2060 Louvers 2 2 0% 26-Nov-20 27-Nov-20 152 CL 2120 Install OH Door 5 5 0% 26-Nov-20 02-Dec-20 208 CL 2045 Building-Attached Exterior Lights 5 5 0% 26-Nov-20 02-Dec-20 211 CL 2050 Exterior Doors & Hardware 5 5 0% 26-Nov-20 02-Dec-20 211 CL 2065 Access Ramp Rails & Misc. Metal Trim 2 2 0% 26-Nov-20 27-Nov-20 214 CL 2070 Frame Entry Canopy Soffit 5 5 0% 01-Dec-20 07-Dec-20 82 CL 2075 SSM Roof Trim @ Suspended Canopies 5 5 0% 01-Dec-20 07-Dec-20 88 CL 2055 Exterior Caulking 3 3 0% 03-Dec-20 07-Dec-20 208 CL 2080 OH Electrical R/I @ Entry Canopy 5 5 0% 08-Dec-20 14-Dec-20 82 CL 2110 Install Exterior Soffits @ Eaves 15 15 0% 10-Dec-20 30-Dec-20 191 CL 2085 Above-Ceiling Inspection @ Entry Canopy 1 1 0% 15-Dec-20 15-Dec-20 82 CL 2090 Cementitious Trim @ Portico 5 5 0% 24-Dec-20 30-Dec-20 76 CL 2095 Paint Cementitious Board Trims 5 5 0% 31-Dec-20 06-Jan-21 76 CL 2100 Install Light in Entry Canopy Soffit 1 1 0% 31-Dec-20 31-Dec-20 190 CL 2115 Install Gutters & Downspouts 15 15 0% 07-Jan-21 27-Jan-21 76

Interior WorkInterior Work 241 241 20-Oct-20 21-Sep-21 11 ep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2020 2021

Set & Protect AHU 2-1 for 2nd Floor Mech Rm High Roof Decking

Erect Low-Roof CFMF Roof Structure Decking for Low Roof

Roof Edge Blocking Install Permanent Fall Protection System

High Roof Ice & Water Shield Install Roof Hatches, Access Ladders & Vents

Install SSM Roofing High Roof Low Roof Ice & Water Shield

Install SSM Roofing Low Roof

Exterior CMU - 2nd Flr Level to Upper Attic-Level Exterior Door Frames @ Masonry Closure

Ground Level CMU Closure & Rigid Insulation Board Air Barrier - 2nd Flr Level to Upper Attic-Level

Exterior Brick Veneer - 2nd Flr Level to Upper Attic-Level Ground Level Air Barrier

Brick Veneer Ground Level & Remainder of Upper Level Upper Level Windows

Lower Level Windows & Storefront

Access Ramp Footings & CIP Wall Access Ramp CMU Access Ramp Drains & Backfill Access Ramp Concrete Slab & Steps Access Ramp Veneer

Erect Entry Canopy Steel & Decking Install Suspended Canopies Brickwash Entry Canopy SSM Roof

Install Cementitious Trim/Fascias @ Eaves Louvers Install OH Door Building-Attached Exterior Lights Exterior Doors & Hardware

Access Ramp Rails & Misc. Metal Trim Frame Entry Canopy Soffit SSM Roof Trim @ Suspended Canopies Exterior Caulking OH Electrical R/I @ Entry Canopy

Install Exterior Soffits @ Eaves Above-Ceiling Inspection @ Entry Canopy

Cementitious Trim @ Portico Paint Cementitious Board Trims

Install Light in Entry Canopy Soffit Install Gutters & Downspouts

Actual Work Remaining Work Critical Remaining Work

Milestone P4042 - New Dental/Medical Clinics Whiting-Turner Contracting Company

Page 4 of 15 © Oracle Corporation

Rem Dur

% Comp Start Finish Total Float

Level 1Level 1 236 236 20-Oct-20 14-Sep-21 12

Level 1, S2Level 1, S2 174 174 20-Oct-20 18-Jun-21 69 Partions & Rough-Ins - L1, SPartions & Rough-Ins - L1, S2 60 60 20-Oct-20 11-Jan-21 119

RI 1 2000 Spray Fireproofing - L1,S2 5 5 0% 20-Oct-20 26-Oct-20 0 RI 1 2005 Non-Structural Masonry Partitions - L1, S2 10 10 0% 27-Oct-20 09-Nov-20 0 RI 1 2010 Duct Mains - L1,S2 15 15 0% 10-Nov-20 30-Nov-20 0 RI 1 2015 Interior Wall Framing - L1,S2 15 15 0% 17-Nov-20 07-Dec-20 35 RI 1 2020 In-Wall Electrical R/I - L1,S2 15 15 0% 24-Nov-20 14-Dec-20 119 RI 1 2025 In-Wall Plumbing R/I (all systems) - L1,S2 10 10 0% 01-Dec-20 14-Dec-20 35 RI 1 2030 Set ATUs & FCUs & Complete Branch Duct - L1,S2 10 10 0% 01-Dec-20 14-Dec-20 59 RI 1 2040 In-Wall Blocking - L1, S2 5 5 0% 08-Dec-20 14-Dec-20 49 RI 1 2045 Sprinkler R/I - L1,S2 15 15 0% 08-Dec-20 28-Dec-20 62 RI 1 2035 Refrigerant R/I Connections to ATUs - L1,S2 10 10 0% 08-Dec-20 21-Dec-20 69 RI 1 2050 OH Electrical R/I - All Systems - L1,S2 15 15 0% 08-Dec-20 28-Dec-20 119 RI 1 2055 Above-Floor Plumbing R/I - DWV - L1,S2 10 10 0% 15-Dec-20 28-Dec-20 35 RI 1 2060 Duct Insulation - L1,S2 10 10 0% 15-Dec-20 28-Dec-20 59 RI 1 2065 OH Plumbing Supply R/I (all Systems) - L1,S2 5 5 0% 15-Dec-20 21-Dec-20 64 RI 1 2070 Controls Connections to Above-Ceiling HVAC - L1,S2 5 5 0% 15-Dec-20 21-Dec-20 69 RI 1 2075 Electrical Connections to Above-Ceiling HVAC - L1,S2 5 5 0% 15-Dec-20 21-Dec-20 134 RI 1 2080 Plumbing Testing - L1,S2 2 2 0% 29-Dec-20 30-Dec-20 35 RI 1 2085 Pull Wire for Lights & Power - L1,S2 10 10 0% 29-Dec-20 11-Jan-21 119 RI 1 2100 Pull Wire for F/A & LV Systems - L1,S2 5 5 0% 29-Dec-20 04-Jan-21 124 RI 1 2090 Plumbing In-Wall Insulation - L1,S2 2 2 0% 31-Dec-20 01-Jan-21 35 RI 1 2095 Plumbing OH Insulation - L1,S2 3 3 0% 04-Jan-21 06-Jan-21 52

GWB & Ceiling Grid - L1, SGWB & Ceiling Grid - L1, S2 67 67 04-Jan-21 06-Apr-21 58 DW 1 2000 In-Wall Inspections & Corrections - L1,S2 5 5 0% 04-Jan-21 08-Jan-21 35 DW 1 2005 Hang GWB Walls - L1,S2 15 15 0% 11-Jan-21 29-Jan-21 35 DW 1 2010 Framing for Hard Ceilings - L1,S2 5 5 0% 28-Jan-21 03-Feb-21 37 DW 1 2015 Framing for Corridor Bulkheads & Soffits - L1,S2 5 5 0% 01-Feb-21 05-Feb-21 35 DW 1 2020 Mech/Elec Attachments to Hard Clg Framing - L1,S2 5 5 0% 04-Feb-21 10-Feb-21 37 DW 1 2025 Mech/Elec Attachments to Blkhd/Soffit Framing - L1,S2 5 5 0% 08-Feb-21 12-Feb-21 35 DW 1 2030 Hang & Finish Hard Ceiling GWB - L1,S2 10 10 0% 11-Feb-21 24-Feb-21 37 DW 1 2035 Hang Corridor Bulkhd/Soffit GWB - L1,S2 10 10 0% 15-Feb-21 26-Feb-21 35 DW 1 2040 Finish GWB Walls & Corridor Blkhd/Soffits - L1,S2 15 15 0% 15-Feb-21 05-Mar-21 35 DW 1 2045 Prime Paint GWB Surfaces in Advance of Grid - L1,S2 10 10 0% 08-Mar-21 19-Mar-21 58 DW 1 2050 Install Ceiling Grid - L1,S2 12 12 0% 22-Mar-21 06-Apr-21 58

Fixtures & Finishes - L1, S2Fixtures & Finishes - L1, S2 65 65 22-Mar-21 18-Jun-21 69 FIN 1 2010 Hard Tile Finishes - L1,S2 10 10 0% 22-Mar-21 02-Apr-21 79 FIN 1 2000 Casework & Millwork - L1,S2 15 15 0% 22-Mar-21 09-Apr-21 104 FIN 1 2005 Interior Glazing - L1,S2 5 5 0% 22-Mar-21 26-Mar-21 124 FIN 1 2015 Sprinkler Drops to Grid & Trimout - L1,S2 10 10 0% 31-Mar-21 13-Apr-21 65 FIN 1 2020 HVAC Attachments to Grid - L1,S2 10 10 0% 31-Mar-21 13-Apr-21 65 FIN 1 2025 Lights in Grid - L1,S2 10 10 0% 31-Mar-21 13-Apr-21 65 FIN 1 2040 Electrical Wall Trimout - L1,S2 10 10 0% 31-Mar-21 13-Apr-21 102 FIN 1 2030 Remainder of Prime Paint & Intermediate Finish Coats - L1,S2 5 5 0% 07-Apr-21 13-Apr-21 58 FIN 1 2055 Medical Specialties - L1,S2 15 15 0% 14-Apr-21 04-May-21 58 FIN 1 2035 Final Above-Ceiling Inspections - L1,S2 5 5 0% 14-Apr-21 20-Apr-21 65 FIN 1 2050 Interior Doors & Hardware - L1,S2 10 10 0% 14-Apr-21 27-Apr-21 67 FIN 1 2130 Install Medical Specialties & Casework - L1, S2 15 15 0% 14-Apr-21 04-May-21 73 FIN 1 2065 Pendant Lights - L1,S2 5 5 0% 14-Apr-21 20-Apr-21 97 FIN 1 2070 F/A Devices - L1,S2 10 10 0% 14-Apr-21 27-Apr-21 102 FIN 1 2080 Telecom Devices - L1,S2 5 5 0% 14-Apr-21 20-Apr-21 107 ep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2020 2021

Spray Fireproofing - L1,S2 Non-Structural Masonry Partitions - L1, S2

Duct Mains - L1,S2 Interior Wall Framing - L1,S2 In-Wall Electrical R/I - L1,S2 In-Wall Plumbing R/I (all systems) - L1,S2 Set ATUs & FCUs & Complete Branch Duct - L1,S2 In-Wall Blocking - L1, S2

Sprinkler R/I - L1,S2 Refrigerant R/I Connections to ATUs - L1,S2 OH Electrical R/I - All Systems - L1,S2 Above-Floor Plumbing R/I - DWV - L1,S2 Duct Insulation - L1,S2

OH Plumbing Supply R/I (all Systems) - L1,S2 Controls Connections to Above-Ceiling HVAC - L1,S2 Electrical Connections to Above-Ceiling HVAC - L1,S2

Plumbing Testing - L1,S2 Pull Wire for Lights & Power - L1,S2

Pull Wire for F/A & LV Systems - L1,S2 Plumbing In-Wall Insulation - L1,S2 Plumbing OH Insulation - L1,S2

In-Wall Inspections & Corrections - L1,S2 Hang GWB Walls - L1,S2 Framing for Hard Ceilings - L1,S2 Framing for Corridor Bulkheads & Soffits - L1,S2 Mech/Elec Attachments to Hard Clg Framing - L1,S2 Mech/Elec Attachments to Blkhd/Soffit Framing - L1,S2

Hang & Finish Hard Ceiling GWB - L1,S2 Hang Corridor Bulkhd/Soffit GWB - L1,S2 Finish GWB Walls & Corridor Blkhd/Soffits - L1,S2

Prime Paint GWB Surfaces in Advance of Grid - L Install Ceiling Grid - L1,S2

Hard Tile Finishes - L1,S2 Casework & Millwork - L1,S2

Interior Glazing - L1,S2 Sprinkler Drops to Grid & Trimout - L1,S2 HVAC Attachments to Grid - L1,S2 Lights in Grid - L1,S2 Electrical Wall Trimout - L1,S2 Remainder of Prime Paint & Intermediate Fin

Medical Specialties - L1,S2 Final Above-Ceiling Inspections - L1,S2 Interior Doors & Hardware - L1,S2 Install Medical Specialties & Casework - L

Pendant Lights - L1,S2 F/A Devices - L1,S2

Telecom Devices - L1,S2

Actual Work Remaining Work Critical Remaining Work

Milestone P4042 - New Dental/Medical Clinics Whiting-Turner Contracting Company

Page 5 of 15 © Oracle Corporation

Rem Dur

% Comp Start Finish Total Float

FIN 1 2085 Security Devices - L1,S2 5 5 0% 14-Apr-21 20-Apr-21 107 FIN 1 2090 Sealed Concrete Floors - L1,S2 5 5 0% 14-Apr-21 20-Apr-21 107 FIN 1 2095 Misc. Wall Protection Devices - L1,S2 5 5 0% 14-Apr-21 20-Apr-21 107 FIN 1 2075 HVAC Wall Trimout - L1,S2 3 3 0% 14-Apr-21 16-Apr-21 109 FIN 1 2045 Install Ceiling Tiles - L1,S2 7 7 0% 21-Apr-21 29-Apr-21 65 FIN 1 2105 Resilient Flooring - L1,S2 10 10 0% 30-Apr-21 13-May-21 90 FIN 1 2115 Carpet Flooring - L1,S2 5 5 0% 30-Apr-21 06-May-21 95 FIN 1 2125 Interior Signage - L1,S2 5 5 0% 14-May-21 20-May-21 90 FIN 1 2060 Set Plumbing Fixtures - L1,S2 5 5 0% 17-May-21 21-May-21 69 FIN 1 2100 Set Bathroom Vanities - L1,S2 5 5 0% 24-May-21 28-May-21 69 FIN 1 2110 Final Plumbing Connections - L1,S2 5 5 0% 31-May-21 04-Jun-21 69 FIN 1 2120 Bathroom Accessories & Partitions - L1,S2 5 5 0% 07-Jun-21 11-Jun-21 69 FIN 1 2135 Final Paint Touch-Up - L1,S2 5 5 0% 14-Jun-21 18-Jun-21 69

Level 1, S1Level 1, S1 193 193 27-Oct-20 22-Jul-21 45 Partions & Rough-Ins - L1, SPartions & Rough-Ins - L1, S1 70 70 27-Oct-20 01-Feb-21 111

RI 1 1000 Spray Fireproofing - L1,S1 5 5 0% 27-Oct-20 02-Nov-20 10 RI 1 1005 Non-Structural Masonry Partitions - L1, S1 10 10 0% 10-Nov-20 23-Nov-20 5 RI 1 1010 Duct Mains - L1,S1 15 15 0% 01-Dec-20 21-Dec-20 0 RI 1 1015 Interior Wall Framing - L1,S1 15 15 0% 08-Dec-20 28-Dec-20 35 RI 1 1020 In-Wall Electrical R/I - L1,S1 15 15 0% 15-Dec-20 04-Jan-21 111 RI 1 1025 In-Wall Plumbing R/I (all systems) - L1,S1 10 10 0% 22-Dec-20 04-Jan-21 35 RI 1 1030 Set ATUs & FCUs & Complete Branch Duct - L1,S1 10 10 0% 22-Dec-20 04-Jan-21 59 RI 1 1045 In-Wall Blocking - L1, S1 5 5 0% 29-Dec-20 04-Jan-21 49 RI 1 1050 Sprinkler R/I - L1,S1 15 15 0% 29-Dec-20 18-Jan-21 62 RI 1 1035 Refrigerant R/I Connections to ATUs - L1,S1 10 10 0% 29-Dec-20 11-Jan-21 69 RI 1 1055 OH Electrical R/I - All Systems - L1,S1 15 15 0% 29-Dec-20 18-Jan-21 111 RI 1 1060 Above-Floor Plumbing R/I - DWV - L1,S1 10 10 0% 05-Jan-21 18-Jan-21 35 RI 1 1065 Duct Insulation - L1,S1 10 10 0% 05-Jan-21 18-Jan-21 59 RI 1 1070 OH Plumbing Supply R/I (all Systems) - L1,S1 5 5 0% 05-Jan-21 11-Jan-21 64 RI 1 1075 Controls Connections to Above-Ceiling HVAC - L1,S1 5 5 0% 05-Jan-21 11-Jan-21 69 RI 1 1080 Electrical Connections to Above-Ceiling HVAC - L1,S1 5 5 0% 05-Jan-21 11-Jan-21 126 RI 1 1085 Plumbing Testing - L1,S1 2 2 0% 19-Jan-21 20-Jan-21 35 RI 1 1090 Pull Wire for Lights & Power - L1,S1 10 10 0% 19-Jan-21 01-Feb-21 111 RI 1 1105 Pull Wire for F/A & LV Systems - L1,S1 5 5 0% 19-Jan-21 25-Jan-21 116 RI 1 1095 Plumbing In-Wall Insulation - L1,S1 2 2 0% 21-Jan-21 22-Jan-21 35 RI 1 1100 Plumbing OH Insulation - L1,S1 3 3 0% 25-Jan-21 27-Jan-21 52

GWB & Ceiling Grid - L1, SGWB & Ceiling Grid - L1, S1 67 67 25-Jan-21 27-Apr-21 50 DW 1 1000 In-Wall Inspections & Corrections - L1,S1 5 5 0% 25-Jan-21 29-Jan-21 35 DW 1 1005 Hang GWB Walls - L1,S1 15 15 0% 01-Feb-21 19-Feb-21 35 DW 1 1010 Framing for Hard Ceilings - L1,S1 5 5 0% 18-Feb-21 24-Feb-21 37 DW 1 1015 Framing for Corridor Bulkheads & Soffits - L1,S1 5 5 0% 22-Feb-21 26-Feb-21 35 DW 1 1020 Mech/Elec Attachments to Hard Clg Framing - L1,S1 5 5 0% 25-Feb-21 03-Mar-21 37 DW 1 1025 Mech/Elec Attachments to Blkhd/Soffit Framing - L1,S1 5 5 0% 01-Mar-21 05-Mar-21 35 DW 1 1030 Hang & Finish Hard Ceiling GWB - L1,S1 10 10 0% 08-Mar-21 19-Mar-21 35 DW 1 1035 Hang Corridor Bulkhd/Soffit GWB - L1,S1 10 10 0% 08-Mar-21 19-Mar-21 35 DW 1 1040 Finish GWB Walls & Corridor Blkhd/Soffits - L1,S1 15 15 0% 08-Mar-21 26-Mar-21 35 DW 1 1045 Prime Paint GWB Surfaces in Advance of Grid - L1,S1 10 10 0% 29-Mar-21 09-Apr-21 50 DW 1 1050 Install Ceiling Grid - L1,S1 12 12 0% 12-Apr-21 27-Apr-21 50

Fixtures & Finishes - L1, S1Fixtures & Finishes - L1, S1 74 74 12-Apr-21 22-Jul-21 45 FIN 1 1010 Hard Tile Finishes - L1,S1 10 10 0% 12-Apr-21 23-Apr-21 74 FIN 1 1000 Casework & Millwork - L1,S1 15 15 0% 12-Apr-21 30-Apr-21 89 FIN 1 1005 Interior Glazing - L1,S1 5 5 0% 12-Apr-21 16-Apr-21 109 FIN 1 1015 Sprinkler Drops to Grid & Trimout - L1,S1 10 10 0% 21-Apr-21 04-May-21 50 ep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2020 2021

Security Devices - L1,S2 Sealed Concrete Floors - L1,S2 Misc. Wall Protection Devices - L1,S2 HVAC Wall Trimout - L1,S2

Install Ceiling Tiles - L1,S2 Resilient Flooring - L1,S2

Carpet Flooring - L1,S2 Interior Signage - L1,S2 Set Plumbing Fixtures - L1,S2 Set Bathroom Vanities - L1,S2 Final Plumbing Connections - L1,S2 Bathroom Accessories & Partitions Final Paint Touch-Up - L1,S2

Spray Fireproofing - L1,S1 Non-Structural Masonry Partitions - L1, S1

Duct Mains - L1,S1 Interior Wall Framing - L1,S1 In-Wall Electrical R/I - L1,S1 In-Wall Plumbing R/I (all systems) - L1,S1 Set ATUs & FCUs & Complete Branch Duct - L1,S1 In-Wall Blocking - L1, S1

Sprinkler R/I - L1,S1 Refrigerant R/I Connections to ATUs - L1,S1 OH Electrical R/I - All Systems - L1,S1 Above-Floor Plumbing R/I - DWV - L1,S1 Duct Insulation - L1,S1

OH Plumbing Supply R/I (all Systems) - L1,S1 Controls Connections to Above-Ceiling HVAC - L1,S1 Electrical Connections to Above-Ceiling HVAC - L1,S1

Plumbing Testing - L1,S1 Pull Wire for Lights & Power - L1,S1

Pull Wire for F/A & LV Systems - L1,S1 Plumbing In-Wall Insulation - L1,S1 Plumbing OH Insulation - L1,S1

In-Wall Inspections & Corrections - L1,S1 Hang GWB Walls - L1,S1 Framing for Hard Ceilings - L1,S1 Framing for Corridor Bulkheads & Soffits - L1,S1 Mech/Elec Attachments to Hard Clg Framing - L1,S1 Mech/Elec Attachments to Blkhd/Soffit Framing - L1

Hang & Finish Hard Ceiling GWB - L1,S1 Hang Corridor Bulkhd/Soffit GWB - L1,S1 Finish GWB Walls & Corridor Blkhd/Soffits - L1,S

Prime Paint GWB Surfaces in Advance of Grid Install Ceiling Grid - L1,S1

Hard Tile Finishes - L1,S1 Casework & Millwork - L1,S1

Interior Glazing - L1,S1 Sprinkler Drops to Grid & Trimout - L1,S1

Actual Work Remaining Work Critical Remaining Work

Milestone P4042 - New Dental/Medical Clinics Whiting-Turner Contracting Company

Page 6 of 15 © Oracle Corporation

Rem Dur

% Comp Start Finish Total Float

FIN 1 1020 HVAC Attachments to Grid - L1,S1 10 10 0% 21-Apr-21 04-May-21 50 FIN 1 1025 Lights in Grid - L1,S1 10 10 0% 21-Apr-21 04-May-21 50 FIN 1 1040 Electrical Wall Trimout - L1,S1 10 10 0% 21-Apr-21 04-May-21 87 FIN 1 1030 Remainder of Prime Paint & Intermediate Finish Coats - L1,S1 5 5 0% 28-Apr-21 04-May-21 52 FIN 1 1035 Final Above-Ceiling Inspections - L1,S1 5 5 0% 05-May-21 11-May-21 50 FIN 1 1050 Interior Doors & Hardware - L1,S1 10 10 0% 05-May-21 18-May-21 52 FIN 1 1055 Medical Specialties - L1,S1 15 15 0% 05-May-21 25-May-21 58 FIN 1 1060 Set Plumbing Fixtures - L1,S1 5 5 0% 05-May-21 11-May-21 77 FIN 1 1065 Pendant Lights - L1,S1 5 5 0% 05-May-21 11-May-21 82 FIN 1 1070 F/A Devices - L1,S1 10 10 0% 05-May-21 18-May-21 87 FIN 1 1080 Telecom Devices - L1,S1 5 5 0% 05-May-21 11-May-21 92 FIN 1 1085 Security Devices - L1,S1 5 5 0% 05-May-21 11-May-21 92 FIN 1 1090 Sealed Concrete Floors - L1,S1 5 5 0% 05-May-21 11-May-21 92 FIN 1 1095 Misc. Wall Protection Devices - L1,S1 5 5 0% 05-May-21 11-May-21 92 FIN 1 1075 HVAC Wall Trimout - L1,S1 3 3 0% 05-May-21 07-May-21 94 FIN 1 1045 Install Ceiling Tiles - L1,S1 7 7 0% 12-May-21 20-May-21 50 FIN 1 1100 Set Bathroom Vanities - L1,S1 5 5 0% 12-May-21 18-May-21 77 FIN 1 1105 Final Plumbing Connections - L1,S1 5 5 0% 19-May-21 25-May-21 77 FIN 1 1110 Resilient Flooring - L1,S1 10 10 0% 26-May-21 08-Jun-21 72 FIN 1 1115 Carpet Flooring - L1,S1 5 5 0% 26-May-21 01-Jun-21 77 FIN 1 1120 Bathroom Accessories & Partitions - L1,S1 5 5 0% 26-May-21 01-Jun-21 77 FIN 1 1125 Interior Signage - L1,S1 5 5 0% 09-Jun-21 15-Jun-21 72 FIN 1 1130 Install Medical Specialties & Casework - L1, S1 15 15 0% 25-Jun-21 15-Jul-21 36 FIN 1 1135 Final Paint Touch-Up - L1,S1 5 5 0% 16-Jul-21 22-Jul-21 45

Level 1, S3Level 1, S3 183 183 03-Nov-20 15-Jul-21 50 Partions & Rough-Ins - L1, SPartions & Rough-Ins - L1, S3 80 80 03-Nov-20 22-Feb-21 96

RI 1 3000 Spray Fireproofing - L1,S3 5 5 0% 03-Nov-20 09-Nov-20 20 RI 1 3005 Non-Structural Masonry Partitions - L1, S3 10 10 0% 24-Nov-20 07-Dec-20 10 RI 1 3010 Duct Mains - L1,S3 15 15 0% 22-Dec-20 11-Jan-21 0 RI 1 3015 Interior Wall Framing - L1,S3 15 15 0% 29-Dec-20 18-Jan-21 35 RI 1 3020 In-Wall Electrical R/I - L1,S3 15 15 0% 05-Jan-21 25-Jan-21 96 RI 1 3025 In-Wall Plumbing R/I (all systems) - L1,S3 10 10 0% 12-Jan-21 25-Jan-21 35 RI 1 3030 Set ATUs & FCUs & Complete Branch Duct - L1,S3 10 10 0% 12-Jan-21 25-Jan-21 59 RI 1 3040 In-Wall Blocking - L1, S3 5 5 0% 19-Jan-21 25-Jan-21 49 RI 1 3045 Sprinkler R/I - L1,S3 15 15 0% 19-Jan-21 08-Feb-21 62 RI 1 3035 Refrigerant R/I Connections to ATUs - L1,S3 10 10 0% 19-Jan-21 01-Feb-21 69 RI 1 3050 OH Electrical R/I - All Systems - L1,S3 15 15 0% 19-Jan-21 08-Feb-21 96 RI 1 3055 Above-Floor Plumbing R/I - DWV - L1,S3 10 10 0% 26-Jan-21 08-Feb-21 35 RI 1 3060 Duct Insulation - L1,S3 10 10 0% 26-Jan-21 08-Feb-21 59 RI 1 3065 OH Plumbing Supply R/I (all Systems) - L1,S3 5 5 0% 26-Jan-21 01-Feb-21 64 RI 1 3070 Controls Connections to Above-Ceiling HVAC - L1,S3 5 5 0% 26-Jan-21 01-Feb-21 69 RI 1 3075 Electrical Connections to Above-Ceiling HVAC - L1,S3 5 5 0% 26-Jan-21 01-Feb-21 111 RI 1 3080 Plumbing Testing - L1,S3 2 2 0% 09-Feb-21 10-Feb-21 35 RI 1 3085 Pull Wire for Lights & Power - L1,S3 10 10 0% 09-Feb-21 22-Feb-21 96 RI 1 3100 Pull Wire for F/A & LV Systems - L1,S3 5 5 0% 09-Feb-21 15-Feb-21 101 RI 1 3090 Plumbing In-Wall Insulation - L1,S3 2 2 0% 11-Feb-21 12-Feb-21 35 RI 1 3095 Plumbing OH Insulation - L1,S3 3 3 0% 15-Feb-21 17-Feb-21 52

GWB & Ceiling Grid - L1, SGWB & Ceiling Grid - L1, S3 67 67 15-Feb-21 18-May-21 35 DW 1 3000 In-Wall Inspections & Corrections - L1,S3 5 5 0% 15-Feb-21 19-Feb-21 35 DW 1 3005 Hang GWB Walls - L1,S3 15 15 0% 22-Feb-21 12-Mar-21 35 DW 1 3010 Framing for Hard Ceilings - L1,S3 5 5 0% 11-Mar-21 17-Mar-21 37 DW 1 3015 Framing for Corridor Bulkheads & Soffits - L1,S3 5 5 0% 15-Mar-21 19-Mar-21 35 DW 1 3020 Mech/Elec Attachments to Hard Clg Framing - L1,S3 5 5 0% 18-Mar-21 24-Mar-21 37 ep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2020 2021

HVAC Attachments to Grid - L1,S1 Lights in Grid - L1,S1 Electrical Wall Trimout - L1,S1 Remainder of Prime Paint & Intermediate Final Above-Ceiling Inspections - L1,S1 Interior Doors & Hardware - L1,S1 Medical Specialties - L1,S1

Set Plumbing Fixtures - L1,S1 Pendant Lights - L1,S1 F/A Devices - L1,S1

Telecom Devices - L1,S1 Security Devices - L1,S1 Sealed Concrete Floors - L1,S1 Misc. Wall Protection Devices - L1,S1 HVAC Wall Trimout - L1,S1

Install Ceiling Tiles - L1,S1 Set Bathroom Vanities - L1,S1 Final Plumbing Connections - L1,S1

Resilient Flooring - L1,S1 Carpet Flooring - L1,S1 Bathroom Accessories & Partitions -

Interior Signage - L1,S1 Install Medical Specialties & Final Paint Touch-Up - L1,S

Spray Fireproofing - L1,S3 Non-Structural Masonry Partitions - L1, S3

Duct Mains - L1,S3 Interior Wall Framing - L1,S3 In-Wall Electrical R/I - L1,S3 In-Wall Plumbing R/I (all systems) - L1,S3 Set ATUs & FCUs & Complete Branch Duct - L1,S3 In-Wall Blocking - L1, S3

Sprinkler R/I - L1,S3 Refrigerant R/I Connections to ATUs - L1,S3 OH Electrical R/I - All Systems - L1,S3 Above-Floor Plumbing R/I - DWV - L1,S3 Duct Insulation - L1,S3

OH Plumbing Supply R/I (all Systems) - L1,S3 Controls Connections to Above-Ceiling HVAC - L1,S3 Electrical Connections to Above-Ceiling HVAC - L1,S3

Plumbing Testing - L1,S3 Pull Wire for Lights & Power - L1,S3

Pull Wire for F/A & LV Systems - L1,S3 Plumbing In-Wall Insulation - L1,S3 Plumbing OH Insulation - L1,S3

In-Wall Inspections & Corrections - L1,S3 Hang GWB Walls - L1,S3 Framing for Hard Ceilings - L1,S3 Framing for Corridor Bulkheads & Soffits - L1,S3 Mech/Elec Attachments to Hard Clg Framing - L

Actual Work Remaining Work Critical Remaining Work

Milestone P4042 - New Dental/Medical Clinics Whiting-Turner Contracting Company

Page 7 of 15 © Oracle Corporation

Rem Dur

% Comp Start Finish Total Float

DW 1 3025 Mech/Elec Attachments to Blkhd/Soffit Framing - L1,S3 5 5 0% 22-Mar-21 26-Mar-21 35 DW 1 3030 Hang & Finish Hard Ceiling GWB - L1,S3 10 10 0% 29-Mar-21 09-Apr-21 35 DW 1 3035 Hang Corridor Bulkhd/Soffit GWB - L1,S3 10 10 0% 29-Mar-21 09-Apr-21 35 DW 1 3040 Finish GWB Walls & Corridor Blkhd/Soffits - L1,S3 15 15 0% 29-Mar-21 16-Apr-21 35 DW 1 3045 Prime Paint GWB Surfaces in Advance of Grid - L1,S3 10 10 0% 19-Apr-21 30-Apr-21 35 DW 1 3050 Install Ceiling Grid - L1,S3 12 12 0% 03-May-21 18-May-21 35

Fixtures & Finishes - L1, S3Fixtures & Finishes - L1, S3 54 54 03-May-21 15-Jul-21 50 FIN 1 3010 Hard Tile Finishes - L1,S3 10 10 0% 03-May-21 14-May-21 69 FIN 1 3000 Casework & Millwork - L1,S3 15 15 0% 03-May-21 21-May-21 74 FIN 1 3005 Interior Glazing - L1,S3 5 5 0% 03-May-21 07-May-21 94 FIN 1 3015 Sprinkler Drops to Grid & Trimout - L1,S3 10 10 0% 12-May-21 25-May-21 35 FIN 1 3020 HVAC Attachments to Grid - L1,S3 10 10 0% 12-May-21 25-May-21 35 FIN 1 3025 Lights in Grid - L1,S3 10 10 0% 12-May-21 25-May-21 35 FIN 1 3040 Electrical Wall Trimout - L1,S3 10 10 0% 12-May-21 25-May-21 72 FIN 1 3030 Remainder of Prime Paint & Intermediate Finish Coats - L1,S3 5 5 0% 19-May-21 25-May-21 37 FIN 1 3035 Final Above-Ceiling Inspections - L1,S3 5 5 0% 26-May-21 01-Jun-21 35 FIN 1 3050 Interior Doors & Hardware - L1,S3 10 10 0% 26-May-21 08-Jun-21 37 FIN 1 3055 Medical Specialties - L1,S3 15 15 0% 26-May-21 15-Jun-21 58 FIN 1 3060 Set Plumbing Fixtures - L1,S3 5 5 0% 26-May-21 01-Jun-21 62 FIN 1 3065 Pendant Lights - L1,S3 5 5 0% 26-May-21 01-Jun-21 67 FIN 1 3070 F/A Devices - L1,S3 10 10 0% 26-May-21 08-Jun-21 72 FIN 1 3080 Telecom Devices - L1,S3 5 5 0% 26-May-21 01-Jun-21 77 FIN 1 3085 Security Devices - L1,S3 5 5 0% 26-May-21 01-Jun-21 77 FIN 1 3090 Sealed Concrete Floors - L1,S3 5 5 0% 26-May-21 01-Jun-21 77 FIN 1 3095 Misc. Wall Protection Devices - L1,S3 5 5 0% 26-May-21 01-Jun-21 77 FIN 1 3075 HVAC Wall Trimout - L1,S3 3 3 0% 26-May-21 28-May-21 79 FIN 1 3045 Install Ceiling Tiles - L1,S3 7 7 0% 02-Jun-21 10-Jun-21 35 FIN 1 3100 Set Bathroom Vanities - L1,S3 5 5 0% 02-Jun-21 08-Jun-21 62 FIN 1 3110 Final Plumbing Connections - L1,S3 5 5 0% 09-Jun-21 15-Jun-21 62 FIN 1 3105 Resilient Flooring - L1,S3 10 10 0% 11-Jun-21 24-Jun-21 60 FIN 1 3115 Carpet Flooring - L1,S3 5 5 0% 11-Jun-21 17-Jun-21 65 FIN 1 3120 Bathroom Accessories & Partitions - L1,S3 5 5 0% 16-Jun-21 22-Jun-21 62 FIN 1 3125 Install Medical Specialties & Casework - L1, S3 15 15 0% 25-Jun-21 15-Jul-21 36 FIN 1 3130 Interior Signage - L1,S3 5 5 0% 25-Jun-21 01-Jul-21 60 FIN 1 3135 Final Paint Touch-Up - L1,S3 5 5 0% 25-Jun-21 01-Jul-21 60

Elec Room 1133Elec Room 1133 36 36 24-Dec-20 12-Feb-21 140 MER 1000 Set MDP & Misc. Elec. Equip & Panels in Main Elec Rm 5 5 0% 24-Dec-20 30-Dec-20 98 MER 1005 Buildout MDP & Panels in Main Elec Room 20 20 0% 31-Dec-20 27-Jan-21 98 MER 1010 Pull Feeders to Rm 1133 5 5 0% 28-Jan-21 03-Feb-21 98 MER 1015 Pull Secondary Wiring to Xfrmr 5 5 0% 04-Feb-21 10-Feb-21 98 MER 1020 Pull Secondary Wiring to Generator 5 5 0% 04-Feb-21 10-Feb-21 98 MER 1025 Energize 1 1 0% 11-Feb-21 11-Feb-21 98 MER 1030 Main Electrical Room & Energize 0 0 0% 12-Feb-21 12-Feb-21 140

Main Mech Rooms - 1Main Mech Rooms - 1209 & 1211 89 89 03-Nov-20 05-Mar-21 85 MMR 1000 Set AHU 1.1 5 5 0% 03-Nov-20 09-Nov-20 126 MMR 1005 Set Boilers & Pumps 5 5 0% 10-Nov-20 16-Nov-20 126 MMR 1010 Duct Connections to AHU 1.1 15 15 0% 17-Nov-20 07-Dec-20 126 MMR 1015 General Piping for Boilers 10 10 0% 17-Nov-20 30-Nov-20 126 MMR 1020 General Piping for Pumps 5 5 0% 01-Dec-20 07-Dec-20 126 MMR 1025 Electrical R/I & Connections to Boilers 10 10 0% 01-Dec-20 14-Dec-20 141 MMR 1030 Controls R/I & Connections to Boilers 10 10 0% 01-Dec-20 14-Dec-20 141 MMR 1035 Piping Connections to AHU 1.1 5 5 0% 08-Dec-20 14-Dec-20 126 MMR 1040 Electrical R/I & Connections to Pumps 10 10 0% 08-Dec-20 21-Dec-20 126 ep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2020 2021

Mech/Elec Attachments to Blkhd/Soffit Framing Hang & Finish Hard Ceiling GWB - L1,S3 Hang Corridor Bulkhd/Soffit GWB - L1,S3 Finish GWB Walls & Corridor Blkhd/Soffits - L

Prime Paint GWB Surfaces in Advance of Install Ceiling Grid - L1,S3

Hard Tile Finishes - L1,S3 Casework & Millwork - L1,S3

Interior Glazing - L1,S3 Sprinkler Drops to Grid & Trimout - L1 HVAC Attachments to Grid - L1,S3 Lights in Grid - L1,S3 Electrical Wall Trimout - L1,S3 Remainder of Prime Paint & Intermed Final Above-Ceiling Inspections - L1, Interior Doors & Hardware - L1,S3 Medical Specialties - L1,S3

Set Plumbing Fixtures - L1,S3 Pendant Lights - L1,S3 F/A Devices - L1,S3

Telecom Devices - L1,S3 Security Devices - L1,S3 Sealed Concrete Floors - L1,S3 Misc. Wall Protection Devices - L1,S HVAC Wall Trimout - L1,S3

Install Ceiling Tiles - L1,S3 Set Bathroom Vanities - L1,S3 Final Plumbing Connections - L1, Resilient Flooring - L1,S3 Carpet Flooring - L1,S3 Bathroom Accessories & Partitio

Install Medical Specialties & Interior Signage - L1,S3 Final Paint Touch-Up - L1,S3

Set MDP & Misc. Elec. Equip & Panels in Main Elec Rm Buildout MDP & Panels in Main Elec Room Pull Feeders to Rm 1133 Pull Secondary Wiring to Xfrmr Pull Secondary Wiring to Generator Energize Main Electrical Room & Energize

Set AHU 1.1 Set Boilers & Pumps

Duct Connections to AHU 1.1 General Piping for Boilers General Piping for Pumps Electrical R/I & Connections to Boilers Controls R/I & Connections to Boilers Piping Connections to AHU 1.1 Electrical R/I & Connections to Pumps

Actual Work Remaining Work Critical Remaining Work

Milestone P4042 - New Dental/Medical Clinics Whiting-Turner Contracting Company

Page 8 of 15 © Oracle Corporation

Rem Dur

% Comp Start Finish Total Float

MMR 1045 Electrical R/I & Connections to AHU 1.1 10 10 0% 15-Dec-20 28-Dec-20 131 MMR 1050 Controls R/I & Connections to AHU 1.1 10 10 0% 15-Dec-20 28-Dec-20 131 MMR 1060 Controls R/I & Connections to Pumps 10 10 0% 22-Dec-20 04-Jan-21 126 MMR 1055 Duct Insulation in Main Mechanical Room 10 10 0% 05-Jan-21 18-Jan-21 116 MMR 1065 Piping Insulation in Main Mechanical Room 15 15 0% 12-Jan-21 01-Feb-21 106 MMR 1070 Start Up AHU 1.1 3 3 0% 03-Mar-21 05-Mar-21 85

ElevatorElevator 153 153 12-Feb-21 14-Sep-21 12 ELEV 1000 Install Elevator Equipment 5 5 0% 12-Feb-21 18-Feb-21 125 ELEV 1005 Set & Buildout Elevator Cab 15 15 0% 28-Jul-21 17-Aug-21 12 ELEV 1010 Elevator Finishes & Landing Trimout 15 15 0% 18-Aug-21 07-Sep-21 12 ELEV 1015 Subcontractor Elevator Testing 5 5 0% 08-Sep-21 14-Sep-21 12

StairsStairs 36 36 19-Jan-21 09-Mar-21 127 West StairWest Stair 36 36 19-Jan-21 09-Mar-21 127

STW 1000 Erect Stair Risers - West Stair 5 5 0% 19-Jan-21 25-Jan-21 127 STW 1005 Pan-Fills & Concrete Landings - West Stair 5 5 0% 26-Jan-21 01-Feb-21 127 STW 1010 Exposed & Above-Ceiling R/Is - West Stairs 5 5 0% 02-Feb-21 08-Feb-21 127 STW 1015 Stairwell Handrails - West Stairs 5 5 0% 02-Feb-21 08-Feb-21 138 STW 1020 Above-Ceiling Inspections - West Stairs 1 1 0% 09-Feb-21 09-Feb-21 127 STW 1025 Hang Soffit GWB - West Stairs 5 5 0% 10-Feb-21 16-Feb-21 127 STW 1030 Finish GWB - West Stairs 5 5 0% 17-Feb-21 23-Feb-21 127 STW 1035 Paint Stairwell - West Stairs 5 5 0% 24-Feb-21 02-Mar-21 127 STW 1040 Stairwell Trimout - West Stairs 5 5 0% 03-Mar-21 09-Mar-21 127

East StairEast Stair 36 36 19-Jan-21 09-Mar-21 127 STE 1000 Erect Stair Risers - East Stair 5 5 0% 19-Jan-21 25-Jan-21 127 STE 1005 Pan-Fills & Concrete Landings - East Stair 5 5 0% 26-Jan-21 01-Feb-21 127 STE 1010 Exposed & Above-Ceiling R/Is - East Stairs 5 5 0% 02-Feb-21 08-Feb-21 127 STE 1015 Stairwell Handrails - East Stairs 5 5 0% 02-Feb-21 08-Feb-21 138 STE 1020 Above-Ceiling Inspections - East Stairs 1 1 0% 09-Feb-21 09-Feb-21 127 STE 1025 Hang Soffit GWB - East Stairs 5 5 0% 10-Feb-21 16-Feb-21 127 STE 1030 Finish GWB - East Stairs 5 5 0% 17-Feb-21 23-Feb-21 127 STE 1035 Paint Stairwell - East Stairs 5 5 0% 24-Feb-21 02-Mar-21 127 STE 1040 Stairwell Trimout - East Stairs 5 5 0% 03-Mar-21 09-Mar-21 127

Level 2Level 2 206 206 08-Dec-20 21-Sep-21 11

L…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .