This document is a Change Order (Add) for the Queen Creek Bridge project, issued by the Arizona Department of Transportation (ADOT) to AMES CONSTRUCTION, INC. on October 16, 2025. The work is managed by ADOT Resident Engineer Mark Guerena, with AMES PROJECT NO. 240302. The change order pertains to project numbers 060 PN 227 H856601C and 060 PN 229 F031501C and addresses emergency repairs resulting from weather-related damage to US Route 60.
The scope of work includes slope, shoulder, and roadway repair for two sections of US 60 that were damaged by a storm, resulting in loss of slope, shoulder, guardrail, and pavement. The work is broken into three sub-areas: Shoulder Grading ($1,181,120.82), Traffic Control ($962,304.00), and Cactus Paving & PMI Striping ($82,635.00). The subtotal for proposed work is $2,226,059.82. After application of 65% of 6.7% gross receipts tax ($96,944.91) and a 0.50% bond requirement ($11,615.02), the total contract amount is $2,334,619.75. Shoulder Grading includes approximately 8,300 cubic yards of rock fill, labor for equipment operation, material disposal, and temporary housing for off-project labor. Traffic Control encompasses 24-hour flagging and pilot car services for 30 days, temporary traffic control signs, barrier and attenuator equipment, and law enforcement support totaling 1,680 hours. Cactus Paving operations include asphalt mix application (126 tons of ADOT 409 mix), tack oil, temporary striping by PMI covering 10,000 linear feet, and striping eradication.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT: Queen Creek Bridge
060 PN 227 H856601C / 060 PN 229 F031501C DATE: 10/16/2025
TO:
Attn.: Mark Guerena, PE AMES PROJECT NO.: 240302
Resident Engineer
INITIATED BY: ADOT
REASON:
QTY Unit Unit Price Total
1 LS $ 2,226,059.82 $ 2,226,059.82
Subtotal 2,226,059.82$
Tax (65% of 6.7%) Gross Rec Tax 96,944.91$
Subtotal 2,323,004.72$
0.50% Bond 11,615.02$
Subtotal 2,334,619.75$
TOTAL 2,334,619.75$
Net Amount of This Proposed Work
2,334,619.75$
SUBMITTED BY: DATE:
ACCEPTED BY: DATE:
(Owner/Engineer)
AMES CONSTRUCTION
Repairing Weather Related Slope and Shoulder Damage (Including Roadway)
Storm caused two sections of US 60 to wash away taking slope, shoulder, guardrail, and pavement
Arizona Department of Transportation
Description
WORK DESCRIPTION:
SLOPE, SHOULDER, AND ROADWAY REPAIR
10/16/2025
ADD
BUDGET WORKSHEET DATE:
Sub Areas QTY UNIT UNIT PRICE SUBTOTALS
Shoulder Grading 1 LS 1,181,120.82$ 1,181,120.82$
Traffic Control 1 LS 962,304.00$ 962,304.00$
Cactus Paving & PMI 1 LS 82,635.00$ 82,635.00$
Total Cost 2,226,059.82$
AMES CONSTRUCTION, INC.
16-Oct-25
Ames Const.
LABOR EA MHRS $/Hr + Fringe SUBTOTALS
EQUIPMENT PIECES HRS $/UNIT SUBTOTALS
MATERIAL Qty Unit $/UNIT SUBTOTALS
SUBCONTRACTOR/MISC Qty Unit Cost SUBTOTALS
Traffic Cont Labor (Flagging & Piloting, 24 HR/DAY) 30.00 DAYS 17,000.00$ 510,000.00$
Temporary Traffic Control Signs (Include Install & Removal) 1.00 LS 28,400.00$ 28,400.00$
Howe Barrier & Atten. Purchase (Replace Broken Att. & Move) 1.00 LS 200,000.00$ 200,000.00$
Law Enforcement (2 HR Travel for Shift) 1,680.00 HRS 106.00$ 178,080.00$
Subcontractor Total Cost 916,480.00$
Total Cost With Markup 5% 962,304.00$
Contractor Support Total Cost -$
Total Cost With Markup 15% -$
Total Cost 962,304.00$
AMES CONSTRUCTION, INC.
16-Oct-25
WORK DESCRIPTION:
TRAFFIC CONTROL LABOR - 24 HOUR FLAGGING & PILOT CAR & REPLACEMENT AND RENTAL OF TEMPORARY
TRAFFIC SIGNS, BARRIER AND ATTENUATOR REPLACE AND PURCHASE AND MOVEMENT
Ames Const. Ames Const.
EQUIPMENT PIECES HRS $/UNIT SUBTOTALS
MATERIAL Qty Unit $/UNIT SUBTOTALS
SUBCONTRACTOR/MISC Qty Unit Cost SUBTOTALS
Cactus Paving Operation -$
Cactus Paving Labor 1 DAY 10,000.00$ 10,000.00$
Cactus Paving Equipment 1 DAY 20,000.00$ 20,000.00$
Cactus Mobilization 1 EA 10,000.00$ 10,000.00$
ADOT 409 (Asphalt Mix) 126 TN 150.00$ 18,900.00$
Tack Oil 2 TN 400.00$ 800.00$
PMI Striping Operation -$
PMI Temp Striping (MOB) 1 EA 5,000.00$ 5,000.00$
PMI Temp Striping (White & Double Yellow) 10000 LF 0.40$ 4,000.00$
PMI Eradication 10000 LF 1.00$ 10,000.00$
Subcontractor Total Cost 78,700.00$
Total Cost With Markup 5% 82,635.00$
Contractor Support Total Cost -$
Total Cost With Markup 15% -$
Total Cost 82,635.00$
AMES CONSTRUCTION, INC.
16-Oct-25
WORK DESCRIPTION: Cactus Paving Operation & PMI Striping
LOADER OPERATOR 1 300 74.68$ 22,404.00$
DOZER OPERATOR 2 290 76.26$ 44,232.83$
EXCAVATOR OPERATOR 2 290 76.26$ 44,232.83$
SKIDSTEER OPERATOR 1 300 74.68$ 22,404.00$
LABORER 3 300 58.12$ 52,312.48$
WATER TRUCK DRIVER 1 300 69.94$ 20,982.31$
FOREMAN 1 300 80.61$ 24,183.00$
SUPERINTENDENT 1 300 98.90$ 29,670.00$
EQUIPMENT PIECES HRS $/UNIT SUBTOTALS
Cat 966 Loader 1 300 93.21$ 27,963.00$
Cat D8 Dozer 1 280 308.54$ 86,391.20$
Cat D6 Dozer 1 300 144.10$ 43,230.00$
Cat Skidsteer 1 300 87.31$ 26,193.00$
Cat 320 Excavator 2 290 94.20$ 54,636.00$
Cat Motorgrader 1 20 210.00$ 4,200.00$
EQUIPMENT MOB (PER EA - IN/OUT) 4 2 3,166.67$ 25,333.36$
Manlift 1 10 78.69$ 786.90$
Water Truck 1 300 65.42$ 19,626.00$
Compactor 1 300 86.12$ 25,836.00$
Crew Van 1 300 28.00$ 8,400.00$
Broom 1 300 61.05$ 18,315.00$
Foreman Pickup 2 300 29.50$ 17,700.00$
Lightplants 4 300 16.87$ 20,248.80$
MATERIAL Qty Unit $/UNIT SUBTOTALS
ASPHALT DISPOSAL 1 LS 30,000.00$ 30,000.00$
GUARDRAIL DISPOSAL 1 LS 30,000.00$ 30,000.00$
AGGREGATE BASE 122 TON 35.00$ 4,270.00$
HOTELS FOR OFF PROJECT LABOR (8 WORKERS/ 30 DAYS) 240 DAYS 200.00$ 48,000.00$
SUBCONTRACTOR/MISC Qty Unit Cost SUBTOTALS
ASPHALT SAW CUT 350 LF 5.00$ 1,750.00$
ROCK HAULING (5 TRUCKS PER SHIFT / 10 HR SHIFT) 1500 HRS 200.00$ 300,000.00$
Subcontractor Total Cost 301,750.00$
Total Cost With Markup 5% 316,837.50$
Contractor Support Total Cost 751,550.71$
Total Cost With Markup 15% 864,283.32$
Total Cost 1,181,120.82$
AMES CONSTRUCTION, INC.
16-Oct-25
WORK DESCRIPTION: Repairing Washout Slopes and Grade Backfilled Shoulders (Approx. 8,300 CY Rock)