Amendment #6.pdf
PDF 64 KB Posted
- Attached to
- Boney Courthouse Mechanical Upgrades Design
- Solicitation number
- ANC-C-B-P-25-0001
- Issued by
- Anchorage Municipality, Alaska
About this file
This is Amendment #6 from the Court System addressing a vendor question about project scheduling. The amendment clarifies that while the anticipated project start date is March 17, 2025, the full design completion deadline of June 16, 2025, will remain fixed. However, the Court System indicates flexibility in considering a designer's proposed "goal" schedule after contract award, provided it is reasonable.
No additional pricing terms, funding requirements, set-asides, or other contract details are included in this amendment.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment #6
Question:
With an anticipated start date of March 17, 2025, can we propose a schedule that extends the full design completion date past June 16, 2025? And if so, then what would be a reasonable extension?
Response:
The full design completion date will remain as June 16, 2025. After an award the Court System is open to a designer’s “goal” schedule that is reasonable.