This is Amendment #2 to a Request for Quote issued by the South Carolina Department of Parks, Recreation & Tourism for soil injection herbicide application services at Cheraw State Park. The solicitation (Number 5400019471) was issued on March 25, 2020, with Procurement Officer Scott Dobereiner listed as the primary contact. The project involves applying herbicide via spray application in a grid pattern across the park grounds. According to the original solicitation requirements, contractors must complete all work by June 30, 2020. The submission deadline was initially extended indefinitely due to COVID-19 uncertainty, with bidders to receive 72 hours' notice of the revised deadline once determined. Access to the site will be provided on a limited basis for vehicles and ATV/UTV use, with a detailed map provided to the awarded contractor. Water sources are available at the maintenance shop during standard business hours (approximately 6:30 a.m. to 4:00 p.m., Monday through Friday), with potential access to a fire hydrant outside the maintenance gate subject to fire department approval.
This amendment addresses five questions and answers submitted by potential offerors regarding project specifications and execution requirements. Generic brand herbicides are acceptable as substitutes, though the South Carolina Department of Parks, Recreation & Tourism reserves the right to reject any generic substitutions. The amendment clarifies that "soil injection" refers to ground-level spray application rather than subsurface chemical injection. No pricing information, set-asides, incumbency details, or funding amounts are specified in this amendment document.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 3.pdf | ||
| Solicitation.pdf | ||
| Amendment #1.pdf | ||
| Site Map-Soil Injection.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SAP
State of South Carolina
Request for Quote Amendment #2
Solicitation Number:
Date Issued:
Procurement Officer:
Phone:
E-Mail Address:
Mailing Address:
5400019471 03/25/2020 Scott Dobereiner
(803) 734-1302 sdobereiner@scprt.com SC Dept. of Parks, Recreation & Tourism; Attn: Procurement 1205 Pendleton Street, Room 517 Columbia SC 29201
DESCRIPTION: Soil Injection Herbicide Application-Cheraw State Park USING GOVERNMENTAL UNIT: SC Dept. of Parks, Recreation & Tourism
Due to the uncertainty surrounding the COVID-19 virus, the Submission Deadline for this solicitation is extended indefinitely.
Revised Submission Deadline cannot be determined at this time, bidders will be given 72 hours’ notice of the revised Submission Deadline once a date has been determined.
QUESTIONS FROM OFFERORS - AMENDMENT (JUN 2017)
THE SOLICITATION IS AMENDED AS PROVIDED HEREIN. INFORMATION OR CHANGES RESULTING FROM QUESTIONS WILL BE SHOWN IN A QUESTION-AND-ANSWER FORMAT. ALL QUESTIONS RECEIVED HAVE BEEN REPRINTED BELOW. THE “STATE’S RESPONSE” SHOULD BE READ WITHOUT REFERENCE TO THE QUESTIONS. THE QUESTIONS ARE INCLUDED SOLELY TO PROVIDE A CROSS-REFERENCE TO THE POTENTIAL OFFEROR THAT SUBMITTED THE QUESTION. QUESTIONS DO NOT FORM A PART OF THE CONTRACT; THE “STATE’S RESPONSE” DOES. ANY RESTATEMENT OF PART OR ALL OF AN EXISTING PROVISION OF THE SOLICITATION IN AN ANSWER DOES NOT MODIFY THE ORIGINAL PROVISION EXCEPT AS FOLLOWS: UNDERLINED TEXT IS ADDED TO THE ORIGINAL PROVISON. STRICKEN TEXT IS DELETED. [02-2A097-1]
The following questions have been received, questions and answers are below. The State’s response is in red.
Q1. Are there water sources available? If available, what hours are the sources available?
There are water sources at the maintenance shop including a garden hose (clean water) and a higher flow hose (water flowing from the lake). These will be available from approximately 6:30am-4:00pm, Monday-Friday. The fire hydrant is stationed just outside of the maintenance gate, and would be available as long as permissions were obtained from the fire department.
Q2. Will there be vehicle and ATV/UTV access to the site?
Some vehicle and ATV/UTV access will be allowed on the project site. A detailed map with access availability will be given to the contractor upon award.
Q3. We’re confused with the term “soil injection”? Won’t the fertilizer just be sprayed?
The ‘soil injection’ term does not describe the chemical being injected into the soil by equipment, the chemical will be sprayed onto the ground in a grid pattern.
Q4. What are the dates for the project completion?
As stated in Section III, Vendor Responsibilities, paragraph 10 (page 13 of the solicitation), the contractor will have until June 30, 2020 to complete.
Q5. Is using a different generic brand of herbicide acceptable?
As stated in Section III, Vendor Responsibilities, paragraph 2 (page 13 of the solicitation), generic brand of herbicide is acceptable. SCPRT reserves the right to reject any generic substitutions.