About this file
This is Amendment #1 to an Invitation for Bid issued by the South Carolina Department of Natural Resources for construction work on Building YWC 7 (Whitemarsh House) at the Tom Yawkey Wildlife Center in Georgetown, South Carolina. The project encompasses four separate lots: Lot 1 covering installation of 13 vinyl replacement windows with composite trim; Lot 2 addressing rough-in and trim-out electrical wiring including meter base, panels, fixtures, outlets, and switches; Lot 3 providing rough-in and trim-out plumbing for supply lines, drain lines, and fixtures in kitchen, bathrooms, laundry room, and exterior spigots; and Lot 4 installing new HVAC ductwork and registers compatible with existing equipment. A mandatory pre-bid conference is scheduled for July 22, 2026 at 11:30 a.m. at Tom Yawkey Wildlife Center, with attendees required to meet at the boat ramp for waterway crossing. Sealed bids must be submitted by August 12, 2026 at 10:00 a.m. EST to the SC Department of Natural Resources Procurement Services office. Questions from bidders must be received by July 23, 2026 at 3:00 p.m. EST. Award notification is scheduled for August 13, 2026, with all work to be completed within 120 days of purchase order receipt, with an estimated contract period from August 14 through November 30, 2026.
The amendment addresses vendor questions and provides clarifications on project scope including generator size specifications (maximum 16 kW), material supply responsibilities, and electrical installation details. SCDNR will supply the main electrical panel for the outdoor shed, the trench from meter to house, overhead lights, ceiling fans, vanity lights, shower valves, faucets, and toilets, while the contractor is responsible for meter base, wire, breakers, conduit, service feeder wire, subpanels if required, and all installation labor. The amendment corrects electrical device quantities in multiple rooms from earlier draft specifications. Payment terms follow South Carolina Code Section 11-35-45, requiring payment within thirty work days following acceptance of goods or services and proper invoice, with interest penalties of up to fifteen percent annually on unpaid balances exceeding the thirty-day period. Award will be made to the lowest responsible and responsive bidder by complete lot(s), with unit prices governing evaluation. Contractors must be licensed in their respective trades, provide current insurance certificates with specified minimum coverage, and offer one-year labor warranties on craftsmanship plus manufacturer warranties on materials.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| No Award Statement.doc | DOC document | |
| Solicitation.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
State of South Carolina
Invitation for Bid Amendment #1 Solicitation:
Date Issued:
Procurement Officer:
Phone:
E-Mail Address:
Mailing Address:
5400029995 7/24/26 Andy Bowman, CPPB 803-734-3933 BowmanA@dnr.sc.gov SC Department of Natural Resources Attn: Procurement Services 260D Epting Lane West Columbia SC 29172
DESCRIPTION: Windows, Electric, Plumbing, and Duct Work-Yawkey WMA
USING GOVERNMENTAL UNIT: SC Department of Natural Resources Admin
The Term "Offer" Means Your "Bid" or "Proposal". Your offer must be submitted in a sealed package. Solicitation Number & Opening Date must appear on package exterior. See "Submitting Your Paper Offer or Modification" provision.
SUBMIT YOUR SEALED OFFER TO EITHER OF THE FOLLOWING ADDRESSES:
MAILING ADDRESS:
SC Department of Natural Resources Attn: Procurement Services 260D Epting Lane West Columbia SC 29172
PHYSICAL ADDRESS:
SC Department of Natural Resources Attn: Procurement Services 260D Epting Lane West Columbia SC 29172
SUBMIT OFFER BY (Opening Date/Time): 8/12/2026 10:00 am e.s.t. (See "Deadline For Submission Of Offer" provision)
QUESTIONS MUST BE RECEIVED BY: 7/23/2026 15:00 AM E.S.T. (See "Questions From Offerors" provision)
NUMBER OF COPIES TO BE SUBMITTED: **** Please submit online thru the Sceis portal, FEDX, UPS, or USPS to the physical address, or drop off in person at the physical address. No emails or faxed responses will be accepted.
CONFERENCE TYPE: PREBID
7/22/2026 11:30 AM
(As appropriate, see "Conferences - Pre-Bid/Proposal" & "Site Visit" provisions) We will meet at the boat ramp –DO NOT BE LATE we will have to cross the waterway by boat.
LOCATION:
Tom Yawkey Wildlife Center 1 Yawkey Way S Georgetown, SC 29440
| AWARD & AMENDMENT |
| Award will be posted on 8/13/2026 . The award, this solicitation, any amendments, and any related notices will be posted at the following web address: http://www.procurement.sc.gov |
You must submit a signed copy of this form with Your Offer. By signing, You agree to be bound by the terms of the Solicitation. You agree to hold Your Offer open for a minimum of ninety (90) calendar days after the Opening Date
NAME OF OFFEROR
(full legal name of business submitting the offer) Any award issued will be issued to, and the contract will be formed with, the entity identified as the Offeror. The entity named as the offeror must be a single and distinct legal entity.
AUTHORIZED SIGNATURE
(Person must be authorized to submit binding offer to contract on behalf of Offeror.)
DATE SIGNED
TITLE
(business title of person signing above)
STATE VENDOR NO.
(Register to Obtain S.C. Vendor No. at www.procurement.sc.gov )
PRINTED NAME
(printed name of person signing above)
STATE OF INCORPORATION
(If you are a corporation, identify the state of incorporation.)
OFFEROR'S TYPE OF ENTITY: (Check one) (See "Signing Your Offer" provision.)
___ Sole Proprietorship ___ Partnership ___ Other_____________________________ ___ Corporate entity (not tax-exempt) ___ Corporation (tax-exempt) ___ Government entity (federal, state, or local)
SQUESTIONS FROM OFFERORS - AMENDMENT (JUN 2017)
THE SOLICITATION IS AMENDED AS PROVIDED HEREIN. INFORMATION OR CHANGES RESULTING FROM QUESTIONS WILL BE SHOWN IN A QUESTION-AND-ANSWER FORMAT. ALL QUESTIONS RECEIVED HAVE BEEN REPRINTED BELOW. THE “STATE’S RESPONSE” SHOULD BE READ WITHOUT REFERENCE TO THE QUESTIONS. THE QUESTIONS ARE INCLUDED SOLELY TO PROVIDE A CROSS-REFERENCE TO THE POTENTIAL OFFEROR THAT SUBMITTED THE QUESTION. QUESTIONS DO NOT FORM A PART OF THE CONTRACT; THE “STATE’S RESPONSE” DOES. ANY RESTATEMENT OF PART OR ALL OF AN EXISTING PROVISION OF THE SOLICITATION IN AN ANSWER DOES NOT MODIFY THE ORIGINAL PROVISION EXCEPT AS FOLLOWS: UNDERLINED TEXT IS ADDED TO THE ORIGINAL PROVISON. STRICKEN TEXT IS DELETED. [02-2A097-1] THE SOLICITATION IS AMENDED AS PROVIDED HEREIN. INFORMATION OR CHANGES RESULTING FROM QUESTIONS WILL BE SHOWN IN A QUESTION-AND-ANSWER FORMAT. ALL QUESTIONS RECEIVED HAVE BEEN REPRINTED BELOW. THE “STATE’S RESPONSE” SHOULD BE READ WITHOUT REFERENCE TO THE QUESTIONS. THE QUESTIONS ARE INCLUDED SOLELY TO PROVIDE A CROSS-REFERENCE TO THE POTENTIAL OFFEROR THAT SUBMITTED THE QUESTION. QUESTIONS DO NOT FORM A PART OF THE CONTRACT; THE “STATE’S RESPONSE” DOES. ANY RESTATEMENT OF PART OR ALL OF AN EXISTING PROVISION OF THE SOLICITATION IN AN ANSWER DOES NOT MODIFY THE ORIGINAL PROVISION
Vendor Questions and Answers:
1. What size generator is needed?
Answer: Max 16 kW in size
2. Can wafer or disc lights be used in place of recessed cans?
Answer: Yes wafer or disc lights can be used in place of cans
3. Who is supplying the overhead lights, ceiling fans, and vanity lights?
Answer: SCDNR will provide overhead lights, ceiling fans and vanity lights
4. I don’t see the trench from the meter to the house in the bid document.
Answer: SCDNR will provide the trench from the meter to the house
5. What about the electrical in the generator room?
Answer: SCDNR will provide the main panel for the outdoor shed but the Contractor is responsible for the meter base, wire, breakers and other items required to run the service from the power company source to the meter base, from the meter base to the main panel (supplied), and from the main panel to the house. If any subpanels are utilized in the house, contractor must supply. Other electrical that supplies the generator room itself are not part of this scope.
6. Confirm all electrical materials and panels are furnished by owner and installed by electrician in outdoor shed.
Answer: SCDNR will provide the main panel for the outdoor shed but the Contractor is responsible for the meter base, wire, breakers and other items required to run the service from the power company source to the meter base, from the meter base to the main panel (supplied), and from the main panel to the house. If any subpanels are utilized in the house, contractor must supply.
7. Confirm conduit, if applicable, and service feeder wire from shed to new house panel in house is furnished and installed by electrician.
Answer: SCDNR will provide the trench but conduit, wire and any other related items are to be furnished and installed by the Contractor.
8. Confirm trench will be dug from shed to house for service feeder by owner Answer: SCDNR will provide the trench from the meter to the house
9. Please confirm on scope of work/specifications document lot 2 (installation of new electrical wiring) that all quantities of electrical devices are correct.
Answer: Unfortunately several quantities from an older draft of the specifications were carried into this announcement. There are several changes in the quantities.
Room 110: Kitchen – (10) Ten Standard Receptacles instead of (9) Nine Room 104: Master Bath – (3)Three receptacles instead of (0) zero Room 105: Master Bedroom – (10) Ten receptacles instead of (7) seven Room 106: Master Closet – (2) Two receptacles instead of (0) zero Room 112: Lower Bath – (1) One receptacle
10. Is there a flood elevation height that any electrical devices need to meet for approved inspection?
Answer: The building is not in a designated flood zone so standard heights required by code are acceptable.
11. What are payment terms after 100% of lot item is completed? Will this be Net 10? Net 30?
Answer: SECTION 11-35-45. Payment for goods and services received by State.
(A) All vouchers for payment of purchases of services, supplies, or information technology must be delivered to the Comptroller General's office within thirty work days from acceptance of the goods or services and proper invoice. After the thirtieth work day, following acceptance or the postmark on the invoice, the Comptroller General shall levy an amount not to exceed fifteen percent each year from the funds available to the agency, this amount to be applied to the unpaid balance to be remitted to the vendor unless the vendor waives imposition of the interest penalty.
(B) All agencies and institutions of the State are required to comply with the provisions of this section. Only the lump sum institutions of higher education are responsible for the payment of all goods or services within thirty work days after the acceptance of the goods or services and proper invoice, whichever is received later, and shall pay an amount not to exceed fifteen percent per annum on any unpaid balance which exceeds the thirty work-day period, if the vendor specifies on the statement or the invoice submitted to such institutions that a late penalty is applicable if not paid within thirty work days after the acceptance of goods or services.
(C) The Comptroller General shall issue written instructions to the agencies to carry out the intent of this section. All offices, institutions, and agencies of state government shall fully cooperate with the Comptroller General in the implementation of this section.
(D) The thirty-day period shall not begin until the agency, whether or not the agency processes vouchers through the Comptroller General, certifies its satisfaction with the received goods or services and proper invoice.
12. Confirm disconnect will be required under “rear exterior”, is this pertaining to HVAC disconnect or disconnect for house that will be located in shed out back? There is no need for two disconnect feeding house.
Answer: This is a reference to the disconnect to be placed for and adjacent to the HVAC unit, not an additional whole house disconnect.
All other terms and conditions remain unchanged