This is a Statement of Work (SOW) for cargo hold hatch cofferdam drain piping renewal work on the USCGC ALDER (WLB 216), a U.S. Coast Guard vessel.
The Keeper of the Tender (KTR) contractor must renew necessary portions of the cargo hold hatch cofferdam drain piping located in compartment 2-30-0-AA. Key deliverables include: furnishing and installing protective measures per SFLC Std Spec 0000; handling all interferences and contaminating prevention in compliance with Federal, state, and local regulations; removing and disposing of fluids from the affected piping system; cropping out 3-inch and 2-inch diameter piping and funnel pieces using Coast Guard Drawing 225-WLB-528-001, REV K as guidance; fabricating and installing new piping with required gaskets and seals; providing sealing means for open piping; furnishing and installing new pipe hangers as necessary; labeling affected piping with system service name, destination, and three-inch directional flow arrows; performing leak testing at normal operating pressure with zero visible leakage acceptance; and installing new insulation materials at appropriate thicknesses per ASTM F683 Tables. Touch-up preservation coating must match existing adjacent surfaces per SFLC Std Spec 6310.
The vessel is available during two periods: May 31 – June 15, 2026, and July 4 – July 25, 2026. Work location is Guard Sector San Francisco, Yerba Buena Island, San Francisco, California 94130. The KTR must provide a Marine Chemist and competent person with appropriate certifications for hot work, notify the vessel's point of contact of planned hot work via the unit-provided Hot Work Chit prior to close of business the day before work, and provide all necessary fire watches. Personnel must provide TWIC identification (preferred) or state-issued identification numbers including issuing state. The contractor must comply with all applicable Federal, State, and Local laws and regulations.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work
USCGC ALDER (WLB 216)
Cargo Hold Hatch Cofferdam Drain Piping Crop & Renew
1. Purpose and Scope KTR shall renew necessary portions of the cargo hold hatch cofferdam drain piping located in compartment 2-30-0-AA, Cargo Hold.
2. Deliverables and Performance Requirements Protective measures: The KTR must furnish and install all protective measures IAW
SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
Interferences: The KTR must handle all interferences IAW SFLC Std Spec0000, (Interferences).
Contamination prevention: The KTR must take all precautions to prevent contamination of personnel and spaces IAW all applicable Federal, state, and local regulations.
Fluid handling: The KTR must remove and dispose of removed fluids from the affected piping system, IAW all applicable Federal, state, and local regulations. Do not drain any fluids into any spaced, bilge, or exterior location.
Piping renewal particulars: The KTR must accomplish the following tasks, using Coast Guard Drawing 225–WLB–528–001, REV K as guidance:
o Crop out necessary length of piping (3” & 2” diameter), to include all necessary funnel pieces of the cofferdam system.
o Fabricate necessary piping arrangement previously cropped IAW CG Drawing.
o Install all fabricated piping to include all required gaskets/seals IAW CG
Drawing.
o KTR must provide a means of sealing any open piping while any portion of the system is open (i.e.: upstream valve blind flange).
Pipe hangers: Furnish, fit, and install new pipe hangers, as necessary.
Pipe labeling: The KTR must label affected piping as follows:
o Name of the piping system service.
o Destination, where feasible.
o Direction of flow, indicated by an arrow three inches long pointing away from the lettering.
Leak Test: After completing all authorized mechanical (i.e. threaded, bolted, etc.)
joint repairs, the Contractor must test the affected piping system's operation using the system fluid at normal operating pressure. Ensure zero visible leakage from or deformation of mechanical parts by repairing all leaks and discrepancies.
Touch-up preservation: The KTR must prepare and coat all new and disturbed surfaces to match existing adjacent surfaces in accordance with SFLC Std Spec 6310, (Touch-ups and minor coating repairs.)
Piping insulation installation: The KTR must install new insulation materials over the exposed pipe surfaces at thicknesses appropriate to the application and temperature ranges specified in ASTM F683 Tables.
o Associated pipe hangers o Valves o Fittings o Flanges
3. Period of Performance
ALDER is available during the following dates:
o 31 May – 15 June 2026 o 04 July – 25 July 2026
4. Location and Method of Performance
Guard Sector San Francisco 1 Yerba Buena Island San Francisco, CA 94130
5. Roles and Responsibilities
KTR shall provide Marine Chemist to include certification and all associated documentation for initial certification and/or recertification for hot work as appropriate.
KTR shall provide competent person to include certification and all associated documentation for initial certification and/or recertification for hot work as appropriate.
KTR shall notify USCGC ALDER POC of any planned hot work via unit provided Hot Work Chit prior to COB the day prior to planned hot work.
KTR shall provide all necessary fire watches.
6. Acceptance Criteria N/A
7. Security and Confidentiality KTR shall provide:
o TWIC identification number (preferred), o State Issued Identification numbers to include issuing state for all personnel.
8. Reporting Requirements
9. Legal Compliance KTR shall comply with all applicable Federal, State, and Local laws and regulations.
10. Performance Monitoring