SF30_Amend_001_Amador_PCT_and_Brushingdoc.pdf
PDF 319 KB Posted
- Attached to
- 2015 Amador Pre-commercial Thinning and Brushing
- Solicitation number
- AG-9JGP-S-15-0104
About this file
Amendment 001
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AG-9JGP-S-15-0104_pre_bid_tour_Q_and_A.pdf | ||
| AG-9JGP-S-15-0104_pre_bid_tour_attendance.pdf | ||
| Solicitation.pdf | ||
| Map_2.pdf | ||
| Map_3.pdf | ||
| Map_1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE PAGE OF PAGES
1 3
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
AMEND 001 6/11/2015 735903
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
USDA Forest Service Central California Acquisition Service Area Tahoe National Forest 631 Coyote Street Nevada City, CA 95959
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State, and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NO.
AG-9JGP-S-15-0104
9B. DATED (SEE ITEM 11)
5/28/2015
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copy of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS, IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED
IN ITEM 14. (TO BE FILLED OUT BY THE CONTRACTING OFFICER)
(X) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN
THE CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor X is not, is required to sign this document and return 1copy to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.
This Amendment extends the due date for response of offers to Wednesday June 17 th
, 2015 at 4:30 PM Local Time.
The amendment adds the Supplemental Specifications Data table to provide clarification of unit Limited Operating Periods LOPs.
Also there was a non-mandatory site visit at the project location in accordance with the solicition. Attached is a list of attendees and the responses to questions and answers given at the site visit.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
Matthew Gagnon, Contracting Officer
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
/s/ Matthew Gagnon 5/26/2015
(Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
30-105 STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
PAGE 2 Amendment 001 Amadaor PCT and Brushing
C.9 Supplemental Specifications
C.9.1 Supplemental Specifications Data Table
Item Stand Acres Map # LOP
1 129-6A 27 1 & 2 N/A
1 129-30 25 1 & 2 N/A 1 129-216 23 2 N/A 1 129-217 27 2 March 1 – August 15
1 129-218A 20 2 March 1 – August 15
1 129-218B 7 2 March 1 – August 15
1 129-218C 37 2 March 1 – August 15
1 129-221A 30 2 March 1 – August 15
1 129-221B 18 2 March 1 – August 15
1 129-232 10 2 March 1 – August 15
1 129-233 13 2 March 1 – August 15
1 131-23A 14 1 N/A 1 131-25 11 1 N/A 1 131-210 17 1 N/A 1 131-212 4 1 March 1 – August 15
1 131-213A 10 1 N/A 1 131-213B 13 1 N/A 1 131-219A 15 1 N/A 1 131-219B 13 1 N/A 1 131-220 31 1 N/A 1 131-256A 25 1 March 1 – August 15
1 131-256B 15 1 March 1 – August 15
1 132-19A 12 1 March 1 – August 15
1 132-19B 15 1 March 1 – August 15
1 132-214A 13 1 March 1 – August 15
1 132-214C 16 1 March 1 – August 15
1 132-217 26 1 N/A
1 132-218 10 1 March 1 – August 15
1 132-256A 21 1 March 1 – August 15
1 132-257B 15 1 March 1 – August 15
1 132-257D 2 1 March 1 – August 15
1 132-257E 3 1 March 1 – August 15
1 132-257F 7 1 March 1 – August 15
2 129-6B 20 1&2 N/A
2 129-219 10 2 March 1 – August 15
2 129-220 43 2 March 1 – August 15
2 131-19 8 1 N/A
2 131-23B 7 1 N/A
2 131-24 4 1 March 1 – August 15
-- Continued on next page.
PAGE 3 Amendment 001 Amadaor PCT and Brushing
C.9.1 Supplemental Specifications Data Table (cont’d)
Item Stand Acres Map # LOP
2 131-214 14 1 N/A
2 131-215 6 1 March 1 – August 15
2 132-210 34 1 N/A
2 132-214B 11 1 March 1 – August 15
2 132-215 10 1 N/A
2 132-216 5 1 March 1 – August 15
2 132-232 6 1 N/A
2 132-254 15 1 March 1 – August 15
2 132-256B 9 1 March 1 – August 15
2 132-257A 41 1 March 1 – August 15
2 132-257C 36 1 March 1 – August 15
2 132-258A 11 1 March 1 – August 15
2 132-258B 24 1 March 1 – August 15
Acres is an estimated quantity, subject to FAR 52.211-18 Variation in Estimated Quantity.