Att 2 REV SPS and Table of Contents.pdf
PDF 572 KB Posted
- Attached to
- RECOVERY-Sugarpine Road Decommissioning
- Solicitation number
- AG-9702-S-10-0268
About this file
Att 2 Revised Specifications
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A-10.pdf | ||
| Attach 1 Amendment 6.pdf | ||
| A-9 SF-30.pdf | ||
| A-8 SF-30.pdf | ||
| Att 1 REVISED PART I SECTION B.doc | DOC document | |
| A-7 SF-30.pdf | ||
| Att 1 REV PART I SECTION B.doc | DOC document | |
| A-6.pdf | ||
| Att 3 REV 8N20 DRAWINGS FINAL.pdf | ||
| A-5 SF-30.pdf | ||
| A-4 SF-30.pdf | ||
| S-10-0268 A-3 SF-30.pdf | ||
| A-2.pdf | ||
| A-1 SF-30.pdf | ||
| Att 2 8N20 DRAWINGS FINAL.pdf | ||
| Att 4 Fire Plan.doc | DOC document | |
| Att 1 SPS and Table of Contents.pdf | ||
| Att 3 Wage Determination Amador CA9.pdf | ||
| RFQ.doc | DOC document |
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STANDARD SPECIFICATIONS FOR CONSTRUCTION
OF ROADS AND BRIDGES ON FEDERAL HIGHWAY PROJECTS -2003
DATE: 1/29/2010 Revised 6/25/2010
Project: 8N20 Road Decommissioning
THE FOLLOWING SPECIFICATIONS AND SPECIAL PROJECT SPECIFICATIONS APPLY TO
ALL ROADS UNLESS SHOWN OTHERWISE ON DRAWINGS
Table of Contents
Table of Contents Preface 101 - Terms, Format, and Definitions
101.01 Meaning of Terms
101.03 Abbreviations
101.04 Definitions
102 - Bid, Award, and Execution of Contract 102 Bid, Award, and Execution of Contract
103 - Scope of Work Deletions
104 - Control of Work Deletions
104.06 Use of Roads by Contractor
105 - Control of Material
105.02 Material Sources
105.02(a) Government-provided sources
105.02 Material Sources
105.02(a) Contractor-provided sources
105.05 Use of Material Found in the Work
106 - Acceptance of Work
106.01 Conformity with Contract Requirements
106.07 Delete
107 - Legal Relations and Responsibility to the Public
107.05 Responsibility for Damage Claims
107.06 Contractor’s Responsibility for Work
107.09 Legal Relationship of the Parties
107.10 Environmental Protection
107.02 Protection and Restoration of Property and Landscape
107 - Legal Relations and Responsibility To the Public
107.11 Protection of Forests, Parks, and Public Lands:
108 - Prosecution and Progress 108 Delete
109 - Measurement and Payment 109 Deletions
109.02 Measurement Terms and Definitions
151 - Mobilization 155 - Schedules for Construction Contracts
155 Delete 156 - Public Traffic
156.08 Traffic and Safety Supervisor
157 - Soil Erosion Control
157.02 Materials
157.03 General
157.08 Water Crossings
170 - Develop Water Supply and Watering 171 - Weed and Disease Prevention 201 - Clearing and Grubbing
201.01 Description
203 - Removal of Structures and Obstructions
203.01 Description
203.03 Salvaging Material
203.04 Removing Material
203.05 Disposing of Material
203.08 PAYMENT
204 - Excavation and Embankment
204.06 Roadway Excavation
204.11 Compaction
204.13 Sloping, Shaping, and Finishing
Table 204-2 Construction tolerances
204.14 Disposal of Unsuitable or Excess Material
204.15 Acceptance
209 - Structure Excavation and Backfill
209.10 Backfill
209.11 Compacting
Table 209-1 Sampling and Testing Requirements
209.12 Acceptance
211 - Roadway Obliteration
211.01 Description
211.02 Construction Requirements
211.03 MEASUREMENT
211.04 PAYMENT
301 - Untreated Aggregate Courses 301 Title Change
303 - Road Reconditioning 602 - Culverts and Drains
602.03 General
650 - Road Closure Devices 703 - Aggregate
703.05 Subbase, Base, Surface Course, and Screened Aggregate
703.10(e) Flakiness Index 703.10(i) Adherent Coating Table 703-2 Correction Table 703-2 Correction Table 703-7 Target Value Ranges
705 - Rock
Preface
Preface_wo_03_15_2004_m
Delete all but the first paragraph and add the following:
The Forest Service, US Department of Agriculture has adopted FP-03 for construction of National Forest System Roads.
101 - Terms, Format, and Definitions
101.01_nat_us_01_22_2009
101.01 Meaning of Terms
Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.
101.03_nat_us_06_16_2006
101.03 Abbreviations.
Add the following to (a) Acronyms:
AFPA
MSHA
NIST
NESC
WCLIB
American Forest and Paper Association Mine Safety and Health Administration National Institute of Standards and Technology National Electrical Safety Code West Coast Lumber Inspection Bureau
Add the following to (b) SI symbols:
mp Milepost ppm Part Per Million
101.04_nat_us_03_29_2007
101.04 Definitions.
Delete the following definitions and substitute the following:
Bid Schedule--The Schedule of Items.
Bridge--No definition.
Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.
Culvert--No definition.
Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or
(2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Add the following:
Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.
Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96 Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.
Forest Service--The United States of America, acting through the Forest Service, U.S. Department of Agriculture.
Neat Line--A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road--Temporary construction access built along the route of the project.
Purchaser--The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction.
Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.
Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.
Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.
Add Figure 101-1—Illustration of road structure terms:
Figure 101-1—Illustration of road structure terms.
102 - Bid, Award, and Execution of Contract
102.00_nat_us_02_16_2005
102 Bid, Award, and Execution of Contract
Delete Section 102 in its entirety.
103 - Scope of Work
103.00_nat_us_02_16_2005
Deletions
Delete all but subsection 103.01 Intent of Contract.
104 - Control of Work
104.00_nat_us_06_16_2006
Deletions
Delete Sections 104.01, 104.02, and 104.04.
104.06_nat_us_02_17_2005
Add the following subsection:
104.06 Use of Roads by Contractor
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
105 - Control of Material
105.02_nat_us_01_18_2007
105.02 Material Sources.
105.02(a) Government-provided sources.
Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material for aggregate regardless of size unless otherwise designated. When required, re-establish vegetation in disturbed areas according to section 625.
105.02_nat_us_03_08_2007
105.02 Material Sources.
105.02(a) Contractor-provided sources.
All material (e.g., soil, gravel, sand, borrow, aggregate, etc.) transported onto National Forest System land or incorporated into the work will be weed-free. The Contracting Officer may request written documentation of methods used to determine the weed-free status of any and all materials furnished by the contractor. Contractor-provided expertise and methods to establish weed-free status must be appropriate for the weeds of concern in the local area.
105.05_nat_us_05_12_2004
105.05 Use of Material Found in the Work.
Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:
Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.
106 - Acceptance of Work
106.01_nat_us_07_31_2007
106.01 Conformity with Contract Requirements.
Delete Subsection 106.01 and substitute the following:
Follow the requirements of FAR Clause 52.246-12 Inspection of Construction.
References to standard test methods of AASHTO, ASTM, GSA, and other recognized standard authorities refer to the methods in effect on the date of solicitation for bids.
Perform all work to the lines, grades, cross-sections, dimensions, and processes or material requirements shown on the plans or specified in the contract.
Incorporate manufactured materials into the work according to the manufacturer’s recommendations or to these specifications, whichever is more strict.
Plan dimensions and contract specification values are the values to be strived for and complied with as the design values from which any deviations are allowed. Perform work and provide material that is uniform in character and reasonably close to the prescribed value or within the specified tolerance range. The purpose of a tolerance range is to accommodate occasional minor variations from the median zone that are unavoidable for practical reasons.
When standard manufactured items are specified (such as fence, wire, plates, rolled shapes, pipe conduits, etc., that are identified by gauge, unit mass, section dimensions, etc.), the identification will be considered to be nominal masses or dimensions. Unless specific contract tolerances are noted, established manufacturing tolerances will be accepted.
The Government may inspect, sample, or test all work at any time before final acceptance of the project. When the Government tests work, copies of test reports are furnished to the Contractor upon request. Government tests may or may not be performed at the work site. If Contractor testing and inspection is verified by the Government, the Contractor’s results may be used by the Government to evaluate work for acceptance. Do not rely on the availability of Government test results for process control.
Acceptable work conforming to the contract will be paid for at the contract unit bid price. Four methods of determining conformity and accepting work are described in Subsections 106.02 to 106.05 inclusive. The primary method of acceptance is specified in each Section of work. However, work may be rejected at any time it is found by any of the methods not to comply with the contract.
Remove and replace work that does not conform to the contract, or to prevailing industry standards where no specific contract requirements are noted, at no cost to the Government.
(a) Disputing Government test results. If the accuracy of Government test results is disputed, promptly inform the CO. If the dispute is unresolved after reasonable steps are taken to resolve the dispute, further evaluation may be obtained by written request. Include a narrative describing the dispute and a proposed resolution protocol that addresses the following:
(1) Sampling method;
Number of samples;
Sample transport;
Test procedures;
Testing laboratories;
Reporting;
Estimated time and costs; and
Validation process.
If the evaluation requires additional sampling or testing be performed, mutually agree with the Government on witnessing procedures and on sampling and testing by a third party laboratory. Use a third party laboratory accredited by the AASHTO accreditation program. Provide proof of the laboratory’s accreditation for the test procedures to be used. Do not use the same laboratory that produced the disputed Government test results or that produced the test results used as a basis for the dispute.
The CO will review the proposed resolution protocol and may modify it before final approval and execution.
The Government will use the approved resolution protocol test results to determine the validity of the disputed testing. If the Government test results are validated, the Contractor will be responsible for all costs associated with developing and performing the resolution protocol. If the Government test results are not validated, the Government will be responsible for all costs associated with developing and performing the resolution protocol. If the validity of the Government test results cannot be determined, the Contractor and Government will equally share all costs associated with developing and carrying out the resolution protocol.
(b) Alternatives to removing and replacing non-conforming work. As an alternative to removal and replacement, the Contractor may submit a written request to:
(1) Have the work accepted at a reduced price; or
(2) Be given permission to perform corrective measures to bring the work into conformity.
The request must contain supporting rationale and documentation. Include references or data justifying the proposal based on an evaluation of test results, effect on service life, value of material or work, quality, aesthetics, and other tangible engineering basis. The CO will determine disposition of the nonconforming work.
106.07_nat_us_05_11_2004
106.07 Delete
Delete subsection 106.07.
107 - Legal Relations and Responsibility to the Public
107.05_nat_us_05_11_2004
107.05 Responsibility for Damage Claims.
Delete the entire subsection.
107.06_nat_us_06_16_2006
107.06 Contractor’s Responsibility for Work.
Delete the following from the first paragraph.
“except as provided in Subsection 106.07”.
107.09_nat_us_06_16_2006
107.09 Legal Relationship of the Parties.
Delete the entire subsection.
107.10_nat_us_06_16_2006
107.10 Environmental Protection.
Add the following:
Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.
Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill.
Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:
• Description of the item spilled (including identity, quantity, manifest number, and other identifying information).
• Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.
• Exact time and location of spill including a description of the area involved.
• Containment procedures.
• Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.
• Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.
When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.
The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.
107.10_05_us_05_04_2007
107.02 Protection and Restoration of Property and Landscape
Meet the requirements chapters 10, 11, and 12.2 in their entirety of “Water Quality Management for National Forest System Lands in California Best Management Practices” dated September 2000
107 - Legal Relations and Responsibility To the Public
107.11_nat_us_02_17_2005
107.11 Protection of Forests, Parks, and Public Lands:
Add appropriate fire plan and equipment language.
108 - Prosecution and Progress
108.00_nat_us_02_16_2005
108 Delete.
Delete Section 108 in its entirety.
109 - Measurement and Payment
109.00_nat_us_02_17_2005
109 Deletions Delete the following entire subsections:
109.06 Pricing of Adjustments.
109.07 Eliminated Work.
109.08 Progress Payments.
109.09 Final Payment.
109.02_nat_us_06_16_2006
109.02 Measurement Terms and Definitions.
(b) Contract quantity.
Add the following:
Contract quantities will be adjusted only when there are errors in the original design of 15% or more.
Change the following:
“(b) Cubic yard” to “(c) Cubic yard”.
Add the following definition:
(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.
151 - Mobilization
151.00_01_us_10_11_2006
Delete Section 151 in its entirety and replace with the following.
Description
151.01 This work consists of moving personnel, equipment, material, and incidentals to the project and performing all work necessary before beginning work at the project site; obtaining of permits, insurance, and bonds. This work also includes washing and treating construction equipment and vehicles necessary for equipment transport to remove seeds, plants, and plant fragments before the equipment is used on Forest Service lands, according to the requirements within.
Construction Requirements
Wash the sides, tops, and undercarriages of all construction equipment. Remove all seeds, plants, plant fragments, dirt, and debris from the construction equipment. Only equipment inspected by the Forest Service will be allowed to operate within the project area. All subsequent move-ins of equipment to the project area will be treated in the same manner as the initial move-in. This requirement does not apply to cars, pickup trucks, and other vehicles that regularly travel between the construction site and areas off the National Forest.
Equipment will be considered free of soil, seed, and other such debris when a visual inspection does not disclose such material. Disassembly of equipment, components or the need for specialized inspection tools is not required.
Notify the CO in writing at least 72 hours before moving any construction equipment onto the national forest. Notification will include an agreed upon location where the equipment will be available for inspection by the Forest Service. Inspection will be required after every cleaning.
Use methods of cleaning and locations for cleaning approved by the CO.
For work at a commercial washing facility, use an approved facility.
New infestations of noxious weeds of concern to Forest Service and identified by either Contractor or Forest Service, in the Project Area or on the haul route, will be promptly reported to the other party.
Contractor and Forest Service will agree on treatment methods to reduce or stop the spread of noxious weeds when new infestations are found. A current list of noxious weeds of concern to Forest Service is available at each Forest Service office.
Measurement
151.02 Clean equipment prior to moving onto this project. The initial cleaning will not be included in the measurement for payment. Payment for cleaning will only be made if subsequent cleanings are ordered by the CO. Measurement shall be on an “each” basis, meaning one complete cleaning of all equipment required for this contract. Subsequent cleanings necessitated by the Contractor’s actions but not directed by the CO will not be included in the measurement for payment.
Measure mobilization according to Subsection 109.02.
Payment
151.03 The accepted quantity, measured as provided in Subsection 109.02, will be paid at the contract price per unit of measurement for the Section 151 pay item shown in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.
Progress payments for mobilization lump sum will be paid as follows:
(a) If applicable, bond premiums will be reimbursed according to FAR Clause 52.232-5 Payments Under Fixed-Price Construction Contracts, after receipt of the evidence of payment.
(b) When 5 percent of the original contract amount is earned from other bid items, 50 percent of the mobilization item, or 5 percent of the original contract amount, whichever is less, will be paid.
(c) When 10 percent of the original contract amount is earned from other bid items, 100 percent of the mobilization item, or 10 percent of the original contract amount, whichever is less, will be paid.
(d) Any portion of the mobilization item in excess of 10 percent of the original contract amount will be paid after final acceptance.
Include all costs associated with the initial cleaning of equipment in the unit bid price for Mobilization. Cleaning for subsequent move-ins will not be paid for unless after a suspension ordered by the CO.
155 - Schedules for Construction Contracts
155.00_nat_us_05_11_2004
155 Delete.
Delete Section 155 in its entirety.
156 - Public Traffic
156.00_nat_us_04_17_2007
Delete Section 156 in its entirety and replace with the following:
156.01 This work consists of controlling and protecting public traffic adjacent to and within the project.
Material
156.02 Conform to the MUTCD and the following Sections and Subsections:
Construction sign panels 633
Retro-reflective sheeting 718.01
Temporary concrete barrier 618
Temporary plastic fence 710.11
Temporary traffic control devices 718.22
156.03 General. Unless otherwise provided for in Table 156-1, keep existing roads open to all traffic during road improvement work, and maintain them in a condition that will adequately accommodate traffic. Delays may not exceed 30 minutes at any one time followed by an open period of no less than 5 minutes or as necessary.
Perform no work that interferes or conflicts with traffic or existing access to the roadway surface until a traffic control plan has been approved. Post construction signs and traffic control devices in conformance with MUTCD. All required signs will be in place and approved prior to beginning work on project.
If the Contractor agrees in writing to allow public traffic to use a new road being constructed prior to completion, it will be considered an existing road for traffic control purposes.
156.04 Temporary Traffic Control. Install and maintain temporary traffic control devices adjacent to and within the project as required by the approved traffic control plan and the MUTCD. Install and maintain traffic control devices as follows:
Furnish and install traffic control devices before the start of construction operations.
All detours outside of clearing limits will be approved in writing by the Contracting Officer as part of the traffic control plan.
Install only those traffic control devices needed for each stage or phase.
Relocate temporary traffic control devices as necessary.
Remove devices that no longer apply to the existing conditions.
Immediately replace any device that is lost, stolen, destroyed, or inoperative.
Keep temporary traffic control devices clean.
Remove all temporary traffic control devices upon contract completion or when approved.
When required, use flaggers certified by the American Traffic Safety Services Association, the National Safety Council, the International Municipal Signal Association, a state agency, or other acceptable organization. Perform the work described under MUTCD Part 6. Use type III, VII, VIII, or IX retroreflective sheeting on flagger paddles. Do not use flags. Flaggers must wear high visibility safety apparel as required by MUTCD 6E.02.
156.05 Temporary Closures. Road segments may be closed as shown in Table 156-1. The maximum consecutive days of closure shall be followed by a minimum number of consecutive days open to traffic as shown. Maintain traffic control devices during closure period(s). Appropriate barricades and signs will be erected and maintained as shown in the traffic control plan or as otherwise designated.
Prior to closing roads during construction, give written notice to the Contracting Officer at least 10 days in advance.
Table 156-1
Temporary Road Closures
Road Number
From Terminus
To Terminus Maximum Consecutive Days of Closure
Minimum Consecutive Days Open
8N20 12798 17717 0 0
8N20 17717 21389 Closed Closed
8N20 21389 23383 5 0
Acceptance. Public traffic work will be evaluated under Subsection 106.02.
Measurement and Payment
156.07 Do not measure Public Traffic for payment. Compensation is made as an indirect payment.
156.08_nat_us_02_24_2005
156.08 Traffic and Safety Supervisor.
Delete this subsection in its entirety.
157 - Soil Erosion Control
157.02_01_us_08_23_2004
157.02 Materials
Provide bales, wattles, logs and rolls from a certified noxious weed free source.
157.03 General
Delete the entire subsection and replace with the following:
Prior to the start of construction, submit a written plan that provides permanent and temporary erosion control measures to minimize erosion and sedimentation during and after construction. Do not begin work until the necessary controls for that particular phase of work have been implemented. Do not modify the type, size, or location of any control. An alternate erosion control plan with all necessary permits may be submitted 30 days before intended use.
Incorporate all permanent erosion control features into the project at the earliest practicable time, as outlined in the approved plan.
When erosion control measures are not functioning as intended, immediately take corrective action.
Upon completion of construction at the site, all temporary dewatering materials and equipment are to be removed from Government property.
157.08 Water Crossings.
At any channel crossing where there is running water dewater by rerouting water flow around the site before and during excavation and embankment operations.
170 - Develop Water Supply and Watering
170.00_nat_us_03_30_2005
Description
170.01 This work consists of developing an acceptable water supply, furnishing, hauling, and applying water.
Materials
170.02 Conform to the following subsection.
Water 725.01.
170.03 Development of Supply & Access. Develop water supplies and access to the water supplies as required. Use designated water sources or other approved water sources. Before using non-designated water sources, obtain all necessary permissions, water rights, and permits.
170.04 Equipment. Provide mobile watering equipment with watertight tanks of known capacity.
Provide for positive control of water application from the driver’s position.
170.05 Application. Apply water uniformly without ponding or washing.
170.06 Acceptance. Developing water supplies and watering will be evaluated under Subsections
106.02 and 106.04.
170.07 Measure the Section 170 items listed in the bid schedule according to Subsection 109.02.
170.08 There will be no separate payment for this work. Work shall be considered to other paid work is this contract.
171 - Weed and Disease Prevention
171.00_nat_us_03_30_2005
171.01 This work consists of washing and treating construction equipment to remove seeds, plants, and plant fragments from the equipment before the equipment is used on National Forest System lands.
Conform to the following Subsection:
Water 725.01
171.03 General . Notify the CO in writing at least 15 days before moving any construction equipment onto National Forest System lands. Construction equipment does not include cars, pickup trucks, and other vehicles that regularly travel between the construction site and areas outside of National Forest System lands.
Perform all work at a location designated on the plans or other locations approved in writing. Provide the CO with an opportunity to monitor the washing and inspection.
Equipment. Use a high pressure washing system.
For work on National Forest System lands, use a washing system that traps all wash water and either stores it for removal from National Forest System lands or recycles the water for continued use. If the equipment recycles the water, provide adequate filters for seed removal. Dispose of the filter material and removed seeds in an approved manner. Do not mix soaps, detergents, or other chemicals with the wash water.
For work at a commercial washing facility, use an approved facility.
171.05 Washing. Wash the sides, tops, and undercarriages of all construction equipment. Remove all seeds, plants, plant fragments, dirt, and debris from the construction equipment.
171.06 Inspection. Inspect the washed construction equipment, including the undercarriage, to ensure that the washing removed the dirt, debris, and seeds from the construction equipment. Rewash the construction equipment as necessary or as directed.
171.07 Acceptance. Weed prevention will be evaluated under Subsection 106.02.
171.08 Do not measure weed prevention for payment.
171.09 Include all costs associated with the Section 171-Weed Prevention in the unit price for Section 151-Mobilization.
201 - Clearing and Grubbing
201.01_nat_us_02_18_2005
201.01 Description
Replace with the following
This work consists of clearing and grubbing within clearing limits and other designated areas.
203 - Removal of Structures and Obstructions
203.01_nat_us_02_25_2005
203.01 Description.
Delete and replace with the following:
This work consists of disposing of construction slash and debris, salvaging, removing, and disposing of buildings, fences, structures, pavements, culverts, utilities, curbs, sidewalks, and other obstructions.
203.03_0510_us_01_25_2005
203.03 Salvaging Material.
Delete entire section and add the following:
"All culverts removed are NOT DESIGNATED for salvage and will be removed and disposed of off Government land. Remove entire culvert and all associated items of the drainage structure.”
203.04_nat_us_02_18_2005
203.04 Removing Material.
Replace the fourth and fifth paragraphs with the following:
Where an existing culvert is removed, remove the entire culvert.
Remove structures and obstructions in the roadbed to 12 inches below subgrade elevation or to bedrock whichever is less. Remove structures and obstructions outside the roadbed to 12 inches below finished ground or to the natural stream bottom.
203.05_nat_us_02_24_2005
203.05 Disposing of Material.
Add the following:
(e): Scattering. Scatter pieces of wood greater than 3 inches in diameter and 3 feet in length outside the clearing limits. Do not place construction slash in lakes, meadows, streams, or streambeds.
Immediately remove construction slash that interferes with drainage structures.
203.08 PAYMENT.
Add after the first sentence:
“Payment is based upon the removal and disposal of all structures designated in the contract, and includes the excavation necessary to access these structures.”
204 - Excavation and Embankment
204.06_nat_us_03_02_2005
204.06 Roadway Excavation
(a) General.
Add the following:
Retrieve material deposited outside of the clearing limits as directed by the CO. Place unsuitable material in designated areas.
204.06_0114_us_07_06_2005
204.06 Roadway Excavation
Drainage Excavation. Drainage excavation includes construction of side ditches, minor channel changes, inlet and outlet ditches, furrow ditches, rolling drainage dips, surface water deflectors and other minor earth drainage structures as shown on the plans. Compaction for drainage excavation is as shown on the plans.
204.11 Compaction
Delete this section and replace it with the following:
For compaction according to method (a), (b), or (c), use AASHTO T 27 to determine the amount of material retained on a Number. 4 sieve. For compaction methods (d), (e), or (f) no sieve test is required.
Add the following compaction methods:
(d) Hauling and Spreading Equipment. Adjust the moisture content to a level suitable for compaction.
Compact the material by operating equipment over the full width of the roadway.
(e) Roller Compaction. (Compaction Method B) Place the material in 12 inch layers and adjust the moisture content to a level suitable for compaction. Operate Rollers over the full width of each layer until visual displacement ceases, but not fewer than five complete passes. Use rollers that meet the following requirements:
(1) Steel wheeled rollers, other than vibratory, capable of exerting a force of not less than 250 pounds per inch of width of the compression roll or rolls.
(2) Vibratory steel wheeled rollers equipped with amplitude and frequency controls with a minimum weight of 6 tons, specifically designed to compact the material on which it is used.
(3) Pneumatic-tired rollers with smooth tread tires of equal size that will provide a uniform compacting pressure for the full width of the roller and capable of exerting a ground pressure of at least 80 psi.
(4) Sheepsfoot, tamping, or grid rollers capable of exerting a force of 250 lbs/inch of width of roller drum.
(f) Mechanical Tamper. Adjust the moisture content of the backfill material to a moisture content suitable for compaction. Compact each 6 inch layer with a minimum of three complete passes with a mechanical tamper, approved by the CO.
204.13_nat_us_03_02_2005
204.13 Sloping, Shaping, and Finishing.
Delete section (d) and add the following:
(d) Finishing. For surfaced roads, remove all material larger than 6 inches from the top 6 inches of the roadbed. For all roads, finish the roadbed to be smooth and uniform, and shaped to conform to the typical sections. Remove unsuitable material from the roadbed and replace it with suitable material. Finish roadbeds to the tolerance class shown in table 204-2.
Ensure that the subgrade for both surfaced and unsurfaced roads is visibly moist during shaping and dressing. Scarify to 6 inches below the bottom of low sections, holes, cracks, or depressions and bring back to grade with suitable material. Maintain proper ditch drainage.
For unsurfaced roads, use one of the following methods to finish the roadbed:
(1) Method A. Remove all material larger than 6 inches from the top 6 inches of the roadbed and replace with suitable material.
(2) Method B. Use a vibratory grid roller or approved equal with a minimum weight of 10 tons.
Roll at least 5 full-width passes or until visible displacement ceases.
(3) Method C. For roads designated as Construction Tolerance Class K, L, or M, finish the roadbed by spreading the excavation. Eliminate rock berms.
Add Table 204-2—Construction Tolerances:
Table 204-2 Construction tolerances.
Tolerance Class(a)
A B C D E F G H I J K L M
Roadbed width (ft) +0.5 +0.5 +1.0 +1.0 +1.0 +1.0 +1.5 +1.0 +2.0 +2.0 +2.0 +2.0 +2.0
Subgrade elevation
(ft)
+0.1 +0.2 +0.2 +0.5 +0.5 +1.0 +1.0 +1.5 +2.0 +3.0 +2.0 +3.0 (c)
Centerline alignment (ft)
+0.2 +0.2 +0.5 +0.5 +1.0 +1.0 `+1.5 +1.5 +2.0 +3.0 +3.0 +5.0 (c)
Slopes, excavation, and embankment (% slope(b)
+3 +5 +5 +5 +5 +5 +10 +10 +10 +10 +20 +20 +20
a. Maximum allowable deviation from construction stakes and drawings.
b. Maximum allowable deviation from staked slope measured from slope stakes or hinge points.
c. Unless otherwise shown the centerline alignment and subgrade elevation, as built, have no horizontal curves with a radius of less than 80 feet, and no vertical curves with a curve length of less than 80 feet when the algebraic difference in the grade change is less than 10 percent, or a curve length of less than 100 feet when the algebraic difference of the grade change is greater than or equal to 10 percent. The centerline grade is not to exceed 20 percent in 100 feet of length.
204.14_nat_us_03_02_2005
204.14 Disposal of Unsuitable or Excess Material.
Delete the text of the first paragraph and substitute the following:
Dispose of unsuitable or excess material at designated sites or legally off of the project.
204.15 Acceptance
Delete the first paragraph.
209 - Structure Excavation and Backfill
209.10_nat_us_10_23_2007
209.10 Backfill.
(a) General.
Add the following:
Replace any pipe that is distorted by more than 5 percent of nominal dimensions, or that is ruptured or broken.
Do not place or backfill pipe that meets any of the following conditions until the excavation and foundation have been approved in writing by the CO:
• Embankment height greater than 6 feet at subgrade centerline.
• Installation in a protected streamcourse.
• Round pipe with a diameter of 48 inches or greater.
• Pipe arches with a span of 50 inches or greater.
• Any box culvert of structure other than pipe culverts.
(b) Pipe culverts.
(1) Pipe culverts with compacted backfill.
Add the following:
Excavate an area on each side of the pipe as needed to effectively achieve compaction requirements.
Backfill without damaging or displacing the pipe. Complete backfilling of the trench with suitable material.
209.11_nat_us_02_24_2005
209.11 Compacting.
Delete the subsection and add the following:
Compact backfill using designated compaction method A, B, or C:
Method A. Ensure that backfill density exceeds the density of the surrounding embankment.
Method B. Adjust the moisture content of the backfill material to a moisture content suitable for compaction. Compact each layer using appropriate compaction equipment until visual displacement ceases. For compaction under sections 252, 254, 255, 257, 258 and compact with a vibratory steel wheeled roller with a mass of at least 8 tons.
Method C. Determine optimum moisture content and maximum density according to AASHTO T 99 method C. Adjust the moisture content of the backfill material to a moisture content suitable for compaction. Compact material placed in all layers to at least 95 percent of the maximum density.
Determine the in place density and moisture content according to AASHTO T 310 or other approved test procedures.
Table 209-1 Sampling and Testing Requirements
(2) Compaction methods (A) and (B) do not require AASHTO T-99 or T-310 test methods for foundation fill.
209.12 Acceptance
Compaction methods (A) and (B) do not require sampling and testing.
211 - Roadway Obliteration
211.01 Description.
Delete this section and substitute the following:
When required this work shall consist of closing designated roads to use by all motorized vehicles and returning the roadway to resource production using one or a combination of the following items as specified in the Schedule of Items and as shown in the Drawings:
removing drainage structures, seeding, fertilizing, scarification, ripping with wing rippers, outsloping roadbed, earth barricade, rock barricade, slashing, and camouflaging road junction.
211.02 Construction Requirements.
a. Removal of Drainage Structures.
1. All designated drainage structures such as culverts, metal or wooden open top water diverters, and rubber water diverters shall be removed. Dips and waterbars shall not be removed.
2. Culverts shall be hauled off of public lands and disposed of at approved disposal facilities.
3. Dewatering for culvert removal – Contractor shall supply dewatering plan to Contracting Officer for approval 48 hours prior to culvert removal. .
4. Wooden open top water diverters, metal open top water diverters, and rubber water diverters shall be treated the same as culverts.
5. Stream channel width after drainage structures have been removed shall be no less than that of existing channel in the vicinity of the inlet and outlet. Stream banks shall be sloped to 3:1 or flatter unless agreed to otherwise. This work is incidental to structure removal. Riprap, when shown in the Drawings, shall be placed to the length and dimension shown in the Drawings.
b. Seeding
1. When required this work consists of furnishing and placing required seed mix on all areas disturbed under this contract and on any other areas specified. Seeding may not be done until all other ground disturbing work on the road has been completed and accepted. Unless a specific seeding season is listed below, seeding shall be done as soon as other ground disturbing work is accepted.
Seeding season: to .
2. The seed shall be applied in the following amounts and mixtures:
Species % of Mixture Application Rate (lb./acre)
3. Hand operated seeding devices, or other devices approved by the Government, shall be used to apply seed.
4. Seed shall meet the requirements of Federal Specification JJJ-S-181. Seed shall be furnished separately or in mixture in standard containers with (1) seed name; (2) lot number; (3) net weight; (4) percentages of purity and of germination (in case of legumes, percentage of germination to include hard seed); and (5) percentage of maximum weed seed content clearly marked for each kind of seed. The contractor shall furnish the Government duplicate signed copies of a statement by the vendor, certifying that each lot of seed has been tested by a recognized laboratory for seed testing within 12 months of date of delivery. This statement shall include (1) name and address of laboratory, (2) date of test, (3) lot number for each kind of seed, and
(4) results of tests as to name, percentages of purity and of germination, and percentage of weed content for each kind of seed furnished, and, in case of a mixture, the proportions of each kind of seed. Legume seed shall be inoculated with approved cultures in accordance with the instructions of the manufacturer.
c. Fertilizing
1. When required this work consists of furnishing and placing dry fertilizer on all areas disturbed under this contract and on any other areas specified. The contractor shall apply fertilizer as soon as all other ground disturbing work on the road has been completed and accepted, but not before seeding has been completed.
2. The minimum percentage of available nutrients shall be:
% Nitrogen % Phosphorus % Potassium % Sulfur
3. Fertilizer shall be applied at lbs/acre.
4. Hand operated fertilizing devices, or other devices approved by the Government, shall be used to apply the fertilizer.
d. Scarification
1. When required this work shall consist of seedbed preparation on an existing roadbed by scarification.
2. Scarification shall be accomplished by rippers spaced not more than 6 inches apart and/or with heavy duty gang discs.
3. Scarification depth shall not be less the 3 inches or deeper than 12 inches unless otherwise agreed.
e. Ripping With Wing Rippers
1. When required this work shall consist of subsoiling an existing roadbed by ripping with a winged ripper as shown in the Drawings or an approved equivalent tool approved by the Contracting Officer.
2. The distance between ripper shanks shall not exceed 36 inches. Each shank shall be equipped with a shoe and wings which have a total width of at least 18 inches.
The design of the shank and wing will be such that the treated soils are slightly lifted and well fractured rather than plowed, mixed or displaced.
3. Ripping shall be accomplished to a minimum depth of 18 inches. The Government may agree to a lesser depth when excessive rock is encountered.
f. Outsloping Roadbed
1. Designated roads or segments of roads shall be outsloped by pulling the fill shoulder towards the cut bank. Excavated material shall be spread over the roadbed forming a minimum outslope equal to the existing road grade percent. The Government may agree to a lesser outslope percent if soil conditions warrant.
2. Any existing ditches at the toe of the cut shall be filled with the material excavated during outsloping.
g. Earth, Log and Rock Barricades
1. Earth, log or rock barricades shall be constructed in locations specified in accordance with the attached drawings.
2. Multiple log barricades at one site may be specified. Logs shall be a minimum dimension shown in the Drawings.
3. Rock barricades shall be of the minimum size and dimension Shown in the
Drawings and placed so that motorized vehicles greater than 36 inches cannot pass.
4. Measurement and Payment shall be according to section 650 – Road Cloasure Devices.
h. Slashing
1. When required this work shall consist of placing woody material over the roadbed to discourage vehicle traffic.
2. Woody material shall be dead timber and slash removed from an area within thirty five (35) feet of the road shoulders in the vicinity of the areas where it is to be placed. When there is inadequate material to slash road and when directed by the Contracting Officer, Contractor shall fell marked trees adjacent to road. Trees shall be felled diagonally across road.
3. Material shall be placed randomly over the roadbed to give a similar appearance of the surrounding area and may include rocks and other material.
i. Camouflaging Road Junction
1. When required this work shall consist of manipulating the cut and fill slopes of the designated road so the road template is not obvious. One or more of the following methods will be specified:
A. When the designated roadway section is a cut-fill section, excavate the fill slope section and place material against the cut section so the designated road is not obvious. The height of the replaced material shall be equal to the existing cut or a maximum of six (6) feet.
B. When the designated roadway section is a fill section, remove the road fill and place the material as a berm along the road junctioned, creating what appears to be a cut section.
j. Recontouring Cut and Fill Slopes
1. Cut and fill slopes shall be reshaped as nearly as practical to the surrounding hill slope topography. Reshaping of cut and fill slopes shall be prescribed on a site specific basis by the hydrologist where unstable slopes create geologic hazards or excessive erosion.
k. Waterbars
1. Waterbars shall be installed at locations shown in the Drawings or staked on the ground. Unless specified otherwise in the Drawings all waterbars are to be the non-drivable type. See typicals.
2. Measure and Payment shall be according to Section 204 – Excavation and Embankment.
l. Transplanting Native Trees
1. This work shall consist of transplanting native trees designated by the Government from areas adjacent to the road to areas designated by the Government on the roadbed. Transplanting will be limited to trees less than 4 inches in diameter.
Transplanting must be done with a tree spade or other equipment specifically designed for transplanting trees with minimal damage to the root system. No damage to the tree stem will be permitted. No more than 20 percent of the limbs may be damaged during the transplanting operation. The north side of trees to be transplanted shall be marked before the trees are removed. When the trees are transplanted they shall be oriented with the north side facing north. Transplanting shall be limited to the period from October 15 to May 31 annually. Transplanted trees shall be watered liberally immediately after transplanting.
m. Road Closure
1. This work shall consist of minor grading and shaping of road to ensure drainage. Work also includes to construction of swales, waterbars and barricades where shown in the Drawings or staked on the ground.
n. Swales
1. Swales shall be installed at locations shown in the Drawings or staked on the ground. See typicals.
o. Riprap
1. This work consists of placing riprap at locations specified in the Drawings. Riprap shall be of the size and mass specified in Section 705 – Riprap Rock
211.03 MEASUREMENT
Measurement under this Section will be made by the number of units for each item listed in the Schedule of Items completed and accepted.
211.04 PAYMENT
a. The accepted quantity will be paid for at the contract unit price. This payment will be full compensation for all labor, equipment, tools, and incidentals necessary to complete the work.
b. Payment will be made under:
Pay Item Pay Unit
211(01) Road Decommissioning LS
301 - Untreated Aggregate Courses
301 Title Change.
Change the title to: Section 301 Aggregate Courses
Delete this Section in its entirety and substitute the following:
301.01 This work consists of constructing one or more courses of aggregate on a prepared surface.
Work includes producing aggregate by grid rolling, pit-run, screening, or crushing methods, or placing commercially produced aggregate meeting Caltrans specification.
Surface aggregate grading is designated as shown in Table 703-3.
Subbase and base aggregate grading is designated as shown in Table 703-2.
Screened aggregate grading is designated as shown in Table 703-16.
Material
301.02 Conform to the following Subsections:
Aggregate 703.05
301.03 General. Prepare the surface on which the aggregate course is placed according to Section 204 or 303 as applicable.
Request approval of the roadbed in writing before placing aggregate.
Submit target values within the gradation ranges shown in Table 703-2 or 703-3 for the required grading.
After reviewing the Contractor’s proposed target values the CO will determine the final values for the gradation and notify the Contractor in writing.
For screened, pit run, or grid-rolled material, furnish material smaller than the maximum size. No gradation other than maximum size will be required for pit run and grid-rolled material. For grid rolling, use all suitable material that can be reduced to maximum size.
After processing on the road, remove all oversize material from the road and dispose of it as directed by the CO.
If the aggregate is produced and stockpiled before placement, handle and stockpiled according to Section 320. Establish stockpile sites at approved locations.
301.04 Mixing and Spreading. Mix the aggregate and adjust the moisture content to obtain a uniform mixture with a moisture content suitable for the specified compaction method. Spread and shape the mixture on the prepared surface in a uniform layer with no segregation of size, and to a loose depth that will provide the required compacted thickness.
Do not place the mixture in a layer exceeding 6 inches in compacted thickness or twice the maximum particle size, whichever is less. When more than one layer is necessary, compact each layer according to Subsection 302.05 before placing the next layer. Route hauling and leveling equipment uniformly over the full width.
When placing aggregate over geotextile, place aggregate in a single lift to the full depth specified.
301.05 Compacting. Compact each layer full width. Roll from the sides to the center, parallel to the centerline of the road. Along curbs, headers, walls, and all places not accessible to the roller, compact the material with approved tampers or compactors.
Compact the aggregate using one of the following methods as specified:
Compaction D. Moisten or dry the aggregate to a uniform moisture content between 5 and 7 percent based on total dry weight of the mixture. Operate rollers and compact as specified in Subsection 204.11 (e) Roller Compaction.
For all compaction methods, blade the surface of…